Offshore operations and the EIA:
lessons learned from seismic IEEs, and next steps
22-25 September 2015
Review process of IEE and EIA
reports in EIA procedure
EIA procedure, Annex (1)
IEE EIA No EIA/IEE
Screening Process on Oil and Gas Sector
All sizes • Onshore Oil and Gas Seismic Surveys
- All sizes • Onshore Oil and Gas Exploration Drillings
- All sizes • Onshore Oil and Gas Production drilling and
production activities; transportation activities
including pipelines; pump stations, compressor
stations and storage facilities; ancillary and support
operations; and decommissioning
All sizes - • Offshore Oil and Gas Seismic Surveys
- All sizes • Offshore Oil and Gas Exploration Drillings
- All sizes • Offshore Oil and Gas Production drilling and
production activities; offshore pipeline
operations, offshore transportation, compressor
stations and storage facilities; ancillary and
support operations; and decommissioning
Reviewing IEE Report
IEE
Review and Approval Process for IEE & EIA report
Initial and final reviewed by EIA Division under ECD
Approved by MONREC
Issued ECC by MONREC
To Undertake EIA
If required
Reviewing EIA Scoping Report and ToR
Reviewed by ECD
Approved by ECD (15 Days)
Review and Approval Process for IEE & EIA report (Cont’d)
Scoping Report and ToR
In accordance with Ministry Guidance
Reviewing EIA Reports
EIA
Initial Reviewed by ECD
Reviewed by Review Team (RT)
Approved by MONREC( ECC)
Issued ECC by MONREC
Rejected by
MONREC
Appeal
Project Termination
Review and Approval Process for IEE & EIA report (Cont’d)
No Yes
Not Satisfactory
Satisfactory
7
Time frame (IEE & EIA Review Process )
EIA Process Duration
Screening Proposal (IEE/EIA/Non) 15 days
IEE Process
• IEE expert approval (Third party or not) 7 days
• Preparing IEE Report ?
• IEE Report approval 60 days
EIA Process
• EIA expert approval (Third party or not) 7 days
• Developing Scoping Report and TOR ?
• Scoping report &TOR approval 15 days
• Investigation & Developing EIA Report ?
• EIA report approval 90 days
Background Information of EIA Review Team
— EIA Report Review Team, consisting of 39 members from
government agencies, i.e. MOECAF, 18 related ministries,
attorney General Office and 3 civil Development committee
of Yangon, Mandalay and Nay Pyi Taw, with a total of 39
members was formed, and the reviewing task was assigned
by MOECAF with reference number-2/220/(B) (3)/ (8007/
2013) dated 28-11-2013.
— With MOECAF’s reference number-2/220/(B) (3)/(8008/
2013) dated 28-11-2013, EIA report Review Team was also
recruited into 4 sub-groups based on Land use Sector,
Mining and Energy Sector, Urban and Construction Sector
and Industry Sector respectively.
Institutional Structure of EIA Review Team
EIA
review
Team
(39 members
from 18
Ministries,
Attorney
General
Office ,
NDC, YCDC
and MCDC)
RT Sub-group on Land use Sector
(11 members)
RT Sub-group on Mining and Energy Sector
(8 members) + (6 members from other sectors)
RT Sub-group on Urban and Construction
Sector (15 members)
RT Sub-group on Industry
( 9 members)
Contents and Structure of
IEE and EIA reports
IEE Report
1. Executive Summary
2. Details of the project proponent
3. Description of the project
4. Legal requirements
5. Governing parameters
6. Summary of Impacts
7. Description of proposed mitigation measures
8. Monitoring Program
9. Reporting requirements
10. Responsibilities for mitigation and monitoring
11. Emergency Plan
12. Capacity development and training
13. Public consultation and information disclosure
14. Work plan and implementation schedule
15. Review of the EMP
16. Conclusion and Recommendation
1. Executive Summary
2. Introduction
3. Policy, Legal and Institutional Framework
4. Project Descriptions and Alternatives Selection
(a) Project Background
(b) Project Location
(c) Comparison and Selection of the Alternatives
(d) Description of the selected alternatives
5. Description of the Surrounding Environment
(a) Setting the Study Limits
(b) Methodology for data collection and analysis
(c) Physical Components
(d) Biological Components
(e) Socio-Economic Components
(f) Cultural Components
(g) Visual Components
EIA Report Format
6. Impact Assessment and Mitigation Measures
(a) Impact Assessment Methodology and Approach
(b) Scope of Assessment
(c) Identification of Impacts
(d) Determination of significance of those impacts
(e) Mitigation Measures
(f) Incorporation of mitigation measures into project design
(g) Determination of any residual impacts
7. Risk Assessment
8. Cumulative Impact Assessment
9. Summary of Environmental Management Plan
10. Public Consultation and Disclosure
11. Conclusion and Recommendations
EIA Report Format (Cont’d;)
On-Shore Operation Off-shore Operation
Grand
Total
EIA/ESHIA,
SIA
Total IEE EIA
Scopi
ng
Monito
ring
Total
SeismicSurveyand
ExplorationDrilling
Production
2D&3DSeismic
Surrey
2D&3DSeismic
Surrey
Explorationdrilling
Production
ExplorationDrilling
3DSeismicSurvey
12 - 12 20 2 2 - 1 1 26 38
Current Status of IEE/ EIA/ Scoping and Monitoring Reports from
Onshore and Offshore Operations Received by ECD
( 12-10- 2013 to 30-6-2016)
Source: NR & EIA division, ECD, July 2016
On-shore Operation Off-shore Operation
Total
EIA IEE EIA Scoping Monitoring
InProgress
InitialReview
ReviewTeam
Meeting
Approved
InProgress
InitialComment
Approved
InProgress
Inprogress
InitialComment
Inprogress
InitialComment
7 2 3 - 4 11 7 2* 1 - 1 - 38
Current Status of IEE/ EIA/ Scoping and Monitoring Reports from
Onshore and Offshore Operations Reviewed by ECD
( 12-10- 2013 to 30-6-2016)
* 2 EIA reports for Seismic Survey
- To continue issuing ECC for approved IEE reports on Offshore Seismic Campaign
Source: NR & EIA division, ECD, July 2016
Seismic Operation (2D &3D) Exploration Drilling
Total
IEE Report (22) EIA
Monit
oring
EIA Report (2) Scoping
InProgress
InitialComment
Approved
InProgress
InProgress
InProgress
InitialReview
ReviewTeam
Meeting
Approved
InProgress
4 11 7 2* 1 - 2 - - 1 26+2*
Current Status of IEE/ EIA, Scoping and Monitoring Reports from
Only Offshore Operation Reviewed by ECD
( 12-10- 2013 to 30-6-2016)
* 2 EIA reports for Seismic Survey
- To continue issuing ECC for approved IEE reports on Offshore Seismic Campaign
Source: NR & EIA division, ECD, July 2016
Director	(1)	+	(11)	
Natural	Resources	Conservation	and	EIA	Division
Deputy Director (-)
Deputy	Director	General	
Director	General
Current Institutional Structure of Natural Resources Conservation and EIA Division
Natural	Resources	Conservation	
Sub-Division	(3)
EIA	Sub-Division	(8)
Assistant	Director	-EIA	Unit	(1)	
Urban,	Construction	and	Industry	sector
Assistant	Director	-EIA	Unit	(2)	
Land	Use,	Mining	and	Energy		Sector
Staff	Officer	(1)
(Energy	&	Land	use	Sector)
Staff	Officer	(1)
(Mining	Sector)
Deputy	Staff	Officer	(1)
Staff	Officer	(1)
(Urban	&	Construction	Sector)
Staff	Officer	(1)
(	Industry	Sector)
Deputy	Staff	Officer	(1)
Remaining Challenges for ECD
Ø Influx of Reports from various sectors
Ø Lack of Sectoral Guidelines for Reviewing (Oil and Gas
Review Guidelines)
Ø ECD has to take full responsibility for approval of IEE
reports. (26/38 mentioned in previous slide)
Ø Limited Staff and Capacity (HQ and Regional/ States)
Ø EIA Staff assigned by Ministry to take responsibilities
rather than Review Work.
Ø Urgent need of ECC guidelines
Ø No experts in oil and gas sector
Ø EIA review process is quite new to RT.
Ø Lack of Review Framework and specific sectoral
guidelines for oil and gas sector
Ø Cannot pay full attention to review work as they have their
own work
Ø Cannot fully participate in the whole review process of
EIA report of a project
Ø Responsible to review EIA reports coming from various
sectors rather than specific oil and gas sector.
Remaining Challenges for Review Team (RT)
Current Efforts to tackle Remaining Challenges
Ø General EIA Review and ECC Guidelines under
preparation with ADB technical assistance
Ø Final draft of Oil and Gas Sectoral Guidelines with NEA
technical assistance
Ø Review Checklists under preparation with JICA technical
assistance
Ø Capacity Building (Clinical Training, Field Trips,
Workshops and Meetings, etc)
Ø Recruited only 12 staffs for reviewing purpose
Current Efforts to tackle Remaining Challenges (Cont’d)
Ø Planning to recruit 20 Government experts from 20
relevant Ministries
Ø Cooperation with local professionals for reviewing EA
reports
Ø Already Recruited and Assigned EIA staffs for reviewing
specific sectors (For Oil and Gas sector – 4 staffs only)
(not including 12 new staffs)
Ways Forward
Ø To seek technical and financial assistances from
Development Partners
Ø To issue ECC (ADB)
Ø To establish Environmental Management Fund
(UNDP)
Ø To issue guidelines for oil and gas sector(NEA)
Ø To issue general review guidelines (ADB)
Ø To develop sectoral checklists (JICA)
Contact Information
— Contact Person: Dr. San Oo (Director)
Ms. Sa Aung Thu( Assistant Director)
— Contact Phone/Fax: 067- 431329 (Office)
— Contact Email:
— NR & EIA Division (office) nreia.env@gmail.com
— Mr. Sa Aung Thu (AD) 2012saungthu@gmail.com
— Relevant Information is available at ECD website
(www.ecd.gov.mm)
Thank You Very Much For Your Kind
Attention!

More Related Content

PDF
Recap of 2014 meeting and this meeting’s Objectives
PPTX
Sector Specific EIA Guidelines for Oil and Gas Activities in Myanmar - Initia...
PPT
Environmental Impact Assessment
PPTX
Current trends in EIA
PPTX
Environment Impact Assessment - EIA
PDF
E2.KEY_ELEMENTS_OF_EIA_PROCESS-1
DOCX
Environment impact assessment
PPTX
Environment Impact Assessment Draft 2020
Recap of 2014 meeting and this meeting’s Objectives
Sector Specific EIA Guidelines for Oil and Gas Activities in Myanmar - Initia...
Environmental Impact Assessment
Current trends in EIA
Environment Impact Assessment - EIA
E2.KEY_ELEMENTS_OF_EIA_PROCESS-1
Environment impact assessment
Environment Impact Assessment Draft 2020

What's hot (19)

PDF
Emerging Requirements for Environmental and Social Impact Assessment in Myanmar
PPTX
Assessing proposed project development under EIA
RTF
Environmental impact assessment
PPT
Eia basic concepts_15_dec05
PPT
Environmental Impact Assessment
DOCX
Environment impact assessment
PPTX
Environmental Impact Assessment and Meaningful Citizen Participation
PDF
Environmental Impact
PPTX
Environmental Impact Assessment
PPTX
PEISS
PPTX
EIA report presentation
PPTX
PEISS
PDF
Environmental Impact assessment
PPTX
ZIP
Environmental Impact Assessment
DOCX
EIA Report
PPTX
ENVIRONMENT IMPACT ASSESSMENT
Emerging Requirements for Environmental and Social Impact Assessment in Myanmar
Assessing proposed project development under EIA
Environmental impact assessment
Eia basic concepts_15_dec05
Environmental Impact Assessment
Environment impact assessment
Environmental Impact Assessment and Meaningful Citizen Participation
Environmental Impact
Environmental Impact Assessment
PEISS
EIA report presentation
PEISS
Environmental Impact assessment
Environmental Impact Assessment
EIA Report
ENVIRONMENT IMPACT ASSESSMENT
Ad

Viewers also liked (7)

PDF
SHELL / BG OFFSHORE SEISMIC SURVEY CAMPAIGN IEE PROCESS Lessons learned
PDF
Recap of 2014 meeting and this meeting’s objectives (Burmese)
PDF
IEE for 2D Seismic Survey AD-10 Process and Lessons Learned
PDF
IEE for 2D Seismic Survey AD-10 Process and Lessons Learned (my)
PDF
Woodside Energy (en) Exploration Drilling
PDF
Woodside Energy (my)
PDF
SHELL / BG OFFSHORE SEISMIC SURVEY CAMPAIGN IEE PROCESS Lessons learned (Burm...
SHELL / BG OFFSHORE SEISMIC SURVEY CAMPAIGN IEE PROCESS Lessons learned
Recap of 2014 meeting and this meeting’s objectives (Burmese)
IEE for 2D Seismic Survey AD-10 Process and Lessons Learned
IEE for 2D Seismic Survey AD-10 Process and Lessons Learned (my)
Woodside Energy (en) Exploration Drilling
Woodside Energy (my)
SHELL / BG OFFSHORE SEISMIC SURVEY CAMPAIGN IEE PROCESS Lessons learned (Burm...
Ad

Similar to Update on Implementation of the EIA Process and Remaining Challenges in Oil and Gas Sector (20)

PDF
2. EIA Process Experience to Date - Htin Aung Kyaw
PPTX
Environmental management
PDF
Kenya projectsummaryreport20181001
PDF
Smp2 part c action plan final
PDF
Beige and Brown Aesthetic Group Project Presentation_20230920_011228_0000.pdf
PDF
manunath1-copy-170405123133 (1).pdf
PPT
environmental impact assessment
PPTX
349275491-EIA-Guidelines-in-Malaysia.pptx
PPTX
ENVIRONMENTAL IMPACT ACCESSMENT ( EIA) GUIDELINES IN MALAYSIA
PDF
RPN 2022 Manila: Session 3.7 Kathleen Mangune NEDA Philippines.pdf
PDF
20151013 ISO TC 67 at Offshore Energy 2015
PDF
ENVIRONMENTAL IMPACT Assessment, concepts, mitigation, EC
PPT
APR Workshop 2010-APR Performance-Maria Donnat
PDF
South africaprojectprojectproposal20151102
PPTX
Environmental impact assessment 2020
PPTX
EIA;- EC
PDF
Integrated Oil Field Development Plan - FDP. Criteria, strategy and process f...
PDF
Environmental Impact Evaluation of Mining
PDF
Aem 606 eia eac-b9-2
PDF
4. Myanmar's EIA Process
2. EIA Process Experience to Date - Htin Aung Kyaw
Environmental management
Kenya projectsummaryreport20181001
Smp2 part c action plan final
Beige and Brown Aesthetic Group Project Presentation_20230920_011228_0000.pdf
manunath1-copy-170405123133 (1).pdf
environmental impact assessment
349275491-EIA-Guidelines-in-Malaysia.pptx
ENVIRONMENTAL IMPACT ACCESSMENT ( EIA) GUIDELINES IN MALAYSIA
RPN 2022 Manila: Session 3.7 Kathleen Mangune NEDA Philippines.pdf
20151013 ISO TC 67 at Offshore Energy 2015
ENVIRONMENTAL IMPACT Assessment, concepts, mitigation, EC
APR Workshop 2010-APR Performance-Maria Donnat
South africaprojectprojectproposal20151102
Environmental impact assessment 2020
EIA;- EC
Integrated Oil Field Development Plan - FDP. Criteria, strategy and process f...
Environmental Impact Evaluation of Mining
Aem 606 eia eac-b9-2
4. Myanmar's EIA Process

More from Ethical Sector (20)

PDF
Verbit - The State of Inclusivity, A Global Perspective
PDF
Acoustic Protocol 2021
PPTX
Skillset
PDF
Labour Issues in the Telecom Sector: Myanmar Labour Laws and Reform Plans
PDF
Community Grievance Management Experiences
PDF
Community Outreach (SLO)
PDF
Workplace Safety in Telecom Industry
PDF
Health and Safety in Myanmar
PDF
Workshop on Safety and Labour Issues in the Myanmar Telecoms Sector
PDF
Virtual Roundtable Discussion with CSOs on Extractives and Inclusive Business
PPTX
AirQualityAsia
PPT
Health and Pollution Action Planning (HPAP)
PPT
HPAP - Health and Pollution Action Plan
PPTX
Dr. Dewi Aryani : Raising Awareness Towards Pollution and its Impact to Human...
PDF
How are Persons with Disabilities in Myanmar Experiencing Covid-19, Including...
PDF
Launch of the 2020 Pwint Thit Sa Report research phase
PDF
2020 Pwint Thit Sa - Webinar
PPTX
Business & Digital Rights (Myanmar Business Associations Status)
PPTX
4b steve crown mdrf 2020
PPTX
3e myanmar consumers u nion mdrf2020
Verbit - The State of Inclusivity, A Global Perspective
Acoustic Protocol 2021
Skillset
Labour Issues in the Telecom Sector: Myanmar Labour Laws and Reform Plans
Community Grievance Management Experiences
Community Outreach (SLO)
Workplace Safety in Telecom Industry
Health and Safety in Myanmar
Workshop on Safety and Labour Issues in the Myanmar Telecoms Sector
Virtual Roundtable Discussion with CSOs on Extractives and Inclusive Business
AirQualityAsia
Health and Pollution Action Planning (HPAP)
HPAP - Health and Pollution Action Plan
Dr. Dewi Aryani : Raising Awareness Towards Pollution and its Impact to Human...
How are Persons with Disabilities in Myanmar Experiencing Covid-19, Including...
Launch of the 2020 Pwint Thit Sa Report research phase
2020 Pwint Thit Sa - Webinar
Business & Digital Rights (Myanmar Business Associations Status)
4b steve crown mdrf 2020
3e myanmar consumers u nion mdrf2020

Recently uploaded (20)

PDF
Introducrion of creative nonfiction lesson 1
PPT
The Central Civil Services (Leave Travel Concession) Rules, 1988, govern the ...
PDF
AAAAAAAAAAAAAAAAAaaaaaaaAAAAAAAt - ĐV.pdf
PDF
CXPA Finland Webinar - Modern Components of Service Quality - Alec Dalton - ...
PPTX
Core Humanitarian Standard Presentation by Abraham Lebeza
PDF
eVerify Overview and Detailed Instructions to Set up an account
PPTX
Part I CSO Conference and AVP Overview.pptx
PDF
Concept_Note_-_GoAP_Primary_Sector_-_The_Great_Rural_Reset_-_Updated_18_June_...
PDF
Redefining Diplomacy: Françoise Joly on Navigating a Multipolar Order
PPTX
Water-Energy-Food (WEF) Nexus interventions, policy, and action in the MENA r...
PPTX
Reactivity of metals with oxygen, rusting.pptx
PDF
Building Bridges (of Hope) over Our Troubled Waters_PART 1
PPTX
20231018_SRP Tanzania_IRC2023 FAO side event.pptx
PDF
Item # 8 - 218 Primrose Place variance req.
PPTX
LUNG CANCER PREDICTION MODELING USING ARTIFICIAL NEURAL NETWORK.pptx
PPTX
Robotics_Presentation.pptxdhdrhdrrhdrhdrhdrrh
PPTX
Part II LGU Accreditation of CSOs and Selection of Reps to LSBs ver2.pptx
PDF
4_Key Concepts Structure and Governance plus UN.pdf okay
PPTX
International Tracking Project Unloading Guidance Manual V1 (1) 1.pptx
PPTX
SUKANYA SAMRIDDHI YOJANA RESEARCH REPORT AIMS OBJECTIVES ITS PROVISION AND IM...
Introducrion of creative nonfiction lesson 1
The Central Civil Services (Leave Travel Concession) Rules, 1988, govern the ...
AAAAAAAAAAAAAAAAAaaaaaaaAAAAAAAt - ĐV.pdf
CXPA Finland Webinar - Modern Components of Service Quality - Alec Dalton - ...
Core Humanitarian Standard Presentation by Abraham Lebeza
eVerify Overview and Detailed Instructions to Set up an account
Part I CSO Conference and AVP Overview.pptx
Concept_Note_-_GoAP_Primary_Sector_-_The_Great_Rural_Reset_-_Updated_18_June_...
Redefining Diplomacy: Françoise Joly on Navigating a Multipolar Order
Water-Energy-Food (WEF) Nexus interventions, policy, and action in the MENA r...
Reactivity of metals with oxygen, rusting.pptx
Building Bridges (of Hope) over Our Troubled Waters_PART 1
20231018_SRP Tanzania_IRC2023 FAO side event.pptx
Item # 8 - 218 Primrose Place variance req.
LUNG CANCER PREDICTION MODELING USING ARTIFICIAL NEURAL NETWORK.pptx
Robotics_Presentation.pptxdhdrhdrrhdrhdrhdrrh
Part II LGU Accreditation of CSOs and Selection of Reps to LSBs ver2.pptx
4_Key Concepts Structure and Governance plus UN.pdf okay
International Tracking Project Unloading Guidance Manual V1 (1) 1.pptx
SUKANYA SAMRIDDHI YOJANA RESEARCH REPORT AIMS OBJECTIVES ITS PROVISION AND IM...

Update on Implementation of the EIA Process and Remaining Challenges in Oil and Gas Sector

  • 1. Update on Implementation of the EIA process and Remaining Challenges in Oil and Gas Sector Mr. Sa Aung Thu Assistant Director Environmental Conservation Department Ministry of Natural Resources and Environmental Conservation 11 July 2016 Hilton, Nay Pyi Taw Offshore operations and the EIA: lessons learned from seismic IEEs, and next steps 22-25 September 2015
  • 2. Review process of IEE and EIA reports in EIA procedure
  • 3. EIA procedure, Annex (1) IEE EIA No EIA/IEE Screening Process on Oil and Gas Sector All sizes • Onshore Oil and Gas Seismic Surveys - All sizes • Onshore Oil and Gas Exploration Drillings - All sizes • Onshore Oil and Gas Production drilling and production activities; transportation activities including pipelines; pump stations, compressor stations and storage facilities; ancillary and support operations; and decommissioning All sizes - • Offshore Oil and Gas Seismic Surveys - All sizes • Offshore Oil and Gas Exploration Drillings - All sizes • Offshore Oil and Gas Production drilling and production activities; offshore pipeline operations, offshore transportation, compressor stations and storage facilities; ancillary and support operations; and decommissioning
  • 4. Reviewing IEE Report IEE Review and Approval Process for IEE & EIA report Initial and final reviewed by EIA Division under ECD Approved by MONREC Issued ECC by MONREC To Undertake EIA If required
  • 5. Reviewing EIA Scoping Report and ToR Reviewed by ECD Approved by ECD (15 Days) Review and Approval Process for IEE & EIA report (Cont’d) Scoping Report and ToR In accordance with Ministry Guidance
  • 6. Reviewing EIA Reports EIA Initial Reviewed by ECD Reviewed by Review Team (RT) Approved by MONREC( ECC) Issued ECC by MONREC Rejected by MONREC Appeal Project Termination Review and Approval Process for IEE & EIA report (Cont’d) No Yes Not Satisfactory Satisfactory
  • 7. 7 Time frame (IEE & EIA Review Process ) EIA Process Duration Screening Proposal (IEE/EIA/Non) 15 days IEE Process • IEE expert approval (Third party or not) 7 days • Preparing IEE Report ? • IEE Report approval 60 days EIA Process • EIA expert approval (Third party or not) 7 days • Developing Scoping Report and TOR ? • Scoping report &TOR approval 15 days • Investigation & Developing EIA Report ? • EIA report approval 90 days
  • 8. Background Information of EIA Review Team — EIA Report Review Team, consisting of 39 members from government agencies, i.e. MOECAF, 18 related ministries, attorney General Office and 3 civil Development committee of Yangon, Mandalay and Nay Pyi Taw, with a total of 39 members was formed, and the reviewing task was assigned by MOECAF with reference number-2/220/(B) (3)/ (8007/ 2013) dated 28-11-2013. — With MOECAF’s reference number-2/220/(B) (3)/(8008/ 2013) dated 28-11-2013, EIA report Review Team was also recruited into 4 sub-groups based on Land use Sector, Mining and Energy Sector, Urban and Construction Sector and Industry Sector respectively.
  • 9. Institutional Structure of EIA Review Team EIA review Team (39 members from 18 Ministries, Attorney General Office , NDC, YCDC and MCDC) RT Sub-group on Land use Sector (11 members) RT Sub-group on Mining and Energy Sector (8 members) + (6 members from other sectors) RT Sub-group on Urban and Construction Sector (15 members) RT Sub-group on Industry ( 9 members)
  • 10. Contents and Structure of IEE and EIA reports
  • 11. IEE Report 1. Executive Summary 2. Details of the project proponent 3. Description of the project 4. Legal requirements 5. Governing parameters 6. Summary of Impacts 7. Description of proposed mitigation measures 8. Monitoring Program 9. Reporting requirements 10. Responsibilities for mitigation and monitoring 11. Emergency Plan 12. Capacity development and training 13. Public consultation and information disclosure 14. Work plan and implementation schedule 15. Review of the EMP 16. Conclusion and Recommendation
  • 12. 1. Executive Summary 2. Introduction 3. Policy, Legal and Institutional Framework 4. Project Descriptions and Alternatives Selection (a) Project Background (b) Project Location (c) Comparison and Selection of the Alternatives (d) Description of the selected alternatives 5. Description of the Surrounding Environment (a) Setting the Study Limits (b) Methodology for data collection and analysis (c) Physical Components (d) Biological Components (e) Socio-Economic Components (f) Cultural Components (g) Visual Components EIA Report Format
  • 13. 6. Impact Assessment and Mitigation Measures (a) Impact Assessment Methodology and Approach (b) Scope of Assessment (c) Identification of Impacts (d) Determination of significance of those impacts (e) Mitigation Measures (f) Incorporation of mitigation measures into project design (g) Determination of any residual impacts 7. Risk Assessment 8. Cumulative Impact Assessment 9. Summary of Environmental Management Plan 10. Public Consultation and Disclosure 11. Conclusion and Recommendations EIA Report Format (Cont’d;)
  • 14. On-Shore Operation Off-shore Operation Grand Total EIA/ESHIA, SIA Total IEE EIA Scopi ng Monito ring Total SeismicSurveyand ExplorationDrilling Production 2D&3DSeismic Surrey 2D&3DSeismic Surrey Explorationdrilling Production ExplorationDrilling 3DSeismicSurvey 12 - 12 20 2 2 - 1 1 26 38 Current Status of IEE/ EIA/ Scoping and Monitoring Reports from Onshore and Offshore Operations Received by ECD ( 12-10- 2013 to 30-6-2016) Source: NR & EIA division, ECD, July 2016
  • 15. On-shore Operation Off-shore Operation Total EIA IEE EIA Scoping Monitoring InProgress InitialReview ReviewTeam Meeting Approved InProgress InitialComment Approved InProgress Inprogress InitialComment Inprogress InitialComment 7 2 3 - 4 11 7 2* 1 - 1 - 38 Current Status of IEE/ EIA/ Scoping and Monitoring Reports from Onshore and Offshore Operations Reviewed by ECD ( 12-10- 2013 to 30-6-2016) * 2 EIA reports for Seismic Survey - To continue issuing ECC for approved IEE reports on Offshore Seismic Campaign Source: NR & EIA division, ECD, July 2016
  • 16. Seismic Operation (2D &3D) Exploration Drilling Total IEE Report (22) EIA Monit oring EIA Report (2) Scoping InProgress InitialComment Approved InProgress InProgress InProgress InitialReview ReviewTeam Meeting Approved InProgress 4 11 7 2* 1 - 2 - - 1 26+2* Current Status of IEE/ EIA, Scoping and Monitoring Reports from Only Offshore Operation Reviewed by ECD ( 12-10- 2013 to 30-6-2016) * 2 EIA reports for Seismic Survey - To continue issuing ECC for approved IEE reports on Offshore Seismic Campaign Source: NR & EIA division, ECD, July 2016
  • 17. Director (1) + (11) Natural Resources Conservation and EIA Division Deputy Director (-) Deputy Director General Director General Current Institutional Structure of Natural Resources Conservation and EIA Division Natural Resources Conservation Sub-Division (3) EIA Sub-Division (8) Assistant Director -EIA Unit (1) Urban, Construction and Industry sector Assistant Director -EIA Unit (2) Land Use, Mining and Energy Sector Staff Officer (1) (Energy & Land use Sector) Staff Officer (1) (Mining Sector) Deputy Staff Officer (1) Staff Officer (1) (Urban & Construction Sector) Staff Officer (1) ( Industry Sector) Deputy Staff Officer (1)
  • 18. Remaining Challenges for ECD Ø Influx of Reports from various sectors Ø Lack of Sectoral Guidelines for Reviewing (Oil and Gas Review Guidelines) Ø ECD has to take full responsibility for approval of IEE reports. (26/38 mentioned in previous slide) Ø Limited Staff and Capacity (HQ and Regional/ States) Ø EIA Staff assigned by Ministry to take responsibilities rather than Review Work. Ø Urgent need of ECC guidelines Ø No experts in oil and gas sector
  • 19. Ø EIA review process is quite new to RT. Ø Lack of Review Framework and specific sectoral guidelines for oil and gas sector Ø Cannot pay full attention to review work as they have their own work Ø Cannot fully participate in the whole review process of EIA report of a project Ø Responsible to review EIA reports coming from various sectors rather than specific oil and gas sector. Remaining Challenges for Review Team (RT)
  • 20. Current Efforts to tackle Remaining Challenges Ø General EIA Review and ECC Guidelines under preparation with ADB technical assistance Ø Final draft of Oil and Gas Sectoral Guidelines with NEA technical assistance Ø Review Checklists under preparation with JICA technical assistance Ø Capacity Building (Clinical Training, Field Trips, Workshops and Meetings, etc) Ø Recruited only 12 staffs for reviewing purpose
  • 21. Current Efforts to tackle Remaining Challenges (Cont’d) Ø Planning to recruit 20 Government experts from 20 relevant Ministries Ø Cooperation with local professionals for reviewing EA reports Ø Already Recruited and Assigned EIA staffs for reviewing specific sectors (For Oil and Gas sector – 4 staffs only) (not including 12 new staffs)
  • 22. Ways Forward Ø To seek technical and financial assistances from Development Partners Ø To issue ECC (ADB) Ø To establish Environmental Management Fund (UNDP) Ø To issue guidelines for oil and gas sector(NEA) Ø To issue general review guidelines (ADB) Ø To develop sectoral checklists (JICA)
  • 23. Contact Information — Contact Person: Dr. San Oo (Director) Ms. Sa Aung Thu( Assistant Director) — Contact Phone/Fax: 067- 431329 (Office) — Contact Email: — NR & EIA Division (office) nreia.env@gmail.com — Mr. Sa Aung Thu (AD) 2012saungthu@gmail.com — Relevant Information is available at ECD website (www.ecd.gov.mm)
  • 24. Thank You Very Much For Your Kind Attention!