®



                   Volume 12 Number 02 - February 2012
World Pipelines	                                         FEBRUARY 2012   www.energyglobal.com
Figure 1. Crossing the Waupisoo River.
Scheduled

     for
                                                      Hubert Geier,
                                                  Managing Director,
                                                     Linear Project,
                                                  Germany, explains
                                                     the advantages
                                                            of linear
                                                      scheduling for
                                                   pipeline projects.




     success
     T
               raditional planning and scheduling software for the
               construction industry is dominated by Primavera
               and Microsoft Project. Both solutions enable a
               planner to develop a series of activities that are
     logically connected, to provide a sequence of events from
                                                                                 linear project such as a pipeline, high voltage power lines, rail
                                                                                 system or roadway.
                                                                                     The Gantt chart, with tasks grouped and sorted in different
                                                                                 ways, is the most common approach these programmes use
                                                                                 to present schedules. Using traditional planning software, the
     project start to finish. While these tools are designed for                 project execution can only be represented by increasing the
     the construction of buildings and other facilities (power                   number of tasks to split the work of a crew into many small
     generating stations, refineries, etc.), they are not adequate               parts to reflect the constructability issues (i.e., reverse lays,
     for the constructability issues and demands of building a                   environmental restrictions) of the project. The end result is




58

                                                   Reprinted from FEBRUARY 2012 | World pipelines
large schedules that do not readily provide an overview of the   the tasks and resource usage, as well as the sequencing and
interaction between site and schedule.                           direction of the work.
    The difference in a linear project, such as a pipeline, is       This article introduces TILOS, a linear planning and
that the work is highly repetitive, with the crews moving        management tool that through the use of march charts (also
along a defined right‑of‑way (ROW). Changing site conditions,    known as time distance diagrams), enables a pipeline planner
environmental and regulatory constraints impact the              to integrate the schedule with the site data and logistical
production methods, work rate and the logistics of building      constraints. Rather than presenting the plan as a series of
the pipeline along the length of the project. The planner        Gantt bars, this approach allows the planner to integrate
always needs to be aware of these conditions when planning       and print as much detail as required about the schedule on
                                                                                                      a single page. This detail
                                                                                                      can include elevation
                                                                                                      profiles, land acquisition,
                                                                                                      environmental windows,
                                                                                                      crossings and crew
                                                                                                      movement and direction of
                                                                                                      travel.
                                                                                                           The key is the use of
                                                                                                      two axes: the time and the
                                                                                                      location axis in a 2D grid. In
                                                                                                      Figure 2, the location axis
                                                                                                      is horizontal and the time
                                                                                                      axis is vertical, but this can
                                                                                                      be changed on demand.
                                                                                                      Each task is defined by the
                                                                                                      start and end co‑ordinates
                                                                                                      in both time and location.
                                                                                                      The line between these
                                                                                                      points defines the task and
                                                                                                      describes when the crew
                                                                                                      is at a specific location.
                                                                                                      The slope of the line
Figure 2. An example of a TILOS 1 page time-distance plan.                                            indicates the speed of
                                                                                                      each crew in the different
                                                                                                      segments. The steeper the
                                                                                                      slope, the slower the crew
                                                                                                      is moving. Furthermore,
                                                                                                      the sequence of tasks in
                                                                                                      pipeline construction is
                                                                                                      strongly determined by
                                                                                                      the production processes,
                                                                                                      one crew cannot overtake
                                                                                                      the other. Using TILOS,
                                                                                                      any lines that cross
                                                                                                      immediately indicate
                                                                                                      clashes.
                                                                                                           Activities such as
                                                                                                      horizontal directional drills,
                                                                                                      road bores or mainline
                                                                                                      block valves are typically
                                                                                                      shown as rectangles
                                                                                                      because the crews are
                                                                                                      working in one location.
                                                                                                      Environmental constraints
                                                                                                      and hydrotest segments are
                                                                                                      also typically represented
                                                                                                      by rectangles, as these are
                                                                                                      clearly defined in time and
Figure 3. Linear schedule with ribbons.                                                               distance.



                                                                                              Reprinted from FEBRUARY 2012 | World pipelines
Connecting alignment sheets with the schedule                                using the ‘clearing’ profile and is shown as a table. The table
In the pipeline industry, detailed information about the ROW                 also represents the land coverage showing each type as a
is documented in the alignment sheets that are typically                     different colour. The work rate in the last column adjusts the
prepared with CAD systems. This information includes:                        work rate of the clearing task for that segment.
elevation, crossings, pipe thickness and type, pipe weight
requirements, environmental restrictions, land permitting, and               Integrating GPS data
municipal districts that the pipeline is traversing.                         The integration of maps and satellite can further enhance
    This type of information is added in a TILOS view as a                   the time distance diagram. If GPS co-ordinates are available,
ribbon along the distance axis that represents the ROW. These                the ROW can be drawn as a route on a map and the pictures
ribbons can contain graphs that are generated using TILOS                    can be added to the TILOS view. Locations of crossings,
profile data, which are easily imported from Excel or other                  camps, stockpiles and access roads to the ROW are important
data files. Thus, a time distance diagram looks similar to an                components of the planning process. All of these can be
alignment sheet but also has an extra ROW that displays the                  readily identified and located in TILOS using GPS data during
schedule in a march chart form.                                              planning.
    Figure 3 shows the main crew movements as different                          TILOS is able to slice the task data to any time period or
coloured lines. The road bores and the hydrotest tasks are                   distance section. By mapping the KP values of the tasks to
shown as rectangles. The area between KP 59+000 and 62+600                   the GPS co-ordinates of the ROW, each task can be shown in
(where the pipeline is crossing a valley) is represented in the              the map view as well. Setting time filters, snap shots of the
overview plan by just a single summary task. This section is                 progress can be shown. Furthermore, it allows a simulation of
performed by a special crew and is detailed in another time                  the construction process by moving the time stepwise forward
distance diagram using a different scale to show more details.               and adding the built section for the time periods.
    Environmental restrictions and land tracks that have not
been acquired are monitored as rectangles to indicate that                   Reporting and controlling
there is no access to these areas. Each crew line touching                    During project execution, the time distance diagram is a
these objects represents a clash and the planner is notified of               valuable tool as it provides all the necessary information
these events during a reschedule in TILOS. In Figure 3, the blue              about stockpile sites, restricted access, crew locations, and
rectangle indicates a weather restriction that the planner has                access roads to plan the daily construction.
had to consider in developing the project execution strategy.                      Daily progress is typically recorded in worksheets that
    Figure 4 shows a portion of the entire schedule discussed                 are then entered into Excel or a company‑owned reporting
earlier. In this view, a filter has been applied to display                   system. This progress data is easily imported into TILOS using
only the clearing activity. The different clearing work rates                 its extended import facilities and allows the construction team
(here m/d) along the ROW are indicated by the changing slope                  to monitor the progress along the ROW. While traditional
of the task line and the differential work rate is generated                  project management systems report on a % completed for
                                                                                                                   each task, TILOS also records
                                                                                                                   the location and date where
                                                                                                                   the work has been executed.
                                                                                                                   Recording both the time
                                                                                                                   and location of completed
                                                                                                                   activities quickly identifies
                                                                                                                   where move arounds and work
                                                                                                                   stoppages have occurred.
                                                                                                                       Finally, a good progress
                                                                                                                   overview can be achieved
                                                                                                                   using the distance‑based
                                                                                                                   Gantt chart in TILOS. This is a
                                                                                                                   unique feature that show bars
                                                                                                                   along a distance axis (not using
Figure 4. Clearing crew with a variable work rate.                                                                 a time axis that is typical of
                                                                                                                   Gantt charts). By grouping the
                                                                                                                   task by crew and filtering for
                                                                                                                   only performed sections, the
                                                                                                                   distance Gantt chart clearly
                                                                                                                   displays the sections that
                                                                                                                   each crew has completed.
                                                                                                                   Other information can also
                                                                                                                   include earned value analysis
                                                                                                                   on a crew or project basis.
Figure 5. Satellite view with pipeline route, crossings and progress situation.
                                                                                                                   This includes: % completed



Reprinted from FEBRUARY 2012 | World pipelines
to date, % complete planned,
completed quantity, remaining
quantity, earned value and
schedule variance. A distance
Gantt chart is shown in
Figure 5.
    TILOS calculates the
expected end date using the
actual work rate to date. After
rescheduling, any remaining
work can be easily planned
using a new work rate required
to recover the baseline end
date if necessary.

Integration concepts              Figure 6. Progress in a march chart and distance Gantt chart.
Compiling all this information
into the plan does not
necessarily mean that a lot of effort is required. Most of the           data to the company portfolio management tools, such as
information is already available and can be imported into                Oracle’s Primavera using the API integration tools developed
TILOS during the planning phase.                                         for TILOS. The software exchange module can import the
    In TILOS, most graphs are not simply pictures but are                whole project including WBS structures and resource usage
generated based on grid data that can be easily imported.                into Primavera Project management. For MS Project, a similar
Spreadsheets, the most common tool used by engineers for                 integration is available using a VBA application that can build
calculation and management, are easily imported into the                 the whole project from scratch.
software by using the clipboard or importing XML data.
    The TILOS template strategy allows a planner to setup                Summary
a project in a minimum amount of time. The layout of the                 This article has shown a new approach to the traditional
view, including ribbons, and the standard task templates                 planning methodology. By visually developing the
with predefined work rates can be predefined and saved as a              project, while incorporating all known constraints and
TILOS template. New projects are then created based on this              constructability issues, the planner can readily develop a
template. Setting the execution time and the distance axis               feasible execution plan. Using the layer‑based cell system in
values adjusts all the views in the project automatically.               TILOS, as much detail as required by the planner and project
    The planning starts by importing site data such as                   team can be incorporated into a TILOS view. Company
crossings, county list and elevation to generate the ribbons             tailored templates reduce the work efforts and costs for
for the view. Activities can be added by drawing them directly           planning by providing more precision during the early
on the view or importing them from Excel or another project              planning phase.
management system.                                                           Many owner organisations now require a march chart
                                                                         submission as part of the bid package so that the contractor
Portfolio management                                                     can demonstrate an understanding of the constructability
In many large organisations, TILOS is used to plan and control           issues and constraints and to prove that the work can be
individual projects because of its comprehensive schedule                completed in the required timeframe.
presentation. In these organisations, TILOS is used to push




                                                                               COMING NEXT MONTH




                                                                                                     Reprinted from FEBRUARY 2012 | World pipelines

More Related Content

PPTX
PDF
2006 tres tipos_de_saber_del_profesor_y_competencias_una_relacion_compleja_za...
PPTX
1 ux בשירות הממסד הפיננסי
PPTX
Tim Marston.
PPSX
Grosse Ile High School
DOCX
Lecture notes elasticity
PDF
rcs / cvs はもうやめよう
DOCX
Qustionaire (ranbir kumar singh)
2006 tres tipos_de_saber_del_profesor_y_competencias_una_relacion_compleja_za...
1 ux בשירות הממסד הפיננסי
Tim Marston.
Grosse Ile High School
Lecture notes elasticity
rcs / cvs はもうやめよう
Qustionaire (ranbir kumar singh)

Viewers also liked (10)

PDF
MRAI, BGP Widthdrawn and Packet Loss
PDF
ルーティングチュートリアル - AS間経路制御
PPTX
Business Case Analysis - Indomie
PPT
Jenis - Jenis Musik
PPTX
Pr 4.0 - VAGABOND AND COMPANY Marketing Group
DOCX
Excel.
PDF
Crystal Saga guide for Thailand
DOCX
Excel
DOCX
Word.
PPTX
Bilangan cacah
MRAI, BGP Widthdrawn and Packet Loss
ルーティングチュートリアル - AS間経路制御
Business Case Analysis - Indomie
Jenis - Jenis Musik
Pr 4.0 - VAGABOND AND COMPANY Marketing Group
Excel.
Crystal Saga guide for Thailand
Excel
Word.
Bilangan cacah
Ad

Similar to World pipeline tilos_article (20)

PDF
TILOS: World Pipelines Article
PDF
Utilizing Linear Planning and Scheduling for Project Control and Claims Avoid...
PPT
Linear scheduling LSM
PDF
RBF in ENR on BIM
PDF
HCLT Brochure: Mobile Data Terminal - Maintenance of Way (MOW)
PDF
Outdoor Advertising Professionals Pvt (I) Ltd
PDF
Using Value Stream Mapping As a Strategic Planning & Implementation Tool
PPTX
Project scheduling and planning ppt for study
PDF
Using TILOS in Pipelines
PPT
L6.2 planing&scheduling
PDF
PDF
Smart Grid Operational Services GIS POV
PPTX
Vico Office - 5D BIM
PPTX
Emergency Management
PDF
Presentation Classification Of Schedule Types
PDF
perini 2005_Second_Century
PDF
10. Urban Development Capability Statement
PDF
PDF
Creating a Complete Street Active Transportation Network - Mark Goode III
TILOS: World Pipelines Article
Utilizing Linear Planning and Scheduling for Project Control and Claims Avoid...
Linear scheduling LSM
RBF in ENR on BIM
HCLT Brochure: Mobile Data Terminal - Maintenance of Way (MOW)
Outdoor Advertising Professionals Pvt (I) Ltd
Using Value Stream Mapping As a Strategic Planning & Implementation Tool
Project scheduling and planning ppt for study
Using TILOS in Pipelines
L6.2 planing&scheduling
Smart Grid Operational Services GIS POV
Vico Office - 5D BIM
Emergency Management
Presentation Classification Of Schedule Types
perini 2005_Second_Century
10. Urban Development Capability Statement
Creating a Complete Street Active Transportation Network - Mark Goode III
Ad

Recently uploaded (20)

PPTX
Share_Module_2_Power_conflict_and_negotiation.pptx
PDF
Environmental Education MCQ BD2EE - Share Source.pdf
PPTX
DRUGS USED FOR HORMONAL DISORDER, SUPPLIMENTATION, CONTRACEPTION, & MEDICAL T...
PDF
LIFE & LIVING TRILOGY- PART (1) WHO ARE WE.pdf
PDF
Literature_Review_methods_ BRACU_MKT426 course material
PDF
FOISHS ANNUAL IMPLEMENTATION PLAN 2025.pdf
PPTX
B.Sc. DS Unit 2 Software Engineering.pptx
PDF
BP 505 T. PHARMACEUTICAL JURISPRUDENCE (UNIT 2).pdf
PDF
David L Page_DCI Research Study Journey_how Methodology can inform one's prac...
PDF
LEARNERS WITH ADDITIONAL NEEDS ProfEd Topic
PPTX
ELIAS-SEZIURE AND EPilepsy semmioan session.pptx
PDF
Vision Prelims GS PYQ Analysis 2011-2022 www.upscpdf.com.pdf
PDF
Journal of Dental Science - UDMY (2021).pdf
PPTX
Unit 4 Computer Architecture Multicore Processor.pptx
PDF
BP 704 T. NOVEL DRUG DELIVERY SYSTEMS (UNIT 2).pdf
PDF
Empowerment Technology for Senior High School Guide
PPTX
A powerpoint presentation on the Revised K-10 Science Shaping Paper
PDF
English Textual Question & Ans (12th Class).pdf
PDF
HVAC Specification 2024 according to central public works department
PDF
CISA (Certified Information Systems Auditor) Domain-Wise Summary.pdf
Share_Module_2_Power_conflict_and_negotiation.pptx
Environmental Education MCQ BD2EE - Share Source.pdf
DRUGS USED FOR HORMONAL DISORDER, SUPPLIMENTATION, CONTRACEPTION, & MEDICAL T...
LIFE & LIVING TRILOGY- PART (1) WHO ARE WE.pdf
Literature_Review_methods_ BRACU_MKT426 course material
FOISHS ANNUAL IMPLEMENTATION PLAN 2025.pdf
B.Sc. DS Unit 2 Software Engineering.pptx
BP 505 T. PHARMACEUTICAL JURISPRUDENCE (UNIT 2).pdf
David L Page_DCI Research Study Journey_how Methodology can inform one's prac...
LEARNERS WITH ADDITIONAL NEEDS ProfEd Topic
ELIAS-SEZIURE AND EPilepsy semmioan session.pptx
Vision Prelims GS PYQ Analysis 2011-2022 www.upscpdf.com.pdf
Journal of Dental Science - UDMY (2021).pdf
Unit 4 Computer Architecture Multicore Processor.pptx
BP 704 T. NOVEL DRUG DELIVERY SYSTEMS (UNIT 2).pdf
Empowerment Technology for Senior High School Guide
A powerpoint presentation on the Revised K-10 Science Shaping Paper
English Textual Question & Ans (12th Class).pdf
HVAC Specification 2024 according to central public works department
CISA (Certified Information Systems Auditor) Domain-Wise Summary.pdf

World pipeline tilos_article

  • 1. ® Volume 12 Number 02 - February 2012 World Pipelines FEBRUARY 2012 www.energyglobal.com
  • 2. Figure 1. Crossing the Waupisoo River.
  • 3. Scheduled for Hubert Geier, Managing Director, Linear Project, Germany, explains the advantages of linear scheduling for pipeline projects. success T raditional planning and scheduling software for the construction industry is dominated by Primavera and Microsoft Project. Both solutions enable a planner to develop a series of activities that are logically connected, to provide a sequence of events from linear project such as a pipeline, high voltage power lines, rail system or roadway. The Gantt chart, with tasks grouped and sorted in different ways, is the most common approach these programmes use to present schedules. Using traditional planning software, the project start to finish. While these tools are designed for project execution can only be represented by increasing the the construction of buildings and other facilities (power number of tasks to split the work of a crew into many small generating stations, refineries, etc.), they are not adequate parts to reflect the constructability issues (i.e., reverse lays, for the constructability issues and demands of building a environmental restrictions) of the project. The end result is 58 Reprinted from FEBRUARY 2012 | World pipelines
  • 4. large schedules that do not readily provide an overview of the the tasks and resource usage, as well as the sequencing and interaction between site and schedule. direction of the work. The difference in a linear project, such as a pipeline, is This article introduces TILOS, a linear planning and that the work is highly repetitive, with the crews moving management tool that through the use of march charts (also along a defined right‑of‑way (ROW). Changing site conditions, known as time distance diagrams), enables a pipeline planner environmental and regulatory constraints impact the to integrate the schedule with the site data and logistical production methods, work rate and the logistics of building constraints. Rather than presenting the plan as a series of the pipeline along the length of the project. The planner Gantt bars, this approach allows the planner to integrate always needs to be aware of these conditions when planning and print as much detail as required about the schedule on a single page. This detail can include elevation profiles, land acquisition, environmental windows, crossings and crew movement and direction of travel. The key is the use of two axes: the time and the location axis in a 2D grid. In Figure 2, the location axis is horizontal and the time axis is vertical, but this can be changed on demand. Each task is defined by the start and end co‑ordinates in both time and location. The line between these points defines the task and describes when the crew is at a specific location. The slope of the line Figure 2. An example of a TILOS 1 page time-distance plan. indicates the speed of each crew in the different segments. The steeper the slope, the slower the crew is moving. Furthermore, the sequence of tasks in pipeline construction is strongly determined by the production processes, one crew cannot overtake the other. Using TILOS, any lines that cross immediately indicate clashes. Activities such as horizontal directional drills, road bores or mainline block valves are typically shown as rectangles because the crews are working in one location. Environmental constraints and hydrotest segments are also typically represented by rectangles, as these are clearly defined in time and Figure 3. Linear schedule with ribbons. distance. Reprinted from FEBRUARY 2012 | World pipelines
  • 5. Connecting alignment sheets with the schedule using the ‘clearing’ profile and is shown as a table. The table In the pipeline industry, detailed information about the ROW also represents the land coverage showing each type as a is documented in the alignment sheets that are typically different colour. The work rate in the last column adjusts the prepared with CAD systems. This information includes: work rate of the clearing task for that segment. elevation, crossings, pipe thickness and type, pipe weight requirements, environmental restrictions, land permitting, and Integrating GPS data municipal districts that the pipeline is traversing. The integration of maps and satellite can further enhance This type of information is added in a TILOS view as a the time distance diagram. If GPS co-ordinates are available, ribbon along the distance axis that represents the ROW. These the ROW can be drawn as a route on a map and the pictures ribbons can contain graphs that are generated using TILOS can be added to the TILOS view. Locations of crossings, profile data, which are easily imported from Excel or other camps, stockpiles and access roads to the ROW are important data files. Thus, a time distance diagram looks similar to an components of the planning process. All of these can be alignment sheet but also has an extra ROW that displays the readily identified and located in TILOS using GPS data during schedule in a march chart form. planning. Figure 3 shows the main crew movements as different TILOS is able to slice the task data to any time period or coloured lines. The road bores and the hydrotest tasks are distance section. By mapping the KP values of the tasks to shown as rectangles. The area between KP 59+000 and 62+600 the GPS co-ordinates of the ROW, each task can be shown in (where the pipeline is crossing a valley) is represented in the the map view as well. Setting time filters, snap shots of the overview plan by just a single summary task. This section is progress can be shown. Furthermore, it allows a simulation of performed by a special crew and is detailed in another time the construction process by moving the time stepwise forward distance diagram using a different scale to show more details. and adding the built section for the time periods. Environmental restrictions and land tracks that have not been acquired are monitored as rectangles to indicate that Reporting and controlling there is no access to these areas. Each crew line touching During project execution, the time distance diagram is a these objects represents a clash and the planner is notified of valuable tool as it provides all the necessary information these events during a reschedule in TILOS. In Figure 3, the blue about stockpile sites, restricted access, crew locations, and rectangle indicates a weather restriction that the planner has access roads to plan the daily construction. had to consider in developing the project execution strategy. Daily progress is typically recorded in worksheets that Figure 4 shows a portion of the entire schedule discussed are then entered into Excel or a company‑owned reporting earlier. In this view, a filter has been applied to display system. This progress data is easily imported into TILOS using only the clearing activity. The different clearing work rates its extended import facilities and allows the construction team (here m/d) along the ROW are indicated by the changing slope to monitor the progress along the ROW. While traditional of the task line and the differential work rate is generated project management systems report on a % completed for each task, TILOS also records the location and date where the work has been executed. Recording both the time and location of completed activities quickly identifies where move arounds and work stoppages have occurred. Finally, a good progress overview can be achieved using the distance‑based Gantt chart in TILOS. This is a unique feature that show bars along a distance axis (not using Figure 4. Clearing crew with a variable work rate. a time axis that is typical of Gantt charts). By grouping the task by crew and filtering for only performed sections, the distance Gantt chart clearly displays the sections that each crew has completed. Other information can also include earned value analysis on a crew or project basis. Figure 5. Satellite view with pipeline route, crossings and progress situation. This includes: % completed Reprinted from FEBRUARY 2012 | World pipelines
  • 6. to date, % complete planned, completed quantity, remaining quantity, earned value and schedule variance. A distance Gantt chart is shown in Figure 5. TILOS calculates the expected end date using the actual work rate to date. After rescheduling, any remaining work can be easily planned using a new work rate required to recover the baseline end date if necessary. Integration concepts Figure 6. Progress in a march chart and distance Gantt chart. Compiling all this information into the plan does not necessarily mean that a lot of effort is required. Most of the data to the company portfolio management tools, such as information is already available and can be imported into Oracle’s Primavera using the API integration tools developed TILOS during the planning phase. for TILOS. The software exchange module can import the In TILOS, most graphs are not simply pictures but are whole project including WBS structures and resource usage generated based on grid data that can be easily imported. into Primavera Project management. For MS Project, a similar Spreadsheets, the most common tool used by engineers for integration is available using a VBA application that can build calculation and management, are easily imported into the the whole project from scratch. software by using the clipboard or importing XML data. The TILOS template strategy allows a planner to setup Summary a project in a minimum amount of time. The layout of the This article has shown a new approach to the traditional view, including ribbons, and the standard task templates planning methodology. By visually developing the with predefined work rates can be predefined and saved as a project, while incorporating all known constraints and TILOS template. New projects are then created based on this constructability issues, the planner can readily develop a template. Setting the execution time and the distance axis feasible execution plan. Using the layer‑based cell system in values adjusts all the views in the project automatically. TILOS, as much detail as required by the planner and project The planning starts by importing site data such as team can be incorporated into a TILOS view. Company crossings, county list and elevation to generate the ribbons tailored templates reduce the work efforts and costs for for the view. Activities can be added by drawing them directly planning by providing more precision during the early on the view or importing them from Excel or another project planning phase. management system. Many owner organisations now require a march chart submission as part of the bid package so that the contractor Portfolio management can demonstrate an understanding of the constructability In many large organisations, TILOS is used to plan and control issues and constraints and to prove that the work can be individual projects because of its comprehensive schedule completed in the required timeframe. presentation. In these organisations, TILOS is used to push COMING NEXT MONTH Reprinted from FEBRUARY 2012 | World pipelines