SlideShare a Scribd company logo
Foundations for infrastructure projects in MENA
an approach to reduce risk and construction costs
Geotechnica ME - 4th & 5th December 2013
Benoît Latapie
Senior Geotechnical Engineer
WS Atkins & Partners Overseas
Foundations for infrastructure projects in MENA
Table of contents
2
• Some critical geotechnical issues in MENA
• Common geotechnical approach in MENA
• An approach to reduce risk and construction costs
• Benefit of GI specification and supervision by specialist consultant
• Limitations of AASHTO for pile design in MENA
• Pile design in weak carbonate rocks – τmax = f(σc) & cost savings
• Can we account for pile end bearing resistance?
• The importance of preliminary pile testing for design
• Osterberg Cell (O-Cell) test to avoid overdesign
• BS EN 1997-1 & Pile foundations
• Pile design to EC7 and τmax = f(σc) – cost savings
Some critical geotechnical issues in MENA
Geotechnical Investigation Practices:
• Clients often see GI as mandatory without appreciating its benefits
• Quality of investigation is very variable
• GI interpretation (GIR) is often produced by GI contractors
• GI contractors often provide the only supervision themselves
• GI standards and methods used on projects are often very low
Geotechnical Design issues:
• Contract specifications often demand use a mixture of codes
• Approval bodies often misunderstand the difference between soil and rock
• Approval bodies staff often is not specialised in geotechnical engineering
• Geotechnical design is often done by the GI contractor
GI = Ground Investigation 3
Common geotechnical approach in MENA
4
• Early stage project involvement
• Desk study
• Design/scoping and specification of
high quality GI
• Carry out GI
• Full time GI supervision
• Factual reporting by contractor
• Review of factual reporting
• Interpretation
• Ground model + parameters + design
STANDALONE
GROUND
INVESTIGATION
CONTRACTOR
CONSERVATIVE / UN-ECONOMIC / RISK ADVERSE SOLUTION
An approach to reduce risk and construction costs
5
• Early stage project involvement
• Desk study
• Design/scoping and specification of
high quality GI
• Carry out GI
• Full time GI supervision
• Factual reporting by contractor
• Review of factual reporting
• Interpretation
• Ground model + parameters + design
SPECIALISTGEOTECHNICAL
CONSULTANT
ECONOMIC RISK CONTROLLED FOUNDATION SOLUTION
By GI Contractor
• D&B contracts are becoming more common
• Field data used in back-analysis to validate geotechnical parameters
• GI contractors are getting more experienced and invest in
newer/better plant
• The benefits of GI supervision by a specialist consultant is more
accepted and even mandated in some cases
• Clients are now better informed and have more experienced staff
• Unforeseen ground conditions are getting recognised as a latent
condition
MENA geotechnical practices are getting better
6
Benefit of GI specification and supervision by
specialist consultant
7
Weak to medium strong, off-white to pale
yellow Limestone with inclusions of silt/clay
Non intact core recovered as medium to
coarse gravel of weak dolomitic limestone
Conventional single tube core barrel Rotary coring with double tube
core barrel (and plastic lining)
Two sites a few kilometres
away from each other,
at similar depth
Benefit of specialist consultant in GI specification
and supervision
8
Weak to medium strong, off-white to pale
yellow Limestone with inclusions of silt/clay
Non intact core recovered as medium to
coarse gravel of weak dolomitic limestone
Conventional single tube core barrel Rotary coring with double tube
core barrel (and plastic lining)
Rock modelled as soil
Conservative Design
Pile design often to AASHTO
Rock modelled as rock
Cost Efficient Design
Pile design for Carbonate rock
Low strength/stiffness High strength/stiffness
Benefit of specialist consultant in GI specification
and supervision
9
• Based on a 35 years old correlation
• It does not take account of the recent research and fully
instrumented pile load tests
• Not suitable for carbonate rocks that are predominant in MENA
• AASHTO τmax correlation it is the most conservative published
method when compared with correlations for carbonate rocks,
• Gives artificially low τmax for RQD<50%
10
Table 10.4.6.5-1—Estimation of
Em Based on RQD
(after O’Neill and Reese, 1999)
Table 10.8.3.5.4b-1—Estimation of αE
(O’Neill and Reese, 1999)
Pile design in weak carbonate rocks
The limitations of AASHTO for pile design in MENA
Pile design in weak carbonate rocks – τmax = f(σc)
11
0
100
200
300
400
500
600
700
800
900
1000
0 1 2 3 4 5 6 7 8 9 10
AASHTO LRFD
0
100
200
300
400
500
600
700
800
900
1000
0 1 2 3 4 5 6 7 8 9 10
Design Value for Burj Khalifa
Mall of the Emirates Dubai
Pentominium Tower Dubai
AASHTO LRFD
0
100
200
300
400
500
600
700
800
900
1000
0 1 2 3 4 5 6 7 8 9 10
Design Value for Burj Khalifa
Mall of the Emirates Dubai
Pentominium Tower Dubai
AASHTO LRFD
Zhang and Einstein (Rough)
Rowe and Armitage (Rough)
0
100
200
300
400
500
600
700
800
900
1000
0 1 2 3 4 5 6 7 8 9 10
Design Value for Burj Khalifa
Mall of the Emirates Dubai
Pentominium Tower Dubai
AASHTO LRFD
Abbs and Needham
Zhang and Einstein (Rough)
Rowe and Armitage (Rough)
RQD<50%
RQD=100%
Smooth
RegularRough
UltimateUnitSkinFrictionτmax[kPa]
Unconfined Compressive Strength σc [MPa]
Design values improved by
preliminary pile testing
Pile design in weak carbonate rocks - τmax=f(σc)
Year Name Recommended τmax Comments
1985
Abbs and
Needham
0.375*σc σc<1MPa
0.375+0.1875*(σc-1) σc=1-3MPa
0.750 σc>3MPa
Weak carbonate rock
Calcarenite / Calcisiltite
1987
Rowe and
Armitage
0.45*(σc)0.5 Regular
0.60*(σc)0.5 Rough
Based on large number of field
tests on weak rocks with no
open discontinuities
1997
Zhang &
Einstein
0.40*(σc)0.5 Smooth
0.80*(σc)0.5 Rough
Recommendation base on a
review of numerous available
relationships
2010 AASHTO 0.65*αE*pa*(σc/pa)0.5 Based on Horvath & Kenney,
1979 for Shale and Mudstone
Legend:
σc Unconfined Compressive Strength (UCS)
αE Reduction factor to account for jointing in rock
pa Atmospheric Pressure (0.101 MPa)
12
Pile design in weak carbonate rocks = cost savings
Soil
Rock
UCS=2.0MPa
Conventional AASHTO
Carbonate rocks method confirmed by
preliminary testing
Skin
friction
ignored
End
bearing
ignored
Socket
Length
10m
Socket
Length
4m
131kPa<τmax<161kPa
τmax=350kPa
FULS=4,400kN FULS=4,400kN
Ø=1.0m
Ø=1.0m
Concrete saving
≈4.7m3 per pile
13
Can we account for end bearing resistance?
14
• YES!
• There are many methods available to estimate the end bearing
resistance of a pile socketed into weak rock, for example:
• AASHTO LRFD: qp = 2.5*σc
• Zhang & Einstein, 1998: qp = (3.0 to 6.6)*(σc)0.5
For σc = 2.0MPa
4,200kPa < qp < 9,300kPa
Supplementary ultimate load bearing
capacity for a 1.0m diameter pile:
3,300kN to 7,300kN
Same order of magnitude than
skin friction contribution
Can we account for end bearing resistance?
15
• Necessary precautions to account for end bearing
AASHTO LRFD
No base cleaning = GAP
End bearing ignored
Base cleaning = NO GAP
End bearing considered
Often, programme constraints
do not allow this procedure
ACCURATE SKIN FRICTION ESTIMATION IS PARAMOUNT
The importance of preliminary pile testing for design
Conventional approach in MENA
Verification pile test
& Construction
Conservative skin friction estimate
Conservative pile design
Conservative design is built
No contingency measures if the
verification test fails
Specialist Consultant
Low quality GI
Preliminary pile
test to failure
(O-Cell)
Realistic skin
friction estimate
Refined skin friction
& design update
Cost-efficient design is built
Design assumptions and installation
methods verified before construction
Construction
16
High quality GI
Pile testing solutions
Monodirectionaltest
Bi-directionaltest
Conventional Test Osterberg (O-Cell) Test
17
Pile testing solutions
Monodirectionaltest
Bi-directionaltest
Conventional Test Osterberg (O-Cell) Test
18
Reinforcement
cage
O-Cell
Osterberg Cell (O-Cell) test – Typical results
Load [MN]
Displacement[mm]
• Independent measurements of side shear and end bearing
• The test results are easier to incorporate in the design
• Helps identify improper construction techniques
• Conventional reaction system not required
19
20
Osterberg Cell (O-Cell) test to avoid overdesign
Ratio of Measured to Estimated ultimate loads – M/E
M/E
Ultimate capacity not reached
Low result due to poor construction
M/E=2.0
21
Osterberg Cell (O-Cell) test to avoid overdesign
Ratio of Measured to Estimated ultimate loads – M/E
M/E
Ultimate capacity not reached
Low result due to poor construction
M/E=2.0
COST/MN
TEST LOAD – MN
22
BS EN 1997-1 & Pile foundations
Eurocode 7 prescribes the following (Clause 7.6.2.1):
“To demonstrate that the pile foundation will support the design load
with adequate safety against compressive failure, the following
inequality shall be satisfied for all ultimate limit state load cases and
load combinations:”
Fc;d ≤ Rc;d
Where: Fc;d is the design axial compression load on a pile or a group of piles
Rc;d is the design value of Rc, the compressive resistance of the ground
against a pile, at the ultimate limit state
ULS shaft resistance ULS base resistance
γRd = Model Factor
Shaft Factor Base Factor
The design resistance in compression is given by:
23
BS EN 1997-1 & Pile foundations
For the design of pile foundations, the UK National Annex to BS EN
1997-1 proposes different set of partial factors that relate to the amount
of in situ pile testing carried out.
Clause A.3.3.2 recommends the following model factors:
• Without preliminary load test γRd = 1.4
• With preliminary load test γRd = 1.2
“If serviceability is verified by load tests (preliminary and/or working)
carried out on more than 1% of the constructed piles to loads not less
than 1.5 times the representative loads for which they are designed, the
resistance factors can be reduced:”
For bored piles γs γb
• Without testing 1.6 2.0
• With testing 1.4 1.7
24
BS EN 1997-1 & Pile foundations in MENA
• In MENA:
• end bearing is often ignored
• Bored piles are often used
• Using BS EN 1997-1 and the UK National Annex leads to savings:
γRd x γs Saving
FOS without testing 2.24 N/A
FOS with testing to UK NA 1.68 -25%
Pile design to EC7 and τmax=f(σc) – cost savings
Soil
Rock
UCS=2.0MPa
Conventional AASHTO Carbonate rocks method + pile testing to EC7
Skin
friction
ignored
End
bearing
ignored
Socket
Length
≈10m
Socket
Length
4m
131kPa<τmax<161kPa
τmax = 350 kPa
FULS = 4,400kN
Ø=1.0m
Ø=1.0m
Concrete saving
≈4.7m3 per pile
Socket
Length
3m
Ø=1.0m
Concrete saving
≈5.5m3 per pile
OR
FSLS = 1,960kN
FULS = 4,400kN
FSLS = 2,620kN
FULS = 3,290kN
FSLS = 1,960kN
FOS=2.24
FOS=1.68
FOS=1.68
25
An approach to reduce risk and construction costs
26
• Early stage project involvement
• Desk study
• Design/scoping and specification of
high quality GI
• Carry out GI
• Full time GI supervision
• Factual reporting by contractor
• Review of factual reporting
• Interpretation
• Ground model + parameters + design
SPECIALISTGEOTECHNICAL
CONSULTANT
ECONOMIC RISK CONTROLLED FOUNDATION SOLUTION
By GI Contractor
Study based on highway construction
Totalincreaseinconstructioncost(%)
Investment in high quality GI saves on construction
cost and reduces risk
Geotechnical study cost / Construction tender cost (%)
15%
5%
27
References
28
• AASHTO LRFD Bridge Design Specification 2010
• Foundation design for the Burj Dubai - the world's tallest building - Poulos &
Bunce, 2008
• Foundation design for the Pentominium tower in Dubai - Ibrahim, 2009
• Rock socket piles at mall of the emirates, Dubai – Alrifai, 2007
• Grouted Piles in Weak Carbonate Rocks – Abbs & Needham, 1985
• End bearing capacity of drilled shafts in rock – Zhang & Einstein, 1998
• A new design method for drilled piers in soft rock - Implications relating to three
published case histories – Rowe and Armitage, 1987
• The landmark Osterberg Cell test, the deep foundations institute, nov/dec 2012.
• The Osterberg Cell and bored pile testing – a symbiosis – Schmertmann and
Hayes, 1997
• Bi-directional static load testing – State of the Art – England, 2003.
• BS EN 199-1:2004 Geotechnical design – Part 1: General rules
Foundations for infrastructure projects in MENA
an approach to reduce risk and construction costs
Geotechnica ME - 4th & 5th December 2013
Benoît Latapie
Senior Geotechnical Engineer
WS Atkins & Partners Overseas
+971 55 300 3797
benoit.latapie@atkinsglobal.com
QUESTIONS?

More Related Content

PPTX
Elastic beams
PPTX
The 7 principles of Engineering Economy
PDF
Barge Transportation Analysis & Load out activities in Modular Construction
PPTX
Critical Path Ppt
PDF
Table of Fixed End Moments Formulas
PPT
Asme section ii c new
PDF
transmission line tower design
Elastic beams
The 7 principles of Engineering Economy
Barge Transportation Analysis & Load out activities in Modular Construction
Critical Path Ppt
Table of Fixed End Moments Formulas
Asme section ii c new
transmission line tower design

What's hot (20)

DOCX
Wps report
PDF
Machine Foundation Design
PDF
Unit_6_WAVE_FORCE_ON_SMALL_DIAMETER_MEMB.pdf
PDF
Engineering & piping design
DOCX
Thermo problem set no. 2
PPT
Wind provisions
PPT
Lists of Civil Engineering Review Centers in the Philippines
PDF
Analysis of 3+ story building in staad pro
PDF
Hibbeler chapter5
PPT
Blast Resistant Design
PDF
Calculation of blast loads
PDF
Design calculations of raft foundation
PDF
Matrix stiffness method 0910
PPT
Fundamentals of scheduling
PDF
stocks.pdf
PDF
Designing a Cold-Formed Steel Beam Using AS4600:2018 and 2005 - Webinar
PDF
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الثاني
PPT
Rayleigh Ritz Method
Wps report
Machine Foundation Design
Unit_6_WAVE_FORCE_ON_SMALL_DIAMETER_MEMB.pdf
Engineering & piping design
Thermo problem set no. 2
Wind provisions
Lists of Civil Engineering Review Centers in the Philippines
Analysis of 3+ story building in staad pro
Hibbeler chapter5
Blast Resistant Design
Calculation of blast loads
Design calculations of raft foundation
Matrix stiffness method 0910
Fundamentals of scheduling
stocks.pdf
Designing a Cold-Formed Steel Beam Using AS4600:2018 and 2005 - Webinar
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الثاني
Rayleigh Ritz Method
Ad

Viewers also liked (6)

PPT
ASCEMLSTPRESENTATION 05-06-03.PPT
PDF
Pile Foundations
PPTX
The osterberg cell static loading test
PPT
Bullock bidirectional testing
PPT
Pile foundation
PPTX
Building Failures and its Causes- Theory of structures
ASCEMLSTPRESENTATION 05-06-03.PPT
Pile Foundations
The osterberg cell static loading test
Bullock bidirectional testing
Pile foundation
Building Failures and its Causes- Theory of structures
Ad

Similar to 2. Benoit Latapie - Foundations for infrastructure projects in MENA (20)

PPTX
Risk Assessment in Geotechnical Engineering .pptx
PDF
Bridge Foundation Design
DOCX
Foundation design of burj khalifa (deep foundation&lt;piles>)
DOC
Material Testing.doc
PPT
General & geotechnical considerations for pile design
PPT
Bridge structural foundations-and_earth_retaining_structures
PDF
161115 FDTB - from pile group to piled raft_Benoit Latapie
PDF
A short course in foundation engineering
PDF
Ashort courseinfoundation engineering
PDF
Quality assurance for_deep_bored_piles
PDF
The management of geotechnical risk on major infrastructure projects
PPTX
Risk Assessment in Geotechnical Engineering .pptx
PPTX
deep-foundation-selection-driven-pile-or-drilled good for presentation.pptx
PDF
Basics of Foundation Design
PDF
Fellenius bases de diseño de pilotes de fundación
PDF
Fellenius bases de diseño de pilotes de fundación
PDF
Risk evaluation according to standards cristina de hc tsuha
PPTX
Study of design and construction methods of bored piles
PDF
Sachpazis: The Role of Geotechnical Engineers in the Optimal Design of Long-S...
Risk Assessment in Geotechnical Engineering .pptx
Bridge Foundation Design
Foundation design of burj khalifa (deep foundation&lt;piles>)
Material Testing.doc
General & geotechnical considerations for pile design
Bridge structural foundations-and_earth_retaining_structures
161115 FDTB - from pile group to piled raft_Benoit Latapie
A short course in foundation engineering
Ashort courseinfoundation engineering
Quality assurance for_deep_bored_piles
The management of geotechnical risk on major infrastructure projects
Risk Assessment in Geotechnical Engineering .pptx
deep-foundation-selection-driven-pile-or-drilled good for presentation.pptx
Basics of Foundation Design
Fellenius bases de diseño de pilotes de fundación
Fellenius bases de diseño de pilotes de fundación
Risk evaluation according to standards cristina de hc tsuha
Study of design and construction methods of bored piles
Sachpazis: The Role of Geotechnical Engineers in the Optimal Design of Long-S...

2. Benoit Latapie - Foundations for infrastructure projects in MENA

  • 1. Foundations for infrastructure projects in MENA an approach to reduce risk and construction costs Geotechnica ME - 4th & 5th December 2013 Benoît Latapie Senior Geotechnical Engineer WS Atkins & Partners Overseas
  • 2. Foundations for infrastructure projects in MENA Table of contents 2 • Some critical geotechnical issues in MENA • Common geotechnical approach in MENA • An approach to reduce risk and construction costs • Benefit of GI specification and supervision by specialist consultant • Limitations of AASHTO for pile design in MENA • Pile design in weak carbonate rocks – τmax = f(σc) & cost savings • Can we account for pile end bearing resistance? • The importance of preliminary pile testing for design • Osterberg Cell (O-Cell) test to avoid overdesign • BS EN 1997-1 & Pile foundations • Pile design to EC7 and τmax = f(σc) – cost savings
  • 3. Some critical geotechnical issues in MENA Geotechnical Investigation Practices: • Clients often see GI as mandatory without appreciating its benefits • Quality of investigation is very variable • GI interpretation (GIR) is often produced by GI contractors • GI contractors often provide the only supervision themselves • GI standards and methods used on projects are often very low Geotechnical Design issues: • Contract specifications often demand use a mixture of codes • Approval bodies often misunderstand the difference between soil and rock • Approval bodies staff often is not specialised in geotechnical engineering • Geotechnical design is often done by the GI contractor GI = Ground Investigation 3
  • 4. Common geotechnical approach in MENA 4 • Early stage project involvement • Desk study • Design/scoping and specification of high quality GI • Carry out GI • Full time GI supervision • Factual reporting by contractor • Review of factual reporting • Interpretation • Ground model + parameters + design STANDALONE GROUND INVESTIGATION CONTRACTOR CONSERVATIVE / UN-ECONOMIC / RISK ADVERSE SOLUTION
  • 5. An approach to reduce risk and construction costs 5 • Early stage project involvement • Desk study • Design/scoping and specification of high quality GI • Carry out GI • Full time GI supervision • Factual reporting by contractor • Review of factual reporting • Interpretation • Ground model + parameters + design SPECIALISTGEOTECHNICAL CONSULTANT ECONOMIC RISK CONTROLLED FOUNDATION SOLUTION By GI Contractor
  • 6. • D&B contracts are becoming more common • Field data used in back-analysis to validate geotechnical parameters • GI contractors are getting more experienced and invest in newer/better plant • The benefits of GI supervision by a specialist consultant is more accepted and even mandated in some cases • Clients are now better informed and have more experienced staff • Unforeseen ground conditions are getting recognised as a latent condition MENA geotechnical practices are getting better 6
  • 7. Benefit of GI specification and supervision by specialist consultant 7 Weak to medium strong, off-white to pale yellow Limestone with inclusions of silt/clay Non intact core recovered as medium to coarse gravel of weak dolomitic limestone Conventional single tube core barrel Rotary coring with double tube core barrel (and plastic lining) Two sites a few kilometres away from each other, at similar depth
  • 8. Benefit of specialist consultant in GI specification and supervision 8 Weak to medium strong, off-white to pale yellow Limestone with inclusions of silt/clay Non intact core recovered as medium to coarse gravel of weak dolomitic limestone Conventional single tube core barrel Rotary coring with double tube core barrel (and plastic lining) Rock modelled as soil Conservative Design Pile design often to AASHTO Rock modelled as rock Cost Efficient Design Pile design for Carbonate rock Low strength/stiffness High strength/stiffness
  • 9. Benefit of specialist consultant in GI specification and supervision 9
  • 10. • Based on a 35 years old correlation • It does not take account of the recent research and fully instrumented pile load tests • Not suitable for carbonate rocks that are predominant in MENA • AASHTO τmax correlation it is the most conservative published method when compared with correlations for carbonate rocks, • Gives artificially low τmax for RQD<50% 10 Table 10.4.6.5-1—Estimation of Em Based on RQD (after O’Neill and Reese, 1999) Table 10.8.3.5.4b-1—Estimation of αE (O’Neill and Reese, 1999) Pile design in weak carbonate rocks The limitations of AASHTO for pile design in MENA
  • 11. Pile design in weak carbonate rocks – τmax = f(σc) 11 0 100 200 300 400 500 600 700 800 900 1000 0 1 2 3 4 5 6 7 8 9 10 AASHTO LRFD 0 100 200 300 400 500 600 700 800 900 1000 0 1 2 3 4 5 6 7 8 9 10 Design Value for Burj Khalifa Mall of the Emirates Dubai Pentominium Tower Dubai AASHTO LRFD 0 100 200 300 400 500 600 700 800 900 1000 0 1 2 3 4 5 6 7 8 9 10 Design Value for Burj Khalifa Mall of the Emirates Dubai Pentominium Tower Dubai AASHTO LRFD Zhang and Einstein (Rough) Rowe and Armitage (Rough) 0 100 200 300 400 500 600 700 800 900 1000 0 1 2 3 4 5 6 7 8 9 10 Design Value for Burj Khalifa Mall of the Emirates Dubai Pentominium Tower Dubai AASHTO LRFD Abbs and Needham Zhang and Einstein (Rough) Rowe and Armitage (Rough) RQD<50% RQD=100% Smooth RegularRough UltimateUnitSkinFrictionτmax[kPa] Unconfined Compressive Strength σc [MPa] Design values improved by preliminary pile testing
  • 12. Pile design in weak carbonate rocks - τmax=f(σc) Year Name Recommended τmax Comments 1985 Abbs and Needham 0.375*σc σc<1MPa 0.375+0.1875*(σc-1) σc=1-3MPa 0.750 σc>3MPa Weak carbonate rock Calcarenite / Calcisiltite 1987 Rowe and Armitage 0.45*(σc)0.5 Regular 0.60*(σc)0.5 Rough Based on large number of field tests on weak rocks with no open discontinuities 1997 Zhang & Einstein 0.40*(σc)0.5 Smooth 0.80*(σc)0.5 Rough Recommendation base on a review of numerous available relationships 2010 AASHTO 0.65*αE*pa*(σc/pa)0.5 Based on Horvath & Kenney, 1979 for Shale and Mudstone Legend: σc Unconfined Compressive Strength (UCS) αE Reduction factor to account for jointing in rock pa Atmospheric Pressure (0.101 MPa) 12
  • 13. Pile design in weak carbonate rocks = cost savings Soil Rock UCS=2.0MPa Conventional AASHTO Carbonate rocks method confirmed by preliminary testing Skin friction ignored End bearing ignored Socket Length 10m Socket Length 4m 131kPa<τmax<161kPa τmax=350kPa FULS=4,400kN FULS=4,400kN Ø=1.0m Ø=1.0m Concrete saving ≈4.7m3 per pile 13
  • 14. Can we account for end bearing resistance? 14 • YES! • There are many methods available to estimate the end bearing resistance of a pile socketed into weak rock, for example: • AASHTO LRFD: qp = 2.5*σc • Zhang & Einstein, 1998: qp = (3.0 to 6.6)*(σc)0.5 For σc = 2.0MPa 4,200kPa < qp < 9,300kPa Supplementary ultimate load bearing capacity for a 1.0m diameter pile: 3,300kN to 7,300kN Same order of magnitude than skin friction contribution
  • 15. Can we account for end bearing resistance? 15 • Necessary precautions to account for end bearing AASHTO LRFD No base cleaning = GAP End bearing ignored Base cleaning = NO GAP End bearing considered Often, programme constraints do not allow this procedure ACCURATE SKIN FRICTION ESTIMATION IS PARAMOUNT
  • 16. The importance of preliminary pile testing for design Conventional approach in MENA Verification pile test & Construction Conservative skin friction estimate Conservative pile design Conservative design is built No contingency measures if the verification test fails Specialist Consultant Low quality GI Preliminary pile test to failure (O-Cell) Realistic skin friction estimate Refined skin friction & design update Cost-efficient design is built Design assumptions and installation methods verified before construction Construction 16 High quality GI
  • 18. Pile testing solutions Monodirectionaltest Bi-directionaltest Conventional Test Osterberg (O-Cell) Test 18 Reinforcement cage O-Cell
  • 19. Osterberg Cell (O-Cell) test – Typical results Load [MN] Displacement[mm] • Independent measurements of side shear and end bearing • The test results are easier to incorporate in the design • Helps identify improper construction techniques • Conventional reaction system not required 19
  • 20. 20 Osterberg Cell (O-Cell) test to avoid overdesign Ratio of Measured to Estimated ultimate loads – M/E M/E Ultimate capacity not reached Low result due to poor construction M/E=2.0
  • 21. 21 Osterberg Cell (O-Cell) test to avoid overdesign Ratio of Measured to Estimated ultimate loads – M/E M/E Ultimate capacity not reached Low result due to poor construction M/E=2.0 COST/MN TEST LOAD – MN
  • 22. 22 BS EN 1997-1 & Pile foundations Eurocode 7 prescribes the following (Clause 7.6.2.1): “To demonstrate that the pile foundation will support the design load with adequate safety against compressive failure, the following inequality shall be satisfied for all ultimate limit state load cases and load combinations:” Fc;d ≤ Rc;d Where: Fc;d is the design axial compression load on a pile or a group of piles Rc;d is the design value of Rc, the compressive resistance of the ground against a pile, at the ultimate limit state ULS shaft resistance ULS base resistance γRd = Model Factor Shaft Factor Base Factor The design resistance in compression is given by:
  • 23. 23 BS EN 1997-1 & Pile foundations For the design of pile foundations, the UK National Annex to BS EN 1997-1 proposes different set of partial factors that relate to the amount of in situ pile testing carried out. Clause A.3.3.2 recommends the following model factors: • Without preliminary load test γRd = 1.4 • With preliminary load test γRd = 1.2 “If serviceability is verified by load tests (preliminary and/or working) carried out on more than 1% of the constructed piles to loads not less than 1.5 times the representative loads for which they are designed, the resistance factors can be reduced:” For bored piles γs γb • Without testing 1.6 2.0 • With testing 1.4 1.7
  • 24. 24 BS EN 1997-1 & Pile foundations in MENA • In MENA: • end bearing is often ignored • Bored piles are often used • Using BS EN 1997-1 and the UK National Annex leads to savings: γRd x γs Saving FOS without testing 2.24 N/A FOS with testing to UK NA 1.68 -25%
  • 25. Pile design to EC7 and τmax=f(σc) – cost savings Soil Rock UCS=2.0MPa Conventional AASHTO Carbonate rocks method + pile testing to EC7 Skin friction ignored End bearing ignored Socket Length ≈10m Socket Length 4m 131kPa<τmax<161kPa τmax = 350 kPa FULS = 4,400kN Ø=1.0m Ø=1.0m Concrete saving ≈4.7m3 per pile Socket Length 3m Ø=1.0m Concrete saving ≈5.5m3 per pile OR FSLS = 1,960kN FULS = 4,400kN FSLS = 2,620kN FULS = 3,290kN FSLS = 1,960kN FOS=2.24 FOS=1.68 FOS=1.68 25
  • 26. An approach to reduce risk and construction costs 26 • Early stage project involvement • Desk study • Design/scoping and specification of high quality GI • Carry out GI • Full time GI supervision • Factual reporting by contractor • Review of factual reporting • Interpretation • Ground model + parameters + design SPECIALISTGEOTECHNICAL CONSULTANT ECONOMIC RISK CONTROLLED FOUNDATION SOLUTION By GI Contractor
  • 27. Study based on highway construction Totalincreaseinconstructioncost(%) Investment in high quality GI saves on construction cost and reduces risk Geotechnical study cost / Construction tender cost (%) 15% 5% 27
  • 28. References 28 • AASHTO LRFD Bridge Design Specification 2010 • Foundation design for the Burj Dubai - the world's tallest building - Poulos & Bunce, 2008 • Foundation design for the Pentominium tower in Dubai - Ibrahim, 2009 • Rock socket piles at mall of the emirates, Dubai – Alrifai, 2007 • Grouted Piles in Weak Carbonate Rocks – Abbs & Needham, 1985 • End bearing capacity of drilled shafts in rock – Zhang & Einstein, 1998 • A new design method for drilled piers in soft rock - Implications relating to three published case histories – Rowe and Armitage, 1987 • The landmark Osterberg Cell test, the deep foundations institute, nov/dec 2012. • The Osterberg Cell and bored pile testing – a symbiosis – Schmertmann and Hayes, 1997 • Bi-directional static load testing – State of the Art – England, 2003. • BS EN 199-1:2004 Geotechnical design – Part 1: General rules
  • 29. Foundations for infrastructure projects in MENA an approach to reduce risk and construction costs Geotechnica ME - 4th & 5th December 2013 Benoît Latapie Senior Geotechnical Engineer WS Atkins & Partners Overseas +971 55 300 3797 benoit.latapie@atkinsglobal.com QUESTIONS?