SlideShare a Scribd company logo
-Super Lightweight Tank-
A Risk Management Case Study in
Mass Reduction
AN INOVATIVE DISTRIBUTED PROJECT CONTROL
APPROACH : A CASE STUDY OF THE CASSINI MIS
Presented by Yulhendri Saputra & Marcel Bernadi
 Introduction
 Problem Issues
 Environmental Scanning
 Alternatives Course of Actions
 Key Success Factors
 Selection of Best Alternatives
 Recommendation
INTRODUCTION
 Originally. Congress approved funding for a joint program composed of a
Comet Rendezvous/Asteroid Flyby (CRAF) mission and the Cassini mission.
 The program was authorized with the stipulation that it would be canceled if
original cost estimates were exceeded.
 In response, Jet Propulsion Laboratory (JPL) chose to implement a classical
earned-value system for controlling schedule and cost.
 In 1990, after purchasing a full-featured commercialoff-the-shelf (COTS)
project management system, the project hired 20 schedulers and planners to
implement a full) integrated network schedule.
 The system was based on classic program evaluation and review technique
(PERT) concepts (developed in 1958) and the Cost/Schedule Control System
Criteria (C/SCSC) formalized by the U.S. Department of Defense in 1967.
 A large expenditure was made for training at all project levels. By late 199 1 ,
CRAF/Cassini project managers observed somt: trends with the entire project
control process: This refereed c a s e study article w a s accepted January
1996.
ENVIRONMENTAL SCANNING
 The COTS project management system process countered JPL's effort to
having decision making shifted to lower levels in the organization.
 Considering the large expenditure for project control, no corresponding
improvement was made with regard to communication between the
different project elements.
 The COTS project management system was not viewed as an easy-to-use
tool.
 The COTS project management system did not provide a straightforward
method for addressing uncertainty.
PROBLEM ISSUES
"Network-based techniques as planning tools do not consider the issue of
uncertainty in identifying tasks and the relationship among tasks in the network"
(Morad and Vorster, 1993).
 
"A network models only one set of schedule options at any given time"
(Mathews, 1993).
"The current approach to planning and controlling complex projects has
traditionally been to eliminate mcertainty and change from our projects, or at
ieast treat them as if change will not occur7' (Archibald and Lichtenburg, 1994).
"Older packages emphasize the critical path method, which can be very clumsy
when scheduling people. Classic approaches tend to be expensive and roo!ed
in legacy technologies" (Wood, 1995). In short, the project found that the
cleanliness of theory (PERT, CISCSC) was no match for the clutter of reality.
ALTERNATIVE COURSE OF ACTION
1. CPM and PERT
Network-based techniques as planning tools do not consider the issue of uncertainty in
identifying tasks and the relationship among tasks in the network"
 
Eliminate uncertainty and change from our projects, or treat them as if no change
Older packages emphasize the critical path method, which can be very clumsy. In short,
the project found that the cleanliness of theory was no match for the clutter of reality.
2. CMlS
• All project products have to be someone's deliverable (Del) and another's receivable
• Once a deliverer and receiver reach an agreement on the need t
• Each Reciving and Delivery agreement
• Any person on the project is able to determine a Rec/Dells status at any given time
KEY SUCCES FACTOR
The value of this approach became immediately apparent:
I. The CMIS schedule control module facilitated and increased communication. It also
highlighted where communication between project elements was deficient. Product
specification and delivery schedule disputes were easily identified, problems were
quickly addressed. and schedule confusion vanished.
2. Schedule tracking and statusing became virtually effortless. The project implemented
an automated statusing system that polled receivers on a weekly basis about whether
they had received their agreed-to deliveries for that week. Receiver responses to the
messages were automatically compiled and summarized in weekly metric reports to
management. In addition, on-line statusing within CMIS was provided.
3. The single-database design allowed current project-level schedule reports to be
generated at any time.
4. CMIS reduced centralized project control costs to less than 0.25% of the total project
budget. The workforce of planners/schedulers dropped from
20 people to an operations staff of 3 . This yielded a savings of greater than 60 work-
years over the project's development phase.
SELECTION OF BEST ALTERNATIVES
CMIS Schedule Control Module Planning Reports and Metrics.
•Before CMIS implementation, many seasoned managers expected that the simple level
of formality (that is, requiring technical managers to input only the product's
name, source, destination, and delivery date) would not be beneficial. This perception
changed dramatically when only 3 of the initial 1,200 products submitted to the CMIS
database had matching receiver and deliverer information. Moreover, technical
managers quickly recognized that CMIS allowed them to formalize their external delivery
commitments without limiting their ability to modify their internal schedules to best meet
their delivery commitments.
•The reconciliation process found holes in the plan where needed products were not
being supplied or were being supplied but not needed. The process also uncovered
many occurrences of product delivery dates that were much later than those needed by
receivers.
•CMIS provides metrics for tracking the level of reconciliation at the project. system. and
subsystem levels.
•
RecIDel metrics are reviewed weekly by the project manager and his staff. Lack of a
reconciled plan immediately draws management attention.
Recommendation
• For large research and development projects, effective cost and schedule control is
possible without incurring the large costs associated with centralized project control
systems.
• An effective cost/schedule management information system for all levels of
management can be built by focusing on satisfying the requirements of first-line
managers and lead engineers. Such an approach removes the inherent noise in
management reports
created by planning and control staffs.
•
An effective way to deal with schedule uncertainty is to simplify the project control
approach to focus on the areas where schedule uncertainty has the greatest impacts
(that is, the interfaces between receivers and deliverers).
Thank you
Ref :
Tuman, John, "It's Time to Re-engineer Project Management." PM Network, 7: 1 (January 1993),
pp. 40-4 1 .
Morad, Ayman A., and Michael C. Vorster, "Network-based Versus A 1-Based Techniques in
Project Planning." Project Management Journal, 24: 1 (March 1993), p. 25.
Mathews, Mark D., "Introducing Networks to an In-Progress Project." Project Management Journal,
24:2 (June 1993), p. 9. Archibald, Russell D., and Lichtenburg Steen, "Uncertainty and Change
Require a New Management Model." PAM NETwork, 7:5 (May 1994), pp. 6-10.
Wood, Lamont, "Project Management Perfect Harmony.“ nformation Week,No. 526 (May 8, 1995),
pp. 42-54.
Thank you
1.Please elaborate the different between
PERT project evaluation review technique VS
CPM critical path method ,CMIS contstruction
management information system ?
2.What are the benefit and disadvantages of
using PERT/CPM/CMIS ?

More Related Content

PDF
Applicability of heuristic approach in planning and scheduling project
PDF
Earned Value Analysis
PDF
Does Better Scheduling Drive Execution Success?
PPT
Project management cpm-pert
PPT
Project Management Techniques
PPTX
Unit v mha project evaluation review technique (pert)
DOCX
Project risk management (1)
Applicability of heuristic approach in planning and scheduling project
Earned Value Analysis
Does Better Scheduling Drive Execution Success?
Project management cpm-pert
Project Management Techniques
Unit v mha project evaluation review technique (pert)
Project risk management (1)

Similar to 6 An Innovative Distributed Project Control (20)

PPTX
Mba ii pmom_unit-4.1 project management a
PDF
Topic 8A - Project Management PERT-CPM Part 1.pdf
PPTX
Presentation-1555555555555555555555.pptx
PPTX
Pert cpm-120421125920-phpapp02
PPTX
OR PERT CPM AND JOB SCHEDULING
PPTX
Unit IV-Project Management
PPTX
PERT-AND-CPM JNIBJJJJJJJJJJJJJJJJJJ.pptx
PPTX
Chapt5.pptx it is notes of the 5th chapter
PDF
PDF
Project Management for Business Engineering and Technology Third Edition John...
PPTX
Pert cpm
PPT
Introduction to Project Management
PPT
Project management in general and some methods
PDF
project management cpm and peat digram .pdf
PPTX
Objective of marketing in industrial management
PPTX
Project Networking CPM PERT MPH(PHSM) 3rd semester
PPT
7. (lecture 5) Project scheduling..ppt
PPTX
project management information system
PPT
Project-Management.ppt
Mba ii pmom_unit-4.1 project management a
Topic 8A - Project Management PERT-CPM Part 1.pdf
Presentation-1555555555555555555555.pptx
Pert cpm-120421125920-phpapp02
OR PERT CPM AND JOB SCHEDULING
Unit IV-Project Management
PERT-AND-CPM JNIBJJJJJJJJJJJJJJJJJJ.pptx
Chapt5.pptx it is notes of the 5th chapter
Project Management for Business Engineering and Technology Third Edition John...
Pert cpm
Introduction to Project Management
Project management in general and some methods
project management cpm and peat digram .pdf
Objective of marketing in industrial management
Project Networking CPM PERT MPH(PHSM) 3rd semester
7. (lecture 5) Project scheduling..ppt
project management information system
Project-Management.ppt
Ad

More from pmb25 (16)

PPT
4 Super Lightweight Tank - Risk Management
PPT
5 Application of Project Scheduling System for Construction Supply Chain Mana...
PPT
7 Ave Maria Nursing Home Audit
PPTX
6 monitoring and evaluation
PPTX
7 the identity project : Audit Case
PPTX
5 project scheduling in agriculture of stabilization 300 hectares grape gard...
PPTX
4 risk analysis in oil and gas projects
PPTX
3 Dart Risk Management Case Study
PPTX
6 A Guide to Project Management Auditing Assessment and Recommendation
PPTX
5 Design and Monitoring of Shellfish Restoration Projects
PPTX
4 an activity analysis of project scheduling problem a case study 1
PPT
Project Management Effectiveness in organizational Conditions
PPTX
Organizational Structure and Cross Cultural Management
PPTX
Advancing Project Management in Learning Organization
PPT
Restoring legitimacy in order to remain sustainable
PPTX
Dealing with conflict in project management
4 Super Lightweight Tank - Risk Management
5 Application of Project Scheduling System for Construction Supply Chain Mana...
7 Ave Maria Nursing Home Audit
6 monitoring and evaluation
7 the identity project : Audit Case
5 project scheduling in agriculture of stabilization 300 hectares grape gard...
4 risk analysis in oil and gas projects
3 Dart Risk Management Case Study
6 A Guide to Project Management Auditing Assessment and Recommendation
5 Design and Monitoring of Shellfish Restoration Projects
4 an activity analysis of project scheduling problem a case study 1
Project Management Effectiveness in organizational Conditions
Organizational Structure and Cross Cultural Management
Advancing Project Management in Learning Organization
Restoring legitimacy in order to remain sustainable
Dealing with conflict in project management
Ad

Recently uploaded (20)

PDF
Module 4: Burden of Disease Tutorial Slides S2 2025
PDF
O7-L3 Supply Chain Operations - ICLT Program
PPTX
1st Inaugural Professorial Lecture held on 19th February 2020 (Governance and...
PPTX
IMMUNITY IMMUNITY refers to protection against infection, and the immune syst...
PPTX
Pharmacology of Heart Failure /Pharmacotherapy of CHF
PPTX
202450812 BayCHI UCSC-SV 20250812 v17.pptx
PPTX
school management -TNTEU- B.Ed., Semester II Unit 1.pptx
PDF
Microbial disease of the cardiovascular and lymphatic systems
PDF
Chapter 2 Heredity, Prenatal Development, and Birth.pdf
PPTX
Final Presentation General Medicine 03-08-2024.pptx
PDF
GENETICS IN BIOLOGY IN SECONDARY LEVEL FORM 3
PDF
Anesthesia in Laparoscopic Surgery in India
PDF
Classroom Observation Tools for Teachers
PPTX
Presentation on HIE in infants and its manifestations
PDF
The Lost Whites of Pakistan by Jahanzaib Mughal.pdf
PDF
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
PDF
grade 11-chemistry_fetena_net_5883.pdf teacher guide for all student
PPTX
Institutional Correction lecture only . . .
PPTX
Cell Types and Its function , kingdom of life
PPTX
PPT- ENG7_QUARTER1_LESSON1_WEEK1. IMAGERY -DESCRIPTIONS pptx.pptx
Module 4: Burden of Disease Tutorial Slides S2 2025
O7-L3 Supply Chain Operations - ICLT Program
1st Inaugural Professorial Lecture held on 19th February 2020 (Governance and...
IMMUNITY IMMUNITY refers to protection against infection, and the immune syst...
Pharmacology of Heart Failure /Pharmacotherapy of CHF
202450812 BayCHI UCSC-SV 20250812 v17.pptx
school management -TNTEU- B.Ed., Semester II Unit 1.pptx
Microbial disease of the cardiovascular and lymphatic systems
Chapter 2 Heredity, Prenatal Development, and Birth.pdf
Final Presentation General Medicine 03-08-2024.pptx
GENETICS IN BIOLOGY IN SECONDARY LEVEL FORM 3
Anesthesia in Laparoscopic Surgery in India
Classroom Observation Tools for Teachers
Presentation on HIE in infants and its manifestations
The Lost Whites of Pakistan by Jahanzaib Mughal.pdf
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
grade 11-chemistry_fetena_net_5883.pdf teacher guide for all student
Institutional Correction lecture only . . .
Cell Types and Its function , kingdom of life
PPT- ENG7_QUARTER1_LESSON1_WEEK1. IMAGERY -DESCRIPTIONS pptx.pptx

6 An Innovative Distributed Project Control

  • 1. -Super Lightweight Tank- A Risk Management Case Study in Mass Reduction AN INOVATIVE DISTRIBUTED PROJECT CONTROL APPROACH : A CASE STUDY OF THE CASSINI MIS Presented by Yulhendri Saputra & Marcel Bernadi
  • 2.  Introduction  Problem Issues  Environmental Scanning  Alternatives Course of Actions  Key Success Factors  Selection of Best Alternatives  Recommendation
  • 3. INTRODUCTION  Originally. Congress approved funding for a joint program composed of a Comet Rendezvous/Asteroid Flyby (CRAF) mission and the Cassini mission.  The program was authorized with the stipulation that it would be canceled if original cost estimates were exceeded.  In response, Jet Propulsion Laboratory (JPL) chose to implement a classical earned-value system for controlling schedule and cost.  In 1990, after purchasing a full-featured commercialoff-the-shelf (COTS) project management system, the project hired 20 schedulers and planners to implement a full) integrated network schedule.  The system was based on classic program evaluation and review technique (PERT) concepts (developed in 1958) and the Cost/Schedule Control System Criteria (C/SCSC) formalized by the U.S. Department of Defense in 1967.  A large expenditure was made for training at all project levels. By late 199 1 , CRAF/Cassini project managers observed somt: trends with the entire project control process: This refereed c a s e study article w a s accepted January 1996.
  • 4. ENVIRONMENTAL SCANNING  The COTS project management system process countered JPL's effort to having decision making shifted to lower levels in the organization.  Considering the large expenditure for project control, no corresponding improvement was made with regard to communication between the different project elements.  The COTS project management system was not viewed as an easy-to-use tool.  The COTS project management system did not provide a straightforward method for addressing uncertainty.
  • 5. PROBLEM ISSUES "Network-based techniques as planning tools do not consider the issue of uncertainty in identifying tasks and the relationship among tasks in the network" (Morad and Vorster, 1993).   "A network models only one set of schedule options at any given time" (Mathews, 1993). "The current approach to planning and controlling complex projects has traditionally been to eliminate mcertainty and change from our projects, or at ieast treat them as if change will not occur7' (Archibald and Lichtenburg, 1994). "Older packages emphasize the critical path method, which can be very clumsy when scheduling people. Classic approaches tend to be expensive and roo!ed in legacy technologies" (Wood, 1995). In short, the project found that the cleanliness of theory (PERT, CISCSC) was no match for the clutter of reality.
  • 6. ALTERNATIVE COURSE OF ACTION 1. CPM and PERT Network-based techniques as planning tools do not consider the issue of uncertainty in identifying tasks and the relationship among tasks in the network"   Eliminate uncertainty and change from our projects, or treat them as if no change Older packages emphasize the critical path method, which can be very clumsy. In short, the project found that the cleanliness of theory was no match for the clutter of reality. 2. CMlS • All project products have to be someone's deliverable (Del) and another's receivable • Once a deliverer and receiver reach an agreement on the need t • Each Reciving and Delivery agreement • Any person on the project is able to determine a Rec/Dells status at any given time
  • 7. KEY SUCCES FACTOR The value of this approach became immediately apparent: I. The CMIS schedule control module facilitated and increased communication. It also highlighted where communication between project elements was deficient. Product specification and delivery schedule disputes were easily identified, problems were quickly addressed. and schedule confusion vanished. 2. Schedule tracking and statusing became virtually effortless. The project implemented an automated statusing system that polled receivers on a weekly basis about whether they had received their agreed-to deliveries for that week. Receiver responses to the messages were automatically compiled and summarized in weekly metric reports to management. In addition, on-line statusing within CMIS was provided. 3. The single-database design allowed current project-level schedule reports to be generated at any time. 4. CMIS reduced centralized project control costs to less than 0.25% of the total project budget. The workforce of planners/schedulers dropped from 20 people to an operations staff of 3 . This yielded a savings of greater than 60 work- years over the project's development phase.
  • 8. SELECTION OF BEST ALTERNATIVES CMIS Schedule Control Module Planning Reports and Metrics. •Before CMIS implementation, many seasoned managers expected that the simple level of formality (that is, requiring technical managers to input only the product's name, source, destination, and delivery date) would not be beneficial. This perception changed dramatically when only 3 of the initial 1,200 products submitted to the CMIS database had matching receiver and deliverer information. Moreover, technical managers quickly recognized that CMIS allowed them to formalize their external delivery commitments without limiting their ability to modify their internal schedules to best meet their delivery commitments. •The reconciliation process found holes in the plan where needed products were not being supplied or were being supplied but not needed. The process also uncovered many occurrences of product delivery dates that were much later than those needed by receivers. •CMIS provides metrics for tracking the level of reconciliation at the project. system. and subsystem levels. • RecIDel metrics are reviewed weekly by the project manager and his staff. Lack of a reconciled plan immediately draws management attention.
  • 9. Recommendation • For large research and development projects, effective cost and schedule control is possible without incurring the large costs associated with centralized project control systems. • An effective cost/schedule management information system for all levels of management can be built by focusing on satisfying the requirements of first-line managers and lead engineers. Such an approach removes the inherent noise in management reports created by planning and control staffs. • An effective way to deal with schedule uncertainty is to simplify the project control approach to focus on the areas where schedule uncertainty has the greatest impacts (that is, the interfaces between receivers and deliverers).
  • 10. Thank you Ref : Tuman, John, "It's Time to Re-engineer Project Management." PM Network, 7: 1 (January 1993), pp. 40-4 1 . Morad, Ayman A., and Michael C. Vorster, "Network-based Versus A 1-Based Techniques in Project Planning." Project Management Journal, 24: 1 (March 1993), p. 25. Mathews, Mark D., "Introducing Networks to an In-Progress Project." Project Management Journal, 24:2 (June 1993), p. 9. Archibald, Russell D., and Lichtenburg Steen, "Uncertainty and Change Require a New Management Model." PAM NETwork, 7:5 (May 1994), pp. 6-10. Wood, Lamont, "Project Management Perfect Harmony.“ nformation Week,No. 526 (May 8, 1995), pp. 42-54.
  • 11. Thank you 1.Please elaborate the different between PERT project evaluation review technique VS CPM critical path method ,CMIS contstruction management information system ? 2.What are the benefit and disadvantages of using PERT/CPM/CMIS ?