0 | P a g e
Steven Viljoen
7-9-2015
VIRTUAL DESIGN MASTER 3
REDFOG DESIGN
DOCUMENT V1.5
Challenge 2
1 | P a g e
Contents
Revision History ................................................................................................................................................................3
Executive summary...........................................................................................................................................................4
Executive objectives..........................................................................................................................................................4
General Application Requirements...................................................................................................................................5
Constraints........................................................................................................................................................................5
Risks ..................................................................................................................................................................................5
Assumptions......................................................................................................................................................................5
OBJECTIVE A......................................................................................................................................................................6
Common Infrastructure services.......................................................................................................................................6
PTP Time synchronization.............................................................................................................................................6
LDAP and DNS ...............................................................................................................................................................6
Time tracking application..................................................................................................................................................7
Functional Requirements:.............................................................................................................................................7
Level Overview..............................................................................................................................................................7
High Availability ............................................................................................................................................................7
Components..................................................................................................................................................................7
Requirements................................................................................................................................................................7
LSS Conceptual Design......................................................................................................................................................8
Application layout.....................................................................................................................................................8
Emergency Control (EC) ............................................................................................................................................8
Level 3 Architectural design..............................................................................................................................................9
Functional Requirements:.............................................................................................................................................9
Level Overview..............................................................................................................................................................9
High Availability ............................................................................................................................................................9
Components..................................................................................................................................................................9
Sensors......................................................................................................................................................................9
Actuators...................................................................................................................................................................9
Compute modules.....................................................................................................................................................9
Data flows ...................................................................................................................................................................10
Capacity requirements................................................................................................................................................10
Network requirements................................................................................................................................................10
Connections ............................................................................................................................................................10
Bandwidth...............................................................................................................................................................10
Compute requirements...............................................................................................................................................10
Level 2 Architectural design............................................................................................................................................11
Functional requirements.............................................................................................................................................11
Level Overview............................................................................................................................................................11
2 | P a g e
High Availability ..........................................................................................................................................................11
Components................................................................................................................................................................11
Processing module..................................................................................................................................................11
User interface module ............................................................................................................................................11
Alarm module..........................................................................................................................................................11
Capacity requirements................................................................................................................................................12
Network requirements................................................................................................................................................12
Connections ............................................................................................................................................................12
Bandwidth...............................................................................................................................................................12
Compute requirements...............................................................................................................................................12
Level 1 Architectural design............................................................................................................................................13
Functional requirements.............................................................................................................................................13
Level Overview............................................................................................................................................................13
High Availability ..........................................................................................................................................................13
Components................................................................................................................................................................13
Capacity requirements................................................................................................................................................14
IOPS requirements..................................................................................................................................................14
Network requirements................................................................................................................................................14
Connections ............................................................................................................................................................14
Bandwidth...............................................................................................................................................................14
Compute requirements...............................................................................................................................................14
OBJECTIVE B....................................................................................................................................................................15
Redfog cloud infrastructure............................................................................................................................................15
Maturity ......................................................................................................................................................................15
Functionality ...............................................................................................................................................................15
Availability...................................................................................................................................................................15
Compatibility...............................................................................................................................................................15
REDFOG environment.....................................................................................................................................................16
Common infrastructure services.................................................................................................................................17
Time tracker................................................................................................................................................................17
Life Support system.....................................................................................................................................................18
Level 2 .....................................................................................................................................................................18
Level 1 .....................................................................................................................................................................19
Appendix A – Level 3 Data sizing Telemetry and Command traffic................................................................................20
Sensors........................................................................................................................................................................20
Actuators.....................................................................................................................................................................20
References ......................................................................................................................................................................21
3 | P a g e
Revision History
Date Revision
number
Author Comments
9 July 2015 V1.0 S.Viljoen Initial document draft
10 July 2015 V1.1 S.Viljoen
Added Level 3 storage capacity and wishing I had paid more
attention in maths class.
11 July 2015 v1.2 S.Viljoen Hmm, is this really what was required?
12 July 2015 v1.3
S.Viljoen Think that I have misunderstood the challenge requirements
completely.
12 July 2015 v1.4 S.Viljoen All kinds of lost.
13 July 2015 v1.5 S.Viljoen Redfog descending
4 | P a g e
Executive summary
The first part of this document defines the infrastructure agnostic layout and interaction for 2 applications:
1) Time tracking application
This is a non-critical application that will be used by the greenhouse botanists to track their working hours.
It has been defined as a single layer system.
2) Critical Life Support System application.
This is a critical system that is used to monitor and maintain the environment in all habitable environments
on Mars. This system is highly available on all levels to ensure that the 20 minute MTD is not breached.
The second part identifies an existing Earth based public cloud infrastructure provider that will be recreated on
Mars.
The 2 applications defined in the first section are then mapped to the public cloud provider products to illustrate the
final layout and requirements of the entire environment.
Executive objectives
This project has 2 main objectives
Objective A
1. Design an environment that includes
a. A web based time tracking application for the botanists in the greenhouses.
b. A critical enterprise life support system application.
2. Define all application requirements.
Objective B
1. Select an existing public cloud infrastructure that will be recreated on mars and justify why it was chosen.
2. Publish the environment to the selected public cloud infrastructure.
5 | P a g e
General Application Requirements
Reference Description
APR01 Must run autonomously
APR02 Must ensure a 20min MTD.
APR03 Must include a failsafe located outside the cloud environment.
APR04 Must store logs for at least 2 years.
APR05 Must be highly available.
APR06 Must facilitate base expansion.
APR07 Must store environment data for 5 years for environment analysis
APR08
Initial Application design should be infrastructure agnostic so that it can be mapped
to any chosen public cloud infrastructure.
Constraints
Reference Description
CS001 Infrastructure must be based on an existing public cloud infrastructure
CS002 Design needs to be completed in 5 days.
CS003
Risks
Reference Description
RI001 Moving the Life Support Systems away from the local environment
introduces risk of NW failures leading to fatalities.
RI002 Critical life support systems are outside the direct control of the local admins.
Assumptions
Reference Description
AS001
The benefits of moving the LSS systems to a cloud environment outweigh the
risks.
AS002
The alarm module (not in scope for this document) is configured to be highly
available.
AS003 Someone with more than 2 days of AWS ‘knowledge’ will implement the final
solution.
6 | P a g e
OBJECTIVE A
1. Design an environment that includes
a. A web based time tracking application for the botanists in the greenhouses.
b. A critical enterprise life support system application.
2. Define all application requirements.
Common Infrastructure services
The following systems will be centrally installed to provide infrastructure services to, amongst others, both the LSS
application and the Time tracking application.
PTP Time synchronization
Accurate time synchronization is essential in any environment and especially in a control environment like the LSS to
ensure that datatime stamp records from all the sensor driven components are accurate. This allows specific
condition sets to be identified and acted upon. (I.e. increased light, pressure and thermal reading at the same time
probably means that someone just lit a cigarette in the oxygen chamber and will be requiring medical assistance).
In addition to this the time synchronization sub system will most likely also be used for scientific systems (which are
not in scope for this document) but would need highly precise time synchronization.
This environment will use the IEEE 1588 PTP (Precision Time Protocol) as it is:
 More accurate than NTP and
 Less expensive than GPS (especially if you need to start launching satellites.)
Requirements:
 Boundary clocks located in both the cloud environment + onsite environment.
 Grandmaster and clients must reside in the same PTP domain.
 PTP will be run in Unicast mode (Redfog (AWS) does not support multicast) which will require that the
master is added to the Acceptable Master Table in each slave.
LDAP and DNS
LDAP and DNS services will be provided throughout the environment by the 3 Domain controllers for ‘base.mars’
domain.
 APDC1.base.mars
 WPDC1.base.mars
 FPDC1.base.mars
Each domain controller will be deployed to a separate availability zone and each will be configured as Global Catalog
Servers.
7 | P a g e
Time tracking application
Functional Requirements:
Reference Description
TTR01 Should provide web based access to botanists.
TTR02 Should store time data the last 15 months.
TTR03 Last 30 days of data must be backed up.
Level Overview
High Availability
The time tracking system is not considered to be critical and as such does not require any level of redundancy.
Backups will be taken every day to ensure that data can be restored if needed.
Retention period is set to 30 days as the botanists are known to query each pay slip and it is needed to have at least
the last month’s data available if challenged.
Components
The time tracking environment will consist of a single server with the following 3 applications running.
1. Web interface: nginx
2. Application layer: PHP running Symfony 2
3. Database layer: MySQL
Requirements
Scope Requirement
CPU 1
Memory 2 GB
Storage – OS + Application 30 GB
Storage - Data 70 GB
Network - Connections 1x Ethernet
Network – Bandwidth Low
Botanists are not known to track their time regularly.
8 | P a g e
LSS Conceptual Design
Application layout
The LSS will use a 3 level structure as shown in the diagram below. It will also be split between local onsite
components that require hardwire analogue connections to the various sensors and actuators and the cloud based
components that will communicate via Ethernet.
The benefits of using this approach are:
1. Modularity: Allows new components (upgrades, repairs, etc.) to be inserted without requiring a complete
redesign of all levels.
2. Scalability: As the base grows, new habitable areas requiring LSS can easily be added by installing local level
3 components and connecting them to the existing level 2 systems. [APR06]
3. Granularity: Provides multiple differing layers of redundancy that can be defined on a level by level basis to
reduce costs and increase HA.
Emergency Control (EC)
The emergency control module is located in the local site. As it is a separated fail safe mechanism for the core Life
Support System no independent redundancy is required.
The EC monitors upper level availability and in case of catastrophic failure of Level 1 or 2 will take over control of
Level 3 and maintain a basic life supporting environment until the issues are repaired.[APR03]
The module will be completely segregated (different Hardware, OS and software) from the core LSS as shown below
to prevent issues bringing down the core systems and also affecting the Emergency control:
9 | P a g e
Level 3 Architectural design
Functional Requirements:
Reference Description
L3R01 Receive and send analogue data
L3R02 Convert analogue signals to digital and vice versa
L3R03 Receive and send digital data via Ethernet to and from Level 2
Level Overview
High Availability
No application level high availability is needed as redundancy is ensured on the hardware level as shown above.
Each Sensor bundle and Actuator set is connected to its own separated Level 3 compute module. Each habitable area
will have at least 3 sensor bundles and 2 actuator sets per room as illustrated.
This forms a hardware redundancy group for that habitable area.
Components
Sensors
The sensors are responsible for providing environmental data to the L3 compute modules.
Each sensor bundle will consist of a number of different sensors types, each of which will send telemetry data
messages at fixed intervals based on criticality of that metric.
Actuators
The actuators are responsible for carrying out the command messages sent from L3 Compute modules to influence
various aspects of the environment.
Compute modules
Level 3 compute modules will not need to be very powerful as their main role will be to function as Analogue Digital
convertors. Any microcomputer (i.e. Raspberry Pi) with an ADC module will suffice.
10 | P a g e
Data flows
The following diagram details the basic data flows derived from the Level 3 functions.
Capacity requirements
Level 3 does not store any data locally but does generate data that needs to be accounted for in the higher levels.
The table below summarizes the minimum storage capacity requirement as generated by Level 3 components.
Capacity calculations are shown in Appendix A.
Daily
Total sensor data
(GB)
Daily
Total actuator data
(GB)
Daily
Total combined data
(GB)
Yearly
Total combined data
0.484 0.155 0.623 233 GB
Network requirements
Connections
1. Analogue connections : Level 3 - SensorsArrays
2. Ethernet: Level 3 - Level 2
Bandwidth
The minimum required Bandwidth between Level 3 and Level 2 is, based on similar systems and data size
calculations (Appendix A), to be at least 16kbps.
Compute requirements
As each sensor bundle is connected to its own level 3 compute module and tasks performed by each compute
module are not CPU nor Memory intensive, it is possible to benchmark against industry standard microcomputers.
(Raspberry Pi for instance is able to convert analogue to digital and transmit data via Ethernet at the required
messaging frequencies)
CPU: Single core (700MHz) Memory: 512 MB
11 | P a g e
Level 2 Architectural design
Functional requirements
Reference Description
L2R01 Must be at least 1 failure
L2R02 Connectivity to Level 1 and Level 3
L2R03 Connectivity to User interface module
L2R04 Connectivity to Alarm module
L2R05 Support CPU and Memory intensive processing
Level Overview
High Availability
High availability will be provided by having 3 application instances running behind a central load balancer. As these
are processing units and do not have large amounts of data stored locally deployment could be scripted to quickly
deploy a new instance if 1 fails.
Components
Processing module
 Critical component
 3 Application instances
 1 load balancer to distribute load amongst them.
 This setup provides HA [APR05] and also allows for the environment to be expanded [APR06] by simply
adding additional application instances behind the load balancer.
User interface module
 Non critical [APR01]
 1 web server
Alarm module
 Not in scope for the LSS design document but will be set up for high availability. [AS003]
12 | P a g e
Capacity requirements
Level 2 compute modules do not store data locally but do generate data that needs to be accounted for in the higher
level (level 1). The majority of the data generated from level 2 will be related to logging.
Based on similar systems and anticipated data flows it is possible to define the minimum expected storage capacity
requirement generated by level 2. This is shown in the table below.
Monthly log size:
User interface
(MB)
Monthly log size:
Alarm module
(MB)
Monthly log size:
Level 3
(MB)
Monthly log size:
Level 1
(MB)
200 100 750 300
Total capacity requirements
Monthly
Combined log size (MB)
Yearly
Combined log size (MB)
1350 16200
Network requirements
Connections
1. Ethernet: Load balancer – Level 3
2. Ethernet: Load balancer - Level 2
3. Ethernet: Level 2 – Level 1
4. Ethernet: level 2 – Level 2 (Inter instance communication)
5. Ethernet: Level 2 – Web server (user interface module)
6. Ethernet: Level 2 – Alarm module
Bandwidth
Peak Level 3 bandwidth (16kbps) is already incorporated above in Level 3 network requirements so will not be
duplicated here.
Logging traffic is expected to be 4 times more than data traffic given the anticipated checkpoints at which log data
would be written to the database for each data message received from Level 3.
The additional traffic generated by the User interface and Alarm module is expected, based on similar systems, to
add an additional 20kbps.
The minimum required bandwidth for level 2 would then be:
16kbps + 64kbps + 20kbps = 100kbps
Note: As these will be the central instances for any base expansion plans that require LSS the minimum bandwidth
will be defined as 10 Mbps.
Compute requirements
As the layer 2 processing modules are relatively memory intensive as compared to other resource usage the
following specifications have been calculated as being the minimum requirements per instance.
CPU: 2 x 2.2MHz Memory: 15 GB
Instances will be monitored throughout the initial first month and if required then additional resources can be
added.
13 | P a g e
Level 1 Architectural design
Functional requirements
Reference Description
L1R01 Must support at least 1 failure
L1R02 Connectivity to Level 2
L1R03 Support high IOPS
L1R04 Must have enough capacity to store 2 years logs
L1R05 Must have enough capacity to store 5 years of environmental data
Level Overview
High Availability
High availability will be ensured by running an additional hot standby instance that will be able to take over in case
of any issues with the active instance. In addition to this a read only copy will be created to provide additional
redundancy and also allow for future expansion. [APR06]
Components
1. 1 Active database instance
2. 1 hot standby database instance
3. 1 read only copy
14 | P a g e
Capacity requirements
The total database capacity requirement (taking into account required retention periods for environmental data
[APR04] and log data [APR04] and including log data generated by level 1 components) is shown below.
[APR07]
5 Year
environmental data
- Level 3
(GB)
[APR04]
2 Year
log size
- Level 2
(GB)
[APR04]
2 Year
log size
- Level 1
(GB)
Total Combined
database size
(GB)
1165 32.4 20 1217.4
IOPS requirements
Calculated IOPS requirement is <3500
Network requirements
Connections
1. Ethernet: Level 2 – level 1
2. Ethernet: Level 1 – Emergency Control module
The Hot standby and read only copy will be created on the hypervisor layer.
Bandwidth
Minimum bandwidth requirements are the same as calculated above for level 2.
Minimum bandwidth: 100kbps
Note: As these will be the central instances for any base expansion plans that require LSS the minimum bandwidth
will be defined as 10 Mbps.
Compute requirements
Database compute specifications will be based on similar systems.
CPU: 2 x 2.5MHz Memory: 15 GB
Instances will be monitored throughout the initial first month and if required then additional resources can be
added.
15 | P a g e
OBJECTIVE B
1. Select an existing public cloud infrastructure that will be recreated on mars and justify why it was chosen.
2. Publish the environment to the selected public cloud infrastructure.
Redfog cloud infrastructure
While most of the major Earth based public cloud providers offer similar services and functionality Amazon web
services (AWS) has been selected as the model on which to base Mars’ first public cloud infrastructure.
Maturity
AWS was launched in 2006 (4 years before Azure and 7 years before vCloud Air) and as such has the most experience
in the field.
They are (were?) also trusted by major companies with customers including NASA and the CIA proving that they are
able to handle space related data and keep it safe.
Functionality
AWS provides a number of supported functionalities that while not used for this project could be required at a later
date.
1. Native Windows Failover Clusters (even Azure has issues with this).
2. Support for Hyper-V on-premises connectivity (AWS storage gateway)
3. Multiple OS version support (RHEL for instance is not supported in Azure)
4. AWS marketplace which has the largest number of solutions available.
Availability
AWS provides a number of crucial availability products.
1. Availability zones and the possibility of deploying environments across multiple availability zones.
2. Auto scaling which allows new instances to be deployed automatically based on certain user defined
thresholds.
3. Database hot standby and Read replicas provide simple to implement high availability protection.
Compatibility
Assuming that the designs from challenge 1 will be put in place then Zerto (the replication product chosen) already
provides a way to easily a) migrate or b) failover to cloud the entire local environment using Zerto Virtual Replication
for Amazon AWS.
16 | P a g e
REDFOG environment
The following section provides an overview of the application environment layout once deployed to Redfog and follows up with the mapping of the individual infrastructure
agnostic components defined in Objective A onto the individual Redfog products.
17 | P a g e
Common infrastructure services
PTP server
3 Servers will be deployed (1 Grandmaster + 2 Boundary clocks) in VPC 1.
Instance Instance
Type
OS CPU Mem Network Availability
Zone
Storage AWS
Backups
Notes
APTP1 t2.micro RHEL 7.1 1 (2.5GHz) 1GB VPC1 – LowModerate Zone 1 20GB Magnetic No
WPTP2 t2.micro RHEL 7.1 1 (2.5GHz) 1GB VPC1 – LowModerate Zone 1 20GB Magnetic No
FPTP3 t2.micro RHEL 7.1 1 (2.5GHz) 1GB VPC1 – LowModerate Zone2 20GB Magnetic No
Domain controllers
3 deployed (VPC1) Domain controllers will be used instead of the AWS Directory service as this does not provide future capabilities like multi-factor authentication or
domain trusts except when deploying an AD Connector however that would require an existing onsite MS Active Directory which is not available.
Instance Instance
Type
OS CPU Mem Network Availability
Zone
Storage AWS
Backups
Notes
APDC1 t2.medium WS2012 Std. 2(2.5GHz) 4GB VPC1 – LowModerate Zone 1 50GB Magnetic No
WPDC1 t2.medium WS2012 Std. 2(2.5GHz) 4GB VPC1 – LowModerate Zone 2 50GB Magnetic No
FPDC1 t2.medium WS2012 Std. 2(2.5GHz) 4GB VPC1 – LowModerate Zone 3 50GB Magnetic No
Time tracker
Based on requirements the following product will be deployed in a separate subnet (VPC2) as follows:
Instance Instance
Type
CPU Mem Network Multi-AZ Storage AWS
Backups
Notes
WPTT1 db.t2.small 1 2GB VPC2 -Low No 100 GB Magnetic 35 day retention Publicly accessible: Yes
The following components will be used
 Web: nginx
 App: PHP running Symfony 2
 DB: MySQL
18 | P a g e
Life Support system
Level 2
Application layer
The LSS Application modules will be set up as part of an Auto scaling group to ensure that there are always 3 instances available.
The Auto Scaling Group will stretch across 3 Availability Zones.
Application deployment will be handled using AWS CodeDeploy.
Instance Instance
Type
CPU Mem Network Availabilit
y Zone
Storage Backups Notes
APLSS1 m4.large WS2012
Standard
2 (2.4GHz) 15GB VPC – High Multi AZ 100GB - SSD 35 day
retention
300 IOPS
APLSS2 m4.large WS2012
Standard
2 (2.4GHz) 15GB VPC – High Multi AZ 100GB - SSD 35 day
retention
300 IOPS
APLSS3 m4.large WS2012
Standard
2 (2.4GHz) 15GB VPC – High Multi AZ 100GB - SSD 35 day
retention
300 IOPS
Load balancer
An Elastic Load Balancer will be created within the main VPC to balance the load across the Application instances.
The ELB will stretch across all AZ subnets.
Health Check Protocol: TCP Ping Port: 4700
Response timeout: 5 seconds Health Check Interval: 10 seconds Unhealthy Threshold: 3 Healthy Threshold: 5
ELB will be bound to all 3 Application instances and Cross zone load balancing will be enabled
User Interface
The web server for the user interface will use the following to run nginx web server.
Instance Instance
Type
CPU Mem Network Availabilit
y Zone
Storage Notes
FPGUI1 t2.small RHEL 7.1 1 (2.4GHz) 2GB VPC –Low to
Moderate
default to
Zone 3
30GB -
Magnetic
300 IOPS – auto config
19 | P a g e
Level 1
MySQL 5.6 has been chosen for this environment as it allows the following:
 Allows the creation of read replicas
 Allows the read replica to be created in a separate Availability Zone (MySQL 5.6 only)
The level 1 database layer will be deployed as follows:
Instance Instance
Type
CPU Mem Network Availability
Zone
Storage Backups Notes
APDB1 db.m3.xlarge 4 (2.5GHz) 15GB VPC – High Multi AZ 2TB - SSD 35 day
retention
MySQL 5.6.23
6000 IOPS – minimum configurable
Not publicly accessible
Includes Hot standby
Includes read replica
20 | P a g e
Appendix A – Level 3 Data sizing Telemetry and Command traffic.
Sensors
Telemetry and status message size (including sensor ID, datetime stamp, and meter reading) is estimated at 50
Bytes per message.
Sensor type Messaging
frequency
Telemetry message
size (Bytes)
Status check
frequency
Status message size
– return trip
Oxygen 3s 50 2s 50
Nitrogen 3s 50 2s 50
CO2
3s 50 2s 50
Hydrogen 3s 50 2s 50
Contaminates 3s 50 2s 50
Pressure 3s 50 2s 50
Radiation 3s 50 2s 50
Heat 10s 50 2s 50
Light 60s 50 2s 50
Humidity 60s 50 2s 50
Number of sensors required
 1 Sensor bundle per 200M3
or per room if smaller separated rooms are used.
 Assuming that the maximum measured area would be a single 1000M3
room.
Measured
area (M3
)
Sensor bundles
needed per
200M3
Number of
sensor bundles
(N)
Total number of
redundant sensor
bundles (3N)
Daily data size
per bundle (MB)
Total daily data
size (MB)
1000 1 5 15 32 484
Actuators
The actuators are responsible for carrying out the command messages sent from L3 Compute modules to influence
various aspects of the environment. Command and status message size (including sensor ID, datetime stamp, and
meter reading) is estimated at 50 Bytes per message.
Actuator type Messaging
frequency
- estimated
average
Command
message size
(Bytes)
Status check
frequency
Status message size –
return trip
(Bytes)
Light control 120s 50 2s 50
Atmosphere control 120s 50 2s 50
Vent control 120s 50 2s 50
Pressure control 60s 50 2s 50
Thermal control 30s 50 2s 50
Fire suppressing control 240s 50 2s 50
Alarm control 240s 50 2s 50
Number of actuator sets required
 Estimated at 1 actuator set per 100M3
or per room if smaller separated rooms are used.
 Assuming that the maximum measured area would be a single 1000M3
room.
Measured
area (M3
)
Actuator sets
needed per
100M3
Number of
actuator sets
(N)
Total number of
redundant actuator
sets (2N)
Daily data size
per set (MB)
Total daily data
size (MB)
1000 1 5 10 15 155
21 | P a g e
References
Arnold, Douglas. "Unicast PTP." 2014. <http://blog.meinbergglobal.com/2014/04/16/unicast-ptp/>.
Texas Instruments. "AN-1728 IEEE 1588 Precision Time Protocol Time." 2013.
<http://www.ti.com/lit/an/snla098a/snla098a.pdf>.

More Related Content

PDF
#VirtualDesignMaster 3 Challenge 1 - Steven Viljoen
PDF
Ryan Fu-Sum Nanofiltration Membrane Report
PDF
TOC training KeyCloak Redhat SSO core
PDF
TOC training Keycloak RedhatSSO advanced
PDF
Bmf 6 english bible survey
PDF
IMechE Report Final_Fixed
PDF
E book lplt
PDF
Fdi in tradable_services___8211__final_report
#VirtualDesignMaster 3 Challenge 1 - Steven Viljoen
Ryan Fu-Sum Nanofiltration Membrane Report
TOC training KeyCloak Redhat SSO core
TOC training Keycloak RedhatSSO advanced
Bmf 6 english bible survey
IMechE Report Final_Fixed
E book lplt
Fdi in tradable_services___8211__final_report

What's hot (19)

PDF
Non Prime Select Guidelines call Jesse B Lucero 702-551-3125
PDF
Led mqp paper_final_dwan_horgan
PDF
Stair climbing hand truck
PDF
Clancy95barriers geetal
DOCX
ABC Catalog company
PDF
Manufacturing of liquid insulators
PDF
PDF
Binder1.compressed
DOC
Contest awards-bulletin-september-2013
PDF
FasterCures-GivingSmarter-Alzheimers-April2015
DOCX
Final Project - COMBINATION
PDF
Hilltop, Columbus, Ohio Neighborhood Stabilization Program Recommendations Re...
PDF
Trimble total station help
PDF
Project standard and pro 2010 product guide
PDF
(Ximb) sustainability brewing industry
PDF
Deller rpl thesis
PDF
English manual life-skills
PDF
Nft s explained 2022
DOCX
VIBE Glasses
Non Prime Select Guidelines call Jesse B Lucero 702-551-3125
Led mqp paper_final_dwan_horgan
Stair climbing hand truck
Clancy95barriers geetal
ABC Catalog company
Manufacturing of liquid insulators
Binder1.compressed
Contest awards-bulletin-september-2013
FasterCures-GivingSmarter-Alzheimers-April2015
Final Project - COMBINATION
Hilltop, Columbus, Ohio Neighborhood Stabilization Program Recommendations Re...
Trimble total station help
Project standard and pro 2010 product guide
(Ximb) sustainability brewing industry
Deller rpl thesis
English manual life-skills
Nft s explained 2022
VIBE Glasses
Ad

Viewers also liked (20)

PDF
LUXURY RETAIL
PDF
Catalog Cercul de Donatori Cluj, 15 mai 2014
PDF
Active in europe_travel_guide
DOCX
Active citizens - Crete (Greece)
PDF
Asiakaskeskeisyyttä läpi koko organisaation - Tuula Uitto TeliaSonera
PPTX
Chemical engineering brunson
PDF
#VirtualDesignMaster 3 Challenge 2 - Abdullah Abdullah
DOC
Madariaga dorretxea ibon laka
PPTX
The Factor Usability on Location Based Services in the Retail Environment
PDF
De ce să vii la Cercul de Donatori Cluj?
DOCX
Uas k eamanan komputer
PPTX
Mother teresa[1]
PPT
Diamondback Terrapins in the Indian River Lagoon (IRL)
PDF
#VirtualDesignMaster 3 Challenge 4 - Harshvardhan Gupta
PDF
Research on Afghan Legal Courts
PPTX
Evaluation
PPTX
Сборка "Порядков мышления"
DOCX
electronic mixer
PPTX
Fire detector and control pump using flame sensor
PPTX
Radio advert feedback
LUXURY RETAIL
Catalog Cercul de Donatori Cluj, 15 mai 2014
Active in europe_travel_guide
Active citizens - Crete (Greece)
Asiakaskeskeisyyttä läpi koko organisaation - Tuula Uitto TeliaSonera
Chemical engineering brunson
#VirtualDesignMaster 3 Challenge 2 - Abdullah Abdullah
Madariaga dorretxea ibon laka
The Factor Usability on Location Based Services in the Retail Environment
De ce să vii la Cercul de Donatori Cluj?
Uas k eamanan komputer
Mother teresa[1]
Diamondback Terrapins in the Indian River Lagoon (IRL)
#VirtualDesignMaster 3 Challenge 4 - Harshvardhan Gupta
Research on Afghan Legal Courts
Evaluation
Сборка "Порядков мышления"
electronic mixer
Fire detector and control pump using flame sensor
Radio advert feedback
Ad

Similar to #VirtualDesignMaster 3 Challenge 2 - Steven Viljoen (20)

PDF
Byron Schaller - Challenge 1 - Virtual Design Master
PDF
Cryoserver v7 Administration Guide
PDF
Link SDVOSB Past Performance Summaries
PDF
Link Resources Past Performance Summaries
PDF
Link SDVOSB Past Performance Summaries
DOCX
Citrus College - NASA SL Criticla Design Review
PDF
ARQUIVO ROUBADO
PDF
Dissertation_katia_2015_ultima
PDF
IMechE Report Final_Fixed
PDF
Soa In The Real World
PDF
API Project Capstone Paper
PDF
Robotic_Arm_Controller_Bachelor_of_Engin.pdf
PDF
Albpm60 studio reference_guide
PDF
PDF
WebIT2 Consultants Proposal
PDF
Byron Schaller - Challenge 2 - Virtual Design Master
PDF
GoogleReportFlat
PDF
Netex learningMaker | Multipage Template v2.5.3 [En]
PDF
OAuth with Restful Web Services
Byron Schaller - Challenge 1 - Virtual Design Master
Cryoserver v7 Administration Guide
Link SDVOSB Past Performance Summaries
Link Resources Past Performance Summaries
Link SDVOSB Past Performance Summaries
Citrus College - NASA SL Criticla Design Review
ARQUIVO ROUBADO
Dissertation_katia_2015_ultima
IMechE Report Final_Fixed
Soa In The Real World
API Project Capstone Paper
Robotic_Arm_Controller_Bachelor_of_Engin.pdf
Albpm60 studio reference_guide
WebIT2 Consultants Proposal
Byron Schaller - Challenge 2 - Virtual Design Master
GoogleReportFlat
Netex learningMaker | Multipage Template v2.5.3 [En]
OAuth with Restful Web Services

More from vdmchallenge (20)

PDF
#VirtualDesignMaster 3 Challenge 4 - Steven Viljoen
PDF
#VirtualDesignMaster 3 Challenge 4 - Dennis George
PDF
#VirtualDesignMaster 3 Challenge 4 – James Brown
PDF
#VirtualDesignMaster 3 Challenge 4 - Abdullah Abdullah
PDF
#VirtualDesignMaster 3 Challenge 3 - Steven Viljoen
DOCX
#VirtualDesignMaster 3 Challenge 3 - Lubomir Zvolensky
PDF
#VirtualDesignMaster 3 Challenge 3 – James Brown
PDF
#VirtualDesignMaster 3 Challenge 3 - Harshvardhan Gupta
PDF
#VirtualDesignMaster 3 Challenge 3 - Dennis George
PDF
#VirtualDesignMaster 3 Challenge 3 - Abdullah Abdullah
DOCX
#VirtualDesignMaster 3 Challenge 2 - Lubomir Zvolensky
PDF
#VirtualDesignMaster 3 Challenge 2 – James Brown
PDF
#VirtualDesignMaster 3 Challenge 2 - Harshvardhan Gupta
PDF
#VirtualDesignMaster 3 Challenge 2 - Dennis George
PDF
#VirtualDesignMaster 3 Challenge 1 - Abdullah Abdullah
PDF
#VirtualDesignMaster 3 Challenge 1 - Dennis George
PDF
#VirtualDesignMaster 3 Challenge 1 - Harshvardhan Gupta
PDF
#VirtualDesignMaster 3 Challenge 1 – James Brown
DOCX
#VirtualDesignMaster 3 Challenge 1 - Lubomir Zvolensky
PDF
#VirtualDesignMaster 3 Challenge 1 - Mohamed Ibrahim
#VirtualDesignMaster 3 Challenge 4 - Steven Viljoen
#VirtualDesignMaster 3 Challenge 4 - Dennis George
#VirtualDesignMaster 3 Challenge 4 – James Brown
#VirtualDesignMaster 3 Challenge 4 - Abdullah Abdullah
#VirtualDesignMaster 3 Challenge 3 - Steven Viljoen
#VirtualDesignMaster 3 Challenge 3 - Lubomir Zvolensky
#VirtualDesignMaster 3 Challenge 3 – James Brown
#VirtualDesignMaster 3 Challenge 3 - Harshvardhan Gupta
#VirtualDesignMaster 3 Challenge 3 - Dennis George
#VirtualDesignMaster 3 Challenge 3 - Abdullah Abdullah
#VirtualDesignMaster 3 Challenge 2 - Lubomir Zvolensky
#VirtualDesignMaster 3 Challenge 2 – James Brown
#VirtualDesignMaster 3 Challenge 2 - Harshvardhan Gupta
#VirtualDesignMaster 3 Challenge 2 - Dennis George
#VirtualDesignMaster 3 Challenge 1 - Abdullah Abdullah
#VirtualDesignMaster 3 Challenge 1 - Dennis George
#VirtualDesignMaster 3 Challenge 1 - Harshvardhan Gupta
#VirtualDesignMaster 3 Challenge 1 – James Brown
#VirtualDesignMaster 3 Challenge 1 - Lubomir Zvolensky
#VirtualDesignMaster 3 Challenge 1 - Mohamed Ibrahim

Recently uploaded (20)

PPTX
A Presentation on Artificial Intelligence
PDF
Mobile App Security Testing_ A Comprehensive Guide.pdf
PDF
Network Security Unit 5.pdf for BCA BBA.
PPTX
Detection-First SIEM: Rule Types, Dashboards, and Threat-Informed Strategy
PPTX
20250228 LYD VKU AI Blended-Learning.pptx
PDF
Peak of Data & AI Encore- AI for Metadata and Smarter Workflows
PDF
Modernizing your data center with Dell and AMD
PDF
cuic standard and advanced reporting.pdf
PDF
7 ChatGPT Prompts to Help You Define Your Ideal Customer Profile.pdf
PDF
Electronic commerce courselecture one. Pdf
PDF
Bridging biosciences and deep learning for revolutionary discoveries: a compr...
PDF
Machine learning based COVID-19 study performance prediction
PDF
Encapsulation theory and applications.pdf
PDF
Architecting across the Boundaries of two Complex Domains - Healthcare & Tech...
PPTX
VMware vSphere Foundation How to Sell Presentation-Ver1.4-2-14-2024.pptx
PDF
Unlocking AI with Model Context Protocol (MCP)
PDF
Per capita expenditure prediction using model stacking based on satellite ima...
PDF
Agricultural_Statistics_at_a_Glance_2022_0.pdf
PDF
Building Integrated photovoltaic BIPV_UPV.pdf
PDF
Chapter 3 Spatial Domain Image Processing.pdf
A Presentation on Artificial Intelligence
Mobile App Security Testing_ A Comprehensive Guide.pdf
Network Security Unit 5.pdf for BCA BBA.
Detection-First SIEM: Rule Types, Dashboards, and Threat-Informed Strategy
20250228 LYD VKU AI Blended-Learning.pptx
Peak of Data & AI Encore- AI for Metadata and Smarter Workflows
Modernizing your data center with Dell and AMD
cuic standard and advanced reporting.pdf
7 ChatGPT Prompts to Help You Define Your Ideal Customer Profile.pdf
Electronic commerce courselecture one. Pdf
Bridging biosciences and deep learning for revolutionary discoveries: a compr...
Machine learning based COVID-19 study performance prediction
Encapsulation theory and applications.pdf
Architecting across the Boundaries of two Complex Domains - Healthcare & Tech...
VMware vSphere Foundation How to Sell Presentation-Ver1.4-2-14-2024.pptx
Unlocking AI with Model Context Protocol (MCP)
Per capita expenditure prediction using model stacking based on satellite ima...
Agricultural_Statistics_at_a_Glance_2022_0.pdf
Building Integrated photovoltaic BIPV_UPV.pdf
Chapter 3 Spatial Domain Image Processing.pdf

#VirtualDesignMaster 3 Challenge 2 - Steven Viljoen

  • 1. 0 | P a g e Steven Viljoen 7-9-2015 VIRTUAL DESIGN MASTER 3 REDFOG DESIGN DOCUMENT V1.5 Challenge 2
  • 2. 1 | P a g e Contents Revision History ................................................................................................................................................................3 Executive summary...........................................................................................................................................................4 Executive objectives..........................................................................................................................................................4 General Application Requirements...................................................................................................................................5 Constraints........................................................................................................................................................................5 Risks ..................................................................................................................................................................................5 Assumptions......................................................................................................................................................................5 OBJECTIVE A......................................................................................................................................................................6 Common Infrastructure services.......................................................................................................................................6 PTP Time synchronization.............................................................................................................................................6 LDAP and DNS ...............................................................................................................................................................6 Time tracking application..................................................................................................................................................7 Functional Requirements:.............................................................................................................................................7 Level Overview..............................................................................................................................................................7 High Availability ............................................................................................................................................................7 Components..................................................................................................................................................................7 Requirements................................................................................................................................................................7 LSS Conceptual Design......................................................................................................................................................8 Application layout.....................................................................................................................................................8 Emergency Control (EC) ............................................................................................................................................8 Level 3 Architectural design..............................................................................................................................................9 Functional Requirements:.............................................................................................................................................9 Level Overview..............................................................................................................................................................9 High Availability ............................................................................................................................................................9 Components..................................................................................................................................................................9 Sensors......................................................................................................................................................................9 Actuators...................................................................................................................................................................9 Compute modules.....................................................................................................................................................9 Data flows ...................................................................................................................................................................10 Capacity requirements................................................................................................................................................10 Network requirements................................................................................................................................................10 Connections ............................................................................................................................................................10 Bandwidth...............................................................................................................................................................10 Compute requirements...............................................................................................................................................10 Level 2 Architectural design............................................................................................................................................11 Functional requirements.............................................................................................................................................11 Level Overview............................................................................................................................................................11
  • 3. 2 | P a g e High Availability ..........................................................................................................................................................11 Components................................................................................................................................................................11 Processing module..................................................................................................................................................11 User interface module ............................................................................................................................................11 Alarm module..........................................................................................................................................................11 Capacity requirements................................................................................................................................................12 Network requirements................................................................................................................................................12 Connections ............................................................................................................................................................12 Bandwidth...............................................................................................................................................................12 Compute requirements...............................................................................................................................................12 Level 1 Architectural design............................................................................................................................................13 Functional requirements.............................................................................................................................................13 Level Overview............................................................................................................................................................13 High Availability ..........................................................................................................................................................13 Components................................................................................................................................................................13 Capacity requirements................................................................................................................................................14 IOPS requirements..................................................................................................................................................14 Network requirements................................................................................................................................................14 Connections ............................................................................................................................................................14 Bandwidth...............................................................................................................................................................14 Compute requirements...............................................................................................................................................14 OBJECTIVE B....................................................................................................................................................................15 Redfog cloud infrastructure............................................................................................................................................15 Maturity ......................................................................................................................................................................15 Functionality ...............................................................................................................................................................15 Availability...................................................................................................................................................................15 Compatibility...............................................................................................................................................................15 REDFOG environment.....................................................................................................................................................16 Common infrastructure services.................................................................................................................................17 Time tracker................................................................................................................................................................17 Life Support system.....................................................................................................................................................18 Level 2 .....................................................................................................................................................................18 Level 1 .....................................................................................................................................................................19 Appendix A – Level 3 Data sizing Telemetry and Command traffic................................................................................20 Sensors........................................................................................................................................................................20 Actuators.....................................................................................................................................................................20 References ......................................................................................................................................................................21
  • 4. 3 | P a g e Revision History Date Revision number Author Comments 9 July 2015 V1.0 S.Viljoen Initial document draft 10 July 2015 V1.1 S.Viljoen Added Level 3 storage capacity and wishing I had paid more attention in maths class. 11 July 2015 v1.2 S.Viljoen Hmm, is this really what was required? 12 July 2015 v1.3 S.Viljoen Think that I have misunderstood the challenge requirements completely. 12 July 2015 v1.4 S.Viljoen All kinds of lost. 13 July 2015 v1.5 S.Viljoen Redfog descending
  • 5. 4 | P a g e Executive summary The first part of this document defines the infrastructure agnostic layout and interaction for 2 applications: 1) Time tracking application This is a non-critical application that will be used by the greenhouse botanists to track their working hours. It has been defined as a single layer system. 2) Critical Life Support System application. This is a critical system that is used to monitor and maintain the environment in all habitable environments on Mars. This system is highly available on all levels to ensure that the 20 minute MTD is not breached. The second part identifies an existing Earth based public cloud infrastructure provider that will be recreated on Mars. The 2 applications defined in the first section are then mapped to the public cloud provider products to illustrate the final layout and requirements of the entire environment. Executive objectives This project has 2 main objectives Objective A 1. Design an environment that includes a. A web based time tracking application for the botanists in the greenhouses. b. A critical enterprise life support system application. 2. Define all application requirements. Objective B 1. Select an existing public cloud infrastructure that will be recreated on mars and justify why it was chosen. 2. Publish the environment to the selected public cloud infrastructure.
  • 6. 5 | P a g e General Application Requirements Reference Description APR01 Must run autonomously APR02 Must ensure a 20min MTD. APR03 Must include a failsafe located outside the cloud environment. APR04 Must store logs for at least 2 years. APR05 Must be highly available. APR06 Must facilitate base expansion. APR07 Must store environment data for 5 years for environment analysis APR08 Initial Application design should be infrastructure agnostic so that it can be mapped to any chosen public cloud infrastructure. Constraints Reference Description CS001 Infrastructure must be based on an existing public cloud infrastructure CS002 Design needs to be completed in 5 days. CS003 Risks Reference Description RI001 Moving the Life Support Systems away from the local environment introduces risk of NW failures leading to fatalities. RI002 Critical life support systems are outside the direct control of the local admins. Assumptions Reference Description AS001 The benefits of moving the LSS systems to a cloud environment outweigh the risks. AS002 The alarm module (not in scope for this document) is configured to be highly available. AS003 Someone with more than 2 days of AWS ‘knowledge’ will implement the final solution.
  • 7. 6 | P a g e OBJECTIVE A 1. Design an environment that includes a. A web based time tracking application for the botanists in the greenhouses. b. A critical enterprise life support system application. 2. Define all application requirements. Common Infrastructure services The following systems will be centrally installed to provide infrastructure services to, amongst others, both the LSS application and the Time tracking application. PTP Time synchronization Accurate time synchronization is essential in any environment and especially in a control environment like the LSS to ensure that datatime stamp records from all the sensor driven components are accurate. This allows specific condition sets to be identified and acted upon. (I.e. increased light, pressure and thermal reading at the same time probably means that someone just lit a cigarette in the oxygen chamber and will be requiring medical assistance). In addition to this the time synchronization sub system will most likely also be used for scientific systems (which are not in scope for this document) but would need highly precise time synchronization. This environment will use the IEEE 1588 PTP (Precision Time Protocol) as it is:  More accurate than NTP and  Less expensive than GPS (especially if you need to start launching satellites.) Requirements:  Boundary clocks located in both the cloud environment + onsite environment.  Grandmaster and clients must reside in the same PTP domain.  PTP will be run in Unicast mode (Redfog (AWS) does not support multicast) which will require that the master is added to the Acceptable Master Table in each slave. LDAP and DNS LDAP and DNS services will be provided throughout the environment by the 3 Domain controllers for ‘base.mars’ domain.  APDC1.base.mars  WPDC1.base.mars  FPDC1.base.mars Each domain controller will be deployed to a separate availability zone and each will be configured as Global Catalog Servers.
  • 8. 7 | P a g e Time tracking application Functional Requirements: Reference Description TTR01 Should provide web based access to botanists. TTR02 Should store time data the last 15 months. TTR03 Last 30 days of data must be backed up. Level Overview High Availability The time tracking system is not considered to be critical and as such does not require any level of redundancy. Backups will be taken every day to ensure that data can be restored if needed. Retention period is set to 30 days as the botanists are known to query each pay slip and it is needed to have at least the last month’s data available if challenged. Components The time tracking environment will consist of a single server with the following 3 applications running. 1. Web interface: nginx 2. Application layer: PHP running Symfony 2 3. Database layer: MySQL Requirements Scope Requirement CPU 1 Memory 2 GB Storage – OS + Application 30 GB Storage - Data 70 GB Network - Connections 1x Ethernet Network – Bandwidth Low Botanists are not known to track their time regularly.
  • 9. 8 | P a g e LSS Conceptual Design Application layout The LSS will use a 3 level structure as shown in the diagram below. It will also be split between local onsite components that require hardwire analogue connections to the various sensors and actuators and the cloud based components that will communicate via Ethernet. The benefits of using this approach are: 1. Modularity: Allows new components (upgrades, repairs, etc.) to be inserted without requiring a complete redesign of all levels. 2. Scalability: As the base grows, new habitable areas requiring LSS can easily be added by installing local level 3 components and connecting them to the existing level 2 systems. [APR06] 3. Granularity: Provides multiple differing layers of redundancy that can be defined on a level by level basis to reduce costs and increase HA. Emergency Control (EC) The emergency control module is located in the local site. As it is a separated fail safe mechanism for the core Life Support System no independent redundancy is required. The EC monitors upper level availability and in case of catastrophic failure of Level 1 or 2 will take over control of Level 3 and maintain a basic life supporting environment until the issues are repaired.[APR03] The module will be completely segregated (different Hardware, OS and software) from the core LSS as shown below to prevent issues bringing down the core systems and also affecting the Emergency control:
  • 10. 9 | P a g e Level 3 Architectural design Functional Requirements: Reference Description L3R01 Receive and send analogue data L3R02 Convert analogue signals to digital and vice versa L3R03 Receive and send digital data via Ethernet to and from Level 2 Level Overview High Availability No application level high availability is needed as redundancy is ensured on the hardware level as shown above. Each Sensor bundle and Actuator set is connected to its own separated Level 3 compute module. Each habitable area will have at least 3 sensor bundles and 2 actuator sets per room as illustrated. This forms a hardware redundancy group for that habitable area. Components Sensors The sensors are responsible for providing environmental data to the L3 compute modules. Each sensor bundle will consist of a number of different sensors types, each of which will send telemetry data messages at fixed intervals based on criticality of that metric. Actuators The actuators are responsible for carrying out the command messages sent from L3 Compute modules to influence various aspects of the environment. Compute modules Level 3 compute modules will not need to be very powerful as their main role will be to function as Analogue Digital convertors. Any microcomputer (i.e. Raspberry Pi) with an ADC module will suffice.
  • 11. 10 | P a g e Data flows The following diagram details the basic data flows derived from the Level 3 functions. Capacity requirements Level 3 does not store any data locally but does generate data that needs to be accounted for in the higher levels. The table below summarizes the minimum storage capacity requirement as generated by Level 3 components. Capacity calculations are shown in Appendix A. Daily Total sensor data (GB) Daily Total actuator data (GB) Daily Total combined data (GB) Yearly Total combined data 0.484 0.155 0.623 233 GB Network requirements Connections 1. Analogue connections : Level 3 - SensorsArrays 2. Ethernet: Level 3 - Level 2 Bandwidth The minimum required Bandwidth between Level 3 and Level 2 is, based on similar systems and data size calculations (Appendix A), to be at least 16kbps. Compute requirements As each sensor bundle is connected to its own level 3 compute module and tasks performed by each compute module are not CPU nor Memory intensive, it is possible to benchmark against industry standard microcomputers. (Raspberry Pi for instance is able to convert analogue to digital and transmit data via Ethernet at the required messaging frequencies) CPU: Single core (700MHz) Memory: 512 MB
  • 12. 11 | P a g e Level 2 Architectural design Functional requirements Reference Description L2R01 Must be at least 1 failure L2R02 Connectivity to Level 1 and Level 3 L2R03 Connectivity to User interface module L2R04 Connectivity to Alarm module L2R05 Support CPU and Memory intensive processing Level Overview High Availability High availability will be provided by having 3 application instances running behind a central load balancer. As these are processing units and do not have large amounts of data stored locally deployment could be scripted to quickly deploy a new instance if 1 fails. Components Processing module  Critical component  3 Application instances  1 load balancer to distribute load amongst them.  This setup provides HA [APR05] and also allows for the environment to be expanded [APR06] by simply adding additional application instances behind the load balancer. User interface module  Non critical [APR01]  1 web server Alarm module  Not in scope for the LSS design document but will be set up for high availability. [AS003]
  • 13. 12 | P a g e Capacity requirements Level 2 compute modules do not store data locally but do generate data that needs to be accounted for in the higher level (level 1). The majority of the data generated from level 2 will be related to logging. Based on similar systems and anticipated data flows it is possible to define the minimum expected storage capacity requirement generated by level 2. This is shown in the table below. Monthly log size: User interface (MB) Monthly log size: Alarm module (MB) Monthly log size: Level 3 (MB) Monthly log size: Level 1 (MB) 200 100 750 300 Total capacity requirements Monthly Combined log size (MB) Yearly Combined log size (MB) 1350 16200 Network requirements Connections 1. Ethernet: Load balancer – Level 3 2. Ethernet: Load balancer - Level 2 3. Ethernet: Level 2 – Level 1 4. Ethernet: level 2 – Level 2 (Inter instance communication) 5. Ethernet: Level 2 – Web server (user interface module) 6. Ethernet: Level 2 – Alarm module Bandwidth Peak Level 3 bandwidth (16kbps) is already incorporated above in Level 3 network requirements so will not be duplicated here. Logging traffic is expected to be 4 times more than data traffic given the anticipated checkpoints at which log data would be written to the database for each data message received from Level 3. The additional traffic generated by the User interface and Alarm module is expected, based on similar systems, to add an additional 20kbps. The minimum required bandwidth for level 2 would then be: 16kbps + 64kbps + 20kbps = 100kbps Note: As these will be the central instances for any base expansion plans that require LSS the minimum bandwidth will be defined as 10 Mbps. Compute requirements As the layer 2 processing modules are relatively memory intensive as compared to other resource usage the following specifications have been calculated as being the minimum requirements per instance. CPU: 2 x 2.2MHz Memory: 15 GB Instances will be monitored throughout the initial first month and if required then additional resources can be added.
  • 14. 13 | P a g e Level 1 Architectural design Functional requirements Reference Description L1R01 Must support at least 1 failure L1R02 Connectivity to Level 2 L1R03 Support high IOPS L1R04 Must have enough capacity to store 2 years logs L1R05 Must have enough capacity to store 5 years of environmental data Level Overview High Availability High availability will be ensured by running an additional hot standby instance that will be able to take over in case of any issues with the active instance. In addition to this a read only copy will be created to provide additional redundancy and also allow for future expansion. [APR06] Components 1. 1 Active database instance 2. 1 hot standby database instance 3. 1 read only copy
  • 15. 14 | P a g e Capacity requirements The total database capacity requirement (taking into account required retention periods for environmental data [APR04] and log data [APR04] and including log data generated by level 1 components) is shown below. [APR07] 5 Year environmental data - Level 3 (GB) [APR04] 2 Year log size - Level 2 (GB) [APR04] 2 Year log size - Level 1 (GB) Total Combined database size (GB) 1165 32.4 20 1217.4 IOPS requirements Calculated IOPS requirement is <3500 Network requirements Connections 1. Ethernet: Level 2 – level 1 2. Ethernet: Level 1 – Emergency Control module The Hot standby and read only copy will be created on the hypervisor layer. Bandwidth Minimum bandwidth requirements are the same as calculated above for level 2. Minimum bandwidth: 100kbps Note: As these will be the central instances for any base expansion plans that require LSS the minimum bandwidth will be defined as 10 Mbps. Compute requirements Database compute specifications will be based on similar systems. CPU: 2 x 2.5MHz Memory: 15 GB Instances will be monitored throughout the initial first month and if required then additional resources can be added.
  • 16. 15 | P a g e OBJECTIVE B 1. Select an existing public cloud infrastructure that will be recreated on mars and justify why it was chosen. 2. Publish the environment to the selected public cloud infrastructure. Redfog cloud infrastructure While most of the major Earth based public cloud providers offer similar services and functionality Amazon web services (AWS) has been selected as the model on which to base Mars’ first public cloud infrastructure. Maturity AWS was launched in 2006 (4 years before Azure and 7 years before vCloud Air) and as such has the most experience in the field. They are (were?) also trusted by major companies with customers including NASA and the CIA proving that they are able to handle space related data and keep it safe. Functionality AWS provides a number of supported functionalities that while not used for this project could be required at a later date. 1. Native Windows Failover Clusters (even Azure has issues with this). 2. Support for Hyper-V on-premises connectivity (AWS storage gateway) 3. Multiple OS version support (RHEL for instance is not supported in Azure) 4. AWS marketplace which has the largest number of solutions available. Availability AWS provides a number of crucial availability products. 1. Availability zones and the possibility of deploying environments across multiple availability zones. 2. Auto scaling which allows new instances to be deployed automatically based on certain user defined thresholds. 3. Database hot standby and Read replicas provide simple to implement high availability protection. Compatibility Assuming that the designs from challenge 1 will be put in place then Zerto (the replication product chosen) already provides a way to easily a) migrate or b) failover to cloud the entire local environment using Zerto Virtual Replication for Amazon AWS.
  • 17. 16 | P a g e REDFOG environment The following section provides an overview of the application environment layout once deployed to Redfog and follows up with the mapping of the individual infrastructure agnostic components defined in Objective A onto the individual Redfog products.
  • 18. 17 | P a g e Common infrastructure services PTP server 3 Servers will be deployed (1 Grandmaster + 2 Boundary clocks) in VPC 1. Instance Instance Type OS CPU Mem Network Availability Zone Storage AWS Backups Notes APTP1 t2.micro RHEL 7.1 1 (2.5GHz) 1GB VPC1 – LowModerate Zone 1 20GB Magnetic No WPTP2 t2.micro RHEL 7.1 1 (2.5GHz) 1GB VPC1 – LowModerate Zone 1 20GB Magnetic No FPTP3 t2.micro RHEL 7.1 1 (2.5GHz) 1GB VPC1 – LowModerate Zone2 20GB Magnetic No Domain controllers 3 deployed (VPC1) Domain controllers will be used instead of the AWS Directory service as this does not provide future capabilities like multi-factor authentication or domain trusts except when deploying an AD Connector however that would require an existing onsite MS Active Directory which is not available. Instance Instance Type OS CPU Mem Network Availability Zone Storage AWS Backups Notes APDC1 t2.medium WS2012 Std. 2(2.5GHz) 4GB VPC1 – LowModerate Zone 1 50GB Magnetic No WPDC1 t2.medium WS2012 Std. 2(2.5GHz) 4GB VPC1 – LowModerate Zone 2 50GB Magnetic No FPDC1 t2.medium WS2012 Std. 2(2.5GHz) 4GB VPC1 – LowModerate Zone 3 50GB Magnetic No Time tracker Based on requirements the following product will be deployed in a separate subnet (VPC2) as follows: Instance Instance Type CPU Mem Network Multi-AZ Storage AWS Backups Notes WPTT1 db.t2.small 1 2GB VPC2 -Low No 100 GB Magnetic 35 day retention Publicly accessible: Yes The following components will be used  Web: nginx  App: PHP running Symfony 2  DB: MySQL
  • 19. 18 | P a g e Life Support system Level 2 Application layer The LSS Application modules will be set up as part of an Auto scaling group to ensure that there are always 3 instances available. The Auto Scaling Group will stretch across 3 Availability Zones. Application deployment will be handled using AWS CodeDeploy. Instance Instance Type CPU Mem Network Availabilit y Zone Storage Backups Notes APLSS1 m4.large WS2012 Standard 2 (2.4GHz) 15GB VPC – High Multi AZ 100GB - SSD 35 day retention 300 IOPS APLSS2 m4.large WS2012 Standard 2 (2.4GHz) 15GB VPC – High Multi AZ 100GB - SSD 35 day retention 300 IOPS APLSS3 m4.large WS2012 Standard 2 (2.4GHz) 15GB VPC – High Multi AZ 100GB - SSD 35 day retention 300 IOPS Load balancer An Elastic Load Balancer will be created within the main VPC to balance the load across the Application instances. The ELB will stretch across all AZ subnets. Health Check Protocol: TCP Ping Port: 4700 Response timeout: 5 seconds Health Check Interval: 10 seconds Unhealthy Threshold: 3 Healthy Threshold: 5 ELB will be bound to all 3 Application instances and Cross zone load balancing will be enabled User Interface The web server for the user interface will use the following to run nginx web server. Instance Instance Type CPU Mem Network Availabilit y Zone Storage Notes FPGUI1 t2.small RHEL 7.1 1 (2.4GHz) 2GB VPC –Low to Moderate default to Zone 3 30GB - Magnetic 300 IOPS – auto config
  • 20. 19 | P a g e Level 1 MySQL 5.6 has been chosen for this environment as it allows the following:  Allows the creation of read replicas  Allows the read replica to be created in a separate Availability Zone (MySQL 5.6 only) The level 1 database layer will be deployed as follows: Instance Instance Type CPU Mem Network Availability Zone Storage Backups Notes APDB1 db.m3.xlarge 4 (2.5GHz) 15GB VPC – High Multi AZ 2TB - SSD 35 day retention MySQL 5.6.23 6000 IOPS – minimum configurable Not publicly accessible Includes Hot standby Includes read replica
  • 21. 20 | P a g e Appendix A – Level 3 Data sizing Telemetry and Command traffic. Sensors Telemetry and status message size (including sensor ID, datetime stamp, and meter reading) is estimated at 50 Bytes per message. Sensor type Messaging frequency Telemetry message size (Bytes) Status check frequency Status message size – return trip Oxygen 3s 50 2s 50 Nitrogen 3s 50 2s 50 CO2 3s 50 2s 50 Hydrogen 3s 50 2s 50 Contaminates 3s 50 2s 50 Pressure 3s 50 2s 50 Radiation 3s 50 2s 50 Heat 10s 50 2s 50 Light 60s 50 2s 50 Humidity 60s 50 2s 50 Number of sensors required  1 Sensor bundle per 200M3 or per room if smaller separated rooms are used.  Assuming that the maximum measured area would be a single 1000M3 room. Measured area (M3 ) Sensor bundles needed per 200M3 Number of sensor bundles (N) Total number of redundant sensor bundles (3N) Daily data size per bundle (MB) Total daily data size (MB) 1000 1 5 15 32 484 Actuators The actuators are responsible for carrying out the command messages sent from L3 Compute modules to influence various aspects of the environment. Command and status message size (including sensor ID, datetime stamp, and meter reading) is estimated at 50 Bytes per message. Actuator type Messaging frequency - estimated average Command message size (Bytes) Status check frequency Status message size – return trip (Bytes) Light control 120s 50 2s 50 Atmosphere control 120s 50 2s 50 Vent control 120s 50 2s 50 Pressure control 60s 50 2s 50 Thermal control 30s 50 2s 50 Fire suppressing control 240s 50 2s 50 Alarm control 240s 50 2s 50 Number of actuator sets required  Estimated at 1 actuator set per 100M3 or per room if smaller separated rooms are used.  Assuming that the maximum measured area would be a single 1000M3 room. Measured area (M3 ) Actuator sets needed per 100M3 Number of actuator sets (N) Total number of redundant actuator sets (2N) Daily data size per set (MB) Total daily data size (MB) 1000 1 5 10 15 155
  • 22. 21 | P a g e References Arnold, Douglas. "Unicast PTP." 2014. <http://blog.meinbergglobal.com/2014/04/16/unicast-ptp/>. Texas Instruments. "AN-1728 IEEE 1588 Precision Time Protocol Time." 2013. <http://www.ti.com/lit/an/snla098a/snla098a.pdf>.