International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 10 | Oct 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 287
COMPARISON BETWEEN CONVENTIONAL AND PREFABRICATED
BUILDING USING PRIMAVERA
Aishwarya Kiresur1, Prof. Shashank U.Vanakudari2
1M.TECH (CCT) Student, Civil Engineering Dept, Jain College of Engineering, Belagavi, Karnataka, India.
2 Assistant Professor, Civil Engineering Dept, Jain College of Engineering, Belagavi, Karnataka, India
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract – Primavera is a project-Management
Software. It includes project management, scheduling,
risk analysis, opportunity management, resource
management, collaboration and control capabilities and
integrates with other enterprises software such as oracle
and SAP’s ERP systems.
The project is based on the comparison between
conventional and prefabricated building using primavera
P6 software considering G+4 building
Key Words: Risk analysis, Resource management, Cost,
Time
1. INTRODUCTION
ABOUT PRIMAVERA SOFTWARE
The original company’s name was primavera system
and established in 1993 by Joel Kopple- men and Dick
Faris in Philadelphia, USA. In 1988 software system
started to develop in a server-based approach that
allows primavera to act as a portfolio system. This is
split into two version of software one is stand-alone
version used for small projects, the second is enterprise
portfolio system this allows primavera to use
throughout organizations to manage the projects. In
2008, Oracle brought primavera and turned into
primavera Global Business unit. Primavera P6’s is the
world’s largest Pharmaceutical, oil and gas, refinery
infrastructure clients and engineering suppliers.
ABOUT CONVENTIONAL BUILDING
Conventional construction method is an ordinary or a
standard construction. It involves utility of traditional
materials, and remains with a specific-parameters.
Most of the conventional buildings are based on plans
and measurements, as well as floor plans. While
prefabricated construction needs less time same
dependability as convectional construction. The
advantage of conventional construction is that causes
no two building to be same each building is constructed
individually designed from the ground up. Conventional
buildings have more durability than a prefabricated
building.
ABOUT PREFABRICATED BUILDING
Prefabricated building is a prefab building that is
manufactured and constructed using prefabrication. It is
factory made components that will be transported and
assembled on site for a building. Buildings are built and in
one place and can be reassembled in another place this
was true for mobile activities. Elimina Castle the first slave
from west Africa was the first European to build first
prefabricated building. The world’s first prefabricated,
precast panelled apartment blocks were pioneered in live
pool.
1.1 OBJECTIVES
The main objectives of this study are as follows
 To study the difference between conventional and
preconventional buildings using primavera
1.2 LITERATURE REVIEW
The main purpose is to study and determine constraints in
adopting prefabrication in construction industry. To find
the different methodology in both construction and to
conclude which construction is best. Conventional
construction is old method and prefabricated construction
is new one. We can find many buildings are prefabricated.
In this paper they have considered G+7 to estimate the
quantities of conventional building and prefabricated
building. Estimation of quantities is done to find
requirement of materials for both conventional and
prefabricated. Hear both are considered and estimated
how much quantity of materials needed for the
construction. Project duration is also main important for
completion of the project. Conventional building needs
more time compare to prefabricated buildings. Cost
analysis is determined by considering the resource,
materials, labour and machineries. By considering these
factors we can come to cost factor of both constructions.
Data collection is also most important in project. From this
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 10 | Oct 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 288
paper we can come to know the difference between
conventional building and prefabricated building.
2. RESEARCH METHODOLOGY
The steps start with creating a project in primavera
and creating a sequence of activities. After creating the
project, the important thing is to add the dates, project
planning start and must finish by. These dates will be
given during the start of the project, we give these dates
according to planning it may change during construction
if date changes, we can change in software (fig 2)
Fig-3: Completion of creating project
2.1. WORK BREAKDOWN
Work breakdown structure in primavera, in work
breakdown structure works are divided into smaller
parts or components. Work breakdown structure is key
project that is deliverable to team’s work to the
manageable section. In work breakdown structure it
provides the brief information about the project, by
seeing the work breakdown structure can understand
the project. Breaking down the work and making them
in parts and allotting to the different department to
procced the work. By breaking down the work load it
will be easy to do the work.
Fig-1: Methodology
Selecting the EPS in these eps we will select in which
project our document is added, we can select according
to us and we can give names which will be convenient to
us. After selecting all the factors then our project will be
created. After creating the project, we can procced to add
activities
Fig-2: Entering start and end dates
Fig-4: Work breakdown of conventional building
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 10 | Oct 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 289
2.1. Project Calendar
Calendars are used to make our work easy; calendar
defines the workdays and workhours available in a day.
In calendars we can add holidays like government
holidays, festivals, if works are not present on those
particular days in calendar. We can establish our own
calendar according to our company’s work, we can
assign resources and activity on calendars.
According to us and our work. Based on calendar
resource will come to site before we should order the
items so that it delivers on the day which we mentioned
on the calendar.
If the work is not completed in time or it is delayed from
certain reasons then we can change the dates in
primavera. This calendar may change if the resource and
labours are not available or due to climatic effect. Before
planning of the project, we consider the dates according
to our planning but it may vary during the construction
time.
Fig-7: Network Diagram
2.3. RESOURCE ALLOCATION
construction.
Fig-5: Work breakdown of prefabricated building
In primavera resource allocation of resource is
important, for each activity which are the resource
needed and which type of engineers needed to complete
that particular task. Resource includes equipment,
labours that are used for construction, these resources
are based on the time and they are used in between
activities. Creation of resource will be use full in the
project and it makes work easy while construction. In
primavera we can add the resources if they are not there
in the list, we can add units of the resource and we can
add price of the resource which will be used for the
The clay accessed from location location proven to
achieve different geotechnical features. The result is
produced in the table 1. Different geotechnical features
like grain magnitude distribution, specific gravity,
consistency limit, compaction traits, shear substance
components etc. are tabulated.
Fig-6: Project Calendar
2.11. ADDING ACTIVITIES:
Network diagram shows the activities of the task, when
we add activities, it shows the network diagram.
Network diagram shows the connectivity of the activities
which is liked to which activity it will be shown in
network diagram, shows the sequence of the activity.
The network diagram shows the relationship between
activities.
Fig-6: Activities of the project
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 10 | Oct 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 290
Fig-8: Resource allocation
graphical representation of the project. By using Gantt
chat we can understand the work easily, it is graphical
representation of schedule, activity and time. From
primavera software we can plan start and finish dates
and chat will represent the dates according to our
activities. In this we can add which colour we want to
understand our activity, we can add bars, we can make
settings according to our choice.
Fig-9: Gantt Chart
Cost of the conventional building is taken from the
commercial building mentioned in the case study. Which
helps us to discover cost of the building, the substructure
cost relatively equal in two constructions. The
superstructure cost will vary the cost of prefabricated
structure will be more as compared to conventional
building.
Table-1: Conventional Building
Table-2: Prefabricted Building
Fig-9: Material Resource allocation
2.4. GANTT CHART
Gantt chat is a tool or a basic tool, it represents the
3. ESTIMATION OF THE PROJECT
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 10 | Oct 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 291
Table-3: Estimation time of Conventional Building
Estimation of duration
4. RESULTS
 By comparing conventional building and
prefabricated building we can know that
prefabricated building will be constructed in
lesser time, but conventional building needs
more time.
 Prefabricated building needs less materials as
compared to conventional building.
 When we compare cost of both buildings the
cost of prefabricated building is 77,50,000 and
conventional building is 64,00,000.
 As we compare cost of prefabricated and
conventional buildings, prefabricated building
cost more than a conventional building. By using
primavera software when we compare the days
conventional building needs more days as
compared to prefabricated building. The cost of
prefabricated building is more due to structural
steel and equipment cost is more manpower is
used less and machinery work will be more in
prefabricated building.
 Conventional building is traditional type of
construction where it needs more man power,
more materials, needs more time but cost is less
as compared to prefabricated building.
 In both the construction types different types of
activities are added not similar type.
 For each activity time and dates are provided so
that the work completes within the time of
scheduling.
 The lifespan of both buildings is comparatively
same.
 The approximately budget made for the two
buildings based on the planning and scheduling
of the project.
 If we have more time and budget amount then
we can go for the conventional type of
construction or else if we have less time and
more budget then we can go for prefabricated
type of construction.
Table-4: Estimation time of Prefabricated Building
Cost Estimation Graph
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 10 | Oct 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 292
5. COST ESTIMATION FROM PRIMAVERA
SOFTWARE
Fig 10: cost of conventional building
Fig 11: cost of prefabricated building
5.1. COST AND TIME OF CONVENTIONAL
BUILDING
5.2. COST AND TIME GRAPH OF
PREFABRICATED BUILDING
6. CONCLUSION
 From the project we can know that by using
primavera software it’s easy to plan and schedule
the project.
 Primavera helps us to estimate the project time,
cost, materials and labours used for construction.
 Considering two buildings in primavera scheduling
and planning and assigning the resources, there
are two types of resources materials and labours
we can assign the resources according to our use.
 The activity needs which kind of materials or
equipment by considering that we can assign the
resource.
 Primavera software helps us to save time and
manage the project in proper way in the
construction of a project.
 By using primavera software, we can understand
the critical path that helps us to identify the critical
activity and we can do it in a better way.
 While construction we can face many problems
like design, planning etc, by using primavera we
can coordinate on the persons present on the site.
 When we compare conventional and prefabricated
building, we can understand the difference
between them. In conventional building it is a
traditional method which is coming from ancient
time, whereas prefabricated construction method
is a new method of construction which needs less
time to construct.
 The lifespan of both buildings is comparatively
same, the main difference is that time and cost.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 09 Issue: 10 | Oct 2022 www.irjet.net p-ISSN: 2395-0072
© 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 293
 From estimation we can know that prefabricated
building needs less time and more cost, whereas
the conventional building needs more time and
less cost as compared to the prefabricated
building.
 In prefabricated building there are many new
techniques used for construction of prefabricated
buildings, machines are used more but in
conventional building machines and labours are
used in equal.
 From this project we can conclude that both
construction methods are good but we have more
time we can go for conventional construction, if we
have lesser time then we can go for prefabricated
construction method the cost will be more in
prefabricated construction method as the steel
rate is more.
7. REFERENCES
[1] Time Analysis of Pre-Engineered Building with
Conventional Steel Building by using Primavera
P6 2019
[2] Study The Application Of Primavera In Planning
And Scheduling Of Prefabrication Technology
Used In Construction
BIOGRAPHIES
Aishwarya Kiresur M.TECH (CCT)
Student, Civil Engineering Dept,
Jain College of Engineering, Belagavi,
Karnataka, India.
Shashank U Vanakudari
Professor, Civil Engineering Dept,
Jain College of Engineering,
Belagavi, Karnataka, India.

More Related Content

PDF
IRJET- Analysis of Pre-Engineered Building and Conventional Building usin...
PDF
Project Scheduling of a High-rise Building using Primavera P6
PDF
Analysis of Prefabricational Construction And Conventional Construction
PDF
Review on Planning and Scheduling of Construction Project by Management Tool ...
PDF
TESTED PDF REPORT.pdf
PDF
Primavera P6
PDF
IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...
PPTX
Prefabrication for improving Sustainability and Economics of Civil Engineerin...
IRJET- Analysis of Pre-Engineered Building and Conventional Building usin...
Project Scheduling of a High-rise Building using Primavera P6
Analysis of Prefabricational Construction And Conventional Construction
Review on Planning and Scheduling of Construction Project by Management Tool ...
TESTED PDF REPORT.pdf
Primavera P6
IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...
Prefabrication for improving Sustainability and Economics of Civil Engineerin...

Similar to COMPARISON BETWEEN CONVENTIONAL AND PREFABRICATED BUILDING USING PRIMAVERA (20)

PDF
“PLANNING AND SCHEDULING OF MULTI STOREY BUILDING USING BIM”
PDF
Primavera p3 [compatibility mode]
PDF
Planning and Scheduling Construction Projects using Primavera Software A Case...
PDF
IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...
PDF
Finance management in construction site
PDF
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
PDF
“OPTIMIZATION OF COST BY ALLOCATION OF RESOURCES USING PRIMAVERA P6”
PDF
BATCH 4 REVIEW.pdf by civil engineering in pulivendula
PDF
Analyze Time-Cost Required for Conventional and Prefabricated Building Compon...
PPTX
presentattion Role and Importance of Pre-Fabrication (3).pptx
PDF
Redefining Construction in India: Advancements in Prefabrication and Their Im...
PPTX
ppt for primevera
PDF
20320130405009
PDF
A Review Of Planning Scheduling Of A Pune Metro Rail Project Using Primaver...
PDF
RELABILITY OF IMPLEMENTING PRIMAVERA P6 IN FAST-TRACK PLANNING OF RESIDENTIAL...
PPTX
Prefab Building CR ppt.pptx
PDF
IRJET- Scheduling and Labour Management for Residential Building Project usin...
PDF
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
PDF
Research study on Optimization of Cost and Duration with Line of Balance by U...
PPTX
5 Ways Prefabrication Benefits your Construction Project.pptx
“PLANNING AND SCHEDULING OF MULTI STOREY BUILDING USING BIM”
Primavera p3 [compatibility mode]
Planning and Scheduling Construction Projects using Primavera Software A Case...
IRJET- Study on Comparison of Precast and Cast In-Situ Construction of the St...
Finance management in construction site
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
“OPTIMIZATION OF COST BY ALLOCATION OF RESOURCES USING PRIMAVERA P6”
BATCH 4 REVIEW.pdf by civil engineering in pulivendula
Analyze Time-Cost Required for Conventional and Prefabricated Building Compon...
presentattion Role and Importance of Pre-Fabrication (3).pptx
Redefining Construction in India: Advancements in Prefabrication and Their Im...
ppt for primevera
20320130405009
A Review Of Planning Scheduling Of A Pune Metro Rail Project Using Primaver...
RELABILITY OF IMPLEMENTING PRIMAVERA P6 IN FAST-TRACK PLANNING OF RESIDENTIAL...
Prefab Building CR ppt.pptx
IRJET- Scheduling and Labour Management for Residential Building Project usin...
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
Research study on Optimization of Cost and Duration with Line of Balance by U...
5 Ways Prefabrication Benefits your Construction Project.pptx
Ad

More from IRJET Journal (20)

PDF
Enhanced heart disease prediction using SKNDGR ensemble Machine Learning Model
PDF
Utilizing Biomedical Waste for Sustainable Brick Manufacturing: A Novel Appro...
PDF
Kiona – A Smart Society Automation Project
PDF
DESIGN AND DEVELOPMENT OF BATTERY THERMAL MANAGEMENT SYSTEM USING PHASE CHANG...
PDF
Invest in Innovation: Empowering Ideas through Blockchain Based Crowdfunding
PDF
SPACE WATCH YOUR REAL-TIME SPACE INFORMATION HUB
PDF
A Review on Influence of Fluid Viscous Damper on The Behaviour of Multi-store...
PDF
Wireless Arduino Control via Mobile: Eliminating the Need for a Dedicated Wir...
PDF
Explainable AI(XAI) using LIME and Disease Detection in Mango Leaf by Transfe...
PDF
BRAIN TUMOUR DETECTION AND CLASSIFICATION
PDF
The Project Manager as an ambassador of the contract. The case of NEC4 ECC co...
PDF
"Enhanced Heat Transfer Performance in Shell and Tube Heat Exchangers: A CFD ...
PDF
Advancements in CFD Analysis of Shell and Tube Heat Exchangers with Nanofluid...
PDF
Breast Cancer Detection using Computer Vision
PDF
Auto-Charging E-Vehicle with its battery Management.
PDF
Analysis of high energy charge particle in the Heliosphere
PDF
A Novel System for Recommending Agricultural Crops Using Machine Learning App...
PDF
Auto-Charging E-Vehicle with its battery Management.
PDF
Analysis of high energy charge particle in the Heliosphere
PDF
Wireless Arduino Control via Mobile: Eliminating the Need for a Dedicated Wir...
Enhanced heart disease prediction using SKNDGR ensemble Machine Learning Model
Utilizing Biomedical Waste for Sustainable Brick Manufacturing: A Novel Appro...
Kiona – A Smart Society Automation Project
DESIGN AND DEVELOPMENT OF BATTERY THERMAL MANAGEMENT SYSTEM USING PHASE CHANG...
Invest in Innovation: Empowering Ideas through Blockchain Based Crowdfunding
SPACE WATCH YOUR REAL-TIME SPACE INFORMATION HUB
A Review on Influence of Fluid Viscous Damper on The Behaviour of Multi-store...
Wireless Arduino Control via Mobile: Eliminating the Need for a Dedicated Wir...
Explainable AI(XAI) using LIME and Disease Detection in Mango Leaf by Transfe...
BRAIN TUMOUR DETECTION AND CLASSIFICATION
The Project Manager as an ambassador of the contract. The case of NEC4 ECC co...
"Enhanced Heat Transfer Performance in Shell and Tube Heat Exchangers: A CFD ...
Advancements in CFD Analysis of Shell and Tube Heat Exchangers with Nanofluid...
Breast Cancer Detection using Computer Vision
Auto-Charging E-Vehicle with its battery Management.
Analysis of high energy charge particle in the Heliosphere
A Novel System for Recommending Agricultural Crops Using Machine Learning App...
Auto-Charging E-Vehicle with its battery Management.
Analysis of high energy charge particle in the Heliosphere
Wireless Arduino Control via Mobile: Eliminating the Need for a Dedicated Wir...
Ad

Recently uploaded (20)

PPTX
Sorting and Hashing in Data Structures with Algorithms, Techniques, Implement...
PDF
ChapteR012372321DFGDSFGDFGDFSGDFGDFGDFGSDFGDFGFD
PPTX
Current and future trends in Computer Vision.pptx
PDF
SMART SIGNAL TIMING FOR URBAN INTERSECTIONS USING REAL-TIME VEHICLE DETECTI...
PDF
Soil Improvement Techniques Note - Rabbi
PPTX
AUTOMOTIVE ENGINE MANAGEMENT (MECHATRONICS).pptx
PDF
Exploratory_Data_Analysis_Fundamentals.pdf
PPTX
Fundamentals of Mechanical Engineering.pptx
PDF
null (2) bgfbg bfgb bfgb fbfg bfbgf b.pdf
PPTX
introduction to high performance computing
PDF
Accra-Kumasi Expressway - Prefeasibility Report Volume 1 of 7.11.2018.pdf
PPTX
6ME3A-Unit-II-Sensors and Actuators_Handouts.pptx
PPTX
CyberSecurity Mobile and Wireless Devices
PPTX
Amdahl’s law is explained in the above power point presentations
PPTX
Management Information system : MIS-e-Business Systems.pptx
PDF
Improvement effect of pyrolyzed agro-food biochar on the properties of.pdf
PDF
August 2025 - Top 10 Read Articles in Network Security & Its Applications
PDF
August -2025_Top10 Read_Articles_ijait.pdf
PPTX
"Array and Linked List in Data Structures with Types, Operations, Implementat...
PPTX
Fundamentals of safety and accident prevention -final (1).pptx
Sorting and Hashing in Data Structures with Algorithms, Techniques, Implement...
ChapteR012372321DFGDSFGDFGDFSGDFGDFGDFGSDFGDFGFD
Current and future trends in Computer Vision.pptx
SMART SIGNAL TIMING FOR URBAN INTERSECTIONS USING REAL-TIME VEHICLE DETECTI...
Soil Improvement Techniques Note - Rabbi
AUTOMOTIVE ENGINE MANAGEMENT (MECHATRONICS).pptx
Exploratory_Data_Analysis_Fundamentals.pdf
Fundamentals of Mechanical Engineering.pptx
null (2) bgfbg bfgb bfgb fbfg bfbgf b.pdf
introduction to high performance computing
Accra-Kumasi Expressway - Prefeasibility Report Volume 1 of 7.11.2018.pdf
6ME3A-Unit-II-Sensors and Actuators_Handouts.pptx
CyberSecurity Mobile and Wireless Devices
Amdahl’s law is explained in the above power point presentations
Management Information system : MIS-e-Business Systems.pptx
Improvement effect of pyrolyzed agro-food biochar on the properties of.pdf
August 2025 - Top 10 Read Articles in Network Security & Its Applications
August -2025_Top10 Read_Articles_ijait.pdf
"Array and Linked List in Data Structures with Types, Operations, Implementat...
Fundamentals of safety and accident prevention -final (1).pptx

COMPARISON BETWEEN CONVENTIONAL AND PREFABRICATED BUILDING USING PRIMAVERA

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 10 | Oct 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 287 COMPARISON BETWEEN CONVENTIONAL AND PREFABRICATED BUILDING USING PRIMAVERA Aishwarya Kiresur1, Prof. Shashank U.Vanakudari2 1M.TECH (CCT) Student, Civil Engineering Dept, Jain College of Engineering, Belagavi, Karnataka, India. 2 Assistant Professor, Civil Engineering Dept, Jain College of Engineering, Belagavi, Karnataka, India ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract – Primavera is a project-Management Software. It includes project management, scheduling, risk analysis, opportunity management, resource management, collaboration and control capabilities and integrates with other enterprises software such as oracle and SAP’s ERP systems. The project is based on the comparison between conventional and prefabricated building using primavera P6 software considering G+4 building Key Words: Risk analysis, Resource management, Cost, Time 1. INTRODUCTION ABOUT PRIMAVERA SOFTWARE The original company’s name was primavera system and established in 1993 by Joel Kopple- men and Dick Faris in Philadelphia, USA. In 1988 software system started to develop in a server-based approach that allows primavera to act as a portfolio system. This is split into two version of software one is stand-alone version used for small projects, the second is enterprise portfolio system this allows primavera to use throughout organizations to manage the projects. In 2008, Oracle brought primavera and turned into primavera Global Business unit. Primavera P6’s is the world’s largest Pharmaceutical, oil and gas, refinery infrastructure clients and engineering suppliers. ABOUT CONVENTIONAL BUILDING Conventional construction method is an ordinary or a standard construction. It involves utility of traditional materials, and remains with a specific-parameters. Most of the conventional buildings are based on plans and measurements, as well as floor plans. While prefabricated construction needs less time same dependability as convectional construction. The advantage of conventional construction is that causes no two building to be same each building is constructed individually designed from the ground up. Conventional buildings have more durability than a prefabricated building. ABOUT PREFABRICATED BUILDING Prefabricated building is a prefab building that is manufactured and constructed using prefabrication. It is factory made components that will be transported and assembled on site for a building. Buildings are built and in one place and can be reassembled in another place this was true for mobile activities. Elimina Castle the first slave from west Africa was the first European to build first prefabricated building. The world’s first prefabricated, precast panelled apartment blocks were pioneered in live pool. 1.1 OBJECTIVES The main objectives of this study are as follows  To study the difference between conventional and preconventional buildings using primavera 1.2 LITERATURE REVIEW The main purpose is to study and determine constraints in adopting prefabrication in construction industry. To find the different methodology in both construction and to conclude which construction is best. Conventional construction is old method and prefabricated construction is new one. We can find many buildings are prefabricated. In this paper they have considered G+7 to estimate the quantities of conventional building and prefabricated building. Estimation of quantities is done to find requirement of materials for both conventional and prefabricated. Hear both are considered and estimated how much quantity of materials needed for the construction. Project duration is also main important for completion of the project. Conventional building needs more time compare to prefabricated buildings. Cost analysis is determined by considering the resource, materials, labour and machineries. By considering these factors we can come to cost factor of both constructions. Data collection is also most important in project. From this
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 10 | Oct 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 288 paper we can come to know the difference between conventional building and prefabricated building. 2. RESEARCH METHODOLOGY The steps start with creating a project in primavera and creating a sequence of activities. After creating the project, the important thing is to add the dates, project planning start and must finish by. These dates will be given during the start of the project, we give these dates according to planning it may change during construction if date changes, we can change in software (fig 2) Fig-3: Completion of creating project 2.1. WORK BREAKDOWN Work breakdown structure in primavera, in work breakdown structure works are divided into smaller parts or components. Work breakdown structure is key project that is deliverable to team’s work to the manageable section. In work breakdown structure it provides the brief information about the project, by seeing the work breakdown structure can understand the project. Breaking down the work and making them in parts and allotting to the different department to procced the work. By breaking down the work load it will be easy to do the work. Fig-1: Methodology Selecting the EPS in these eps we will select in which project our document is added, we can select according to us and we can give names which will be convenient to us. After selecting all the factors then our project will be created. After creating the project, we can procced to add activities Fig-2: Entering start and end dates Fig-4: Work breakdown of conventional building
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 10 | Oct 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 289 2.1. Project Calendar Calendars are used to make our work easy; calendar defines the workdays and workhours available in a day. In calendars we can add holidays like government holidays, festivals, if works are not present on those particular days in calendar. We can establish our own calendar according to our company’s work, we can assign resources and activity on calendars. According to us and our work. Based on calendar resource will come to site before we should order the items so that it delivers on the day which we mentioned on the calendar. If the work is not completed in time or it is delayed from certain reasons then we can change the dates in primavera. This calendar may change if the resource and labours are not available or due to climatic effect. Before planning of the project, we consider the dates according to our planning but it may vary during the construction time. Fig-7: Network Diagram 2.3. RESOURCE ALLOCATION construction. Fig-5: Work breakdown of prefabricated building In primavera resource allocation of resource is important, for each activity which are the resource needed and which type of engineers needed to complete that particular task. Resource includes equipment, labours that are used for construction, these resources are based on the time and they are used in between activities. Creation of resource will be use full in the project and it makes work easy while construction. In primavera we can add the resources if they are not there in the list, we can add units of the resource and we can add price of the resource which will be used for the The clay accessed from location location proven to achieve different geotechnical features. The result is produced in the table 1. Different geotechnical features like grain magnitude distribution, specific gravity, consistency limit, compaction traits, shear substance components etc. are tabulated. Fig-6: Project Calendar 2.11. ADDING ACTIVITIES: Network diagram shows the activities of the task, when we add activities, it shows the network diagram. Network diagram shows the connectivity of the activities which is liked to which activity it will be shown in network diagram, shows the sequence of the activity. The network diagram shows the relationship between activities. Fig-6: Activities of the project
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 10 | Oct 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 290 Fig-8: Resource allocation graphical representation of the project. By using Gantt chat we can understand the work easily, it is graphical representation of schedule, activity and time. From primavera software we can plan start and finish dates and chat will represent the dates according to our activities. In this we can add which colour we want to understand our activity, we can add bars, we can make settings according to our choice. Fig-9: Gantt Chart Cost of the conventional building is taken from the commercial building mentioned in the case study. Which helps us to discover cost of the building, the substructure cost relatively equal in two constructions. The superstructure cost will vary the cost of prefabricated structure will be more as compared to conventional building. Table-1: Conventional Building Table-2: Prefabricted Building Fig-9: Material Resource allocation 2.4. GANTT CHART Gantt chat is a tool or a basic tool, it represents the 3. ESTIMATION OF THE PROJECT
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 10 | Oct 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 291 Table-3: Estimation time of Conventional Building Estimation of duration 4. RESULTS  By comparing conventional building and prefabricated building we can know that prefabricated building will be constructed in lesser time, but conventional building needs more time.  Prefabricated building needs less materials as compared to conventional building.  When we compare cost of both buildings the cost of prefabricated building is 77,50,000 and conventional building is 64,00,000.  As we compare cost of prefabricated and conventional buildings, prefabricated building cost more than a conventional building. By using primavera software when we compare the days conventional building needs more days as compared to prefabricated building. The cost of prefabricated building is more due to structural steel and equipment cost is more manpower is used less and machinery work will be more in prefabricated building.  Conventional building is traditional type of construction where it needs more man power, more materials, needs more time but cost is less as compared to prefabricated building.  In both the construction types different types of activities are added not similar type.  For each activity time and dates are provided so that the work completes within the time of scheduling.  The lifespan of both buildings is comparatively same.  The approximately budget made for the two buildings based on the planning and scheduling of the project.  If we have more time and budget amount then we can go for the conventional type of construction or else if we have less time and more budget then we can go for prefabricated type of construction. Table-4: Estimation time of Prefabricated Building Cost Estimation Graph
  • 6. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 10 | Oct 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 292 5. COST ESTIMATION FROM PRIMAVERA SOFTWARE Fig 10: cost of conventional building Fig 11: cost of prefabricated building 5.1. COST AND TIME OF CONVENTIONAL BUILDING 5.2. COST AND TIME GRAPH OF PREFABRICATED BUILDING 6. CONCLUSION  From the project we can know that by using primavera software it’s easy to plan and schedule the project.  Primavera helps us to estimate the project time, cost, materials and labours used for construction.  Considering two buildings in primavera scheduling and planning and assigning the resources, there are two types of resources materials and labours we can assign the resources according to our use.  The activity needs which kind of materials or equipment by considering that we can assign the resource.  Primavera software helps us to save time and manage the project in proper way in the construction of a project.  By using primavera software, we can understand the critical path that helps us to identify the critical activity and we can do it in a better way.  While construction we can face many problems like design, planning etc, by using primavera we can coordinate on the persons present on the site.  When we compare conventional and prefabricated building, we can understand the difference between them. In conventional building it is a traditional method which is coming from ancient time, whereas prefabricated construction method is a new method of construction which needs less time to construct.  The lifespan of both buildings is comparatively same, the main difference is that time and cost.
  • 7. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 09 Issue: 10 | Oct 2022 www.irjet.net p-ISSN: 2395-0072 © 2022, IRJET | Impact Factor value: 7.529 | ISO 9001:2008 Certified Journal | Page 293  From estimation we can know that prefabricated building needs less time and more cost, whereas the conventional building needs more time and less cost as compared to the prefabricated building.  In prefabricated building there are many new techniques used for construction of prefabricated buildings, machines are used more but in conventional building machines and labours are used in equal.  From this project we can conclude that both construction methods are good but we have more time we can go for conventional construction, if we have lesser time then we can go for prefabricated construction method the cost will be more in prefabricated construction method as the steel rate is more. 7. REFERENCES [1] Time Analysis of Pre-Engineered Building with Conventional Steel Building by using Primavera P6 2019 [2] Study The Application Of Primavera In Planning And Scheduling Of Prefabrication Technology Used In Construction BIOGRAPHIES Aishwarya Kiresur M.TECH (CCT) Student, Civil Engineering Dept, Jain College of Engineering, Belagavi, Karnataka, India. Shashank U Vanakudari Professor, Civil Engineering Dept, Jain College of Engineering, Belagavi, Karnataka, India.