SlideShare a Scribd company logo
Estimate Review / Validation Checklist
Douglas W. Leo CCP CEP FAACE FRICS
Saybrook Associates, Inc.
Chair AACE International Estimating Sub-Committee
AACE Recommended Practices
• Cost Engineers Tool Kit -
– RP 10S-90 Cost Engineering Terminology
– RP 18R-97 Cost Estimating Classification System
– RP 21R-98 Project Code of Accounts
– RP 27R-03 Schedule Classification Systems
– RP 30R-03 Implementing Project Constructability
– RP31R-03 Reviewing, Validating and Documenting an
Estimate
– RP34R-05 Basis of Estimate
– RP 36R-08 Development of Cost Estimating Plans
– RP 38R-06 Documenting the Schedule Basis
Review/Validation Checklist - Introduction
The Project Cost Estimate that was just delivered is
amazing. It is exactly what was expected, costs were
immediately understandable and lower than anticipated.
Management will love this. The work on this project
estimate is worthy of great praise …… outstanding job!!!!
Were these words ever spoken outside of someone’s
dreams? …….. I think not.
Review / Validation Checklist Introduction
• Project Teams universally have the desire to produce
successful outcomes.
• They all want their work to be seen as on time, on
budget, and meeting the desire functionality.
• The desire is for a completed project package that is:
– Transparent
– Explainable
– Defendable
– Acceptable to management
Review / Validation Checklist Introduction
• Three main project drivers: Functionality, Schedule, Cost
• Over the course of the project there is shifting
importance for the three drivers but at some point costs
become the main issue with regards to moving the
project forward.
• When costs become the main focus, a thorough
understanding of the project estimate and how it was
developed is the task at hand.
• A review and validation takes place at multiple levels:
internally by the estimating provider, by the owner
client, by third party reviewers
Review / Validation Checklist Introduction
Completed project estimating package should always
include certain elements:
• Basis of Estimate
• Estimate Summary
• Estimate Detail
• Reconciliation Report
• Historical Cost Metric Report
• Estimate Deliverables Report
• Risk Analysis Report
PHASE 2
SELECT from
Alternatives
Clearly Frame
Goal
Test for
Strategic Fit
Preliminary
Overall Plan
Preliminary
Assessment
~1 % Engr.
AACE Class 5
Cost Estimate
PHASE 1
IDENTIFY & Assess
Opportunity
Fully Define
Scope
Develop
Detailed
Execution Plans
Refine Estimate
Submit Funding
for Approval
~25 % Engr.
AACE Class 3
Cost Estimate
Generate
Alternatives
Preliminary
Development
of Alternatives
Develop
Expected
Value
Identify
Preferred
Alternative
AACE Class 4
Cost Estimate
Operate Asset
Monitor &
Evaluate
Performance
Identify New
Opportunities
PHASE 3
DEVELOP Preferred
Alternative
PHASE 4
EXECUTE
(Detail EPC)
PHASE 5
OPERATE &
Evaluate
Implement
Execution Plan
Minimize
Changes
Finalize
Operating Plan
Business Plan
for Phase 5
Project Review
1 2 3 4 5
AFE
Various Cost Estimates Are Prepared
During the Project Development Process
Process Industry Classification Matrix
Primary Characteristic Secondary Characteristics
LEVEL OF PROJECT
DEFINITION
END USAGE METHODOLOGY ACCURACY RANGE
PREPARATION
EFFORT
ESTIMATE
CLASS
Expressed as % of
complete definition
Typical purpose of
estimate
Typical Estimating
Method
Typical variation in low
and high ranges (a)
Typical degree of effort
relative to least cost
indice of 1 (b)
5 0% to 2% Concept Screening
Capacity Factored,
Parametric Models,
Judgement, or Analogy
-20% to -50%
+30% to +100%
1
4 1% to 15% Study or Feasability
Equipment Factored, or
Parametric Models
-15% to -30%
+20% to +50%
2 to 4
3 10% to 40%
Budget, Authorization,
or Control
Semi-Detailed Unit
Costs w/ Assembly
Level Line Items
-10% to -20%
+10% to +30%
3 to 10
2 30% to 70% Control or Bid/Tender
Detailed Unit Cost w/
Forced Detailed Takeoff
-5% to -15%
+5% to +20%
4 to 20
1 50% to 100%
Check Estimate or
Bid/Tender
Detailed Unit Cost w/
Detailed Takeoff
-3% to -10%
+3% to +15%
5 to 100
Notes: a) The state of process technology and availability of applicable reference cost data affect the range
markedly. The +/- value represents typical percentage variation of actual costs from the cost estimate after
application of contingency (typically at a 50% level of confidence) for given scope.
b) If the range indice value of "1" represents .005%, then an indice value of 100 represents 0.5%
Estimate preparation effort is highly dependent upon the size of the project and the quality of estimating
data and tools.
Estimate Input Checklist and Maturity Matrix
Estimate Classification
CLASS 5 CLASS 4 CLASS 3 CLASS 2 CLASS 1
General Project Data
Project Scope Description General Preliminary Defined Defined Defined
Plant Production/Facility Capacity Assumed Preliminary Defined Defined Defined
Plant Location General Approximate Specific Specific Specific
Soils & Hydrology None Preliminary Defined Defined Defined
Integrated Project Plan None Preliminary Defined Defined Defined
Project Master Schedule None Preliminary Defined Defined Defined
Escalation Strategy None Preliminary Defined Defined Defined
Work Breakdown Structure None Preliminary Defined Defined Defined
Project Code of Accounts None Preliminary Defined Defined Defined
Contracting Strategy Assumed Assumed Preliminary Defined Defined
Engineering Deliverables
Block Flow Diagrams S/P P/C C C C
Plot Plans S P/C C C
Process Flow Diagrams (PFD's) S/P P/C C C
Utility Flow Diagrams (UFD's) S/P P/C C C
Piping & Instrument Diagrams (P&ID's) S P/C C C
Heat & Material Balances S P/C C C
Process Equipment List S/P P/C C C
Utility Equipment List S/P P/C C C
Electrical One-Line Drawings S/P P/C C C
Specifications & Datasheets S P/C C C
General Equipment Arrangement Drawings S P/C C C
Spare Parts Listings S/P P C
Mechanical Discipline Drawings S P P/C
Electrical Discipline Drawings S P P/C
Instrumentation/Control System Discipline Drawings S P P/C
Civi/Structural/Site Discipline Drawings S P P/C
Estimate Review / Validation Checklist
• Total Engineering Completeness - (%) at the time of
MTO creation – primary determination of accuracy and
estimate classification
• Project Estimating Plan – developed, reviewed, agreed
upon by all parties, signed off before start of estimate
• Basis of Estimate – prepared by estimating provider,
reflecting the completed estimate
Estimate Review / Validation Checklist
• Estimate Summary – with a defined WBS / COA
structure
• Estimate Detail – transparent and easily followed that is
in-line with the estimate summary
• Estimate Cost Metrics – how closely are estimated costs
in-line with defendable historical cost metrics (from
established actual costs not estimated costs)
Estimate Review / Validation Checklist
• Estimate Reconciliation – differences and similarities
between Previous estimates for this project or similar
projects
• Estimate Deliverables Checklist – what were the
deliverables utilized to produce the estimate. Who
produced them & when were they available to
estimating (Primary indicator of completeness of scope)
• Project Risk Analysis and Risk Logs – how was
contingency developed and its statistical significance?
How was risk identified and mitigated?
Estimate Review / Validation Checklist
• Material Take Offs – how were MTOs created, by whom
and when in the process? How were updates handled?
Trace MTOs from creation to the estimate
• Equipment pricing – how much is equipment pricing is
from quotes, from historical data or allowances?
• Equipment Bid Tabs – What is the project philosophy
regarding the selection of equipment pricing? Are the
costs in the estimate traceable to quotes?
• Change Management Plan and Change Logs – how is
scope being managed?
Conclusions
• Utilizing the Checklist a reviewer will understand the
development of the project cost and their completeness
and degree of accuracy
• Any items not available will indicate areas of concern
and places to focus greater attention
• But most importantly the checklist, if utilized by
estimating providers and project teams as a guide
during the complete project process, will produce
project costs that will be better understood and
manageable to all project stakeholders.

More Related Content

PPSX
3 pm3 c_2-%20estimating%20costs
PPTX
2.07 cost management 1
PPSX
Project Control System
PDF
Resume - Nermeen Atef sam
PDF
Project Cost & Schedule Integration Lessons Learnt
PDF
Planning and Scheduling Construction Projects, Part 1: The Planning Process
PPT
Project cost management
PDF
BioPharma Projects: Essentials in Project Controls
3 pm3 c_2-%20estimating%20costs
2.07 cost management 1
Project Control System
Resume - Nermeen Atef sam
Project Cost & Schedule Integration Lessons Learnt
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Project cost management
BioPharma Projects: Essentials in Project Controls

What's hot (20)

PPTX
4 an activity analysis of project scheduling problem a case study 1
PDF
Schedule Updates
PDF
30 60 90 percent ifc engineering what is the project progress - Oracle Prim...
PDF
Schedule Recovery Using Earned Value
PPTX
BRQ_PortfolioMgmt BRQPresentation
PDF
IWP Timeline
PPTX
Session 13 4th edition PMP
PPTX
Quality control inspection reports and outcomes wrt contract management
PPT
Implementation
PDF
Project Controls Expo 09/10 Nov London 2011 - An Introduction to Performance ...
PDF
Project Scheduling and Control Projects
PDF
Perform quantitative risk analysis
PPTX
Major Release Initial Planning Review
PDF
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
PPTX
Building a Better PPAP Experience
PDF
Favorite Delay Analysis Methodologies Town Hall SEI
PDF
CDS Construction Execution Process ^0 Strategy
PPT
Marshall Esc Lille Defense R2
PDF
How to build a credible performance measurement baseline (v5)
PDF
construction project planing
4 an activity analysis of project scheduling problem a case study 1
Schedule Updates
30 60 90 percent ifc engineering what is the project progress - Oracle Prim...
Schedule Recovery Using Earned Value
BRQ_PortfolioMgmt BRQPresentation
IWP Timeline
Session 13 4th edition PMP
Quality control inspection reports and outcomes wrt contract management
Implementation
Project Controls Expo 09/10 Nov London 2011 - An Introduction to Performance ...
Project Scheduling and Control Projects
Perform quantitative risk analysis
Major Release Initial Planning Review
EXTENSION OF TIME CLAIMS IN OIL AND GAS CONSTRUCTION PROJECTS
Building a Better PPAP Experience
Favorite Delay Analysis Methodologies Town Hall SEI
CDS Construction Execution Process ^0 Strategy
Marshall Esc Lille Defense R2
How to build a credible performance measurement baseline (v5)
construction project planing
Ad

Similar to 2015 Toronto Section Presentation (20)

PPT
Capital Cost Expenditure Estimating .ppt
PPT
Capital Expenditure Estimating Cost of Project
PPTX
Project Management: Cost Management Knowledge Area
PPT
Software Estimation Checklist
PDF
Topic 12 - Project Cost Management.pdf
PDF
Project Management Day 4 Cost ٌ R02.pdf
PDF
Maksym Vyshnivetskyi: Управління вартістю (Cost) (UA)
PPT
Software Project Management Spm1176
PDF
Project Controls Expo – 13th Nov 2013- "The Key Role of the Cost Engineer Ach...
PPTX
Pmp – pmbok 5th edition chapter7 project cost management
PDF
Day 7 Project Cost Management .pdf
PDF
project Cost management
PPTX
PMP-Cost Management area
PPTX
Construction Cost Estimating - Quality Cost Estimating
PDF
8.project cost management
PDF
Session T7 - Total Cost Management - The synergy between Cost Estimating and ...
PPTX
Session 9 4th edition PMP
PDF
07.cost management updated
PDF
CostManagementSlides.pdf
PDF
L04_Project Cost Management Explained .pdf
Capital Cost Expenditure Estimating .ppt
Capital Expenditure Estimating Cost of Project
Project Management: Cost Management Knowledge Area
Software Estimation Checklist
Topic 12 - Project Cost Management.pdf
Project Management Day 4 Cost ٌ R02.pdf
Maksym Vyshnivetskyi: Управління вартістю (Cost) (UA)
Software Project Management Spm1176
Project Controls Expo – 13th Nov 2013- "The Key Role of the Cost Engineer Ach...
Pmp – pmbok 5th edition chapter7 project cost management
Day 7 Project Cost Management .pdf
project Cost management
PMP-Cost Management area
Construction Cost Estimating - Quality Cost Estimating
8.project cost management
Session T7 - Total Cost Management - The synergy between Cost Estimating and ...
Session 9 4th edition PMP
07.cost management updated
CostManagementSlides.pdf
L04_Project Cost Management Explained .pdf
Ad

2015 Toronto Section Presentation

  • 1. Estimate Review / Validation Checklist Douglas W. Leo CCP CEP FAACE FRICS Saybrook Associates, Inc. Chair AACE International Estimating Sub-Committee
  • 2. AACE Recommended Practices • Cost Engineers Tool Kit - – RP 10S-90 Cost Engineering Terminology – RP 18R-97 Cost Estimating Classification System – RP 21R-98 Project Code of Accounts – RP 27R-03 Schedule Classification Systems – RP 30R-03 Implementing Project Constructability – RP31R-03 Reviewing, Validating and Documenting an Estimate – RP34R-05 Basis of Estimate – RP 36R-08 Development of Cost Estimating Plans – RP 38R-06 Documenting the Schedule Basis
  • 3. Review/Validation Checklist - Introduction The Project Cost Estimate that was just delivered is amazing. It is exactly what was expected, costs were immediately understandable and lower than anticipated. Management will love this. The work on this project estimate is worthy of great praise …… outstanding job!!!! Were these words ever spoken outside of someone’s dreams? …….. I think not.
  • 4. Review / Validation Checklist Introduction • Project Teams universally have the desire to produce successful outcomes. • They all want their work to be seen as on time, on budget, and meeting the desire functionality. • The desire is for a completed project package that is: – Transparent – Explainable – Defendable – Acceptable to management
  • 5. Review / Validation Checklist Introduction • Three main project drivers: Functionality, Schedule, Cost • Over the course of the project there is shifting importance for the three drivers but at some point costs become the main issue with regards to moving the project forward. • When costs become the main focus, a thorough understanding of the project estimate and how it was developed is the task at hand. • A review and validation takes place at multiple levels: internally by the estimating provider, by the owner client, by third party reviewers
  • 6. Review / Validation Checklist Introduction Completed project estimating package should always include certain elements: • Basis of Estimate • Estimate Summary • Estimate Detail • Reconciliation Report • Historical Cost Metric Report • Estimate Deliverables Report • Risk Analysis Report
  • 7. PHASE 2 SELECT from Alternatives Clearly Frame Goal Test for Strategic Fit Preliminary Overall Plan Preliminary Assessment ~1 % Engr. AACE Class 5 Cost Estimate PHASE 1 IDENTIFY & Assess Opportunity Fully Define Scope Develop Detailed Execution Plans Refine Estimate Submit Funding for Approval ~25 % Engr. AACE Class 3 Cost Estimate Generate Alternatives Preliminary Development of Alternatives Develop Expected Value Identify Preferred Alternative AACE Class 4 Cost Estimate Operate Asset Monitor & Evaluate Performance Identify New Opportunities PHASE 3 DEVELOP Preferred Alternative PHASE 4 EXECUTE (Detail EPC) PHASE 5 OPERATE & Evaluate Implement Execution Plan Minimize Changes Finalize Operating Plan Business Plan for Phase 5 Project Review 1 2 3 4 5 AFE Various Cost Estimates Are Prepared During the Project Development Process
  • 8. Process Industry Classification Matrix Primary Characteristic Secondary Characteristics LEVEL OF PROJECT DEFINITION END USAGE METHODOLOGY ACCURACY RANGE PREPARATION EFFORT ESTIMATE CLASS Expressed as % of complete definition Typical purpose of estimate Typical Estimating Method Typical variation in low and high ranges (a) Typical degree of effort relative to least cost indice of 1 (b) 5 0% to 2% Concept Screening Capacity Factored, Parametric Models, Judgement, or Analogy -20% to -50% +30% to +100% 1 4 1% to 15% Study or Feasability Equipment Factored, or Parametric Models -15% to -30% +20% to +50% 2 to 4 3 10% to 40% Budget, Authorization, or Control Semi-Detailed Unit Costs w/ Assembly Level Line Items -10% to -20% +10% to +30% 3 to 10 2 30% to 70% Control or Bid/Tender Detailed Unit Cost w/ Forced Detailed Takeoff -5% to -15% +5% to +20% 4 to 20 1 50% to 100% Check Estimate or Bid/Tender Detailed Unit Cost w/ Detailed Takeoff -3% to -10% +3% to +15% 5 to 100 Notes: a) The state of process technology and availability of applicable reference cost data affect the range markedly. The +/- value represents typical percentage variation of actual costs from the cost estimate after application of contingency (typically at a 50% level of confidence) for given scope. b) If the range indice value of "1" represents .005%, then an indice value of 100 represents 0.5% Estimate preparation effort is highly dependent upon the size of the project and the quality of estimating data and tools.
  • 9. Estimate Input Checklist and Maturity Matrix Estimate Classification CLASS 5 CLASS 4 CLASS 3 CLASS 2 CLASS 1 General Project Data Project Scope Description General Preliminary Defined Defined Defined Plant Production/Facility Capacity Assumed Preliminary Defined Defined Defined Plant Location General Approximate Specific Specific Specific Soils & Hydrology None Preliminary Defined Defined Defined Integrated Project Plan None Preliminary Defined Defined Defined Project Master Schedule None Preliminary Defined Defined Defined Escalation Strategy None Preliminary Defined Defined Defined Work Breakdown Structure None Preliminary Defined Defined Defined Project Code of Accounts None Preliminary Defined Defined Defined Contracting Strategy Assumed Assumed Preliminary Defined Defined Engineering Deliverables Block Flow Diagrams S/P P/C C C C Plot Plans S P/C C C Process Flow Diagrams (PFD's) S/P P/C C C Utility Flow Diagrams (UFD's) S/P P/C C C Piping & Instrument Diagrams (P&ID's) S P/C C C Heat & Material Balances S P/C C C Process Equipment List S/P P/C C C Utility Equipment List S/P P/C C C Electrical One-Line Drawings S/P P/C C C Specifications & Datasheets S P/C C C General Equipment Arrangement Drawings S P/C C C Spare Parts Listings S/P P C Mechanical Discipline Drawings S P P/C Electrical Discipline Drawings S P P/C Instrumentation/Control System Discipline Drawings S P P/C Civi/Structural/Site Discipline Drawings S P P/C
  • 10. Estimate Review / Validation Checklist • Total Engineering Completeness - (%) at the time of MTO creation – primary determination of accuracy and estimate classification • Project Estimating Plan – developed, reviewed, agreed upon by all parties, signed off before start of estimate • Basis of Estimate – prepared by estimating provider, reflecting the completed estimate
  • 11. Estimate Review / Validation Checklist • Estimate Summary – with a defined WBS / COA structure • Estimate Detail – transparent and easily followed that is in-line with the estimate summary • Estimate Cost Metrics – how closely are estimated costs in-line with defendable historical cost metrics (from established actual costs not estimated costs)
  • 12. Estimate Review / Validation Checklist • Estimate Reconciliation – differences and similarities between Previous estimates for this project or similar projects • Estimate Deliverables Checklist – what were the deliverables utilized to produce the estimate. Who produced them & when were they available to estimating (Primary indicator of completeness of scope) • Project Risk Analysis and Risk Logs – how was contingency developed and its statistical significance? How was risk identified and mitigated?
  • 13. Estimate Review / Validation Checklist • Material Take Offs – how were MTOs created, by whom and when in the process? How were updates handled? Trace MTOs from creation to the estimate • Equipment pricing – how much is equipment pricing is from quotes, from historical data or allowances? • Equipment Bid Tabs – What is the project philosophy regarding the selection of equipment pricing? Are the costs in the estimate traceable to quotes? • Change Management Plan and Change Logs – how is scope being managed?
  • 14. Conclusions • Utilizing the Checklist a reviewer will understand the development of the project cost and their completeness and degree of accuracy • Any items not available will indicate areas of concern and places to focus greater attention • But most importantly the checklist, if utilized by estimating providers and project teams as a guide during the complete project process, will produce project costs that will be better understood and manageable to all project stakeholders.