SlideShare a Scribd company logo
11
Most read
12
Most read
13
Most read
The Osterberg Cell Static
Loading Test
Utilizing The Osterberg Cell for Loading test instead of Conventional
Static LoadingTest
12/12/2016 Alaa Mohamed Metwally 1
1. Introduction
• The Osterberg Cell is a Sacrificial jack-like device which the Engineer can have
installed at the tip of a driven pile or on the reinforcement of a bored pile.
• The cell provides the static loading and requires no overhead frame or other
external reaction system.
• Hence, We can now statically test full-sized bored piles (also known as drilled
shafts, drilled piers or caissons) to near their ultimate capacity. Furthermore, we
can do it more conveniently, economically and safely than ever before as no
reaction system required like before.
• O Cell testing and bored pile have a beneficial, cooperative relationship or a
“Symbiosis”.
• Generally high capacity of bored piles, in combination with high cost of top load
system providing more than 10 MN, make conventional top load testing
impractical for routine testing.
12/12/2016 Alaa Mohamed Metwally 2
1. Introduction
• The O Cell static load test method, providing high capacities at affordable costs,
has become an attractive alternative method for testing bored piles.
• At mid 1994 the U.S Federal Highway Administration (FHWA) found that
Engineers and Contractors considered the O Cell “the method of choice” and it’s
use had risen rapidly to about 65% of all bored pile testing, this trend has
continued and usage now exceed 90% not in the U.S only but all over the world.
12/12/2016 Alaa Mohamed Metwally 3
1. Introduction
12/12/2016 Alaa Mohamed Metwally 4
Osterberg
Cell
2. Static load testing using O Cell
12/12/2016 Alaa Mohamed Metwally 5
Fig.
1
Pile
Steel Beam
P=F+Q
F
Q
Pile
F
Q
Expanding
O Cell at the
bottom of
the pile
Ground Level
Ground Level
Reaction System
at the top of pile
Q
2. Static load testing using O Cell
• A Conventional test loads the bored pile in compression, at its tip, using an
overhead reaction system or dead load, side shear F and end bearing Q combine
to resist the top load P and Engineer can only separate this components
approximately by analysis of strain and compression measurements together
with modulus estimates.
• The O Cell also loads the pile in compression, but from its bottom. As the O Cell
expands, the end bearing Q provides reaction for the side shear F. and vice versa.
Until reaching the capacity of one of the two component or the O Cell reaches its
capacity. The vantage point here is that the test separate the side shear and end
bearing components.
• The O Cell test load placed at, or near, the bottom of the pile has twice testing
effectiveness of that same load placed at the top in a conventional test.
12/12/2016 Alaa Mohamed Metwally 6
12/12/2016 Alaa Mohamed Metwally
3. Equipment
7
3. Equipment
• After construction of the shaft, the test operator connects an automatic pump to
the hydraulic lines that provides a pressure conduit to the cell, the load applied
by an O Cell is calibrated versus hydraulic pressure before installation and the
pressure applied to the cell is measured by a pressure transducer.
• Movement measured by electronic gages connected to a computerized
acquisition system.
• The total expansion of the cell is measured by (LVWDTs) Linear vibrating wire
transducers the lower part of which attached to bottom of the cell.
• A steel telltales attached to the bottom of the cell used to measure the upward
movement directly.
• Subtracting the upward movement from total expansion gives the desired
downward movement.
12/12/2016 Alaa Mohamed Metwally 8
12/12/2016 Alaa Mohamed Metwally 9
4. History of Osterberg Cell
• Dr. Jorje Osterberg, professor emeritus at Northwestern university. Developed
and patented test which now carries his name.
• The first experimental test pile was carried out in 1984, after this successful
prototype professorOsterberg works very closely to American Equipment and
Fabrication Corp. to evolve his cell from a bellows type expansion cell to the
current design, very similar to piston type jack used in conventional test, but the
piston extends downward not upward.
• Haley & Aldrich was the first to use O Cell in practical application in 1987, to
driven piles one over a river in Massachusetts and the other on a bridge which
reaches 1.26 and 4 MN respectively.
• Now Osterberg cell has steadily gained popularity all over the world for testing
bored piles.
12/12/2016 Alaa Mohamed Metwally 10
5. Advantages of O Cell
• Economy.
• reduced construction time, saving in outlay capital, no top-of-pile reaction equipment required
and less test design efforts, making the test cost from
1
3
to
2
3
the conventional test.The
comparative cost reduces as the load increases.
• High Load capacity.
• Shear/Bearing Component
• The cell automatically separates the side shear and end bearing components, despite of
conventional test which gives the total capacity at a time
• Improved safety.
• The test energy lies deeply buried and no overhead load at the top of pile.
• Rocket Socket.
• The cell loaded at the bottom of the socket, near its bottom and gives an automated separation
of components
12/12/2016 Alaa Mohamed Metwally 11
5. Advantages of O Cell
• Reduced work area.
• A 65 MN O Cell test, conducted in a 3 meter wide median strip of a busy interstate highway,
which seems impossible when using conventional test as a big area needed for the reaction
system or equipment and kentledge system.
• Over water and battered shafts.
• Static creep and setup effects.
• Because the test is static the test load at any length of time can be estimated, the Engineers
also can obtain separate data about creep behavior for the two components.
• Sequential testing.
• A long term stage tests with minimal efforts can be made for research purposes or other to
obtain “aging” for example, been a unique advantage of O Cell test
12/12/2016 Alaa Mohamed Metwally 12
6. Limitations
• Advance installation required.
• In bored piles and most driven piles, the O Cell must be installed prior construction.
• Balanced component requirement.
• As the cell reaches the ultimate capacity in only one of its components, and shaft capacity limited
to two times the capacity of component reaching ultimate, The Engineer should first analyze the
expected side shear and end bearing components and either attempt to balance the two to get
the most information from both.
• The introduction of multilevel cell mitigates this limitation, and allow calculating ultimate side
shear and end bearing in cases where bearing less than the side shear.
• Equivalent top load curve.
• Although the estimation of equivalent top load curve is conservatism, it remains estimate.
• Sacrificial cell.
• Cell considered expandable and not recovered after the test completed. However, grouting the
tested pile allows using it as a permanent foundation pile.
• Not suitable for certain types of piles.
• H pile and sheet piles.
12/12/2016 Alaa Mohamed Metwally 13
7. Test results
12/12/2016 Alaa Mohamed Metwally 14
Sand and
gravel
shell
8.2
19.2
5.8
2.4
River
18.9
Hydraulic
supply &
telltale casing
35.7 -25
-20
-15
-10
-5
0
5
10
15
20
0 10 20 30
UpwordandDownwordMovement
(mm)
Load (MN)
Osterberg Load-Movement Curve
Purpose: To determine bearing capacity of the drilled shaft supporting a
bridge pier.
Method: Shafts drilled with polymer drilling slurry, 1.9 O.D. casing set on
top of shale and 1.8 m hole drilled 5.8 m into shale 864mm load cell with 1.7
m diameter plate welded to bottom lowered into the hole. Pumped
concrete placed to design top elevation of shaft.
Results: Load reaches capacity of device at 34.56 mm downward and 7.62
mm upward movement, the ultimate capacity was greater than 54 MN.
O-CellTest on a rock socketed bored
pile
-25
-20
-15
-10
-5
0
5
10
15
20
0 5 10 15 20 25 30
UpwordandDownwordMovement(mm)
Load (MN)
Osterberg Load-Movement Curve
8. Interpretation of test results.
12/12/2016 Alaa Mohamed Metwally
-18
-16
-14
-12
-10
-8
-6
-4
-2
0
0 10 20 30 40 50 60
Movement(mm)
Load (MN)
Equivalent Top Load-Movement Curve
8. Interpretation of test results.
• The Osterberg cell loads the test pile in compression similar to a conventional
top load test, and hence the data form o cell is analyzed in much the same way
of conventional test.
• The only significant difference between the two tests is that the o cell provides
two load-movement curves, one for side shear and one for end bearing.
• Combined bearing capacity of the two components obtained as follow:
• Select an arbitrary point on the load movement curve, and determine the side shear.
• Determine the end bearing for the same point.
• From the upper two value we construct a point on “Top Load-Movement curve”.
• Repeat the process for multiple points and construct the curve.
12/12/2016 Alaa Mohamed Metwally 16
9. References
1. John H.Shmertmann & johnA. Hayes “The Osterberg cell and bored pile
testing- a symbiosis".TheThird International Geotechnical Engineering
Conference-Cairo University, 5-8 Jan 1997.
2. https://www.youtube.com/watch?v=fDJVpe37_Qg
3. https://www.youtube.com/watch?v=afKrgdJf2k4&spfreload=10
12/12/2016 Alaa Mohamed Metwally 17
Presented By
Student at Nile Academy for Science and Technology
Code: 130326
Due date: 9-12-2016
12/12/2016 Alaa Mohamed Metwally 18

More Related Content

PDF
PHƯƠNG PHÁP THÍ NGHIỆM OSTERBERG (O-CELL)
PDF
Bài giảng kết cấu bê tông cốt thép
PPTX
Pile load test
PPTX
Breakwaters and types
PPTX
CONSTRUCTION OF ROADS
PDF
Supervision of piling works, ACES, 2011, Singapore
PPT
Gear and Gear trains
PPTX
Highway Construction Materials and Practice
PHƯƠNG PHÁP THÍ NGHIỆM OSTERBERG (O-CELL)
Bài giảng kết cấu bê tông cốt thép
Pile load test
Breakwaters and types
CONSTRUCTION OF ROADS
Supervision of piling works, ACES, 2011, Singapore
Gear and Gear trains
Highway Construction Materials and Practice

What's hot (20)

PDF
Bullock bidirectional testing
PPT
The Pushover Analysis from basics - Rahul Leslie
PDF
Machine Foundation Design
PPTX
Pile foundation
PPTX
3d consolidation test
PPTX
Blast load and its analysis
PDF
Steel design-examples
DOCX
Machine Foundation Design - An Introduction
PDF
Prestressed Concrete Design
PPT
Concrete testing
PPTX
Flexural strength in concrete test
PDF
Lecture 8 raft foundation
DOCX
project report on earth quake resisting building
PPTX
Wind load
DOC
Examples on seepage
PPTX
Non destructive test in CIVIL ENGINEERING Construction
PDF
Chapter 1: Foundation Engineering
PDF
Construction methods and equipments
PPTX
Cbr test
PDF
Calculation of blast loads
Bullock bidirectional testing
The Pushover Analysis from basics - Rahul Leslie
Machine Foundation Design
Pile foundation
3d consolidation test
Blast load and its analysis
Steel design-examples
Machine Foundation Design - An Introduction
Prestressed Concrete Design
Concrete testing
Flexural strength in concrete test
Lecture 8 raft foundation
project report on earth quake resisting building
Wind load
Examples on seepage
Non destructive test in CIVIL ENGINEERING Construction
Chapter 1: Foundation Engineering
Construction methods and equipments
Cbr test
Calculation of blast loads
Ad

Viewers also liked (18)

PDF
Loadtestinghandbook
PPTX
Bai thuyet trinh nhom 6
PDF
2. Benoit Latapie - Foundations for infrastructure projects in MENA
PDF
Stress Calculation | weyer special
PDF
Evaluation of the extreme and fatigue load measurements at alpha ventus
DOCX
De cuong tn 17
PPT
Bullock bidirectional testing
PDF
87924560 chuyende detector
DOC
72. bien phap thi cong coc khan nhoi
PPTX
Cd chap 2 - static loading
PDF
Giáo Trình thí nghiệm và kiểm định công trình
PDF
Bài giảng thí nghiệm và kiểm định công trình- TS.Nguyễn Trung Hiếu
PPT
DESIGN AGAINST FLUCTUATING LOAD
PDF
PED 2016 - Design 101 - Week 2 - Handouts
PPT
Thi công cọc khoan nhồi
PDF
Design of machine_elements_
PPT
Chapter 4 deep foundation ( bi )
PDF
LinkedIn SlideShare: Knowledge, Well-Presented
Loadtestinghandbook
Bai thuyet trinh nhom 6
2. Benoit Latapie - Foundations for infrastructure projects in MENA
Stress Calculation | weyer special
Evaluation of the extreme and fatigue load measurements at alpha ventus
De cuong tn 17
Bullock bidirectional testing
87924560 chuyende detector
72. bien phap thi cong coc khan nhoi
Cd chap 2 - static loading
Giáo Trình thí nghiệm và kiểm định công trình
Bài giảng thí nghiệm và kiểm định công trình- TS.Nguyễn Trung Hiếu
DESIGN AGAINST FLUCTUATING LOAD
PED 2016 - Design 101 - Week 2 - Handouts
Thi công cọc khoan nhồi
Design of machine_elements_
Chapter 4 deep foundation ( bi )
LinkedIn SlideShare: Knowledge, Well-Presented
Ad

Similar to The osterberg cell static loading test (20)

PDF
Ce6411 som l ab 2013_regulation
PPTX
Swel Presentation
PPTX
What if battery would have mind?
PPTX
WL 112 Ch06 ch06 presentation
PPTX
TBEA ENERGY (INDIA) PVT LTD
PDF
Core plugging
PPTX
PDF
Conference Paper on Multi range load cell
PPT
Creative Pultrusions, Inc. SuperPile Marine Products
PPTX
Design and development of horizontal tensile testing machine (5kN)
DOCX
Sheet1Moisture content analysis final resultsGroupValue of m3 (g)A.docx
PDF
Methodology-of-Static-Pile-Load-Test.pdf
PDF
High strain dynamic pile testing - Independent Geoscience Pty Ltd
PPTX
Load banks
PDF
IRJET- Experimental Investigation on RCC Long Hollow Circular Columns with FR...
PDF
"Fatigue testing of reinforced concrete beam instrumented with distributed op...
PDF
31456536-MIT - Masters Thesis, Edward Snow
PPTX
FEA AND EXPERIMENTAL QUASI-STATIC CRUSHING OF ALUMINIUM HONEYCOMB STRUCTURE
PPTX
URC Poster
PDF
Diploma-3-Strength_of_Materials-Lab-manual-by-Bhimsen-Murmu.pdf
Ce6411 som l ab 2013_regulation
Swel Presentation
What if battery would have mind?
WL 112 Ch06 ch06 presentation
TBEA ENERGY (INDIA) PVT LTD
Core plugging
Conference Paper on Multi range load cell
Creative Pultrusions, Inc. SuperPile Marine Products
Design and development of horizontal tensile testing machine (5kN)
Sheet1Moisture content analysis final resultsGroupValue of m3 (g)A.docx
Methodology-of-Static-Pile-Load-Test.pdf
High strain dynamic pile testing - Independent Geoscience Pty Ltd
Load banks
IRJET- Experimental Investigation on RCC Long Hollow Circular Columns with FR...
"Fatigue testing of reinforced concrete beam instrumented with distributed op...
31456536-MIT - Masters Thesis, Edward Snow
FEA AND EXPERIMENTAL QUASI-STATIC CRUSHING OF ALUMINIUM HONEYCOMB STRUCTURE
URC Poster
Diploma-3-Strength_of_Materials-Lab-manual-by-Bhimsen-Murmu.pdf

Recently uploaded (20)

PDF
composite construction of structures.pdf
PPTX
UNIT 4 Total Quality Management .pptx
PPTX
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx
PDF
Unit I ESSENTIAL OF DIGITAL MARKETING.pdf
PPTX
bas. eng. economics group 4 presentation 1.pptx
PPTX
web development for engineering and engineering
PDF
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
PDF
Model Code of Practice - Construction Work - 21102022 .pdf
PDF
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
PDF
PPT on Performance Review to get promotions
PPTX
CH1 Production IntroductoryConcepts.pptx
PPTX
Lecture Notes Electrical Wiring System Components
PPTX
additive manufacturing of ss316l using mig welding
PPTX
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
PPTX
OOP with Java - Java Introduction (Basics)
PDF
Automation-in-Manufacturing-Chapter-Introduction.pdf
PDF
Digital Logic Computer Design lecture notes
PPT
Introduction, IoT Design Methodology, Case Study on IoT System for Weather Mo...
PPTX
Foundation to blockchain - A guide to Blockchain Tech
PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
composite construction of structures.pdf
UNIT 4 Total Quality Management .pptx
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx
Unit I ESSENTIAL OF DIGITAL MARKETING.pdf
bas. eng. economics group 4 presentation 1.pptx
web development for engineering and engineering
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
Model Code of Practice - Construction Work - 21102022 .pdf
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
PPT on Performance Review to get promotions
CH1 Production IntroductoryConcepts.pptx
Lecture Notes Electrical Wiring System Components
additive manufacturing of ss316l using mig welding
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
OOP with Java - Java Introduction (Basics)
Automation-in-Manufacturing-Chapter-Introduction.pdf
Digital Logic Computer Design lecture notes
Introduction, IoT Design Methodology, Case Study on IoT System for Weather Mo...
Foundation to blockchain - A guide to Blockchain Tech
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...

The osterberg cell static loading test

  • 1. The Osterberg Cell Static Loading Test Utilizing The Osterberg Cell for Loading test instead of Conventional Static LoadingTest 12/12/2016 Alaa Mohamed Metwally 1
  • 2. 1. Introduction • The Osterberg Cell is a Sacrificial jack-like device which the Engineer can have installed at the tip of a driven pile or on the reinforcement of a bored pile. • The cell provides the static loading and requires no overhead frame or other external reaction system. • Hence, We can now statically test full-sized bored piles (also known as drilled shafts, drilled piers or caissons) to near their ultimate capacity. Furthermore, we can do it more conveniently, economically and safely than ever before as no reaction system required like before. • O Cell testing and bored pile have a beneficial, cooperative relationship or a “Symbiosis”. • Generally high capacity of bored piles, in combination with high cost of top load system providing more than 10 MN, make conventional top load testing impractical for routine testing. 12/12/2016 Alaa Mohamed Metwally 2
  • 3. 1. Introduction • The O Cell static load test method, providing high capacities at affordable costs, has become an attractive alternative method for testing bored piles. • At mid 1994 the U.S Federal Highway Administration (FHWA) found that Engineers and Contractors considered the O Cell “the method of choice” and it’s use had risen rapidly to about 65% of all bored pile testing, this trend has continued and usage now exceed 90% not in the U.S only but all over the world. 12/12/2016 Alaa Mohamed Metwally 3
  • 4. 1. Introduction 12/12/2016 Alaa Mohamed Metwally 4 Osterberg Cell
  • 5. 2. Static load testing using O Cell 12/12/2016 Alaa Mohamed Metwally 5 Fig. 1 Pile Steel Beam P=F+Q F Q Pile F Q Expanding O Cell at the bottom of the pile Ground Level Ground Level Reaction System at the top of pile Q
  • 6. 2. Static load testing using O Cell • A Conventional test loads the bored pile in compression, at its tip, using an overhead reaction system or dead load, side shear F and end bearing Q combine to resist the top load P and Engineer can only separate this components approximately by analysis of strain and compression measurements together with modulus estimates. • The O Cell also loads the pile in compression, but from its bottom. As the O Cell expands, the end bearing Q provides reaction for the side shear F. and vice versa. Until reaching the capacity of one of the two component or the O Cell reaches its capacity. The vantage point here is that the test separate the side shear and end bearing components. • The O Cell test load placed at, or near, the bottom of the pile has twice testing effectiveness of that same load placed at the top in a conventional test. 12/12/2016 Alaa Mohamed Metwally 6
  • 7. 12/12/2016 Alaa Mohamed Metwally 3. Equipment 7
  • 8. 3. Equipment • After construction of the shaft, the test operator connects an automatic pump to the hydraulic lines that provides a pressure conduit to the cell, the load applied by an O Cell is calibrated versus hydraulic pressure before installation and the pressure applied to the cell is measured by a pressure transducer. • Movement measured by electronic gages connected to a computerized acquisition system. • The total expansion of the cell is measured by (LVWDTs) Linear vibrating wire transducers the lower part of which attached to bottom of the cell. • A steel telltales attached to the bottom of the cell used to measure the upward movement directly. • Subtracting the upward movement from total expansion gives the desired downward movement. 12/12/2016 Alaa Mohamed Metwally 8
  • 10. 4. History of Osterberg Cell • Dr. Jorje Osterberg, professor emeritus at Northwestern university. Developed and patented test which now carries his name. • The first experimental test pile was carried out in 1984, after this successful prototype professorOsterberg works very closely to American Equipment and Fabrication Corp. to evolve his cell from a bellows type expansion cell to the current design, very similar to piston type jack used in conventional test, but the piston extends downward not upward. • Haley & Aldrich was the first to use O Cell in practical application in 1987, to driven piles one over a river in Massachusetts and the other on a bridge which reaches 1.26 and 4 MN respectively. • Now Osterberg cell has steadily gained popularity all over the world for testing bored piles. 12/12/2016 Alaa Mohamed Metwally 10
  • 11. 5. Advantages of O Cell • Economy. • reduced construction time, saving in outlay capital, no top-of-pile reaction equipment required and less test design efforts, making the test cost from 1 3 to 2 3 the conventional test.The comparative cost reduces as the load increases. • High Load capacity. • Shear/Bearing Component • The cell automatically separates the side shear and end bearing components, despite of conventional test which gives the total capacity at a time • Improved safety. • The test energy lies deeply buried and no overhead load at the top of pile. • Rocket Socket. • The cell loaded at the bottom of the socket, near its bottom and gives an automated separation of components 12/12/2016 Alaa Mohamed Metwally 11
  • 12. 5. Advantages of O Cell • Reduced work area. • A 65 MN O Cell test, conducted in a 3 meter wide median strip of a busy interstate highway, which seems impossible when using conventional test as a big area needed for the reaction system or equipment and kentledge system. • Over water and battered shafts. • Static creep and setup effects. • Because the test is static the test load at any length of time can be estimated, the Engineers also can obtain separate data about creep behavior for the two components. • Sequential testing. • A long term stage tests with minimal efforts can be made for research purposes or other to obtain “aging” for example, been a unique advantage of O Cell test 12/12/2016 Alaa Mohamed Metwally 12
  • 13. 6. Limitations • Advance installation required. • In bored piles and most driven piles, the O Cell must be installed prior construction. • Balanced component requirement. • As the cell reaches the ultimate capacity in only one of its components, and shaft capacity limited to two times the capacity of component reaching ultimate, The Engineer should first analyze the expected side shear and end bearing components and either attempt to balance the two to get the most information from both. • The introduction of multilevel cell mitigates this limitation, and allow calculating ultimate side shear and end bearing in cases where bearing less than the side shear. • Equivalent top load curve. • Although the estimation of equivalent top load curve is conservatism, it remains estimate. • Sacrificial cell. • Cell considered expandable and not recovered after the test completed. However, grouting the tested pile allows using it as a permanent foundation pile. • Not suitable for certain types of piles. • H pile and sheet piles. 12/12/2016 Alaa Mohamed Metwally 13
  • 14. 7. Test results 12/12/2016 Alaa Mohamed Metwally 14 Sand and gravel shell 8.2 19.2 5.8 2.4 River 18.9 Hydraulic supply & telltale casing 35.7 -25 -20 -15 -10 -5 0 5 10 15 20 0 10 20 30 UpwordandDownwordMovement (mm) Load (MN) Osterberg Load-Movement Curve Purpose: To determine bearing capacity of the drilled shaft supporting a bridge pier. Method: Shafts drilled with polymer drilling slurry, 1.9 O.D. casing set on top of shale and 1.8 m hole drilled 5.8 m into shale 864mm load cell with 1.7 m diameter plate welded to bottom lowered into the hole. Pumped concrete placed to design top elevation of shaft. Results: Load reaches capacity of device at 34.56 mm downward and 7.62 mm upward movement, the ultimate capacity was greater than 54 MN. O-CellTest on a rock socketed bored pile
  • 15. -25 -20 -15 -10 -5 0 5 10 15 20 0 5 10 15 20 25 30 UpwordandDownwordMovement(mm) Load (MN) Osterberg Load-Movement Curve 8. Interpretation of test results. 12/12/2016 Alaa Mohamed Metwally -18 -16 -14 -12 -10 -8 -6 -4 -2 0 0 10 20 30 40 50 60 Movement(mm) Load (MN) Equivalent Top Load-Movement Curve
  • 16. 8. Interpretation of test results. • The Osterberg cell loads the test pile in compression similar to a conventional top load test, and hence the data form o cell is analyzed in much the same way of conventional test. • The only significant difference between the two tests is that the o cell provides two load-movement curves, one for side shear and one for end bearing. • Combined bearing capacity of the two components obtained as follow: • Select an arbitrary point on the load movement curve, and determine the side shear. • Determine the end bearing for the same point. • From the upper two value we construct a point on “Top Load-Movement curve”. • Repeat the process for multiple points and construct the curve. 12/12/2016 Alaa Mohamed Metwally 16
  • 17. 9. References 1. John H.Shmertmann & johnA. Hayes “The Osterberg cell and bored pile testing- a symbiosis".TheThird International Geotechnical Engineering Conference-Cairo University, 5-8 Jan 1997. 2. https://www.youtube.com/watch?v=fDJVpe37_Qg 3. https://www.youtube.com/watch?v=afKrgdJf2k4&spfreload=10 12/12/2016 Alaa Mohamed Metwally 17
  • 18. Presented By Student at Nile Academy for Science and Technology Code: 130326 Due date: 9-12-2016 12/12/2016 Alaa Mohamed Metwally 18