Using Cost of Delay to de-scale
your organisation through
decentralised decision making
How Cost of Delay can be used from portfolio planning all the way down
to minute by minute decision making to vastly increase the flow of
value.
@mick_fagan
@InnodevPtyLtd
#RethinkEverything
Central
Premise
By quantifying the cost of delay (CoD) and
creating transparency to this across all
initiatives, the people doing the work can
make decisions faster and overall, more
economically sound for the organisation.
We achieve this by:
- Quantification of all benefits including
intangibles expressed in currency.
- Shifting the focus away from full utilisation
and towards value.
- Decentralising decision making assisted by
providing access to CoD data and informal
authority
- Creating easy to use, logical CoD models
- Visualising and instituting data driven
continuous improvement.
Some
Anticipated
Results
Shorter payback period through early
incremental delivery
A strong bias towards reducing number of
Work in Progress (WIP) initiatives, leading
to…
Reduced management overheads as a result
of self organisation
Objective decision making based on facts
rather than just intuition, opinion or
‘politicking’
SAPN: Do More with Less
In SAPNs 2020-2025 regulatory proposal we are
committed to:
• Reduce cost of supply from low base
• The network remains Safe, reliable and fit for
the future
• Incorporating new technology into Australia’s
oldest network.
• Renewables
• Storage
Ref: SAPN - Electricity Distribution Proposal 2020-
2025 -Overview - January 2019_0.pdf
Call to Arms:
“Create a customer driven single-line, whole of life view of core IT work. The focus
is on new work demand with the objective of creating transparency of workflow
and clear expectations of timing and delivery”
Chris Ford, CIO, SA Power Networks
Understanding the Frustrations
The Cost of
Queues:
Yikes
“Small changes can produce big results – but the
areas of highest leverage are often the least
obvious. “– Peter M. Senge
What we want
Success is non linear and
emergent
If you only quantify one thing,
quantify the Cost of Delay.
—Don Reinertsen
How to think
about Cost of
Delay: Small
change with a
huge impact
• What is the penalty of lost value if we delay the availability of our
product by 1 week?
• What is the value to the organisation of early availability of our product
of 1 week?
Value Flow in an Enterprise Portfolio
https://elabor8.com.au/measuring-flow-efficiency/
http://www.agilecoach.ca/wp-content/uploads/2013/03/wsib-ekb-version1-1024.png
• We shift our focus towards optimising our
system for value flow by reducing time
spent waiting in queues.
• The longer the queue the longer the wait
and waiting has a huge negative economic
impact which is mostly opportunity cost.
• In an enterprise there are queues
throughout a value chain
You are what you measure
• ‘Managers who don’t know how to measure what they want settle for
wanting what they can measure’ – Russel Ackoff
• If managers want to measure value and don’t know how they’ll end
up basing judgments on things like:
• Cost
• Scope
• Utilisation
• Velocity
• Schedule
• What do you get if you reward based on these things?
We end up with…
• When will it be done?
• That’s too long, it needs to be sooner
• We’re too slow, we need to work back tonight
• We’re still too slow, we need to work this weekend
• It’ll be faster if I don’t explain and you just do as I ask
• How can we squeeze more from our resources?
• That’s not my problem.
• While I’m waiting, I’ll just start working on something else.
A tie back to agile
• Our highest priority is to satisfy the customer
through early and continuous delivery
of valuable software.
• Build projects around motivated individuals.
Give them the environment and support they need,
and trust them to get the job done.
Formal vs Informal
Authority
• Traditional leadership which relies on “formal
authority” is up to 1000x too slow
• To increase the rate of value flow, driven by true
employee engagement arising from their ability
to make better, faster decisions.
• Agile Transformation isn’t only about making a bunch
of Scrum teams, it is about applying the agile
principles at every level.
Decisions at the source
• Rather than think of an
organisation as individual parts to
be managed, think of it as a living
organism which adapts and
responds as a whole.
• By empowering people to take
decisions based on objective data
linked to a shared vision people are
not simply playing a game according
to a set of rules, they are
responsible for the game - Senge
https://corporate-rebels.com/iceberg-of-ignorance/
Quick Poll
• The intuition of members of the same team typically differs by 50 to
1, so the real estimate surprises most team members – Don
Reinertsen.
How many of you believe your organisation understands the
economic impact of a 1 month delay in schedule over the most
strategically important initiatives in your roadmap?
Because we
know the
economic
impact of
queues
• Speed of decision
making
• Co-location
• Cross-skilling
• Adding an expensive specialist
• Limit WiP
• Cross functional teams
• Mob Programming and Pair Programming
• Embedded Customer Expert
• Perfect vs Good Enough
• Minimum Marketable Feature set vs Big Bang
• What’s the common thread?
Diving into
Cost of
Delay
Always measured in currency per unit time eg
AUD/week
Puts a price (penalty) on schedule delays and to
clearly quantify the trade-off between time and lost
benefits.
Aims to answer these questions simultaneously:
Are we working on the right
things? (value)
Are we working on them at
the right time? (urgency)
Calculating
the Cost of
Delay
• Choose units for delay: week, month, quarter, year. I’ve chosen week.
• Build cashflow model in weeks, model what would happen if we delayed
product availability by 1 week only
• When we delay by 1 week, we in effect lose 1 week of peak benefits + incur 1
week more of costs.
http://blackswanfarming.com/urgency-profiles/
Example:
Real Project
• Model Assumptions:
• Lifespan of software asset is 5 years
• Begins at commencement of development/customisation
• Simple Cashflow model (non discounted)
• 2 teams for 52 weeks
• Then 1 team remaining 72 week incremental rollout
• $10,000 avg daily cost
Self-funding Break-even
Example:
Real Project
• 1 week delay cost: ~206k
• Repeat for 2…n weeks (make a formula)
• Can also depict urgency i.e. the rate at which the initiative is shedding value
• Cost of Delay (green) is the Derivative of ‘Delay Cost’ (blue line)
A Portfolio
View of
Prioritisation
with CoD
• Cost of delay has many advantages, particularly when it comes to prioritisation and optimising for
flow of value.
• A common way to prioritise a backlog of initiatives is using the ‘CD3’ method which is:
• Cost of Delay ÷ Duration
• By clearing the way for high Cost of Delay initiatives we achieve far better economic
outcomes.
Ref: Donald Reinertsen: Principles of Product Development Flow
Trade-offs
and 5 Key
Economic
Objectives
• By quantifying the cost of delay we can objectively know the cost of
making a trade-off decision and do so rationally. We can make good
economic choices if when we understand the overall economic
consequences of our decisions.
Ref: Donald Reinertsen: Principles of Product Development Flow
Other Prioritisation
Schemes
• Voting
• Theme weighting with a scale
• Stack ranking based on intuition
• HiPPO / LVDD
There’s no better way to
shock by quantifying the
economic impact of queues
other than real currency.
WTF $206k p/w !!
You’re nuts!
Other Cost of
Delay Models
• Risk
• Compliance with Penalty
• First Mover Advantage in Competitive
market
• Monopoly with unaffected peak
earnings
• Date Driven
Summary
• What should you do?
• Remember my first slide?
• Transparency and openness
• Visualisation
• Continuous Improvement mindset
• Focus on flow of value not being busy
• Furnish the right information like Cost of
Delay to EVERYBODY and give them the
freedom to think…for themselves.
• Melt the Iceberg!
Thanks!
@mick_fagan
@InnodevPtyLtd
#RethinkEverything

More Related Content

PPTX
Joshua Arnold – Using Cost of Delay
KEY
Estimating Cost of Delay
PPTX
Estimating value through the lens of cost of delay
PDF
Cost of Delay, measurements and parallel vs. sequential project processing
PPTX
XP Day: Using cost of delay – Joshua Arnold
PPTX
5 steps-to-smarter-spending
PDF
ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay
PPTX
Improving planning services
Joshua Arnold – Using Cost of Delay
Estimating Cost of Delay
Estimating value through the lens of cost of delay
Cost of Delay, measurements and parallel vs. sequential project processing
XP Day: Using cost of delay – Joshua Arnold
5 steps-to-smarter-spending
ScrumDay Chile - Value Estimation and Prioritization using Cost of Delay
Improving planning services

What's hot (20)

PDF
Agile Is Not Fragile
PDF
Managing through growth
PDF
Gateway to Agile: Agile Requirements
PDF
Story writing and mapping
PDF
ITIL Service Management: Integrating Normal Incident, Major Incident & Servic...
PPTX
Problem management foundation - Analysing
PDF
Determining Business Value in Agile Development
PPTX
Business change
PDF
Success Secrets for Real World Digital Transformations: Optimizing Business P...
PDF
ABC's of Problem Solving
PDF
ROI: Nonprofit Technology
PDF
Evolve or Die: A3 Thinking and Popcorn Flow in Action (#LKCE14)
PPTX
Agile Business Value
PPTX
Lean Benchmarking and value chain optimisation
PPTX
Agile metrics - Agile KC Meeting 9/26/13
PPT
Decision-Making: The Essence of the Manager’s Job
PPT
Agile EcoSystem
PDF
Strategies for an Efficient and Highly-Effective Support Organisation
PDF
Lean thinking and the agile culture
PDF
Innovations in Strategic Sourcing
Agile Is Not Fragile
Managing through growth
Gateway to Agile: Agile Requirements
Story writing and mapping
ITIL Service Management: Integrating Normal Incident, Major Incident & Servic...
Problem management foundation - Analysing
Determining Business Value in Agile Development
Business change
Success Secrets for Real World Digital Transformations: Optimizing Business P...
ABC's of Problem Solving
ROI: Nonprofit Technology
Evolve or Die: A3 Thinking and Popcorn Flow in Action (#LKCE14)
Agile Business Value
Lean Benchmarking and value chain optimisation
Agile metrics - Agile KC Meeting 9/26/13
Decision-Making: The Essence of the Manager’s Job
Agile EcoSystem
Strategies for an Efficient and Highly-Effective Support Organisation
Lean thinking and the agile culture
Innovations in Strategic Sourcing
Ad

Similar to Using Cost of Delay to de-scale your organisation through decentralised decision making (20)

PPTX
Estimating value through the lens of cost of delay
PPTX
Time is an asset. delay is a cost (London Limited WiP Society)
PDF
Cost of Delay: An Economic Approach to Decision Making
PDF
SAFe City, Agile in the City Bristol
PDF
An introduction to Cost of Delay
PDF
Improving Agility (Learning from Maersk Line's Journey) | Özlem Yüce | Agile ...
PDF
Webinar: Prioritising with cost of delay
PPTX
Feeding the agile beast 2010 talk
PPTX
Cost of delay and prioritization techniques
PDF
Prioritisation techniques tutorial Agile Cambridge 2019
PPTX
Workshop Cost of Delay In Action
PDF
Becoming Agile : Get back to first principles first
PPTX
Lean out your product backlog with Lean product Development and business anal...
PPTX
Lean out your backlog - Lean and Kanban Belgium 2010
PDF
Why agile is failing in large enterprises
PDF
Applied tactics for your transformation
PPTX
Suzanne Nottage (CA Technologies Ltd)
PDF
Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Re...
PDF
How do you know you are delivering value?
PDF
Time is an asset. delay is a cost.
Estimating value through the lens of cost of delay
Time is an asset. delay is a cost (London Limited WiP Society)
Cost of Delay: An Economic Approach to Decision Making
SAFe City, Agile in the City Bristol
An introduction to Cost of Delay
Improving Agility (Learning from Maersk Line's Journey) | Özlem Yüce | Agile ...
Webinar: Prioritising with cost of delay
Feeding the agile beast 2010 talk
Cost of delay and prioritization techniques
Prioritisation techniques tutorial Agile Cambridge 2019
Workshop Cost of Delay In Action
Becoming Agile : Get back to first principles first
Lean out your product backlog with Lean product Development and business anal...
Lean out your backlog - Lean and Kanban Belgium 2010
Why agile is failing in large enterprises
Applied tactics for your transformation
Suzanne Nottage (CA Technologies Ltd)
Deadlines vs. Sad-Lines: Using Cost of Delay to Understand your Customer's Re...
How do you know you are delivering value?
Time is an asset. delay is a cost.
Ad

Recently uploaded (20)

PPTX
TechTalks-8-2019-Service-Management-ITIL-Refresh-ITIL-4-Framework-Supports-Ou...
PDF
Unlocking AI with Model Context Protocol (MCP)
PDF
Encapsulation_ Review paper, used for researhc scholars
PPTX
Programs and apps: productivity, graphics, security and other tools
PDF
Profit Center Accounting in SAP S/4HANA, S4F28 Col11
PDF
MIND Revenue Release Quarter 2 2025 Press Release
PPTX
TLE Review Electricity (Electricity).pptx
PDF
Video forgery: An extensive analysis of inter-and intra-frame manipulation al...
PPTX
cloud_computing_Infrastucture_as_cloud_p
PDF
August Patch Tuesday
PDF
Web App vs Mobile App What Should You Build First.pdf
PDF
Accuracy of neural networks in brain wave diagnosis of schizophrenia
PPTX
SOPHOS-XG Firewall Administrator PPT.pptx
PDF
Getting Started with Data Integration: FME Form 101
PPTX
Group 1 Presentation -Planning and Decision Making .pptx
PDF
Hindi spoken digit analysis for native and non-native speakers
PDF
A comparative analysis of optical character recognition models for extracting...
PDF
Approach and Philosophy of On baking technology
PDF
WOOl fibre morphology and structure.pdf for textiles
PDF
Hybrid model detection and classification of lung cancer
TechTalks-8-2019-Service-Management-ITIL-Refresh-ITIL-4-Framework-Supports-Ou...
Unlocking AI with Model Context Protocol (MCP)
Encapsulation_ Review paper, used for researhc scholars
Programs and apps: productivity, graphics, security and other tools
Profit Center Accounting in SAP S/4HANA, S4F28 Col11
MIND Revenue Release Quarter 2 2025 Press Release
TLE Review Electricity (Electricity).pptx
Video forgery: An extensive analysis of inter-and intra-frame manipulation al...
cloud_computing_Infrastucture_as_cloud_p
August Patch Tuesday
Web App vs Mobile App What Should You Build First.pdf
Accuracy of neural networks in brain wave diagnosis of schizophrenia
SOPHOS-XG Firewall Administrator PPT.pptx
Getting Started with Data Integration: FME Form 101
Group 1 Presentation -Planning and Decision Making .pptx
Hindi spoken digit analysis for native and non-native speakers
A comparative analysis of optical character recognition models for extracting...
Approach and Philosophy of On baking technology
WOOl fibre morphology and structure.pdf for textiles
Hybrid model detection and classification of lung cancer

Using Cost of Delay to de-scale your organisation through decentralised decision making

  • 1. Using Cost of Delay to de-scale your organisation through decentralised decision making How Cost of Delay can be used from portfolio planning all the way down to minute by minute decision making to vastly increase the flow of value. @mick_fagan @InnodevPtyLtd #RethinkEverything
  • 2. Central Premise By quantifying the cost of delay (CoD) and creating transparency to this across all initiatives, the people doing the work can make decisions faster and overall, more economically sound for the organisation. We achieve this by: - Quantification of all benefits including intangibles expressed in currency. - Shifting the focus away from full utilisation and towards value. - Decentralising decision making assisted by providing access to CoD data and informal authority - Creating easy to use, logical CoD models - Visualising and instituting data driven continuous improvement.
  • 3. Some Anticipated Results Shorter payback period through early incremental delivery A strong bias towards reducing number of Work in Progress (WIP) initiatives, leading to… Reduced management overheads as a result of self organisation Objective decision making based on facts rather than just intuition, opinion or ‘politicking’
  • 4. SAPN: Do More with Less In SAPNs 2020-2025 regulatory proposal we are committed to: • Reduce cost of supply from low base • The network remains Safe, reliable and fit for the future • Incorporating new technology into Australia’s oldest network. • Renewables • Storage Ref: SAPN - Electricity Distribution Proposal 2020- 2025 -Overview - January 2019_0.pdf
  • 5. Call to Arms: “Create a customer driven single-line, whole of life view of core IT work. The focus is on new work demand with the objective of creating transparency of workflow and clear expectations of timing and delivery” Chris Ford, CIO, SA Power Networks
  • 8. “Small changes can produce big results – but the areas of highest leverage are often the least obvious. “– Peter M. Senge What we want Success is non linear and emergent
  • 9. If you only quantify one thing, quantify the Cost of Delay. —Don Reinertsen
  • 10. How to think about Cost of Delay: Small change with a huge impact • What is the penalty of lost value if we delay the availability of our product by 1 week? • What is the value to the organisation of early availability of our product of 1 week?
  • 11. Value Flow in an Enterprise Portfolio https://elabor8.com.au/measuring-flow-efficiency/ http://www.agilecoach.ca/wp-content/uploads/2013/03/wsib-ekb-version1-1024.png • We shift our focus towards optimising our system for value flow by reducing time spent waiting in queues. • The longer the queue the longer the wait and waiting has a huge negative economic impact which is mostly opportunity cost. • In an enterprise there are queues throughout a value chain
  • 12. You are what you measure • ‘Managers who don’t know how to measure what they want settle for wanting what they can measure’ – Russel Ackoff • If managers want to measure value and don’t know how they’ll end up basing judgments on things like: • Cost • Scope • Utilisation • Velocity • Schedule • What do you get if you reward based on these things?
  • 13. We end up with… • When will it be done? • That’s too long, it needs to be sooner • We’re too slow, we need to work back tonight • We’re still too slow, we need to work this weekend • It’ll be faster if I don’t explain and you just do as I ask • How can we squeeze more from our resources? • That’s not my problem. • While I’m waiting, I’ll just start working on something else.
  • 14. A tie back to agile • Our highest priority is to satisfy the customer through early and continuous delivery of valuable software. • Build projects around motivated individuals. Give them the environment and support they need, and trust them to get the job done.
  • 15. Formal vs Informal Authority • Traditional leadership which relies on “formal authority” is up to 1000x too slow • To increase the rate of value flow, driven by true employee engagement arising from their ability to make better, faster decisions. • Agile Transformation isn’t only about making a bunch of Scrum teams, it is about applying the agile principles at every level.
  • 16. Decisions at the source • Rather than think of an organisation as individual parts to be managed, think of it as a living organism which adapts and responds as a whole. • By empowering people to take decisions based on objective data linked to a shared vision people are not simply playing a game according to a set of rules, they are responsible for the game - Senge https://corporate-rebels.com/iceberg-of-ignorance/
  • 17. Quick Poll • The intuition of members of the same team typically differs by 50 to 1, so the real estimate surprises most team members – Don Reinertsen. How many of you believe your organisation understands the economic impact of a 1 month delay in schedule over the most strategically important initiatives in your roadmap?
  • 18. Because we know the economic impact of queues • Speed of decision making • Co-location • Cross-skilling • Adding an expensive specialist • Limit WiP • Cross functional teams • Mob Programming and Pair Programming • Embedded Customer Expert • Perfect vs Good Enough • Minimum Marketable Feature set vs Big Bang • What’s the common thread?
  • 19. Diving into Cost of Delay Always measured in currency per unit time eg AUD/week Puts a price (penalty) on schedule delays and to clearly quantify the trade-off between time and lost benefits. Aims to answer these questions simultaneously: Are we working on the right things? (value) Are we working on them at the right time? (urgency)
  • 20. Calculating the Cost of Delay • Choose units for delay: week, month, quarter, year. I’ve chosen week. • Build cashflow model in weeks, model what would happen if we delayed product availability by 1 week only • When we delay by 1 week, we in effect lose 1 week of peak benefits + incur 1 week more of costs. http://blackswanfarming.com/urgency-profiles/
  • 21. Example: Real Project • Model Assumptions: • Lifespan of software asset is 5 years • Begins at commencement of development/customisation • Simple Cashflow model (non discounted) • 2 teams for 52 weeks • Then 1 team remaining 72 week incremental rollout • $10,000 avg daily cost Self-funding Break-even
  • 22. Example: Real Project • 1 week delay cost: ~206k • Repeat for 2…n weeks (make a formula) • Can also depict urgency i.e. the rate at which the initiative is shedding value • Cost of Delay (green) is the Derivative of ‘Delay Cost’ (blue line)
  • 23. A Portfolio View of Prioritisation with CoD • Cost of delay has many advantages, particularly when it comes to prioritisation and optimising for flow of value. • A common way to prioritise a backlog of initiatives is using the ‘CD3’ method which is: • Cost of Delay ÷ Duration • By clearing the way for high Cost of Delay initiatives we achieve far better economic outcomes. Ref: Donald Reinertsen: Principles of Product Development Flow
  • 24. Trade-offs and 5 Key Economic Objectives • By quantifying the cost of delay we can objectively know the cost of making a trade-off decision and do so rationally. We can make good economic choices if when we understand the overall economic consequences of our decisions. Ref: Donald Reinertsen: Principles of Product Development Flow
  • 25. Other Prioritisation Schemes • Voting • Theme weighting with a scale • Stack ranking based on intuition • HiPPO / LVDD There’s no better way to shock by quantifying the economic impact of queues other than real currency. WTF $206k p/w !! You’re nuts!
  • 26. Other Cost of Delay Models • Risk • Compliance with Penalty • First Mover Advantage in Competitive market • Monopoly with unaffected peak earnings • Date Driven
  • 27. Summary • What should you do? • Remember my first slide? • Transparency and openness • Visualisation • Continuous Improvement mindset • Focus on flow of value not being busy • Furnish the right information like Cost of Delay to EVERYBODY and give them the freedom to think…for themselves. • Melt the Iceberg!