Customer Case Study
Implementation, Training
AutoCAD
Autodesk Revit
Autodesk Navisworks Manage
Autodesk Building Design Suite
“
We will be using more BIM and Revit
with energy modeling on all sustainable
projects moving forward.”
Keith G. Pehl, P.E., LEED
President/Electrical Engineer
Optima Engineering, P.A.
Optima Engineering, P.A.
www.optimaengineering.com
1927 South Tryon Street Suite 300
Charlotte, North Carolina 28203
333 Fayetteville Street, Suite 311
Raleigh, NC 27601
®
®
®
®
Embracing Sustainability with Clash
Detection and BIM
Optima Engineering utilized Autodesk Navisworks Manage clash detection
during the design phase of the Warriors in Transition building for the Army
Company Overview
Optima Engineering is a multi discipline,
professional engineering firm
specializing in mechanical, electrical,
plumbing, fire protection, lighting,
sustainable design, commissioning and
energy audit services. The firm has
positioned itself as a leader in
sustainable design for the industries it
serves. Over the past 8 years, Optima
has positioned itself as a pioneer in the
green building industry in North
Carolina. Five years ago, they decided to
practice what they’ve preached in
constructing the first LEED Platinum
building in Charlotte, North Carolina.
Working through the LEED process for
their headquarters, with a solar PV
system and solar water heating, Optima
found they were motivated to truly
embrace sustainability. With the
industry focused on energy
consumption, efficiency and savings
within building systems, Optima is
endorsing the 2030 Challenge. Keith G.
Pehl, P.E.,LEED AP BD+C,
President/Electrical Engineer says, “We
are striving for net zero energy and
carbon impact by 2030. In order to make
this a reality, we are actively seeking
visionary clients.”
Business Problem/Compelling Event
In 2009, Optima was awarded a contract
for The Warriors in Transition (WIT)
building for the U.S. Army Corps of
Engineers who mandated BIM. The
3-story office
building, designated for the Warriors
Transition Unit in Ft. Stewart, GA had to
meet strict federal guidelines with
efficient, sustainable design, while
providing a quantifiable cost savings
within the building systems.
This is where the design-build team’s
collaboration in Autodesk Revit became
necessary. Optima needed to align all of
the project partners through Building
Information Modeling (BIM) in order to
coordinate clash detection using
Autodesk Navisworks Manage and Revit
software. In order to do this, they needed
to upgrade their entire software system
with AutoCAD, AutoCAD MEP, Revit MEP,
Navisworks Manage and Building Design
Suite Ultimate.
The Solution
Optima turned to Advanced Solutions
early in the BIM process to guide them
through the project. Over a six month
timespan Advanced Solutions helped
them implement an entirely new software
with systems upgrade, they provided
customized personal training with each
member of their team, as well as all
collaborative partners. Advanced
Solutions phased in each new software
system and used it within the WIT project
using actual models and specifications,
giving a “real world” training experience.
The continued flexibility of the Advanced
Solutions trainer and being able to adapt
the training in conjunction with the
challenges of the actual project created a
strong partnership between each firm, the
Optima Project, Charlotte, NC
® ®
Platinum Partner
Architecture, Engineering & Construction
Manufacturing
Government Specialized
Advanced Solutions
1901 Eastpoint Parkway, Suite 301
Louisville, KY 40223
www.AdvancedSolutions.com
1-877-GET-ASI-1
client and Advanced Solutions.
The training and implementation of
Autodesk Navisworks Manage enabled
clash detection, which alerted the team
to a potential $75,000-$100,000 error
within the initial Warriors in Transition
project specifications. With what could
have easily been a costly mistake in the
field, detected within the modeling
stages of the project, Optima was able
to see the immediate ROI of this new
software integration.
Performance
Optima came to rely on more than just
the customized, project-specific
training provided by Advanced
Solutions during the BIM adoption
process, as even network and hardware
issues were addressed during the
process. As a result, a hardware
upgrade was necessary in conjunction
with the software adoption to allow
consistent access to Autodesk Revit for
everyone on the project. “Advanced
Solutions was very flexible, adapting to
what we were seeing with the project,
what others involved were noticing and
with any and all challenges thrown
their way,” said Pehl.
In addition to being provided all costs
and training time estimates in advance,
Optima was able to purchase a block of
service hours to be used at their
discretion enabling the team to call on
Advanced Solutions’ specific areas of
expertise when needed.
Results & Benefits
By the end of 2013, Optima expects over
half of their major projects will be
completed in Autodesk Revit. They are
seeing the transition take place with over
120 of their current customers. Optima
recognizes they would not have been able
to cultivate a majority of their newer
clients without having the latest MEP
software. “Given the choice our guys
would rather work in Revit on all
projects,” says Pehl.
Using Autodesk Navisworks Manage on
the back end of this project has been
beneficial in their design process and has
enabled better BIM capabilities with a
drastic decrease in change orders
resulting in a noticeable return on
investment.
Final Thoughts
Evolving each team member’s perspective
with the project specific software
implementation has been one of the
major building blocks in working with
Advanced Solutions. A level of trust has
been cultivated, which has allowed the
entire team on the Warriors in Transition
project to grow beyond expectations. The
continued collaboration with regards to
time, financial constraints and a real
world training situation, has shown a true
valued partnership with a willingness to
solve challenges as a team.
“We will be using more BIM and Revit with
energy modeling on all sustainable projects
moving forward,” says Pehl. “We now have a
long term relationship with BIM and
Advanced Solutions,” he added.
Avoiding costly mistakes with Autodesk
Navisworks Manage and Autodesk Revit
Optima Project, Charlotte, NC
Platinum Partner
Architecture, Engineering & Construction
Manufacturing
Government Specialized

More Related Content

PDF
Infographic: Mission Impossible – Concept on a Napkin to Award-Winning Innova...
PPTX
Operations class project
PPTX
Autodesk University: Designing the Future
PPTX
Why Digital Transformations are Failing at Scale
PDF
Comments provided
PPTX
How BIM Can Accelerate Project-Wide Review Cycles - Webinar, November 11, 2015
PDF
Itsm governance and infrastructure as code
PPTX
From Factories To Flow: Streamlining Software Delivery at Cubic Corporation
Infographic: Mission Impossible – Concept on a Napkin to Award-Winning Innova...
Operations class project
Autodesk University: Designing the Future
Why Digital Transformations are Failing at Scale
Comments provided
How BIM Can Accelerate Project-Wide Review Cycles - Webinar, November 11, 2015
Itsm governance and infrastructure as code
From Factories To Flow: Streamlining Software Delivery at Cubic Corporation

What's hot (20)

PDF
AVEVA World Conference NA - Alan Smith, WorleyParsons
PPTX
30 days of cloud
PPTX
Epdm Agile Webinar 3 2010 F
PDF
CCE’s EnSuite-Cloud ReVue is the Perfect Alternative to Zoom for Engineering ...
PDF
Breitburn Energy Winwire V4 (2)
PDF
bestronics_wow_final - Copy
PDF
Accelerating Product Development FLOW: Kanban at Jaguar Land Rover
PPTX
Elecosoft 4D BIM for CIOB Guildford
PPTX
Advanced Work Packaging (AWP) - Reduction to Practice
PDF
Session T6 - Artificial Intelligence Meets Project Controls
PDF
Beyond Scrum and SAFe
PDF
Data Center Transformation Cisco's Virtualization & Cloud Journey
PDF
Transformational Change in Managing Assets for Operational Excellence by Jan ...
PDF
M3 - An overview of High Speed 2
PPTX
Agile Architecture Belfast Software Architecture User Group
PPTX
Advanced Work Packaging - CCT Solutions at a Glance
PDF
AVEVA World Conference NA - Tom Singer, Aker Solutions
PDF
[SriusCon 2020] Sirius to the Web with Obeo Cloud Platform
PPTX
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
PDF
Create Radically Better Products with Design Optimization and 3D Printing
AVEVA World Conference NA - Alan Smith, WorleyParsons
30 days of cloud
Epdm Agile Webinar 3 2010 F
CCE’s EnSuite-Cloud ReVue is the Perfect Alternative to Zoom for Engineering ...
Breitburn Energy Winwire V4 (2)
bestronics_wow_final - Copy
Accelerating Product Development FLOW: Kanban at Jaguar Land Rover
Elecosoft 4D BIM for CIOB Guildford
Advanced Work Packaging (AWP) - Reduction to Practice
Session T6 - Artificial Intelligence Meets Project Controls
Beyond Scrum and SAFe
Data Center Transformation Cisco's Virtualization & Cloud Journey
Transformational Change in Managing Assets for Operational Excellence by Jan ...
M3 - An overview of High Speed 2
Agile Architecture Belfast Software Architecture User Group
Advanced Work Packaging - CCT Solutions at a Glance
AVEVA World Conference NA - Tom Singer, Aker Solutions
[SriusCon 2020] Sirius to the Web with Obeo Cloud Platform
Project Collaboration on Infrastructure Megaprojects - Webinar, June 3, 2015
Create Radically Better Products with Design Optimization and 3D Printing
Ad

Similar to optima-engineering-case-study (20)

PDF
Bim pres 120319
PDF
Built -aia_southern_arizona_article_draft_v8_send
PPTX
Go beyond design with navisworks
PDF
Paul Nunn v2
PPTX
Coordination using Navisworks or BIMsight
PDF
STUDY OF BUILDING INFORMATION MODELING PROCESS
PDF
Revit software - the best tool for an architect
PDF
key benefits of using bim clash detection with navisworks training-cmpressed.pdf
PPTX
BIM Modelling Service Provider in Canada
PDF
Key benefits of using BIM Clash Detection with Navisworks Training_compressed...
PDF
Software report
PPTX
Bim its applications
PDF
Northwestern University Building Tech Symposium Summary
PDF
REAL TIME 4D AND 5D ANALYSIS BY USING BUILDING INFORMATION MODELLING
DOC
Building Information Modeling
PPT
Implementing Building Information Modelling in Construction
PDF
ENR467723
PDF
Revit Online Training courses-BES.pdf
PDF
Alastair Gardner: BIM Overview
PDF
Top reasons for_using_building_information_modeling_-_copy
Bim pres 120319
Built -aia_southern_arizona_article_draft_v8_send
Go beyond design with navisworks
Paul Nunn v2
Coordination using Navisworks or BIMsight
STUDY OF BUILDING INFORMATION MODELING PROCESS
Revit software - the best tool for an architect
key benefits of using bim clash detection with navisworks training-cmpressed.pdf
BIM Modelling Service Provider in Canada
Key benefits of using BIM Clash Detection with Navisworks Training_compressed...
Software report
Bim its applications
Northwestern University Building Tech Symposium Summary
REAL TIME 4D AND 5D ANALYSIS BY USING BUILDING INFORMATION MODELLING
Building Information Modeling
Implementing Building Information Modelling in Construction
ENR467723
Revit Online Training courses-BES.pdf
Alastair Gardner: BIM Overview
Top reasons for_using_building_information_modeling_-_copy
Ad

optima-engineering-case-study

  • 1. Customer Case Study Implementation, Training AutoCAD Autodesk Revit Autodesk Navisworks Manage Autodesk Building Design Suite “ We will be using more BIM and Revit with energy modeling on all sustainable projects moving forward.” Keith G. Pehl, P.E., LEED President/Electrical Engineer Optima Engineering, P.A. Optima Engineering, P.A. www.optimaengineering.com 1927 South Tryon Street Suite 300 Charlotte, North Carolina 28203 333 Fayetteville Street, Suite 311 Raleigh, NC 27601 ® ® ® ® Embracing Sustainability with Clash Detection and BIM Optima Engineering utilized Autodesk Navisworks Manage clash detection during the design phase of the Warriors in Transition building for the Army Company Overview Optima Engineering is a multi discipline, professional engineering firm specializing in mechanical, electrical, plumbing, fire protection, lighting, sustainable design, commissioning and energy audit services. The firm has positioned itself as a leader in sustainable design for the industries it serves. Over the past 8 years, Optima has positioned itself as a pioneer in the green building industry in North Carolina. Five years ago, they decided to practice what they’ve preached in constructing the first LEED Platinum building in Charlotte, North Carolina. Working through the LEED process for their headquarters, with a solar PV system and solar water heating, Optima found they were motivated to truly embrace sustainability. With the industry focused on energy consumption, efficiency and savings within building systems, Optima is endorsing the 2030 Challenge. Keith G. Pehl, P.E.,LEED AP BD+C, President/Electrical Engineer says, “We are striving for net zero energy and carbon impact by 2030. In order to make this a reality, we are actively seeking visionary clients.” Business Problem/Compelling Event In 2009, Optima was awarded a contract for The Warriors in Transition (WIT) building for the U.S. Army Corps of Engineers who mandated BIM. The 3-story office building, designated for the Warriors Transition Unit in Ft. Stewart, GA had to meet strict federal guidelines with efficient, sustainable design, while providing a quantifiable cost savings within the building systems. This is where the design-build team’s collaboration in Autodesk Revit became necessary. Optima needed to align all of the project partners through Building Information Modeling (BIM) in order to coordinate clash detection using Autodesk Navisworks Manage and Revit software. In order to do this, they needed to upgrade their entire software system with AutoCAD, AutoCAD MEP, Revit MEP, Navisworks Manage and Building Design Suite Ultimate. The Solution Optima turned to Advanced Solutions early in the BIM process to guide them through the project. Over a six month timespan Advanced Solutions helped them implement an entirely new software with systems upgrade, they provided customized personal training with each member of their team, as well as all collaborative partners. Advanced Solutions phased in each new software system and used it within the WIT project using actual models and specifications, giving a “real world” training experience. The continued flexibility of the Advanced Solutions trainer and being able to adapt the training in conjunction with the challenges of the actual project created a strong partnership between each firm, the Optima Project, Charlotte, NC ® ® Platinum Partner Architecture, Engineering & Construction Manufacturing Government Specialized
  • 2. Advanced Solutions 1901 Eastpoint Parkway, Suite 301 Louisville, KY 40223 www.AdvancedSolutions.com 1-877-GET-ASI-1 client and Advanced Solutions. The training and implementation of Autodesk Navisworks Manage enabled clash detection, which alerted the team to a potential $75,000-$100,000 error within the initial Warriors in Transition project specifications. With what could have easily been a costly mistake in the field, detected within the modeling stages of the project, Optima was able to see the immediate ROI of this new software integration. Performance Optima came to rely on more than just the customized, project-specific training provided by Advanced Solutions during the BIM adoption process, as even network and hardware issues were addressed during the process. As a result, a hardware upgrade was necessary in conjunction with the software adoption to allow consistent access to Autodesk Revit for everyone on the project. “Advanced Solutions was very flexible, adapting to what we were seeing with the project, what others involved were noticing and with any and all challenges thrown their way,” said Pehl. In addition to being provided all costs and training time estimates in advance, Optima was able to purchase a block of service hours to be used at their discretion enabling the team to call on Advanced Solutions’ specific areas of expertise when needed. Results & Benefits By the end of 2013, Optima expects over half of their major projects will be completed in Autodesk Revit. They are seeing the transition take place with over 120 of their current customers. Optima recognizes they would not have been able to cultivate a majority of their newer clients without having the latest MEP software. “Given the choice our guys would rather work in Revit on all projects,” says Pehl. Using Autodesk Navisworks Manage on the back end of this project has been beneficial in their design process and has enabled better BIM capabilities with a drastic decrease in change orders resulting in a noticeable return on investment. Final Thoughts Evolving each team member’s perspective with the project specific software implementation has been one of the major building blocks in working with Advanced Solutions. A level of trust has been cultivated, which has allowed the entire team on the Warriors in Transition project to grow beyond expectations. The continued collaboration with regards to time, financial constraints and a real world training situation, has shown a true valued partnership with a willingness to solve challenges as a team. “We will be using more BIM and Revit with energy modeling on all sustainable projects moving forward,” says Pehl. “We now have a long term relationship with BIM and Advanced Solutions,” he added. Avoiding costly mistakes with Autodesk Navisworks Manage and Autodesk Revit Optima Project, Charlotte, NC Platinum Partner Architecture, Engineering & Construction Manufacturing Government Specialized