Try to have a reason…




1       CXO Advisor © Client distribution only
… for taking business decisions.




2            CXO Advisor © Client distribution only
CXO Advisor
       Accelerated business decisions

        2nd Annual IT Infrastructure Summit


Getting difficult IT infrastructure projects
 approved without depending on ROI



   3
Framing the topic
     Why ROI is usually inappropriate for justifying IT projects
     How to achieve alignment with business for all IT projects
     How to get infrastructure projects approved without once
     referring to ROI
     What benefits to consider when implementing infrastructure
     projects
     How to govern projects from idea, through execution, to
     achieving the value intended




              4
ROI is the only way to evaluate the value of
projects?
     What about compliance?          Does nothing for your bottom
                                     line (but it does keep you in
                                     business).
     What about that network         What’s the ROI on a more
     upgrade?                        stable, functionally rich
                                     network?
     What about the speculative      Just call it ‘strategic’ and hope
     project that could change the   for the best?
     industry?

     What about the gorilla in the   Do we fund someone’s ego?
     corner who just wants it
     because he wants it?

              5
RETHINKING PROJECT JUSTIFICATION




  6
Background
     For seven years we have been using the Three Role Model to
     help businesses:
      Budget
      Understand their project investment portfolio
      Prioritise their project investments to achieve maximum utility for the
       business



     This presentation will take you through how the Three Role
     Model works and how initiatives in your portfolio can be
     prioritised using the concept of utility
      For budgeting and project investment portfolio management we have
       other presentations




               7
THE THREE ROLE MODEL IN BUSINESS




  8
Porter’s value chain - sample

                        Strategy / Leadership / Innovation

                                 Manufacture
        Gain          Process                               Collect
                                  / Deliver    Distribute
      Customers       orders                                payment
                                   service


                                   Finance & Admin
                                Human Resources
                                       IT
                                Supply chain
                                  Legal




                  9
Porter’s value chain and three business roles

                          Strategy / Leadership / Innovation

                                   Manufacture
         Gain           Process                               Collect
                                    / Deliver    Distribute
       Customers        orders                                payment
                                     service


                                     Finance & Admin
                                  Human Resources
                                         IT
                                  Supply chain
                                    Legal



   Generally then…



                                                       Shared and                        Strategy
                                                        support         Core business   Leadership
                                                        services                        Innovation




                   10
Keep up the momentum
Business Performance




                                                                                 Business Momentum

                       Mass = staff, branches, geography etc.
                       Speed = how fast and how dependent on continuity
                       Direction = vision, mission, objectives
                                                                            Delivering on your
                                                                     promise / value proposition




                               11
Apply three roles to business performance

                               Shared and       Core business    Strategy
                             support services                   Leadership
                                                                Innovation
      Business Perforamcne




                                                                             Momentum
                                                                             line




                                12
Add five layers or rationales

                                Shared and       Core business    Strategy
                              support services                   Leadership
                                                                 Innovation

                                                                               May do
       Business Perforamcne




                                                                               Can do


                                                                              Should do
                                                                                   Momentum
                                                                                   line
                                                                              Must do



                                                                               Doing




                                 13
Different business drivers per layer

                                Shared and        Core business        Strategy
                              support services                        Leadership
                                                                      Innovation
                              Provide support     Differentiate       Change the
                                                                                      Differentiate
       Business Perforamcne



                                differently       the business       environment

                                 Improve          Improve core        Change the
                                                                                      Improve
                              support services      business           strategy

                                Service the      Service business
                                                                    Looming threats   Service
                              support engine         growth
                                                                                            Momentum
                                                                                            line
                                                   Respond to          Missing /
                                Regulation                                            Fix
                                                 external forces        broken



                              Support engine     Business engine     S L I Engine     Delivery




                                 14
Different reasons for investing in each layer

                                Shared and              Core business      Strategy
                              support services                            Leadership
                                                                          Innovation
                              Provide support Game changer / PoA / Time toChange the
                                                    Differentiate          market              Differentiate
       Business Perforamcne



                                differently         the business         environment

                                 Improve                Improve core            Change the
                                                           ROI / Risk / PoA                    Improve
                              support services            business               strategy

                                Service the          Service business
                                           NPV vs. risk / baseline performance / urgency
                              support engine              growth
                                                                          Looming threats      Service
                                                                                                     Momentum
                                                                                                     line
                                                         Respond to time         Missing /
                                Regulation                   Risk and                          Fix
                                                       external forces            broken



                              Support engine     Cost /Business engine quality equation
                                                        Risk / Service          S L I Engine   Delivery




                                 15
Different measures of success per class of investment

                               Shared and                 Core business           Strategy
                             support services                                    Leadership
                                                                                 Innovation
                                 Outsource                    PoA                  Vision
                                                              LoB                                 Differentiate
      Business Perforamcne


                                 Automate                  ROI > 100%           Game changer

                             •   PoA                  •                     •    Strategic risk
                             •   Capabilities              ROI > IRR        •    Hit rates        Improve

                             •   Sustainability       •    Breakeven        •    Threat
                             •   Efficiency           •    Benchmark             mitigation       Service
                                                                                                        Momentum
                                                                                                        line
                             •   Legality         •       Risk              • Linkages
                             •   Time             •       Time Efficiency   • Short term risk     Fix

                             •   Historical
                                                      •    TCO              •    Innovation
                                 CVA
                                                      •    CVA                   engine
                             •   Ongoing                                                          Delivery
                                 Benefits             •    Quality          •    Strategy
                                                      •    Risk                  execution
                             •   TCO



                                 16
MANAGING PORTFOLIO PRIORITIES




 17
Choosing which projects to do


                                                                                                                                                        Cost
                                                                                                                                                        Return
                        Cost / Return



How do we choose initiatives
that align with business
strategy / objectives?




                                                                                                                                                 0


                                                                                                                                                              1
                                            1



                                                         2


                                                                      3




                                                                                                5


                                                                                                        t6



                                                                                                                      7


                                                                                                                              t8


                                                                                                                                       t9
                                                                                   4




                                                                                                                                                   1


                                                                                                                                                                1
                                         ct



                                                      ct


                                                                   ct


                                                                                ct


                                                                                             ct




                                                                                                                   ct




                                                                                                                                                ct


                                                                                                                                                             ct
                                                                                                     jec




                                                                                                                           jec


                                                                                                                                    jec
                                     o je



                                                  o je


                                                               o je


                                                                            o je


                                                                                          oje




                                                                                                                oje




                                                                                                                                            o je


                                                                                                                                                         o je
                                                                                                       o




                                                                                                                             o


                                                                                                                                      o
                                   Pr



                                                Pr


                                                             Pr


                                                                          Pr


                                                                                       Pr


                                                                                                    Pr


                                                                                                             Pr


                                                                                                                          Pr


                                                                                                                                   Pr


                                                                                                                                          Pr


                                                                                                                                                       Pr
                   18
Example of choosing which projects




           19
Can’t do all the projects
  Initiative               Name                                              Purpose                                   Cost (1000's)   Return ($)    ROI
 Project 1     Customer online             Allow customers to track orders, collaborate, co-source product innovations         9 500        30 100     217%
 Project 2     4 new depots                Open 4 new depots in rural areas                                                   16 342        27 004      65%
 Project 3     Performance management      Introduce new staff performance management based on balanced scorecard              3 564        13 860     289%
 Project 4     Automate transfer pricing   Automate transfer pricing across the value chain                                    1 996         1 760     -12%
 Project 5     Payroll / Time&Attendance   New payroll system with time & attendance. Staff tracking via RFID                 12 030        14 000      16%
 Project 6     Factory 2020                Look at what ICT can do to modernise our factories (Impact study)                   2 000         1 000     -50%
 Project 7     Move call centre            Call centre premises too small - move from Head Office to own site                  8 955        11 194      25%
 Project 8     Refresh desktops            All desktops (3000) to be upgraded - current warrantees lapse in 6 months          20 000        10 000     -50%
 Project 9     Network upgrade             Upgrade our network to accommodate business growth. MPLS                           13 245         2 000     -85%
 Project 10    Poppi                       Comply with protection of private and personal information act by Jan              13 300        -7 500    -156%
                                                                                                                             100 932       103 418       2%




                                 Net cost 101m; Net Return 103m; Net ROI 2%




                                   20
Choose all projects with ROI > 20%
  Initiative               Name                                               Purpose                                  Cost (1000's)   Return ($)    ROI
 Project 1     Customer online             Allow customers to track orders, collaborate, co-source product innovations         9 500        30 100     217%
 Project 2     4 new depots                Open 4 new depots in rural areas                                                   16 342        27 004      65%
 Project 3     Performance management      Introduce new staff performance management based on balanced scorecard              3 564        13 860     289%
 Project 4     Automate transfer pricing   Automate transfer pricing across the value chain                                    1 996         1 760     -12%
 Project 5     Payroll / Time&Attendance   New payroll system with time & attendance. Staff tracking via RFID                 12 030        14 000      16%
 Project 6     Factory 2020                Look at what ICT can do to modernise our factories (Impact study)                   2 000         1 000     -50%
 Project 7     Move call centre            Call centre premises too small - move from Head Office to own site                  8 955        11 194      25%
 Project 8     Refresh desktops            All desktops (3000) to be upgraded - current warrantees lapse in 6 months          20 000        10 000     -50%
 Project 9     Network upgrade             Upgrade our network to accommodate business growth. MPLS                           13 245         2 000     -85%
 Project 10    Poppi                       Comply with protection of private and personal information act by Jan              13 300        -7 500    -156%
                                                                                                                             100 932       103 418       2%



                                                                                                       Cost (1000's)   Return ($)    ROI
                                                                    Cost / Return (Projects 1,2,3,7)          38 361        82 158    114%
                                                              Cost / Return (Projects 4, 5,6,8,9,10)          62 571        21 260     -66%
                                                                                        All projects         100 932       103 418       2%




                                   21
But…

 What about?
     Automated transfer pricing     There is a lot of noise from powerful people
     The payroll system             We need time and attendance
     Factory 2020                   Don’t we have a strategy to be innovative?
     Desktop refresh                The warrantees are running out
     Network upgrade                Can’t open 4 new depots without it
     Poppi                          It’s the law




 The dilemma
   Can’t afford to do it all
   Can’t not do some that don’t cross the ROI hurdle


                  22
Need a new way of prioritising

    Use the Three Role Model (3RM) to classify projects
    Decide what utility we want from projects based on our
    strategic intent
    Weight 3RM classes utility according to strategic intent
    Define utility contribution per project
    Match projects to their classes
    Score projects according to the class weights
    Prioritise based on utility score




              23
The portfolio tracks all possible initiatives
 Initiative                  Name                                             Purpose
Project 1     Customer online             Allow customers to track orders, collaborate, co-source product innovations   1
Project 2     4 new depots                Open 4 new depots in rural areas                                              2
Project 3     Performance management      Introduce new staff performance management based on balanced scorecard        3
Project 4     Automate transfer pricing   Automate transfer pricing across the value chain                              4
Project 5     Payroll / Time&Attendance   New payroll system with time & attendance. Staff tracking via RFID            5
Project 6     Factory 2020                Look at what ICT can do to modernise our factories                            6
Project 7     Move call centre            Call centre premises too small - move from Head Office to own site            7
Project 8     Refresh desktops            All desktops (3000) to be upgraded - current warrantees lapse in 6 months     8
Project 9     Network upgrade             Upgrade our network to accommodate business growth. MPLS                      9
Project 10    Poppi                       Comply with protection of private and personal information act by Jan         10

                                                         Initiative Portfolio




                                    24
Decide what utility we want based on our strategy
     Strategy: Profitable, fast moving, innovative, customer
     focused

     Utility factors

     Return on investment
     Risk
     Time to market
     Paths of action
     Customer focus


                        Strategically aligned utility factors
                            ROI Risk Time PoA Cust



                25
Weight 3RM classes utility according to strategic intent


                            ROI Risk Time PoA Cust




           40 20 10 20 10      35 5   0 20 40        50 0 15 20 15


           30 30 10 20 10      40 20 10 10 20        20 10 20 20 30


           10 40 20 20 10      20 30 15 5 20         10 30 30 10 20


           0 50 30 0 20        0 50 20 0 30          0 40 50 10 0




              26
Define utility contribution per project




            27
Estimating the utility contribution per initiative
                                      Initiative
                   Initiative       contribution             Class utility       Initiative        Init.
 Initiative ID        Class             (0 - 5)                 rules              score          Utility
  1: Customer
     online          Bus I      5    1    2   4    5   x   40 20 10 10 20    40 4    4   8 20     76%
  2: Four New
     Depots         Bus S       3    2    3   1    4   x   20 30 15 5 20     12 12 9 10 16        59%
 3: Performance
       Mgt            SS I      5    2    2   2    3   x   30 30 10 20 10    30 12 4     8    6   60%
  4: Auto Xfer
     pricing         Bus I      0    2    1   1    0   x   40 20 10 10 20    0   8   2   2    0   12%
5: Payroll / T&A      SS S      1    1    3   2    0   x   10 40 20 20 10    2   8 12 8       0   30%
 6: Factory 2000     SLI I      0    0    1   5    2   x   20 10 20 20 30    0   0   4 20 12      36%
 7: Call Centre     Bus S       2    3    5   1    3   x   20 30 15 5 20     8 18 15 10 12        63%
   8: Refresh
    desktops           SS S     0    4    4   1    0
                                                       x   10 40 20 20 10    0 32 16 4        0   52%
   9: Network
    upgrade            SS S     0    4    4   3    2
                                                       x   10 40 20 20 10    0 32 16 12 4         64%
    10: Poppi        Bus X      0     5   5   2    0   x   0 50 20 0 30      0 50 20 0        0
                                                                                                  70%

                         28
Some clarification
                                      Initiative
                   Initiative       contribution             Class utility       Initiative        Init.
 Initiative ID        Class             (0 - 5)                 rules              score          Utility
 1: Customer
    online           Bus I      5    1    2   4    5   x   40 20 10 10 20    40 4    4   8 20     76%
 2: Four New
    Depots          Bus S       3    2    3   1    4   x   20 30 15 5 20     12 12 9 10 16        59%
3: Performance
      Mgt             SS I      5    2    2   2    3   x   30 30 10 20 10    30 12 4     8    6   60%
 4: Auto Xfer
    pricing          Bus I      0    2    1   1    0   x   40 20 10 10 20    0   8   2   2    0   12%
5: Payroll / T&A      SS S      1    1    3   2    0   x   10 40 20 20 10    2   8 12 8       0   30%
6: Factory 2000      SLI I      0    0    1   5    2   x   20 10 20 20 30    0   0   4 20 12      36%
 7: Call Centre     Bus S       2    3    5   1    3   x   20 30 15 5 20     8 18 15 10 12        63%
   8: Refresh
    desktops           SS S     0    4    4   1    0
                                                       x   10 40 20 20 10    0 32 16 4        0   52%
   9: Network
    upgrade            SS S     0    4    4   3    2
                                                       x   10 40 20 20 10    0 32 16 12 4         64%
    10: Poppi        Bus X      0     5   5   2    0   x   0 50 20 0 30      0 50 20 0        0
                                                                                                  70%

                         29
The new order…
                                         Utility           Cumulative               Cumulative Cumulative
Initiative                Name           Score       Cost    Cost       Return        Return      ROI
Project 1    Customer online                  76%    9 500      9 500      30 100        30 100      217%
Project 10   Poppi                            70%   13 300     22 800      -7 500        22 600        -1%
Project 9    Network upgrade                  64%   13 245     36 045       2 000        24 600       -32%
Project 7    Move call centre                 63%    8 955     45 000      11 194        35 794       -20%
Project 3    Performance management           60%    3 564     48 564      13 860        49 654         2%
Project 2    4 new depots                     59%   16 342     64 906      27 004        76 658        18%
Project 8    Refresh desktops                 52%   20 000     84 906      10 000        86 658         2%
Project 6    Factory 2020                     36%    2 000     86 906       1 000        87 658         1%
Project 5    Payroll / Time&Attendance        30%   12 030     98 936      14 000       101 658         3%
Project 4    Automate transfer pricing        12%    1 996    100 932       1 760       103 418         2%




                         30
If we can afford only $50 million…
                                          Utility           Cumulative               Cumulative Cumulative
 Initiative                Name           Score       Cost    Cost       Return        Return      ROI
 Project 1    Customer online                  76%    9 500      9 500      30 100        30 100      217%
 Project 10   Poppi                            70%   13 300     22 800      -7 500        22 600        -1%
 Project 9    Network upgrade                  64%   13 245     36 045       2 000        24 600       -32%
 Project 7    Move call centre                 63%    8 955     45 000      11 194        35 794       -20%
 Project 3    Performance management           60%    3 564     48 564      13 860        49 654         2%
 Project 2    4 new depots                     59%   16 342     64 906      27 004        76 658        18%
 Project 8    Refresh desktops                 52%   20 000     84 906      10 000        86 658         2%
 Project 6    Factory 2020                     36%    2 000     86 906       1 000        87 658         1%
 Project 5    Payroll / Time&Attendance        30%   12 030     98 936      14 000       101 658         3%
 Project 4    Automate transfer pricing        12%    1 996    100 932       1 760       103 418         2%




                          31
But if we want to service business growth…
                                          Utility           Cumulative               Cumulative Cumulative
 Initiative                Name           Score       Cost    Cost       Return        Return      ROI
 Project 1    Customer online                  76%    9 500      9 500      30 100        30 100      217%
 Project 10   Poppi                            70%   13 300     22 800      -7 500        22 600        -1%
 Project 9    Network upgrade                  64%   13 245     36 045       2 000        24 600       -32%
 Project 7    Move call centre                 63%    8 955     45 000      11 194        35 794       -20%
 Project 3    Performance management           60%    3 564     48 564      13 860        49 654         2%
 Project 2    4 new depots                     59%   16 342     64 906      27 004        76 658        18%
 Project 8    Refresh desktops                 52%   20 000     84 906      10 000        86 658         2%
 Project 6    Factory 2020                     36%    2 000     86 906       1 000        87 658         1%
 Project 5    Payroll / Time&Attendance        30%   12 030     98 936      14 000       101 658         3%
 Project 4    Automate transfer pricing        12%    1 996    100 932       1 760       103 418         2%




                          32
What benefits should we be chasing / tracking?
                                     Initiative
                  Initiative       contribution             Class utility      Initiative        Init.
 Initiative ID       Class             (0 - 5)                 rules             score          Utility
 1: Customer
    online          Bus I      5    1    2   4    5   x   40 20 10 10 20    40 4   4   8 20     76%
 2: Four New
    Depots         Bus S       3    2    3   1    4   x   20 30 15 5 20     12 12 9 10 16       59%
3: Performance
      Mgt            SS I      5    2    2   2    3   x   30 30 10 20 10    30 12 4    8    6   60%




 7: Call Centre    Bus S       2    3    5   1    3   x   20 30 15 5 20     8 18 15 10 12       63%


   9: Network
    upgrade           SS S     0    4    4   3    2
                                                      x   10 40 20 20 10    0 32 16 12 4        64%
    10: Poppi       Bus X      0     5   5   2    0   x   0 50 20 0 30      0 50 20 0       0
                                                                                                70%

                        33
IT adds value at different stages

            Plan                           Build                                  Run                             Retire
   Meaning         Attention                                                      Operate

     Idea          Test the       Design and       Implement       Early          Majority         Maturity
                   idea           build                            adoption       adoption

                                                                                                   Un-lockable
                                                                                                     Value

                                                                     Tangible
                                                                      Value
                                                                                   Tangible
                                                                                    Value            Tangible
                                                       Value                                          Value
                                    Value             potential     Intangible
                                   potential                          Value
                                                                                   Intangible
                     Value                                                           Value
     Value                                                                                          Intangible    Cost-cut
                    potential
    potential                                                                                         Value        Value

                                                                                        Value preservation



                                  Monthly cost

                                                    Monthly cost
                                                                   Monthly cost                                     Cost
                   Monthly cost                                                   Monthly cost     Monthly cost
      Cost
       1                2              3                  4             5               6                7           8


                            34
What business currently sees of IT value-add potential

            Plan                              Build                                     Run                              Retire
   Meaning         Attention                                                            Operate

     Idea          Test the           Design and      Implement       Early             Majority          Maturity
                   idea               build                           adoption          adoption

                                                                                                          Un-lockable
                                                                                                            Value
                                                                        Tangible
                                                                         Value
                                Invest-                                                     Tangible
                                 ment                                                        Value         Tangible
                               approval                  Value                                              Value
                                       Value            potential      Intangible
                                      potential                          Value
                                                                                            Intangible
                     Value                                                                    Value
     Value                                                                                                 Intangible    Cost-cut
                    potential
    potential                                                                                                Value        Value

                                                                                               Value preservation

                                                                                 IT Costs
                                     Monthly cost

                                                       Monthly cost
                                                                      Monthly cost                                         Cost
                   Monthly cost                                                         Monthly cost      Monthly cost
      Cost
       1                2                 3                 4              5                    6               7           8


                            35
In summary
    Utility trumps ROI and cost
    Utility rules per class set business expectations and improve
    understanding
    Initiatives are not projects until they are budgeted for
    You set your project budget by scoring the utility contribution
    per initiative and multiply by the utility rule for the class of
    initiative
    Initiatives that don’t make the cut, stay in the initiative
    portfolio
    Benefits realisation plans revolve around expected utility
    Alignment to business priorities and strategy is a given




           36
THANK YOU

• Terry White: (082 537 3887) terryw@cxo-advisor.co.za

More Related Content

PDF
MEGA Webinar - PwC - Baker/Tong - EA & GRC, Separated at Birth
PDF
Custom Overview
PPT
Stand and deliver bpm v4
PDF
Seven Secrets Of Tapping Into The Power Of Your People
PPTX
Sample 3yr Vision Roadmap
PDF
Leadership map by Mr Sudhakar Rao at HRRT organised by ISPE & UPES Dehradun
PPTX
Presentatie capgemini academy v10 eng
PPTX
Introduction to resources
MEGA Webinar - PwC - Baker/Tong - EA & GRC, Separated at Birth
Custom Overview
Stand and deliver bpm v4
Seven Secrets Of Tapping Into The Power Of Your People
Sample 3yr Vision Roadmap
Leadership map by Mr Sudhakar Rao at HRRT organised by ISPE & UPES Dehradun
Presentatie capgemini academy v10 eng
Introduction to resources

What's hot (18)

PPTX
HROplus presentation - Why Outsource HR?
PDF
Tips For Successful Consultant Collaboration
PDF
JD Edwards & Peoplesoft 3 _ Linda Hemsworth _ PeopleSoft HCM 9.1 Achieving Ta...
PDF
Jill M. Powers Resume
PDF
SNX 7AE88A38-45E7-4B82-BFFB-3404FD8027A5_SNX012709
PDF
Understanding Social Business Excellence - Enterprise2.0Summit 2012, Paris
PDF
Excellence in customer experience
PPTX
Enterprise architecture in transformation
PPTX
Mand a toolkit pmi theory
PDF
Lean Enterprise Initiative
PDF
Kibel Green Intro2010
PDF
BDO Payroll Services Brochure
PPT
Transformance for high performance
PPTX
Northwestern Mutual Case Study
PDF
Octo Consulting Group Corporate Capabilities Briefing Slide Share
PDF
Call Me Overview
PDF
Key Steps For Planning A Successful Business Intelligence Dashboard Project
PPT
Kelly slide show ppt adjusted
HROplus presentation - Why Outsource HR?
Tips For Successful Consultant Collaboration
JD Edwards & Peoplesoft 3 _ Linda Hemsworth _ PeopleSoft HCM 9.1 Achieving Ta...
Jill M. Powers Resume
SNX 7AE88A38-45E7-4B82-BFFB-3404FD8027A5_SNX012709
Understanding Social Business Excellence - Enterprise2.0Summit 2012, Paris
Excellence in customer experience
Enterprise architecture in transformation
Mand a toolkit pmi theory
Lean Enterprise Initiative
Kibel Green Intro2010
BDO Payroll Services Brochure
Transformance for high performance
Northwestern Mutual Case Study
Octo Consulting Group Corporate Capabilities Briefing Slide Share
Call Me Overview
Key Steps For Planning A Successful Business Intelligence Dashboard Project
Kelly slide show ppt adjusted
Ad

Viewers also liked (9)

PPT
Introduction To Double Positive Education Live Transfer Platform
PPS
Cost Reduction in the Call Center
PPT
How to Reduce Costs in a Call Center
PPTX
Operating cost analysis of BPO Sector
PPTX
Rod Jones MasterClass - World Class Call Centres - The Key Strategic Issues -...
PDF
Reducing BPO Costs
PPTX
Call Center Management & KPI Metrics
PPTX
presentation on responsibility accounting
PPT
Cost Reduction Strategies:Focus and Techniques
Introduction To Double Positive Education Live Transfer Platform
Cost Reduction in the Call Center
How to Reduce Costs in a Call Center
Operating cost analysis of BPO Sector
Rod Jones MasterClass - World Class Call Centres - The Key Strategic Issues -...
Reducing BPO Costs
Call Center Management & KPI Metrics
presentation on responsibility accounting
Cost Reduction Strategies:Focus and Techniques
Ad

Similar to Utility based portfolio prioritisation (20)

PDF
InCeBE Solutions
PDF
Business Perfection Brochure
PDF
Tenedo english presentation
PDF
Building the Agile Enterprise
PDF
Intelligent Sales & Risk Performance Management Cognos Pb Map Info2008
PPTX
Cxo Advisor Customer Value Prop 2013
PDF
Making Architecture Business Value Driven
PDF
20090901 London Enterprise Session V3 Colour
PPTX
Microsoft Dynamics Academic Alliance: Job Roles
PDF
Praxes Group Capabilities Overview
PPT
Risk management competency dictionary0
PDF
Enterprise analysis – the dark domain
PPTX
Business 2.0
PDF
1513 Driving Sap Value With It Bus Partnership
PPTX
Introduction to Business Beam
PPT
Process Innovation for 2012
PDF
Innovation And It Alignment 121510 Abbreviated
PPT
Best online cloud system for businesses
PDF
Connect2Consult Corporate Profile
PDF
Presentation: Enterprise Architecture design In 3 Minutes or so
InCeBE Solutions
Business Perfection Brochure
Tenedo english presentation
Building the Agile Enterprise
Intelligent Sales & Risk Performance Management Cognos Pb Map Info2008
Cxo Advisor Customer Value Prop 2013
Making Architecture Business Value Driven
20090901 London Enterprise Session V3 Colour
Microsoft Dynamics Academic Alliance: Job Roles
Praxes Group Capabilities Overview
Risk management competency dictionary0
Enterprise analysis – the dark domain
Business 2.0
1513 Driving Sap Value With It Bus Partnership
Introduction to Business Beam
Process Innovation for 2012
Innovation And It Alignment 121510 Abbreviated
Best online cloud system for businesses
Connect2Consult Corporate Profile
Presentation: Enterprise Architecture design In 3 Minutes or so

More from Exo Futures (20)

PDF
Revolutionizing Impact Investing Through Blockchain Integration (3).pdf
PDF
Exo Futures - Exponential Possibilities Exo V2.pdf
PDF
Exo futures abundant exponentiality
PPSX
Digital Transformation Profile
PDF
Why digital means disrupt or die
PPTX
Digital disruption 2016
PDF
Ande entrepreneur ecosystem map 2015
PPSX
Innovation with Rapid Application Delivery
PPSX
Present to-future-creation
PPSX
Present to-nmmu-propella
PDF
Leveraging the-digital-future
PPSX
2016 cxo outsystems jvp 4.5
PPTX
Continuous delivery
PPTX
What is ? Modern business questions 2014
PPSX
The future of innovation - meeting increasing business expectations, rapid in...
PPTX
Customisable Agile readiness assessment
PPTX
Focus on innovation for customer centricity
PDF
Out systems for procurement outpartner value proposition
PPTX
Cxo advisor agile business pitch 2.5
PPTX
Cxo advisor getting more from your cfo
Revolutionizing Impact Investing Through Blockchain Integration (3).pdf
Exo Futures - Exponential Possibilities Exo V2.pdf
Exo futures abundant exponentiality
Digital Transformation Profile
Why digital means disrupt or die
Digital disruption 2016
Ande entrepreneur ecosystem map 2015
Innovation with Rapid Application Delivery
Present to-future-creation
Present to-nmmu-propella
Leveraging the-digital-future
2016 cxo outsystems jvp 4.5
Continuous delivery
What is ? Modern business questions 2014
The future of innovation - meeting increasing business expectations, rapid in...
Customisable Agile readiness assessment
Focus on innovation for customer centricity
Out systems for procurement outpartner value proposition
Cxo advisor agile business pitch 2.5
Cxo advisor getting more from your cfo

Recently uploaded (20)

PDF
Elevate Cleaning Efficiency Using Tallfly Hair Remover Roller Factory Expertise
PDF
20250805_A. Stotz All Weather Strategy - Performance review July 2025.pdf
DOCX
Business Management - unit 1 and 2
PPT
Data mining for business intelligence ch04 sharda
PPTX
The Marketing Journey - Tracey Phillips - Marketing Matters 7-2025.pptx
DOCX
Euro SEO Services 1st 3 General Updates.docx
PPTX
Amazon (Business Studies) management studies
PDF
BsN 7th Sem Course GridNNNNNNNN CCN.pdf
PDF
Katrina Stoneking: Shaking Up the Alcohol Beverage Industry
PDF
Nidhal Samdaie CV - International Business Consultant
PPTX
Lecture (1)-Introduction.pptx business communication
PDF
Reconciliation AND MEMORANDUM RECONCILATION
PPTX
Belch_12e_PPT_Ch18_Accessible_university.pptx
PDF
Types of control:Qualitative vs Quantitative
PDF
IFRS Notes in your pocket for study all the time
PDF
MSPs in 10 Words - Created by US MSP Network
PPTX
Dragon_Fruit_Cultivation_in Nepal ppt.pptx
PDF
A Brief Introduction About Julia Allison
PPT
Chapter four Project-Preparation material
PDF
Training And Development of Employee .pdf
Elevate Cleaning Efficiency Using Tallfly Hair Remover Roller Factory Expertise
20250805_A. Stotz All Weather Strategy - Performance review July 2025.pdf
Business Management - unit 1 and 2
Data mining for business intelligence ch04 sharda
The Marketing Journey - Tracey Phillips - Marketing Matters 7-2025.pptx
Euro SEO Services 1st 3 General Updates.docx
Amazon (Business Studies) management studies
BsN 7th Sem Course GridNNNNNNNN CCN.pdf
Katrina Stoneking: Shaking Up the Alcohol Beverage Industry
Nidhal Samdaie CV - International Business Consultant
Lecture (1)-Introduction.pptx business communication
Reconciliation AND MEMORANDUM RECONCILATION
Belch_12e_PPT_Ch18_Accessible_university.pptx
Types of control:Qualitative vs Quantitative
IFRS Notes in your pocket for study all the time
MSPs in 10 Words - Created by US MSP Network
Dragon_Fruit_Cultivation_in Nepal ppt.pptx
A Brief Introduction About Julia Allison
Chapter four Project-Preparation material
Training And Development of Employee .pdf

Utility based portfolio prioritisation

  • 1. Try to have a reason… 1 CXO Advisor © Client distribution only
  • 2. … for taking business decisions. 2 CXO Advisor © Client distribution only
  • 3. CXO Advisor Accelerated business decisions 2nd Annual IT Infrastructure Summit Getting difficult IT infrastructure projects approved without depending on ROI 3
  • 4. Framing the topic Why ROI is usually inappropriate for justifying IT projects How to achieve alignment with business for all IT projects How to get infrastructure projects approved without once referring to ROI What benefits to consider when implementing infrastructure projects How to govern projects from idea, through execution, to achieving the value intended 4
  • 5. ROI is the only way to evaluate the value of projects? What about compliance? Does nothing for your bottom line (but it does keep you in business). What about that network What’s the ROI on a more upgrade? stable, functionally rich network? What about the speculative Just call it ‘strategic’ and hope project that could change the for the best? industry? What about the gorilla in the Do we fund someone’s ego? corner who just wants it because he wants it? 5
  • 7. Background For seven years we have been using the Three Role Model to help businesses:  Budget  Understand their project investment portfolio  Prioritise their project investments to achieve maximum utility for the business This presentation will take you through how the Three Role Model works and how initiatives in your portfolio can be prioritised using the concept of utility  For budgeting and project investment portfolio management we have other presentations 7
  • 8. THE THREE ROLE MODEL IN BUSINESS 8
  • 9. Porter’s value chain - sample Strategy / Leadership / Innovation Manufacture Gain Process Collect / Deliver Distribute Customers orders payment service Finance & Admin Human Resources IT Supply chain Legal 9
  • 10. Porter’s value chain and three business roles Strategy / Leadership / Innovation Manufacture Gain Process Collect / Deliver Distribute Customers orders payment service Finance & Admin Human Resources IT Supply chain Legal Generally then… Shared and Strategy support Core business Leadership services Innovation 10
  • 11. Keep up the momentum Business Performance Business Momentum Mass = staff, branches, geography etc. Speed = how fast and how dependent on continuity Direction = vision, mission, objectives Delivering on your promise / value proposition 11
  • 12. Apply three roles to business performance Shared and Core business Strategy support services Leadership Innovation Business Perforamcne Momentum line 12
  • 13. Add five layers or rationales Shared and Core business Strategy support services Leadership Innovation May do Business Perforamcne Can do Should do Momentum line Must do Doing 13
  • 14. Different business drivers per layer Shared and Core business Strategy support services Leadership Innovation Provide support Differentiate Change the Differentiate Business Perforamcne differently the business environment Improve Improve core Change the Improve support services business strategy Service the Service business Looming threats Service support engine growth Momentum line Respond to Missing / Regulation Fix external forces broken Support engine Business engine S L I Engine Delivery 14
  • 15. Different reasons for investing in each layer Shared and Core business Strategy support services Leadership Innovation Provide support Game changer / PoA / Time toChange the Differentiate market Differentiate Business Perforamcne differently the business environment Improve Improve core Change the ROI / Risk / PoA Improve support services business strategy Service the Service business NPV vs. risk / baseline performance / urgency support engine growth Looming threats Service Momentum line Respond to time Missing / Regulation Risk and Fix external forces broken Support engine Cost /Business engine quality equation Risk / Service S L I Engine Delivery 15
  • 16. Different measures of success per class of investment Shared and Core business Strategy support services Leadership Innovation Outsource PoA Vision LoB Differentiate Business Perforamcne Automate ROI > 100% Game changer • PoA • • Strategic risk • Capabilities ROI > IRR • Hit rates Improve • Sustainability • Breakeven • Threat • Efficiency • Benchmark mitigation Service Momentum line • Legality • Risk • Linkages • Time • Time Efficiency • Short term risk Fix • Historical • TCO • Innovation CVA • CVA engine • Ongoing Delivery Benefits • Quality • Strategy • Risk execution • TCO 16
  • 18. Choosing which projects to do Cost Return Cost / Return How do we choose initiatives that align with business strategy / objectives? 0 1 1 2 3 5 t6 7 t8 t9 4 1 1 ct ct ct ct ct ct ct ct jec jec jec o je o je o je o je oje oje o je o je o o o Pr Pr Pr Pr Pr Pr Pr Pr Pr Pr Pr 18
  • 19. Example of choosing which projects 19
  • 20. Can’t do all the projects Initiative Name Purpose Cost (1000's) Return ($) ROI Project 1 Customer online Allow customers to track orders, collaborate, co-source product innovations 9 500 30 100 217% Project 2 4 new depots Open 4 new depots in rural areas 16 342 27 004 65% Project 3 Performance management Introduce new staff performance management based on balanced scorecard 3 564 13 860 289% Project 4 Automate transfer pricing Automate transfer pricing across the value chain 1 996 1 760 -12% Project 5 Payroll / Time&Attendance New payroll system with time & attendance. Staff tracking via RFID 12 030 14 000 16% Project 6 Factory 2020 Look at what ICT can do to modernise our factories (Impact study) 2 000 1 000 -50% Project 7 Move call centre Call centre premises too small - move from Head Office to own site 8 955 11 194 25% Project 8 Refresh desktops All desktops (3000) to be upgraded - current warrantees lapse in 6 months 20 000 10 000 -50% Project 9 Network upgrade Upgrade our network to accommodate business growth. MPLS 13 245 2 000 -85% Project 10 Poppi Comply with protection of private and personal information act by Jan 13 300 -7 500 -156% 100 932 103 418 2% Net cost 101m; Net Return 103m; Net ROI 2% 20
  • 21. Choose all projects with ROI > 20% Initiative Name Purpose Cost (1000's) Return ($) ROI Project 1 Customer online Allow customers to track orders, collaborate, co-source product innovations 9 500 30 100 217% Project 2 4 new depots Open 4 new depots in rural areas 16 342 27 004 65% Project 3 Performance management Introduce new staff performance management based on balanced scorecard 3 564 13 860 289% Project 4 Automate transfer pricing Automate transfer pricing across the value chain 1 996 1 760 -12% Project 5 Payroll / Time&Attendance New payroll system with time & attendance. Staff tracking via RFID 12 030 14 000 16% Project 6 Factory 2020 Look at what ICT can do to modernise our factories (Impact study) 2 000 1 000 -50% Project 7 Move call centre Call centre premises too small - move from Head Office to own site 8 955 11 194 25% Project 8 Refresh desktops All desktops (3000) to be upgraded - current warrantees lapse in 6 months 20 000 10 000 -50% Project 9 Network upgrade Upgrade our network to accommodate business growth. MPLS 13 245 2 000 -85% Project 10 Poppi Comply with protection of private and personal information act by Jan 13 300 -7 500 -156% 100 932 103 418 2% Cost (1000's) Return ($) ROI Cost / Return (Projects 1,2,3,7) 38 361 82 158 114% Cost / Return (Projects 4, 5,6,8,9,10) 62 571 21 260 -66% All projects 100 932 103 418 2% 21
  • 22. But… What about?  Automated transfer pricing There is a lot of noise from powerful people  The payroll system We need time and attendance  Factory 2020 Don’t we have a strategy to be innovative?  Desktop refresh The warrantees are running out  Network upgrade Can’t open 4 new depots without it  Poppi It’s the law The dilemma  Can’t afford to do it all  Can’t not do some that don’t cross the ROI hurdle 22
  • 23. Need a new way of prioritising Use the Three Role Model (3RM) to classify projects Decide what utility we want from projects based on our strategic intent Weight 3RM classes utility according to strategic intent Define utility contribution per project Match projects to their classes Score projects according to the class weights Prioritise based on utility score 23
  • 24. The portfolio tracks all possible initiatives Initiative Name Purpose Project 1 Customer online Allow customers to track orders, collaborate, co-source product innovations 1 Project 2 4 new depots Open 4 new depots in rural areas 2 Project 3 Performance management Introduce new staff performance management based on balanced scorecard 3 Project 4 Automate transfer pricing Automate transfer pricing across the value chain 4 Project 5 Payroll / Time&Attendance New payroll system with time & attendance. Staff tracking via RFID 5 Project 6 Factory 2020 Look at what ICT can do to modernise our factories 6 Project 7 Move call centre Call centre premises too small - move from Head Office to own site 7 Project 8 Refresh desktops All desktops (3000) to be upgraded - current warrantees lapse in 6 months 8 Project 9 Network upgrade Upgrade our network to accommodate business growth. MPLS 9 Project 10 Poppi Comply with protection of private and personal information act by Jan 10 Initiative Portfolio 24
  • 25. Decide what utility we want based on our strategy Strategy: Profitable, fast moving, innovative, customer focused Utility factors  Return on investment  Risk  Time to market  Paths of action  Customer focus Strategically aligned utility factors ROI Risk Time PoA Cust 25
  • 26. Weight 3RM classes utility according to strategic intent ROI Risk Time PoA Cust 40 20 10 20 10 35 5 0 20 40 50 0 15 20 15 30 30 10 20 10 40 20 10 10 20 20 10 20 20 30 10 40 20 20 10 20 30 15 5 20 10 30 30 10 20 0 50 30 0 20 0 50 20 0 30 0 40 50 10 0 26
  • 27. Define utility contribution per project 27
  • 28. Estimating the utility contribution per initiative Initiative Initiative contribution Class utility Initiative Init. Initiative ID Class (0 - 5) rules score Utility 1: Customer online Bus I 5 1 2 4 5 x 40 20 10 10 20 40 4 4 8 20 76% 2: Four New Depots Bus S 3 2 3 1 4 x 20 30 15 5 20 12 12 9 10 16 59% 3: Performance Mgt SS I 5 2 2 2 3 x 30 30 10 20 10 30 12 4 8 6 60% 4: Auto Xfer pricing Bus I 0 2 1 1 0 x 40 20 10 10 20 0 8 2 2 0 12% 5: Payroll / T&A SS S 1 1 3 2 0 x 10 40 20 20 10 2 8 12 8 0 30% 6: Factory 2000 SLI I 0 0 1 5 2 x 20 10 20 20 30 0 0 4 20 12 36% 7: Call Centre Bus S 2 3 5 1 3 x 20 30 15 5 20 8 18 15 10 12 63% 8: Refresh desktops SS S 0 4 4 1 0 x 10 40 20 20 10 0 32 16 4 0 52% 9: Network upgrade SS S 0 4 4 3 2 x 10 40 20 20 10 0 32 16 12 4 64% 10: Poppi Bus X 0 5 5 2 0 x 0 50 20 0 30 0 50 20 0 0 70% 28
  • 29. Some clarification Initiative Initiative contribution Class utility Initiative Init. Initiative ID Class (0 - 5) rules score Utility 1: Customer online Bus I 5 1 2 4 5 x 40 20 10 10 20 40 4 4 8 20 76% 2: Four New Depots Bus S 3 2 3 1 4 x 20 30 15 5 20 12 12 9 10 16 59% 3: Performance Mgt SS I 5 2 2 2 3 x 30 30 10 20 10 30 12 4 8 6 60% 4: Auto Xfer pricing Bus I 0 2 1 1 0 x 40 20 10 10 20 0 8 2 2 0 12% 5: Payroll / T&A SS S 1 1 3 2 0 x 10 40 20 20 10 2 8 12 8 0 30% 6: Factory 2000 SLI I 0 0 1 5 2 x 20 10 20 20 30 0 0 4 20 12 36% 7: Call Centre Bus S 2 3 5 1 3 x 20 30 15 5 20 8 18 15 10 12 63% 8: Refresh desktops SS S 0 4 4 1 0 x 10 40 20 20 10 0 32 16 4 0 52% 9: Network upgrade SS S 0 4 4 3 2 x 10 40 20 20 10 0 32 16 12 4 64% 10: Poppi Bus X 0 5 5 2 0 x 0 50 20 0 30 0 50 20 0 0 70% 29
  • 30. The new order… Utility Cumulative Cumulative Cumulative Initiative Name Score Cost Cost Return Return ROI Project 1 Customer online 76% 9 500 9 500 30 100 30 100 217% Project 10 Poppi 70% 13 300 22 800 -7 500 22 600 -1% Project 9 Network upgrade 64% 13 245 36 045 2 000 24 600 -32% Project 7 Move call centre 63% 8 955 45 000 11 194 35 794 -20% Project 3 Performance management 60% 3 564 48 564 13 860 49 654 2% Project 2 4 new depots 59% 16 342 64 906 27 004 76 658 18% Project 8 Refresh desktops 52% 20 000 84 906 10 000 86 658 2% Project 6 Factory 2020 36% 2 000 86 906 1 000 87 658 1% Project 5 Payroll / Time&Attendance 30% 12 030 98 936 14 000 101 658 3% Project 4 Automate transfer pricing 12% 1 996 100 932 1 760 103 418 2% 30
  • 31. If we can afford only $50 million… Utility Cumulative Cumulative Cumulative Initiative Name Score Cost Cost Return Return ROI Project 1 Customer online 76% 9 500 9 500 30 100 30 100 217% Project 10 Poppi 70% 13 300 22 800 -7 500 22 600 -1% Project 9 Network upgrade 64% 13 245 36 045 2 000 24 600 -32% Project 7 Move call centre 63% 8 955 45 000 11 194 35 794 -20% Project 3 Performance management 60% 3 564 48 564 13 860 49 654 2% Project 2 4 new depots 59% 16 342 64 906 27 004 76 658 18% Project 8 Refresh desktops 52% 20 000 84 906 10 000 86 658 2% Project 6 Factory 2020 36% 2 000 86 906 1 000 87 658 1% Project 5 Payroll / Time&Attendance 30% 12 030 98 936 14 000 101 658 3% Project 4 Automate transfer pricing 12% 1 996 100 932 1 760 103 418 2% 31
  • 32. But if we want to service business growth… Utility Cumulative Cumulative Cumulative Initiative Name Score Cost Cost Return Return ROI Project 1 Customer online 76% 9 500 9 500 30 100 30 100 217% Project 10 Poppi 70% 13 300 22 800 -7 500 22 600 -1% Project 9 Network upgrade 64% 13 245 36 045 2 000 24 600 -32% Project 7 Move call centre 63% 8 955 45 000 11 194 35 794 -20% Project 3 Performance management 60% 3 564 48 564 13 860 49 654 2% Project 2 4 new depots 59% 16 342 64 906 27 004 76 658 18% Project 8 Refresh desktops 52% 20 000 84 906 10 000 86 658 2% Project 6 Factory 2020 36% 2 000 86 906 1 000 87 658 1% Project 5 Payroll / Time&Attendance 30% 12 030 98 936 14 000 101 658 3% Project 4 Automate transfer pricing 12% 1 996 100 932 1 760 103 418 2% 32
  • 33. What benefits should we be chasing / tracking? Initiative Initiative contribution Class utility Initiative Init. Initiative ID Class (0 - 5) rules score Utility 1: Customer online Bus I 5 1 2 4 5 x 40 20 10 10 20 40 4 4 8 20 76% 2: Four New Depots Bus S 3 2 3 1 4 x 20 30 15 5 20 12 12 9 10 16 59% 3: Performance Mgt SS I 5 2 2 2 3 x 30 30 10 20 10 30 12 4 8 6 60% 7: Call Centre Bus S 2 3 5 1 3 x 20 30 15 5 20 8 18 15 10 12 63% 9: Network upgrade SS S 0 4 4 3 2 x 10 40 20 20 10 0 32 16 12 4 64% 10: Poppi Bus X 0 5 5 2 0 x 0 50 20 0 30 0 50 20 0 0 70% 33
  • 34. IT adds value at different stages Plan Build Run Retire Meaning Attention Operate Idea Test the Design and Implement Early Majority Maturity idea build adoption adoption Un-lockable Value Tangible Value Tangible Value Tangible Value Value Value potential Intangible potential Value Intangible Value Value Value Intangible Cost-cut potential potential Value Value Value preservation Monthly cost Monthly cost Monthly cost Cost Monthly cost Monthly cost Monthly cost Cost 1 2 3 4 5 6 7 8 34
  • 35. What business currently sees of IT value-add potential Plan Build Run Retire Meaning Attention Operate Idea Test the Design and Implement Early Majority Maturity idea build adoption adoption Un-lockable Value Tangible Value Invest- Tangible ment Value Tangible approval Value Value Value potential Intangible potential Value Intangible Value Value Value Intangible Cost-cut potential potential Value Value Value preservation IT Costs Monthly cost Monthly cost Monthly cost Cost Monthly cost Monthly cost Monthly cost Cost 1 2 3 4 5 6 7 8 35
  • 36. In summary Utility trumps ROI and cost Utility rules per class set business expectations and improve understanding Initiatives are not projects until they are budgeted for You set your project budget by scoring the utility contribution per initiative and multiply by the utility rule for the class of initiative Initiatives that don’t make the cut, stay in the initiative portfolio Benefits realisation plans revolve around expected utility Alignment to business priorities and strategy is a given 36
  • 37. THANK YOU • Terry White: (082 537 3887) terryw@cxo-advisor.co.za