SlideShare a Scribd company logo
"OVERVIEW OF INTERCONNECTED
GRID MANAGEMENT SYSTEM USING
OLD POWER PLANT"
GROUP
1. Bari, Md. Shafiul -11-20010-3
2. Hossain Maruf -11-20056-3
3. Khayum Md.Omar -11-19061-2
Supervisor: Rethwan Faiz
Assistant Professor
American International University Bangladesh
WHY WE CHOSE THIS TOPIC
• By this thesis, we can reduce load demand on
national grid.
• This system is cheaper than hiring quick rental
power plants.
• As using diesel used power generation is more
costly, we chose natural gas as fuel.
• If we interconnect these plants, the system
won’t be reliable on limited amount of plants.
CORE CONCEPT
• The main objective of our thesis was to cover the peak load
demand by using the commissioning based power plants.
• We used the old commissioned power plants only for handling the
peak loads, not for the base loads.
• We collected all power plants data in Bangladesh.
• We choose Gulshan-1 as the targeted area in Dhaka & collected the
necessary power data for this area.
• We created load curves from the collected data.
• We chose appropriate power plants which were commissioned
decades ago(Ashuganj unit-3, unit-4, unit-5).
• We designed a system that shares the load this area generates
between the old plants.
• At last, we ran the system simulation in HOMER.
LOAD DISTRIBUTION GRAPH
TRANSFORMER FOR GULSHAN - 1
PGCB CONTROL ROOM
DATA ANALYSIS
We collected data about all power plants that
are available in our country including new and
old power plants. We chose the Gulshan-1
area as our targeted zone. The power
generation chart that was collected from PDB
annual reports in 2015 is given in the next
slide.
BANGLADESH CURRENT POWER
GENERATION
PLANT SELECTION
For our system, we chose 3 power plant units.
They are: Ashuganj unit-3, unit-4 & unit-5. All
of these plants were commissioned in the late
eighties. As they have suffered mostly in terms
of derated capacities, we chose them as the
worst case scenario.
LOCATION SELECTION
As we have stated before, we chose Gulshan-1
area as our intended area. This zone is
supplied power by the Ullon Power Substation
in west Rampura. It is supplied a 132 KV
source line. We visited this substation and
recorded logbook data for this area. All data
are taken in hourly, weekly, monthly & half-
yearly basis. Load chart and graphs are given
in the later slides.
HOURLY LOAD
The hourly read was taken from 6 July, 2015
(Week 28). The data was taken at 1 hour
interval from 12 AM to 11 PM. As we will see
from the graph, 2:00 PM noon is the time,
when the highest load is 72.7MW. The chart
and graph is given in the next slide.
HOURLY LOAD CHART
LOAD CURVE
WEEKLY LOAD
The weekly load was taken from 29 June, 2015
to 5 July, 2015 (Week 27). The data chart and
graph are given next.
WEEKLY LOAD CHART
LOAD CURVE
MONTHLY LOAD
The monthly read was taken from June 2015
(Week 23-27). As June is the summer month
in Bangladesh, moreover in the middle of the
year, it was chosen as base line. As per chart
we will see, 62.3 MW is the highest load. The
chart and load graph are given next.
MONTHLY LOAD CHART
LOAD CURVE
HALF-YEARLY LOAD
The half-yearly data is taken from the first half
of 2015. All data are converted into load
curves. The chart and graph are given next.
HALF-YEARLY LOAD CHART
LOAD CURVE
PROPOSED GRID DIAGRAM
SIMULATION RESULTS
For this simulation, we used HOMER Micro
power Optimization Tool to simulate proposed
grid and witnessed the desired power
generation, load coverage and consumption
costs.
ON/OFF SCHEDULE
When considering the Ashuganj units, we
devised a yearly schedule assuming seasonal
demand changes. The forced on/off state will
be used to maintain this schedule. In other
times, optimized state will be used.
SCHEDULE GRAPH
UNIT EFFICIENCY
Ashuganj power plant units uses natural gas
as fuel for power generation. The output
efficiency is shown in the next graph.
EFFICIENCY GRAPH
UNIT COST
Ashuganj chosen Units have a derated
capacity spanning from 16 MW to 40 MW. To
maintain stable power generation, a cost
curve covering capital and replacement costs
are given next.
COST CURVE
NET PERCENTAGE COST
The net profit percentage is the ratio of after-
tax profits to net sales. It reveals the
remaining profit after all costs of production,
administration, and financing have been
deducted from sales. As we will see later in
the graph, all 3 units generated net
percentage costs, while one unit actually
handled the 4 billion dollar yearly cost while
the other two could not.
CASH FLOW SUMMARY
Here is a cash flow summery for all 3 units as
a net present cost. It shows net percent curve
for the units. Costs were taken in USD ($)
value. Overall cost will be shown later in the
slides.
NET PERCENT CURVE
TOTAL SYSTEM COST
Here, every unit corresponds to the system in
accordance with capital, replacement,
operating/maintenance and fuel cost as well
as salvage cost. The system result total in
positive value indicates economical viability of
this project.
TOTAL SYSTEM COST CHART
NATIONAL CASH FLOW
National cash flow is the incoming and outgoing
of cash in this system. In our thesis, we derived
the yearly chart for nationwide cash flow. Here,
we will see the demographic chart for the
national cash flow for our designated operating
system. Here, the amount of capital and
replacement ultimately overshadows the overall
replacement costs. The capital shows negative at
start because of lack of financial data from
Siddirganj power plant.
YEARLY CASH FLOW GRAPH
MONTHLY AVERAGE ELECTRICITY
PRODUCTION
In the next slide, we will see a graph that
shows us the monthly average power
generation with three different color opacity
denoting three different units.
PRODUCTION CHART
FUTURE POWER GENERATION
We will see a plot charted by the overall peak
power generated per every decade. According
to the graph, we will see that is it is gradually
declining.
LONG TERM GENERATION
In the next graph, we will see the future power
generation of this system as for 7 years, it will be
capable of handling load demands; therefore
approving our prediction that this system can
serve us for 7-8 years. Given that these are old
power plants, so long term durability is not an
option. Power plot is an graphical analysis of
power generation over on a timely basis. The
power plot shows peak power generation by this
system declining over the years.
POWER PLOT
ADVANTAGES
• The peak load of the power stations can be exchanged. The
excess load can be shared by other power stations
interconnected with each another if the load of a power station
shows a peak demand which is greater than the rated capacity
of the plant.
• This system gives a direct key to use the obsolete power plants.
• This system is quite economical for some of concerned power
stations.
• In interconnected grid system, this system can be more efficient
because here almost all the power plants are connected in
parallel so almost all of them are connected so there is more
chances for the higher efficiencies than other systems.
DISADVANTAGES
• As stated before, Gulshan-1 area power is provided by Siddirganj power
plant relayed through Rampura Substation which acts as the main plant in
this thesis. As we couldn’t collect data from Siddirganj plant, we couldn’t
compare simulation results with them. Therefore, this thesis partially
relies on the type of plant which will serve as the basis.
• If any major breakdown happens it can create big problem to overall
system and sometime it can damage other power stations also if any
major fault happens.
• As almost all the power plants are connected in parallel so there is not
much standby unit or power plants for emergency so it can be a
dangerous in emergency situations.
• The interconnected grid system also requires some extra care, because it’s
a huge system and huge parts to control or if anything ever happens
accidently at any point it will affect the whole system and grid and as well
as to the power plants.
FUTURE IMPROVEMENTS
• As this system is designed with derated power plants,
stabilizing long term reliability(In years) in the future will
benefit the system.
• In the future, additional features to handle unprecedented
load spikes will improve the system.
• If we can maintain these power plants with peak
maintenance for a long time, costs can be reduced even
more in the future.
• In the future, researchers can integrate smart grid system in
our thesis to better utilize the old power plants.
• Using virtual power networks in our system will automate
the entire system.
SPECIAL THANKS
We would like to express our special gratitude
to our honorable Asst. Professor Rethwan faiz
Sir.

More Related Content

DOCX
novel approach for charger of electrical vehicle
PDF
Lecture 2: Electrical load demand analysis and management
PPTX
Project ppt
PDF
Master's Thesis - Reza Pourramezan - 2006
PDF
Anne McNelis: Intelligent Power Controller Development for Human Deep Space ...
PDF
DESIGN OF CONTROL STRATEGIES FOR THE LOAD FREQUENCY CONTROL (LFC) IN MULTI AR...
PPTX
Load flow analysis of 132 kv substation using etap
PDF
Bradley Glenn: Holomorphic Embedding Load Flow Method (helmtm) Algorithm Deve...
novel approach for charger of electrical vehicle
Lecture 2: Electrical load demand analysis and management
Project ppt
Master's Thesis - Reza Pourramezan - 2006
Anne McNelis: Intelligent Power Controller Development for Human Deep Space ...
DESIGN OF CONTROL STRATEGIES FOR THE LOAD FREQUENCY CONTROL (LFC) IN MULTI AR...
Load flow analysis of 132 kv substation using etap
Bradley Glenn: Holomorphic Embedding Load Flow Method (helmtm) Algorithm Deve...

What's hot (20)

PDF
C05321419
PPT
Power system planning & operation [eceg 4410]
PPTX
frequency regulation of deregulated power system having grc integrated with r...
PDF
Automatic generation control of two area interconnected power system using pa...
PDF
Automatic generation-control-of-interconnected-power-system-with-generation-r...
PPTX
POWER SYSTEM OPERATION AND CONTROL. load forecasting - introduction, methodo...
PDF
Automatic generation control of thermal generating unit by using conventional...
PDF
Iaetsd load frequency control for a distributed grid
PPTX
Hydrothermal scheduling
DOCX
A Bidirectional LLC Resonant Converter With Automatic Forward and Backward Mo...
PDF
Automatic load frequency control of two area power system with conventional a...
PDF
An Intelligent Power Management Investigation for Stand-alone Hybrid System U...
PDF
Natf reference-document-reporting-and-verification-of-generating-unit-reactiv...
PDF
Tubitak ucte training 1_1final_eng
PDF
Preliminary electrical load calculation course share
PDF
Analyses and monitoring of 132 k v grid using etap software
PDF
Fuzzy logic control of a hybrid energy
PPTX
Analysis of control systems of small hydro power plant on islanding operation...
PPTX
A bidirectional llc resonant converter with automatic forward and backward mo...
PDF
Benjamin Loop: Simulation Environment for Power Management and Distribution D...
C05321419
Power system planning & operation [eceg 4410]
frequency regulation of deregulated power system having grc integrated with r...
Automatic generation control of two area interconnected power system using pa...
Automatic generation-control-of-interconnected-power-system-with-generation-r...
POWER SYSTEM OPERATION AND CONTROL. load forecasting - introduction, methodo...
Automatic generation control of thermal generating unit by using conventional...
Iaetsd load frequency control for a distributed grid
Hydrothermal scheduling
A Bidirectional LLC Resonant Converter With Automatic Forward and Backward Mo...
Automatic load frequency control of two area power system with conventional a...
An Intelligent Power Management Investigation for Stand-alone Hybrid System U...
Natf reference-document-reporting-and-verification-of-generating-unit-reactiv...
Tubitak ucte training 1_1final_eng
Preliminary electrical load calculation course share
Analyses and monitoring of 132 k v grid using etap software
Fuzzy logic control of a hybrid energy
Analysis of control systems of small hydro power plant on islanding operation...
A bidirectional llc resonant converter with automatic forward and backward mo...
Benjamin Loop: Simulation Environment for Power Management and Distribution D...
Ad

Viewers also liked (15)

DOC
Principles of business
PPTX
Long Run Average Cost Curve
PPT
Tariff and Non Tariff Barriers
PPTX
Tutorial de power point
PPT
Cells to tissues
PDF
ACME Corporation Final Report
PPTX
Scoop it eta diigo… zer dira
PDF
Feedback on the COSO Enterprise Risk Management 20160929 Final
PPTX
Pravees kumar
PDF
06.실행환경 실습교재(easy company,해답)
PPTX
COMM 125 Portfolio
PPTX
Internet connection
PPTX
EC Presentation 8-1 (1)
PDF
Great People Inside Brochure
PDF
Priyanka nandwani participate kaosal vikash mela as a training partner
Principles of business
Long Run Average Cost Curve
Tariff and Non Tariff Barriers
Tutorial de power point
Cells to tissues
ACME Corporation Final Report
Scoop it eta diigo… zer dira
Feedback on the COSO Enterprise Risk Management 20160929 Final
Pravees kumar
06.실행환경 실습교재(easy company,해답)
COMM 125 Portfolio
Internet connection
EC Presentation 8-1 (1)
Great People Inside Brochure
Priyanka nandwani participate kaosal vikash mela as a training partner
Ad

Similar to Overview of interconnected grid system management using old power plants (20)

PPTX
Advanced energy engineering ktu module 1
PPTX
Module-I-AEE-Energy scenario & Power Plants.pptx
PPTX
Power system -Economic Aspect of Electric power Genration
PPTX
Unit-5.pptx
PPTX
PS-I UNIT-3 power system operation and control
PDF
Copy of PSOC-unit1.pdf
PPTX
Economics of power generation
PPTX
PGPO-FA-21-LEC1-05122021-030638pm.pptx
PPTX
Economic of power generation (1) h.pptx
PDF
Power-System.pdf
DOCX
Power sector
DOCX
Optimum performances of ramallah
PPTX
Module-2_POwer System Economics and Generation Expansion
PDF
Indian power sector
PDF
Power System Protection -Plant visiting report
PDF
IRJET- Generation Planning using WASP Software
PDF
Power System Contingency Ranking Using Fast Decoupled Load Flow Method
PPTX
POWER SYSTEM PLANNING
DOCX
PSOkajaiajajsjsjsushehdydnshC_SKG_RG.docx
PPT
Module1-Power-System-operation and-control
Advanced energy engineering ktu module 1
Module-I-AEE-Energy scenario & Power Plants.pptx
Power system -Economic Aspect of Electric power Genration
Unit-5.pptx
PS-I UNIT-3 power system operation and control
Copy of PSOC-unit1.pdf
Economics of power generation
PGPO-FA-21-LEC1-05122021-030638pm.pptx
Economic of power generation (1) h.pptx
Power-System.pdf
Power sector
Optimum performances of ramallah
Module-2_POwer System Economics and Generation Expansion
Indian power sector
Power System Protection -Plant visiting report
IRJET- Generation Planning using WASP Software
Power System Contingency Ranking Using Fast Decoupled Load Flow Method
POWER SYSTEM PLANNING
PSOkajaiajajsjsjsushehdydnshC_SKG_RG.docx
Module1-Power-System-operation and-control

Recently uploaded (20)

DOCX
573137875-Attendance-Management-System-original
PPTX
Foundation to blockchain - A guide to Blockchain Tech
PPTX
Fundamentals of safety and accident prevention -final (1).pptx
PPTX
Internet of Things (IOT) - A guide to understanding
PDF
737-MAX_SRG.pdf student reference guides
PDF
Embodied AI: Ushering in the Next Era of Intelligent Systems
PPTX
web development for engineering and engineering
PPTX
Safety Seminar civil to be ensured for safe working.
PDF
Unit I ESSENTIAL OF DIGITAL MARKETING.pdf
PDF
Well-logging-methods_new................
PDF
PREDICTION OF DIABETES FROM ELECTRONIC HEALTH RECORDS
PPTX
Sustainable Sites - Green Building Construction
PPTX
CYBER-CRIMES AND SECURITY A guide to understanding
PDF
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
DOCX
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
PDF
III.4.1.2_The_Space_Environment.p pdffdf
PPTX
Geodesy 1.pptx...............................................
PPTX
UNIT 4 Total Quality Management .pptx
PDF
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
PPTX
UNIT-1 - COAL BASED THERMAL POWER PLANTS
573137875-Attendance-Management-System-original
Foundation to blockchain - A guide to Blockchain Tech
Fundamentals of safety and accident prevention -final (1).pptx
Internet of Things (IOT) - A guide to understanding
737-MAX_SRG.pdf student reference guides
Embodied AI: Ushering in the Next Era of Intelligent Systems
web development for engineering and engineering
Safety Seminar civil to be ensured for safe working.
Unit I ESSENTIAL OF DIGITAL MARKETING.pdf
Well-logging-methods_new................
PREDICTION OF DIABETES FROM ELECTRONIC HEALTH RECORDS
Sustainable Sites - Green Building Construction
CYBER-CRIMES AND SECURITY A guide to understanding
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
III.4.1.2_The_Space_Environment.p pdffdf
Geodesy 1.pptx...............................................
UNIT 4 Total Quality Management .pptx
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
UNIT-1 - COAL BASED THERMAL POWER PLANTS

Overview of interconnected grid system management using old power plants

  • 1. "OVERVIEW OF INTERCONNECTED GRID MANAGEMENT SYSTEM USING OLD POWER PLANT" GROUP 1. Bari, Md. Shafiul -11-20010-3 2. Hossain Maruf -11-20056-3 3. Khayum Md.Omar -11-19061-2 Supervisor: Rethwan Faiz Assistant Professor American International University Bangladesh
  • 2. WHY WE CHOSE THIS TOPIC • By this thesis, we can reduce load demand on national grid. • This system is cheaper than hiring quick rental power plants. • As using diesel used power generation is more costly, we chose natural gas as fuel. • If we interconnect these plants, the system won’t be reliable on limited amount of plants.
  • 3. CORE CONCEPT • The main objective of our thesis was to cover the peak load demand by using the commissioning based power plants. • We used the old commissioned power plants only for handling the peak loads, not for the base loads. • We collected all power plants data in Bangladesh. • We choose Gulshan-1 as the targeted area in Dhaka & collected the necessary power data for this area. • We created load curves from the collected data. • We chose appropriate power plants which were commissioned decades ago(Ashuganj unit-3, unit-4, unit-5). • We designed a system that shares the load this area generates between the old plants. • At last, we ran the system simulation in HOMER.
  • 7. DATA ANALYSIS We collected data about all power plants that are available in our country including new and old power plants. We chose the Gulshan-1 area as our targeted zone. The power generation chart that was collected from PDB annual reports in 2015 is given in the next slide.
  • 9. PLANT SELECTION For our system, we chose 3 power plant units. They are: Ashuganj unit-3, unit-4 & unit-5. All of these plants were commissioned in the late eighties. As they have suffered mostly in terms of derated capacities, we chose them as the worst case scenario.
  • 10. LOCATION SELECTION As we have stated before, we chose Gulshan-1 area as our intended area. This zone is supplied power by the Ullon Power Substation in west Rampura. It is supplied a 132 KV source line. We visited this substation and recorded logbook data for this area. All data are taken in hourly, weekly, monthly & half- yearly basis. Load chart and graphs are given in the later slides.
  • 11. HOURLY LOAD The hourly read was taken from 6 July, 2015 (Week 28). The data was taken at 1 hour interval from 12 AM to 11 PM. As we will see from the graph, 2:00 PM noon is the time, when the highest load is 72.7MW. The chart and graph is given in the next slide.
  • 14. WEEKLY LOAD The weekly load was taken from 29 June, 2015 to 5 July, 2015 (Week 27). The data chart and graph are given next.
  • 17. MONTHLY LOAD The monthly read was taken from June 2015 (Week 23-27). As June is the summer month in Bangladesh, moreover in the middle of the year, it was chosen as base line. As per chart we will see, 62.3 MW is the highest load. The chart and load graph are given next.
  • 20. HALF-YEARLY LOAD The half-yearly data is taken from the first half of 2015. All data are converted into load curves. The chart and graph are given next.
  • 24. SIMULATION RESULTS For this simulation, we used HOMER Micro power Optimization Tool to simulate proposed grid and witnessed the desired power generation, load coverage and consumption costs.
  • 25. ON/OFF SCHEDULE When considering the Ashuganj units, we devised a yearly schedule assuming seasonal demand changes. The forced on/off state will be used to maintain this schedule. In other times, optimized state will be used.
  • 27. UNIT EFFICIENCY Ashuganj power plant units uses natural gas as fuel for power generation. The output efficiency is shown in the next graph.
  • 29. UNIT COST Ashuganj chosen Units have a derated capacity spanning from 16 MW to 40 MW. To maintain stable power generation, a cost curve covering capital and replacement costs are given next.
  • 31. NET PERCENTAGE COST The net profit percentage is the ratio of after- tax profits to net sales. It reveals the remaining profit after all costs of production, administration, and financing have been deducted from sales. As we will see later in the graph, all 3 units generated net percentage costs, while one unit actually handled the 4 billion dollar yearly cost while the other two could not.
  • 32. CASH FLOW SUMMARY Here is a cash flow summery for all 3 units as a net present cost. It shows net percent curve for the units. Costs were taken in USD ($) value. Overall cost will be shown later in the slides.
  • 34. TOTAL SYSTEM COST Here, every unit corresponds to the system in accordance with capital, replacement, operating/maintenance and fuel cost as well as salvage cost. The system result total in positive value indicates economical viability of this project.
  • 36. NATIONAL CASH FLOW National cash flow is the incoming and outgoing of cash in this system. In our thesis, we derived the yearly chart for nationwide cash flow. Here, we will see the demographic chart for the national cash flow for our designated operating system. Here, the amount of capital and replacement ultimately overshadows the overall replacement costs. The capital shows negative at start because of lack of financial data from Siddirganj power plant.
  • 38. MONTHLY AVERAGE ELECTRICITY PRODUCTION In the next slide, we will see a graph that shows us the monthly average power generation with three different color opacity denoting three different units.
  • 40. FUTURE POWER GENERATION We will see a plot charted by the overall peak power generated per every decade. According to the graph, we will see that is it is gradually declining.
  • 41. LONG TERM GENERATION In the next graph, we will see the future power generation of this system as for 7 years, it will be capable of handling load demands; therefore approving our prediction that this system can serve us for 7-8 years. Given that these are old power plants, so long term durability is not an option. Power plot is an graphical analysis of power generation over on a timely basis. The power plot shows peak power generation by this system declining over the years.
  • 43. ADVANTAGES • The peak load of the power stations can be exchanged. The excess load can be shared by other power stations interconnected with each another if the load of a power station shows a peak demand which is greater than the rated capacity of the plant. • This system gives a direct key to use the obsolete power plants. • This system is quite economical for some of concerned power stations. • In interconnected grid system, this system can be more efficient because here almost all the power plants are connected in parallel so almost all of them are connected so there is more chances for the higher efficiencies than other systems.
  • 44. DISADVANTAGES • As stated before, Gulshan-1 area power is provided by Siddirganj power plant relayed through Rampura Substation which acts as the main plant in this thesis. As we couldn’t collect data from Siddirganj plant, we couldn’t compare simulation results with them. Therefore, this thesis partially relies on the type of plant which will serve as the basis. • If any major breakdown happens it can create big problem to overall system and sometime it can damage other power stations also if any major fault happens. • As almost all the power plants are connected in parallel so there is not much standby unit or power plants for emergency so it can be a dangerous in emergency situations. • The interconnected grid system also requires some extra care, because it’s a huge system and huge parts to control or if anything ever happens accidently at any point it will affect the whole system and grid and as well as to the power plants.
  • 45. FUTURE IMPROVEMENTS • As this system is designed with derated power plants, stabilizing long term reliability(In years) in the future will benefit the system. • In the future, additional features to handle unprecedented load spikes will improve the system. • If we can maintain these power plants with peak maintenance for a long time, costs can be reduced even more in the future. • In the future, researchers can integrate smart grid system in our thesis to better utilize the old power plants. • Using virtual power networks in our system will automate the entire system.
  • 46. SPECIAL THANKS We would like to express our special gratitude to our honorable Asst. Professor Rethwan faiz Sir.