SlideShare a Scribd company logo
2
Most read
3
Most read
DOC NO 
V 
DATE 
PAGE NO 
03 OF 05 
PROJECT 
TITLE 
JOB PROCEDURE FOR HYDRO TEST / WATER FILL 
UP TEST 
JOB PROCEDURE FOR HYDROTEST/WATER FILLUP TEST 
1. SCOPE 
This test procedure shall be carried out to detect the leak in shell weld joints and to 
observe the load stabilization of liquid in interval level height. 
2. PURPOSE 
The purpose of this procedure is providing the guideline and sequential steps for the 
hydro test / water fill up test for the tank. 
3. CHECK LIST 
 After completion of the erection, welding and NDT the following points shall be 
checked before testing. 
 All the mechanical activities completion in respect of the drawing and HPCL 
Specification and code requirements. 
 Radiography completion including repairs. 
 The entire NDT test like chalk-diesel test, LPT, RF .Pad pneumatic test, vacuum box 
test completion. 
 Finally mechanical clearance from the Engineer-In-Charge shall be taken before 
Hydrotest in approved format 
4. TEST MEDIA 
Test media shall be in iron free water, which is clean and free of silt i.e.; Portable 
water 
5. PROCEDURE 
 Proper arrangement shall be carried out for the water filling (pipe connection from 
the water resource point and providing valves and NRV wherever required. 
 markers shall be provided on the shell, 500 mm from the bottom to check tank 
settlement. Size shall be 50 X 50 X 6mm angle and 100 mm long. The nos. of 
setting marker shall be minimum 8 Nos or as per the approved Drg. 
 Code : API 650 (7.3.6) Eleven Edition 
Prepared by 
CONTRACTOR . 
Concurred by 
Name : 
Design: 
Hindustan Petroleum Crop. Ltd. 
Approved by 
Name : 
Design: 
Hindustan Petroleum Crop. Ltd
DOC NO 
VS 
DATE 
PAGE NO 
04 OF 05 
PROJECT 
TITLE 
JOB PROCEDURE FOR HYDRO TEST / WATER FILL 
UP TEST 
 Settling markers shall be provided at every 300 outside the tank at a height of 500 
mm from the top of annular plate. 
 Setting marker shall be welded and initial level reading shall be taken with respect 
to the permanent benchmark using dumpy level / Total station 
 Shell settlement measurements shall be made after tank erection, prior to 
hydrotesting and during water filling at 1000 mm intervals up to maximum filling 
height of tank. 
 The levels taken before water filling called as initial level of the tank and shall be 
record in an approved format. 
 The water filling height shall be restricted to the max. Liquid Level or up to the 
curb angle. 
 The water filling shall be carried out in four stages (25%, 50%, 75%  100% of the 
max liquid level of the tank) 
 Any leaks observed in the shell joint during the hydro test shall be noted and 
repaired with the water level min. of 300mm below the leak spot. 
 The repaired shall be carried out as per the procedure and tank test shall be 
recommenced. 
 After each stage of filling, a load stabilization period shall be observed as 
minimum 24 hours max between each stage of filling. 
 During the stabilization period the settlement reading shall be observed and 
recorded jointly with HPCL Engineer-In-Charge through dumpy level only. 
 Filling rate shall be not exceed 5 meters per day. 
 After completion of the water filling the water load shall be maintained for 24 
hours. After 24 hours the final settlement reading shall be recorded jointly with 
engineer-In-Charge. 
 Tank shall be emptied at a maximum water level variation rate of 5 meters per 
day. Care shall be taken that top manholes are open during empty operation of 
conical roof tanks. 
 If salt water is used then corrosion inhibitor should be sprayed (mixed) prior to 
filling / after hydro test the tank should be thoroughly cleaned with sweat water. 
Prepared by 
CONTRACTOR . 
Concurred by 
Name : 
Design: 
Hindustan Petroleum Crop. Ltd. 
Approved by 
Name : 
Design: 
Hindustan Petroleum Crop. Ltd
DOC NO 
DATE 
PAGE NO 
05 OF 05 
PROJECT 
TITLE 
JOB PROCEDURE FOR HYDRO TEST / WATER FILL 
UP TEST 
6. CLEANING 
After draining the water the tank shall be thoroughly cleaned, free from dirt and 
foreign materials and shall be dried by air. 
7. RECORDS 
Records shall be prepared and submitted to Engineer in-charge for approval. 
8. SAFETY 
All Safety precaution shall be taken during water fill up test. 
9. REFRENCE 
(A) API 650 
(B) OISD 129 
(C) PO Tech Specification 
Note : Permanent B M shall be min. 50Mtr away from Tank shell 
Prepared by 
CONTRACTOR . 
Concurred by 
Name : 
Design: 
Hindustan Petroleum Crop. Ltd. 
Approved by 
Name : 
Design: 
Hindustan Petroleum Crop. Ltd

More Related Content

PPTX
WATER & WASTE WATER ENGINEERING - water treatment process & units
PDF
Presentation on SECVIII
PPS
Mechanical Completions
PPTX
Product management
PDF
Twi cswip welding inspection notes and questions
PPTX
Construction contract
PDF
ASME B31.3 2022 Procces piping code for b31.3
PPTX
Market Segmentation
WATER & WASTE WATER ENGINEERING - water treatment process & units
Presentation on SECVIII
Mechanical Completions
Product management
Twi cswip welding inspection notes and questions
Construction contract
ASME B31.3 2022 Procces piping code for b31.3
Market Segmentation

What's hot (20)

PDF
Aramco inspection handbook
PDF
Piping sample report
PDF
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
PPTX
what is process piping
PPTX
TANK presentation-2.pptx
PDF
Qc piping guide
PPT
143137557 storage-tanks
PDF
Piping interview
PDF
Asme b31.3 interpretation
DOCX
Hydrotest REPORT FOR 4'' 158m Line.
PPT
fundamentals of Piping engineering
PPT
Asme b31,pressure piping code
PPTX
Introduction to piping design
PPT
Floating head heat exchanger - Maintainance
PDF
How to Qualify a Welding Procedure
PDF
Piping handbook
PPT
Pressure vessel types
PDF
Asme b31.3 process_piping
PPT
Engineering & Design of Pipe Supports
Aramco inspection handbook
Piping sample report
Piping Training course-How to be an Expert in Pipe & Fittings for Oil & Gas c...
what is process piping
TANK presentation-2.pptx
Qc piping guide
143137557 storage-tanks
Piping interview
Asme b31.3 interpretation
Hydrotest REPORT FOR 4'' 158m Line.
fundamentals of Piping engineering
Asme b31,pressure piping code
Introduction to piping design
Floating head heat exchanger - Maintainance
How to Qualify a Welding Procedure
Piping handbook
Pressure vessel types
Asme b31.3 process_piping
Engineering & Design of Pipe Supports
Ad

Viewers also liked (16)

PPT
Hydrotest
DOCX
HYDROSTATIC TESTING
PDF
20 Essential Hydrotest Safety Checklist
PDF
Pipe Hydrotest , Inspection, Visual and Dimensional Inspection & Marking
PPTX
Hydro test pump
PPTX
What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure
PPTX
Valves presentation
PDF
Use of nitrogen purge in flare and vent systems
PDF
Valves for hydro power applications
PPTX
Stainless steel tanks
PPTX
Manual Gate Valve Kick-off Meeting (brand : VELAN)
PDF
Welding of pipelines
PPS
Introduction_to_NDT
PPT
Asme sec viii div 2
PPT
Welded steel tanks for storage oil
Hydrotest
HYDROSTATIC TESTING
20 Essential Hydrotest Safety Checklist
Pipe Hydrotest , Inspection, Visual and Dimensional Inspection & Marking
Hydro test pump
What is MAWP? Difference between MAWP , Design Pressure and Operating Pressure
Valves presentation
Use of nitrogen purge in flare and vent systems
Valves for hydro power applications
Stainless steel tanks
Manual Gate Valve Kick-off Meeting (brand : VELAN)
Welding of pipelines
Introduction_to_NDT
Asme sec viii div 2
Welded steel tanks for storage oil
Ad

Similar to 7) hydro test 3 (20)

PPTX
452010057-Piping-Inspection-MT-PPT-pptx.pptx
PPTX
343312365 mt-ppt
PPT
171839416-commissioning-of-hydro-ppt.ppt
DOCX
Method statement tank base concrete pouring
PDF
Flushing cleaning procedure
PDF
468288879-completion-design-apparatus tag
PPTX
hydrostatic rest for open and covered tanks.pptx
PPTX
Horizontal Liner y los retos del trabajo
PPT
Hazard operability study - in Industires and plant
PPT
HAZOP.ppt
PPT
Oil & Gas Production theory cocnepts.ppt
PPT
lpg@12 bulk loading unloading opreration
PPTX
Presentation chapter 5
PPTX
Presentation chapter 5
PDF
Husam CV updated (1)
PPSX
Depleted oil fields regeneration with water shutoff - euco group
PPSX
DEPLETED OIL FIELDS - Regeneration with Water_Shutoff - EUCO Group
PDF
26-grover-john-final
PDF
Operation & maintenance 2011
PDF
NDL FUEL STATION OPERATION
452010057-Piping-Inspection-MT-PPT-pptx.pptx
343312365 mt-ppt
171839416-commissioning-of-hydro-ppt.ppt
Method statement tank base concrete pouring
Flushing cleaning procedure
468288879-completion-design-apparatus tag
hydrostatic rest for open and covered tanks.pptx
Horizontal Liner y los retos del trabajo
Hazard operability study - in Industires and plant
HAZOP.ppt
Oil & Gas Production theory cocnepts.ppt
lpg@12 bulk loading unloading opreration
Presentation chapter 5
Presentation chapter 5
Husam CV updated (1)
Depleted oil fields regeneration with water shutoff - euco group
DEPLETED OIL FIELDS - Regeneration with Water_Shutoff - EUCO Group
26-grover-john-final
Operation & maintenance 2011
NDL FUEL STATION OPERATION

Recently uploaded (20)

PDF
Artificial Superintelligence (ASI) Alliance Vision Paper.pdf
PDF
Human-AI Collaboration: Balancing Agentic AI and Autonomy in Hybrid Systems
PDF
Automation-in-Manufacturing-Chapter-Introduction.pdf
PPT
introduction to datamining and warehousing
PDF
Categorization of Factors Affecting Classification Algorithms Selection
PDF
PREDICTION OF DIABETES FROM ELECTRONIC HEALTH RECORDS
PPTX
Current and future trends in Computer Vision.pptx
PPTX
Fundamentals of safety and accident prevention -final (1).pptx
PPTX
Artificial Intelligence
PDF
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
PPT
INTRODUCTION -Data Warehousing and Mining-M.Tech- VTU.ppt
PDF
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
PPTX
6ME3A-Unit-II-Sensors and Actuators_Handouts.pptx
PDF
86236642-Electric-Loco-Shed.pdf jfkduklg
PDF
Level 2 – IBM Data and AI Fundamentals (1)_v1.1.PDF
PDF
Abrasive, erosive and cavitation wear.pdf
PPT
Introduction, IoT Design Methodology, Case Study on IoT System for Weather Mo...
PPTX
introduction to high performance computing
PDF
BIO-INSPIRED ARCHITECTURE FOR PARSIMONIOUS CONVERSATIONAL INTELLIGENCE : THE ...
PPT
Occupational Health and Safety Management System
Artificial Superintelligence (ASI) Alliance Vision Paper.pdf
Human-AI Collaboration: Balancing Agentic AI and Autonomy in Hybrid Systems
Automation-in-Manufacturing-Chapter-Introduction.pdf
introduction to datamining and warehousing
Categorization of Factors Affecting Classification Algorithms Selection
PREDICTION OF DIABETES FROM ELECTRONIC HEALTH RECORDS
Current and future trends in Computer Vision.pptx
Fundamentals of safety and accident prevention -final (1).pptx
Artificial Intelligence
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
INTRODUCTION -Data Warehousing and Mining-M.Tech- VTU.ppt
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
6ME3A-Unit-II-Sensors and Actuators_Handouts.pptx
86236642-Electric-Loco-Shed.pdf jfkduklg
Level 2 – IBM Data and AI Fundamentals (1)_v1.1.PDF
Abrasive, erosive and cavitation wear.pdf
Introduction, IoT Design Methodology, Case Study on IoT System for Weather Mo...
introduction to high performance computing
BIO-INSPIRED ARCHITECTURE FOR PARSIMONIOUS CONVERSATIONAL INTELLIGENCE : THE ...
Occupational Health and Safety Management System

7) hydro test 3

  • 1. DOC NO V DATE PAGE NO 03 OF 05 PROJECT TITLE JOB PROCEDURE FOR HYDRO TEST / WATER FILL UP TEST JOB PROCEDURE FOR HYDROTEST/WATER FILLUP TEST 1. SCOPE This test procedure shall be carried out to detect the leak in shell weld joints and to observe the load stabilization of liquid in interval level height. 2. PURPOSE The purpose of this procedure is providing the guideline and sequential steps for the hydro test / water fill up test for the tank. 3. CHECK LIST After completion of the erection, welding and NDT the following points shall be checked before testing. All the mechanical activities completion in respect of the drawing and HPCL Specification and code requirements. Radiography completion including repairs. The entire NDT test like chalk-diesel test, LPT, RF .Pad pneumatic test, vacuum box test completion. Finally mechanical clearance from the Engineer-In-Charge shall be taken before Hydrotest in approved format 4. TEST MEDIA Test media shall be in iron free water, which is clean and free of silt i.e.; Portable water 5. PROCEDURE Proper arrangement shall be carried out for the water filling (pipe connection from the water resource point and providing valves and NRV wherever required. markers shall be provided on the shell, 500 mm from the bottom to check tank settlement. Size shall be 50 X 50 X 6mm angle and 100 mm long. The nos. of setting marker shall be minimum 8 Nos or as per the approved Drg. Code : API 650 (7.3.6) Eleven Edition Prepared by CONTRACTOR . Concurred by Name : Design: Hindustan Petroleum Crop. Ltd. Approved by Name : Design: Hindustan Petroleum Crop. Ltd
  • 2. DOC NO VS DATE PAGE NO 04 OF 05 PROJECT TITLE JOB PROCEDURE FOR HYDRO TEST / WATER FILL UP TEST Settling markers shall be provided at every 300 outside the tank at a height of 500 mm from the top of annular plate. Setting marker shall be welded and initial level reading shall be taken with respect to the permanent benchmark using dumpy level / Total station Shell settlement measurements shall be made after tank erection, prior to hydrotesting and during water filling at 1000 mm intervals up to maximum filling height of tank. The levels taken before water filling called as initial level of the tank and shall be record in an approved format. The water filling height shall be restricted to the max. Liquid Level or up to the curb angle. The water filling shall be carried out in four stages (25%, 50%, 75% 100% of the max liquid level of the tank) Any leaks observed in the shell joint during the hydro test shall be noted and repaired with the water level min. of 300mm below the leak spot. The repaired shall be carried out as per the procedure and tank test shall be recommenced. After each stage of filling, a load stabilization period shall be observed as minimum 24 hours max between each stage of filling. During the stabilization period the settlement reading shall be observed and recorded jointly with HPCL Engineer-In-Charge through dumpy level only. Filling rate shall be not exceed 5 meters per day. After completion of the water filling the water load shall be maintained for 24 hours. After 24 hours the final settlement reading shall be recorded jointly with engineer-In-Charge. Tank shall be emptied at a maximum water level variation rate of 5 meters per day. Care shall be taken that top manholes are open during empty operation of conical roof tanks. If salt water is used then corrosion inhibitor should be sprayed (mixed) prior to filling / after hydro test the tank should be thoroughly cleaned with sweat water. Prepared by CONTRACTOR . Concurred by Name : Design: Hindustan Petroleum Crop. Ltd. Approved by Name : Design: Hindustan Petroleum Crop. Ltd
  • 3. DOC NO DATE PAGE NO 05 OF 05 PROJECT TITLE JOB PROCEDURE FOR HYDRO TEST / WATER FILL UP TEST 6. CLEANING After draining the water the tank shall be thoroughly cleaned, free from dirt and foreign materials and shall be dried by air. 7. RECORDS Records shall be prepared and submitted to Engineer in-charge for approval. 8. SAFETY All Safety precaution shall be taken during water fill up test. 9. REFRENCE (A) API 650 (B) OISD 129 (C) PO Tech Specification Note : Permanent B M shall be min. 50Mtr away from Tank shell Prepared by CONTRACTOR . Concurred by Name : Design: Hindustan Petroleum Crop. Ltd. Approved by Name : Design: Hindustan Petroleum Crop. Ltd