McMhord Pipeline
OVERVIEW OF OIL HANDLING OPERATIONS
Training Goals
 To learn the basic description and characteristics of the pipeline
 Understand the leak detection and monitoring systems
 Overview key maintenance components on the pipeline
Description
 Starts at pump station near jet fuel tanks 30002 and 30003
 Ends at the Air Force Base fuel depot
 Length is 14.25 miles long
 Diameter 6’’
Description
 Isolation Valves are located at mile post 2.5 5.1 and 10.0
 Valves are generally only operated on during pipeline maintenance
activities
 Overpressure protection of the pipeline by pressure relief valves located
along the pipeline
 Pressure relief valves are small ¾” thermal relief valves designed to protect
the system from thermal expansion over-pressurization
Description
 The receiving facilities at the air base are protected from excessive transfer
pump pressure by a reverse check valve that automatically closes if the
transfer line pressure at the air force base exceeds 120 psi
 This will shut down the pipeline transfer pumps
 The pumps are designed to shut down in case of high vibration, low
pipeline pressure, and additive injection malfunction.
Leak Detection
 Monitoring key variables for both the jet fuel transfer mode and the static
mode
 During transfer operations, the key leak detection variable is the jet fuel
transfer volume difference
 Measured at the refinery pump station and at the air force base
Leak Detection
 Shut down the transfer and immediately check the pipeline operation if the
volume difference exceeds 2,000 gallons
 The U.S. Oil pump station monitors the pressure and alarms conditions
occur for any pressure drop exceeding 15 psi
 A drop in pressure will trigger an immediate check of the jet fuel volumes
transferred.
Monitoring Mode
 Monitoring the static pressure of the line
 Isolated at both ends and maintained at a minimum of 200 psi
 Unexplained pressure drop in excess of 15 psi will result in an alarm
Pipeline Maintenance
 The Cathodic Protection System-
 Equipped with an impressed current cathodic protection system for the
entire length of the pipeline
 Key system components consist of a rectifier, well-type anodes, and
cabling necessary to connect the system components.
 Periodic testing is required to determine if the cathodic protection is
optimized for best performance.
Pipeline Maintenance
 If the system is under-protected, corrosion damage could occur, while
over-protection could result in damage to the protective coating on the
pipeline
 A complete history of the system in the form of records and previous
measurements, along with a complete set of schematics of system
components provide a baseline for comparison to future measurements
and are useful in troubleshooting any system problems
Review
Starts at pump station near jet fuel
tanks 30002 and 30003
Ends at the Air Force Base fuel
depot
Length is 14.25 miles long
Diameter 6’’
Monitoring key variables for both
the jet fuel transfer mode and the
static mode
During transfer operations, the key
leak detection variable is the jet
fuel transfer volume difference
Measured at the refinery pump
station and at the air force base
The Cathodic Protection System-
Equipped with an impressed current
cathodic protection system for the
entire length of the pipeline
Key system components consist of a
rectifier, well-type anodes, and
cabling necessary to connect the
system components.
Periodic testing is required to
determine if the cathodic protection
is optimized for best performance.

More Related Content

PPTX
Hydraulic flushing rig ppt
PPTX
Hydraulic power pack and actuator system
PPTX
PDF
SunMaxx Datasheet Submittal - XMaxx Solar Hot Water Balancing Valves
PDF
Advanced Anti surge Control System for Turbine Driven Centrifugal Compressors
PPTX
Hydraulic control system
Hydraulic flushing rig ppt
Hydraulic power pack and actuator system
SunMaxx Datasheet Submittal - XMaxx Solar Hot Water Balancing Valves
Advanced Anti surge Control System for Turbine Driven Centrifugal Compressors
Hydraulic control system

What's hot (20)

PPTX
Seminar control valve
PPTX
Presentation on Meter Regulating Skid(MRS)
PPTX
Components of hydraulic & pneumetic
PPTX
Anesthesia workstation , electrical components , high pressure
PPTX
Combined control unit ppt
PDF
High integrity pressure protection system ( HIPPS)
PPTX
Control valves
PDF
Preliminaries of Pneumatics (Basic Components Details)
 
PPTX
Pneumatics & Hydraulics
PDF
Ml one manual-8.5x11_rev_a_final
PPT
Pneumatic1day
PPTX
Aviation Pneumatic Systems
PPT
Instrumentation & Control For Thermal Power Plant
PPTX
Pneumatic system
PDF
H60
PPT
Pneumatic circuits
PPTX
Components of hydraulic system
PPTX
N2 and co2 filling system
PPTX
3 a. industrial pneumatic circuit basic
PDF
Project Report - Spring 2014
Seminar control valve
Presentation on Meter Regulating Skid(MRS)
Components of hydraulic & pneumetic
Anesthesia workstation , electrical components , high pressure
Combined control unit ppt
High integrity pressure protection system ( HIPPS)
Control valves
Preliminaries of Pneumatics (Basic Components Details)
 
Pneumatics & Hydraulics
Ml one manual-8.5x11_rev_a_final
Pneumatic1day
Aviation Pneumatic Systems
Instrumentation & Control For Thermal Power Plant
Pneumatic system
H60
Pneumatic circuits
Components of hydraulic system
N2 and co2 filling system
3 a. industrial pneumatic circuit basic
Project Report - Spring 2014
Ad

More from Joel Ballou (7)

PPT
Dangerous wasteawareness 6 trial 4
PPTX
trial 3 dangerous waste management awareness slides 2
PPTX
Trial 3 dangerous waste management awareness slides 1
PPTX
Trial 2 overview of oil handling operations storage tanks slides
PPTX
Trial 2 overview of oil handling operations slide 1
PPTX
Trial 1 dot general awareness
PPTX
Trial 1 DOT Haz Waste Classification
Dangerous wasteawareness 6 trial 4
trial 3 dangerous waste management awareness slides 2
Trial 3 dangerous waste management awareness slides 1
Trial 2 overview of oil handling operations storage tanks slides
Trial 2 overview of oil handling operations slide 1
Trial 1 dot general awareness
Trial 1 DOT Haz Waste Classification
Ad

Recently uploaded (20)

DOCX
Double Membrane Roofs for Cassava Wastewater Treatment Captures biogas from i...
DOCX
Biogas Balloon for Bio CNG Plants An efficient solution for biogas storage..docx
PDF
1748933543SJA_41_2_826-834 SJA Ihsan ullha.pdf
PDF
The European Green Deal (EU Green Deal)
PPTX
Definition, Causes And Effects Of Greenhouse.pptx
PPTX
Plant Production 7.pptx in grade 7 students
PPTX
RadiationSafetyPt120252026nucchemis.pptx
DOCX
Double Membrane Roofs for Digester Tank Wastewater Treatment Integral to biog...
DOCX
Double Membrane Roofs for Anaerobic Digesters Essential for capturing and sto...
PDF
PAKAM TECHNOLOGY LIMTED PITCH DECK pptx.pdf
PPTX
Corporate Social Responsibility & Governance
PPTX
Soil chemistry lecture 20 presentations agriculture
PPTX
Importance of good air quality and different pollutants.
PPTX
Untitled 1.pptxhhhhhhjjjbbbbb bikinis sis son ka s
PPTX
Biodiversity PPT by Gaithanlung Gonmei.pptx
DOCX
Double Membrane Roofs for Biogas Tanks Securely store produced biogas.docx
PPTX
Pollution, it's Types and Impacts on Global context.pptx
PPTX
102602734019608717246081273460745534.pptx
PPTX
computer of health my name i d kussta lpaggyhsgd
DOCX
The Ripple Effect: Understanding Extreme Weather Patterns and Geomagnetic Dyn...
Double Membrane Roofs for Cassava Wastewater Treatment Captures biogas from i...
Biogas Balloon for Bio CNG Plants An efficient solution for biogas storage..docx
1748933543SJA_41_2_826-834 SJA Ihsan ullha.pdf
The European Green Deal (EU Green Deal)
Definition, Causes And Effects Of Greenhouse.pptx
Plant Production 7.pptx in grade 7 students
RadiationSafetyPt120252026nucchemis.pptx
Double Membrane Roofs for Digester Tank Wastewater Treatment Integral to biog...
Double Membrane Roofs for Anaerobic Digesters Essential for capturing and sto...
PAKAM TECHNOLOGY LIMTED PITCH DECK pptx.pdf
Corporate Social Responsibility & Governance
Soil chemistry lecture 20 presentations agriculture
Importance of good air quality and different pollutants.
Untitled 1.pptxhhhhhhjjjbbbbb bikinis sis son ka s
Biodiversity PPT by Gaithanlung Gonmei.pptx
Double Membrane Roofs for Biogas Tanks Securely store produced biogas.docx
Pollution, it's Types and Impacts on Global context.pptx
102602734019608717246081273460745534.pptx
computer of health my name i d kussta lpaggyhsgd
The Ripple Effect: Understanding Extreme Weather Patterns and Geomagnetic Dyn...

Trial 2 overview of oil handling operations mc cord pipeline

  • 1. McMhord Pipeline OVERVIEW OF OIL HANDLING OPERATIONS
  • 2. Training Goals  To learn the basic description and characteristics of the pipeline  Understand the leak detection and monitoring systems  Overview key maintenance components on the pipeline
  • 3. Description  Starts at pump station near jet fuel tanks 30002 and 30003  Ends at the Air Force Base fuel depot  Length is 14.25 miles long  Diameter 6’’
  • 4. Description  Isolation Valves are located at mile post 2.5 5.1 and 10.0  Valves are generally only operated on during pipeline maintenance activities  Overpressure protection of the pipeline by pressure relief valves located along the pipeline  Pressure relief valves are small ¾” thermal relief valves designed to protect the system from thermal expansion over-pressurization
  • 5. Description  The receiving facilities at the air base are protected from excessive transfer pump pressure by a reverse check valve that automatically closes if the transfer line pressure at the air force base exceeds 120 psi  This will shut down the pipeline transfer pumps  The pumps are designed to shut down in case of high vibration, low pipeline pressure, and additive injection malfunction.
  • 6. Leak Detection  Monitoring key variables for both the jet fuel transfer mode and the static mode  During transfer operations, the key leak detection variable is the jet fuel transfer volume difference  Measured at the refinery pump station and at the air force base
  • 7. Leak Detection  Shut down the transfer and immediately check the pipeline operation if the volume difference exceeds 2,000 gallons  The U.S. Oil pump station monitors the pressure and alarms conditions occur for any pressure drop exceeding 15 psi  A drop in pressure will trigger an immediate check of the jet fuel volumes transferred.
  • 8. Monitoring Mode  Monitoring the static pressure of the line  Isolated at both ends and maintained at a minimum of 200 psi  Unexplained pressure drop in excess of 15 psi will result in an alarm
  • 9. Pipeline Maintenance  The Cathodic Protection System-  Equipped with an impressed current cathodic protection system for the entire length of the pipeline  Key system components consist of a rectifier, well-type anodes, and cabling necessary to connect the system components.  Periodic testing is required to determine if the cathodic protection is optimized for best performance.
  • 10. Pipeline Maintenance  If the system is under-protected, corrosion damage could occur, while over-protection could result in damage to the protective coating on the pipeline  A complete history of the system in the form of records and previous measurements, along with a complete set of schematics of system components provide a baseline for comparison to future measurements and are useful in troubleshooting any system problems
  • 11. Review Starts at pump station near jet fuel tanks 30002 and 30003 Ends at the Air Force Base fuel depot Length is 14.25 miles long Diameter 6’’ Monitoring key variables for both the jet fuel transfer mode and the static mode During transfer operations, the key leak detection variable is the jet fuel transfer volume difference Measured at the refinery pump station and at the air force base The Cathodic Protection System- Equipped with an impressed current cathodic protection system for the entire length of the pipeline Key system components consist of a rectifier, well-type anodes, and cabling necessary to connect the system components. Periodic testing is required to determine if the cathodic protection is optimized for best performance.