TURNING YOUR
PROJECT AROUND
A RECOVERY APPROACH
OVERVIEW
The rate of project failure in today’s economy is becoming what one considers to the norm
for the rollout of projects in today’s business environment.
Poor Requirements Definition 50%
Poor Scope Definition 15%
Inadequate Risk Management 17%
Communication Problems 14%
Lack of Qualified Resources 3%
Other 1%
ESI International Survey - 2000
With these odds vying against project managers it is
becoming more and more necessary that rather than
cancel a project to look at a way that the project can be
turned around and show some form of economic viability
for the project and the company as a whole.
With this change in paradigm it will require some quick
thinking both within the process of how the project is
being managed and getting the buy in from both your
project team and the stakeholders.
OVERVIEW
ADVANTAGES
Turning your project around will allow:
 The firming of the money spent to date
 Projecting earned value and propose a positive
balance in the future .
 That with a change in the approach and some re-
planning you will deliver the project and more
importantly you will deliver the project with the
stakeholder’s blessing and approval.
 That your product will be launched and you will
still keep your foothold in the marketplace
KEEP IN MIND
 The important thing is not to overcomplicate or overthink what
you need to do swift and focussed action is what is required
now both for the project and the business as a whole.
 Remember that for each area in your project that is showing a
problem a resolution can be found.
 At the end of the day every problem has the chance of being
turnaround without cancelling the whole show.
PREPARATION
 Select the recovery team
 Book out the day in their calendars
 Prepare the meeting room
 Send out the recovery approach
 Assign roles and responsibilities for the recovery plan
 Notify the stakeholders and finalise recovery communication
plan
 Assign admin support for the day
 Prepare the costing analysis for the day
 Obtain approval for the cost either via a change control or a
project exception
 Setup a central document storage unit for the recovery
documentation and information
 Agree to the folder structure
 Provide shared access for the information
Project
Manager
Business
Owner
Technical
Business
Analyst
Design Team
External
Suppliers
Production
Manager
Operations
THE RECOVERY TEAM
Please note
The recovery team will be set up in accordance of the full
responsibility required to roll out the project and this could be
the time where new resources are added to get a fresh view
on the way forward. This could result in additional costs for
the project and will need to be approved by the relevant
stakeholders
THE RECOVERY PLAN
The Project Baseline
Assessment
The Recovery Project Plan
Assessing the Risk
Presenting to the
Stakeholders
Go / No Go Decision
Obtain this information from
the original project
documentation
Time – Schedule
Cost – Financial and budget
analysis
Scope – Requirements
documentation and business
case
Against each area of the triple
constraints determine the
actual slippage to date on
time, scope and cost.
Remember this is only based
on actual work days for the
project
Determine the slippage for
each tasks and then roll it up
to Level 1 milestones to get
the full slippage picture
• Actual start date
• Current finish date
• Slippage
You will need to do a projected
view of what is required to roll
out the project to deliver the
completed product.
1. Actual + Slippage = Work
to date
2. Current completed work
plus delta to complete –
final target against cost
and time to get final target
numbers
THE PROJECT BASELINE – ASSESSMENT
Original Plan
Current completed
activity/tasks
Slippage Delta to complete
The assessment will provide an overall picture of the current status of the project, what milestones have
been achieved and what has yet to be accomplished. The recovery assessment must clearly show the
actual slippage to date and the full cost impact of the slippage and risk to the company. Finally you will
need to provide a snapshot of what is still needed to complete the full project and the benefits of this.
THE RECOVERY PROJECT PLAN
Scope
CostTime
Redefine the project baseline setting up
• A revised scope document (this could
be either a requirement document or a
new business case
• Outline the revised project mandate
• Against each revised activity accurately
define the actual time to complete the
task and this must be 100% accurate
• Outline the agreed cost against each
activity. Remember to include any
supplier cost as well
It is important to ensure that the correct
project team and skills are now in place
to take the project through to the finish
line.
Ensure that each and every activity to
complete the task has the correct
resource or team member assigned and
draw up the roles and responsibility
What could be done here is for each team
member and supplier to sign a project
charter to ensure buy in and commitment
to complete the recovered project plan
The final step in the recovery plan will be
to assess the viability of proceeding with
the recovery
• Return on Investment
• Measuring the quality
• Handover of the product whether this
in an on-line product or a product
being sold to the public
• Projected value and how this will
improve the companies market
foothold and competitive standing
Project Baseline Resources Viability
ASSESSING THE RISK
One of the key factors to ensure that you have all
of the information on hand for understanding
whether a project recovery is viable or not is to
conduct a risk assessment based on two key
factors
• To proceed with the recovery
• Not to proceed with the recovery
Medium Level
Risk
High Level Risk
Low Level Risk
Medium Level
Risk
Probability
Impact
Low
Low
High
High
Once the full risk assessment is done you
will need to draw up the findings showing
the result of both recovery routes to
provide data on 9what provides the less
risk for recovery
PRESENTING TO THE STAKEHOLDERS
• Current status of project
• Reasons why to continue
• Reasons why not to continue
• Savings to company if project is cancelled
• Cost to company if recovery plan is approved
• Revised timeline to complete
• Revised charter and mandate
• Agreed actions and decisions
Once you have all of the information at hand and you are able to
provide a full view of what will be required to go ahead or to not go
ahead with the project you will need to present the findings to the
stakeholders and shareholders.
Recommended
THE GO OR NO GO DECISION
Go Decision
• Setup new mandate and project charter
• Baseline the project plan and ensure full
approval has been obtained
• Assign the project team and finalise the
roles and responsibilities
• Setup the recovered project budget
• Ensure the revised SOW has been
obtained from the appointed suppliers
• Finalise the recovered project plan with
the new time, cost and scope baselines
• Agree on quality plan
• Setup agreed documentation folders in
shared drive
• Hold kick off meeting
No Go Decision
• Proceed with your established project
close out process
• Notify the suppliers that the project has
been cancelled and proceed to contract
review and close out and finalise
financials
• Send out release notifications to the
project team and ensure that the correct
termination letters are sent to
contractors where relevant
• Notify PMO or relevant body that the
project is terminated
• Provide final status report on project
• Begin to store all documentation on
shared drive
• Conduct a lessons learnt with the full
team and stakeholders
Once the decision has been obtained on a Go or No Go Decision remember to setup
enough time to plan either option and ensure that the costs for each process has been
approved in writing
The great thing about recovering a project is that all of your
hard work will pay dividends. Clear and absolute focus on the
end goals will ensure that you move forward with your team
and stakeholders to deliver successfully.
Projects will always have challenges and to be able to turn a
project around and move it forward to deliver the vision and
the mission is what makes project management the best place
to be .
A final
word
Contact Information
Email cliona.ohanrahan@yahoo.com
Mobile +44 (0) 77 843 02708
LinkedIn Profile LinkedIn Profile
Skype clionaoh
Cliona O’Hanrahan
MPM; Prince2 ; PMI Professional

More Related Content

PDF
Pmp t09 project_execution_plan_rev_a
PDF
Project management milestones-webinar
PDF
Project Closure Process Steps PowerPoint Presentation Slides
PPTX
Project management assignment slides
PPT
Final Project Closing
PPT
Project control
DOCX
behavioural science groups
Pmp t09 project_execution_plan_rev_a
Project management milestones-webinar
Project Closure Process Steps PowerPoint Presentation Slides
Project management assignment slides
Final Project Closing
Project control
behavioural science groups

What's hot (20)

ZIP
Project Monitoring and Control
PPSX
Project Monitoring and Controlling Processes
PDF
C. Burcham - Project Closure Report
PDF
PMBoK6Ed.lect1.introduction
XLS
Excel Project Management
PPTX
IT-Projects Management presentation
DOCX
SLeahy - Unit 5 Assignment - IT599-01
DOCX
Project Closure Report
PDF
04 project cost managment
PDF
Performance Based Management Handbook
PDF
Practical Project Cost Control for Large Complex Projects
PPT
INAAU Project Management for Telecommunications Professionals
PPTX
Scenario - Project Management Processes | 1 of 2
PDF
Module 12 Monitoring and Control I
PPT
7 cost managmenet
PPT
Project development new1
PPTX
6- PMP Training - Cost Management
PPTX
PMP Training - 07 project cost management
PPTX
Project Management using MS Project 2010
PPT
Top 3 Challenges in Managing Triple Constraint
Project Monitoring and Control
Project Monitoring and Controlling Processes
C. Burcham - Project Closure Report
PMBoK6Ed.lect1.introduction
Excel Project Management
IT-Projects Management presentation
SLeahy - Unit 5 Assignment - IT599-01
Project Closure Report
04 project cost managment
Performance Based Management Handbook
Practical Project Cost Control for Large Complex Projects
INAAU Project Management for Telecommunications Professionals
Scenario - Project Management Processes | 1 of 2
Module 12 Monitoring and Control I
7 cost managmenet
Project development new1
6- PMP Training - Cost Management
PMP Training - 07 project cost management
Project Management using MS Project 2010
Top 3 Challenges in Managing Triple Constraint
Ad

Viewers also liked (6)

PDF
Disrupting traditional development - tales of revolt from OpenCorporates & CHAYN
PDF
Spend Network: Open Contracting
PPTX
Open corporates
PPTX
Mapping Corporate Networks With OpenCorporates
PPTX
10 Ways to Market Your School
PPTX
3 hard facts shaping higher education thinking and behavior
Disrupting traditional development - tales of revolt from OpenCorporates & CHAYN
Spend Network: Open Contracting
Open corporates
Mapping Corporate Networks With OpenCorporates
10 Ways to Market Your School
3 hard facts shaping higher education thinking and behavior
Ad

Similar to Turning your project around (20)

PPTX
Session 22 4th edition PMP
PDF
Project health check updated and improved
PPTX
Session 21 4th edition PMP
DOCX
Hello Class- This is a very rough draft of the assignment. I have
PPTX
The role of the project manager
DOCX
Navigating the PMP Certification in New York_ Understanding PMP Rebaseline.docx
PPSX
Projectmanagement 130721095616-phpapp01
PDF
7 Processes of Prince2
DOCX
CPMGT_300 Week_5__Project Life Cycle Paper.docx
PPTX
Project management pocket skills
PPTX
Unit 1.pptx
PPT
Mmi entrepreneurship 6
PDF
MDP2206-2217-Lec2.pdf
PDF
Measuring project success
PPTX
Project Management Pocket Skills Guide
PPTX
Construction company business plan
PPTX
CW3007-IT PROJECT MANAGEMENT NOTES FOR AUTONOMOUS STUDENT
PPTX
CE168P-5 Lecture 9 Project Monitoring & Control.pptx
PPTX
LN I - PPT.pptx
PPTX
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...
Session 22 4th edition PMP
Project health check updated and improved
Session 21 4th edition PMP
Hello Class- This is a very rough draft of the assignment. I have
The role of the project manager
Navigating the PMP Certification in New York_ Understanding PMP Rebaseline.docx
Projectmanagement 130721095616-phpapp01
7 Processes of Prince2
CPMGT_300 Week_5__Project Life Cycle Paper.docx
Project management pocket skills
Unit 1.pptx
Mmi entrepreneurship 6
MDP2206-2217-Lec2.pdf
Measuring project success
Project Management Pocket Skills Guide
Construction company business plan
CW3007-IT PROJECT MANAGEMENT NOTES FOR AUTONOMOUS STUDENT
CE168P-5 Lecture 9 Project Monitoring & Control.pptx
LN I - PPT.pptx
Online PMP Training Material for PMP Exam - Integration Management Knowledge ...

More from Project Management Solutions (19)

PPTX
A project quick start guide
PPTX
Setting up a project framework phase 1 june 20162
PDF
Taking a web site from concept to launch
PPTX
Managing multiple projects
PPTX
A guide for the rolling out of a software delivery project
PDF
PPTX
Business and project changing the paradigm
PDF
Why not - Words to make you think
PDF
Project management today a step ahead
PPTX
Managing your suppliers makes perfect sense
PPTX
Ready get set go your project is approved
PPTX
The digital project manager
PDF
PPTX
Getting Ready for UAT
PPTX
Is your project not going well this will help you get it back on track
PDF
Pm audit and assessment approach final
PPTX
Pm audit and assessment approach final
PPTX
Strategy planning for small digital companies
PPTX
Cliona O Hanrahan Introduction 2011
A project quick start guide
Setting up a project framework phase 1 june 20162
Taking a web site from concept to launch
Managing multiple projects
A guide for the rolling out of a software delivery project
Business and project changing the paradigm
Why not - Words to make you think
Project management today a step ahead
Managing your suppliers makes perfect sense
Ready get set go your project is approved
The digital project manager
Getting Ready for UAT
Is your project not going well this will help you get it back on track
Pm audit and assessment approach final
Pm audit and assessment approach final
Strategy planning for small digital companies
Cliona O Hanrahan Introduction 2011

Recently uploaded (20)

PDF
Boost the power of design | Design Impulse
PPTX
management development and careerr planning.pptx
PDF
SpatzAI Micro-Conflict Resolution Toolkit - Fairer Teamwork Globally
PPTX
WORLD TRADE ORAGANIZATION- INSTITUTION TO MANAGE TRADE BETWEEN NATIONS
PPTX
Time Management Techniques_All Rules.pptx
PPTX
Spotlight on road Injury in the Philippines
PPTX
Recruitment and bshiwjwnbshshshshhshvej.ppt
PPTX
Management and Leadership across diverse culture
PPSX
Neurodiversity in the Workplace: Navigating the Manager/Employee Relationship
PDF
Geopolitics and the Dynamic Competition Framework
PPTX
Unit 1-setting up practice arvhitectweyre
PDF
SpatzAI Micro-Conflict Resolution Toolkit - Fairer Teamwork Globally
PPTX
Unit 6: Product service and brand.pptx mm
PPT
Software EffortEstimation and Risk Project Planning Activities Software Scope...
PPTX
SM_Behavior Based Safety (BBS)_Unit V.pptx
PPTX
Leading, its definiton, example, and types.pptx
PPT
development_theories chapter 3.ppt undfer
PDF
Dynamic Capabilities: A System-level Approach To New Strategic Challenges
PPTX
1.pptx Awareness course managing. safety
PDF
Jim Kaskade Biography Highlighting A Career Journey August 21 2025
Boost the power of design | Design Impulse
management development and careerr planning.pptx
SpatzAI Micro-Conflict Resolution Toolkit - Fairer Teamwork Globally
WORLD TRADE ORAGANIZATION- INSTITUTION TO MANAGE TRADE BETWEEN NATIONS
Time Management Techniques_All Rules.pptx
Spotlight on road Injury in the Philippines
Recruitment and bshiwjwnbshshshshhshvej.ppt
Management and Leadership across diverse culture
Neurodiversity in the Workplace: Navigating the Manager/Employee Relationship
Geopolitics and the Dynamic Competition Framework
Unit 1-setting up practice arvhitectweyre
SpatzAI Micro-Conflict Resolution Toolkit - Fairer Teamwork Globally
Unit 6: Product service and brand.pptx mm
Software EffortEstimation and Risk Project Planning Activities Software Scope...
SM_Behavior Based Safety (BBS)_Unit V.pptx
Leading, its definiton, example, and types.pptx
development_theories chapter 3.ppt undfer
Dynamic Capabilities: A System-level Approach To New Strategic Challenges
1.pptx Awareness course managing. safety
Jim Kaskade Biography Highlighting A Career Journey August 21 2025

Turning your project around

  • 1. TURNING YOUR PROJECT AROUND A RECOVERY APPROACH
  • 2. OVERVIEW The rate of project failure in today’s economy is becoming what one considers to the norm for the rollout of projects in today’s business environment. Poor Requirements Definition 50% Poor Scope Definition 15% Inadequate Risk Management 17% Communication Problems 14% Lack of Qualified Resources 3% Other 1% ESI International Survey - 2000
  • 3. With these odds vying against project managers it is becoming more and more necessary that rather than cancel a project to look at a way that the project can be turned around and show some form of economic viability for the project and the company as a whole. With this change in paradigm it will require some quick thinking both within the process of how the project is being managed and getting the buy in from both your project team and the stakeholders. OVERVIEW
  • 4. ADVANTAGES Turning your project around will allow:  The firming of the money spent to date  Projecting earned value and propose a positive balance in the future .  That with a change in the approach and some re- planning you will deliver the project and more importantly you will deliver the project with the stakeholder’s blessing and approval.  That your product will be launched and you will still keep your foothold in the marketplace
  • 5. KEEP IN MIND  The important thing is not to overcomplicate or overthink what you need to do swift and focussed action is what is required now both for the project and the business as a whole.  Remember that for each area in your project that is showing a problem a resolution can be found.  At the end of the day every problem has the chance of being turnaround without cancelling the whole show.
  • 6. PREPARATION  Select the recovery team  Book out the day in their calendars  Prepare the meeting room  Send out the recovery approach  Assign roles and responsibilities for the recovery plan  Notify the stakeholders and finalise recovery communication plan  Assign admin support for the day  Prepare the costing analysis for the day  Obtain approval for the cost either via a change control or a project exception  Setup a central document storage unit for the recovery documentation and information  Agree to the folder structure  Provide shared access for the information
  • 7. Project Manager Business Owner Technical Business Analyst Design Team External Suppliers Production Manager Operations THE RECOVERY TEAM Please note The recovery team will be set up in accordance of the full responsibility required to roll out the project and this could be the time where new resources are added to get a fresh view on the way forward. This could result in additional costs for the project and will need to be approved by the relevant stakeholders
  • 8. THE RECOVERY PLAN The Project Baseline Assessment The Recovery Project Plan Assessing the Risk Presenting to the Stakeholders Go / No Go Decision
  • 9. Obtain this information from the original project documentation Time – Schedule Cost – Financial and budget analysis Scope – Requirements documentation and business case Against each area of the triple constraints determine the actual slippage to date on time, scope and cost. Remember this is only based on actual work days for the project Determine the slippage for each tasks and then roll it up to Level 1 milestones to get the full slippage picture • Actual start date • Current finish date • Slippage You will need to do a projected view of what is required to roll out the project to deliver the completed product. 1. Actual + Slippage = Work to date 2. Current completed work plus delta to complete – final target against cost and time to get final target numbers THE PROJECT BASELINE – ASSESSMENT Original Plan Current completed activity/tasks Slippage Delta to complete The assessment will provide an overall picture of the current status of the project, what milestones have been achieved and what has yet to be accomplished. The recovery assessment must clearly show the actual slippage to date and the full cost impact of the slippage and risk to the company. Finally you will need to provide a snapshot of what is still needed to complete the full project and the benefits of this.
  • 10. THE RECOVERY PROJECT PLAN Scope CostTime Redefine the project baseline setting up • A revised scope document (this could be either a requirement document or a new business case • Outline the revised project mandate • Against each revised activity accurately define the actual time to complete the task and this must be 100% accurate • Outline the agreed cost against each activity. Remember to include any supplier cost as well It is important to ensure that the correct project team and skills are now in place to take the project through to the finish line. Ensure that each and every activity to complete the task has the correct resource or team member assigned and draw up the roles and responsibility What could be done here is for each team member and supplier to sign a project charter to ensure buy in and commitment to complete the recovered project plan The final step in the recovery plan will be to assess the viability of proceeding with the recovery • Return on Investment • Measuring the quality • Handover of the product whether this in an on-line product or a product being sold to the public • Projected value and how this will improve the companies market foothold and competitive standing Project Baseline Resources Viability
  • 11. ASSESSING THE RISK One of the key factors to ensure that you have all of the information on hand for understanding whether a project recovery is viable or not is to conduct a risk assessment based on two key factors • To proceed with the recovery • Not to proceed with the recovery Medium Level Risk High Level Risk Low Level Risk Medium Level Risk Probability Impact Low Low High High Once the full risk assessment is done you will need to draw up the findings showing the result of both recovery routes to provide data on 9what provides the less risk for recovery
  • 12. PRESENTING TO THE STAKEHOLDERS • Current status of project • Reasons why to continue • Reasons why not to continue • Savings to company if project is cancelled • Cost to company if recovery plan is approved • Revised timeline to complete • Revised charter and mandate • Agreed actions and decisions Once you have all of the information at hand and you are able to provide a full view of what will be required to go ahead or to not go ahead with the project you will need to present the findings to the stakeholders and shareholders. Recommended
  • 13. THE GO OR NO GO DECISION Go Decision • Setup new mandate and project charter • Baseline the project plan and ensure full approval has been obtained • Assign the project team and finalise the roles and responsibilities • Setup the recovered project budget • Ensure the revised SOW has been obtained from the appointed suppliers • Finalise the recovered project plan with the new time, cost and scope baselines • Agree on quality plan • Setup agreed documentation folders in shared drive • Hold kick off meeting No Go Decision • Proceed with your established project close out process • Notify the suppliers that the project has been cancelled and proceed to contract review and close out and finalise financials • Send out release notifications to the project team and ensure that the correct termination letters are sent to contractors where relevant • Notify PMO or relevant body that the project is terminated • Provide final status report on project • Begin to store all documentation on shared drive • Conduct a lessons learnt with the full team and stakeholders Once the decision has been obtained on a Go or No Go Decision remember to setup enough time to plan either option and ensure that the costs for each process has been approved in writing
  • 14. The great thing about recovering a project is that all of your hard work will pay dividends. Clear and absolute focus on the end goals will ensure that you move forward with your team and stakeholders to deliver successfully. Projects will always have challenges and to be able to turn a project around and move it forward to deliver the vision and the mission is what makes project management the best place to be . A final word Contact Information Email cliona.ohanrahan@yahoo.com Mobile +44 (0) 77 843 02708 LinkedIn Profile LinkedIn Profile Skype clionaoh Cliona O’Hanrahan MPM; Prince2 ; PMI Professional