A Quality Public Transport System, Elements for Consideration
SATC Conference 2016
7 July 2016
Safiyyah Aboo – Aurecon
EJ Robertson – EJ Robertson Consultants
Aim and Scope
• Provide a high level introduction to certain elements in IPTN development
• More detailed experience on certain elements in the development of the GIPTN
• Development Process
• The Network
• Industry Engagements
• Infrastructure Light Approach
• Bus supply dilemma
• Not covered is
• Institutional arrangements
• Role of consultants/advisors
• GIPTN Management and Operations
• Capacity Building - overall
Project History
• Commenced in 2003 as the Sandkraal Road Corridor Mobility Strategy
• Converted to George Integrated Public Transport Network or known to the public
as the GO GEORGE System
• ‘Flagship’ or pilot project
• Project was initiated by the Province of the Western Cape (DTPW), partnered with
George Municipality through and IGA and FA – in terms of Section 12 of the NLTA
• Engagement with existing local taxi and bus operators commenced in 2007 with
the aim of establishing them into a private company, and
• Awarding them a 12 year negotiated bus contract as per the Section 41 of the NLTA
Concept&Strategy
Started in 2005
Project Scoping
Travel surveys
conducted
MBT studies
Economic
Assessments
conducted for
George
Engagement
Engagement
with the Taxi
Industry
Public
Consultation
Planning
Operational
Planning:
Infrastructure,
systems &
technology
Institutional
Assessment
Establishment
Formalisation of
operator
company
Signing the
IGA between
DTPW & MoG
Developed
institutional
arrangements
Engage in
detailed
negotiations
with industry
Implementation
Operator
Contract signed
in November
2014
Services
commences on 8
December 2014
Phases 1-3 have
rolled out
2005 2006/7 – 2009/10
Introduction
of the NLTA 2011-2013 2014-2016
Development Process
The Network
System Design
System Roll-out Phases
• Includes both the urban and rural areas of
George Municipality
• Services are operational in Rosemoor,
Loerie Park, Denneoord, Blanco,
Pacaltsdorp and the CBD
• Remaining areas are to be implemented in
late 2016 and 2017
Salient Features of the System
• Routes
• Main
• Community or feeder type
• Intersuburb – linking rural settlements
• Intertown - services between George and neighbouring towns (planned)
• Demand responsive service for rural communities (planned)
• Present sedan taxi operators converted to metered taxi to compliment the service (planned)
• Minimum policy level of service
• Spatial and temporal coverage
• Operating hours of service – 14-18 hours, 7 days a week
• Walking distances – 400m to 600m to most of the urban population of George
• Mixed Fleet
• Selection of appropriate vehicle for the respective demand level, mix of urban and rural
environment, mixed topography
Design Philosophy and Intended Benefits
• Understanding that virtually all formal PT operations require some form of
government subsidy
• ‘user pay’ principle is unrealistic
• given the high portion of poor and unemployed persons
• amplifies by apartheid legacy
• Any IPTN must be established and maintained in manner that will minimise the
financial burden on both user and government
• Should provide the urban poor with less costly access to employment to reduce
the household disposable income spent on transport
• GIPTN
• Fare and policy structure based on user affordability criteria – linked to the
minimum gazetted labour rate for the urban domestic worker
• Not linked to operations cost recovery model
Design Philosophy and Intended Benefits
Public
Contracting
Authority
Vehicle
Operating
Company
QualityCharter
RespondingtoUserNeeds
PassengerCharter
DeliveredServices
Contract
Operating Obligations
• Quality triangle
• Governments role in consulting with and
providing the public with public transport
services
• Government contracts a service provider to
provide the service
• Government then makes the decision as to
the quality of service provided
• Once the quality of service is set and
maintained at an appropriate quality level
• Encourage car owners to use the PT system
• Introduction of car use restraints as a future
consideration
• TDM measures
Replicating MBT operations
• Fallacy in the belief that IPTN operations should in some way replicate the
replaced MBT and bus operations– reality is that it will be inefficient and
ultimately non-sustainable
• IPTN demand profile must draw on a wide range of sources to ensure adequate
capacity provision including CPTR, census, household surveys, on the ground
surveys etc
• Shift to a structured network presents specific challenges since the negotiating
status of the existing taxi industry and their advisors will change
• GIPTN
• Strongly association linked – 3 associations
• Single bus operating contract – initially prior to NLTA, Province would be the
Contracting Authority, however GIPTN now functions under Section 12 of the NLTA
for joint controls - GM and DTPW (WC)
• Removal of racial bias or competition between associations
• After the 12 year contract, can be split up into more than one contract
Scheduled Bus System
• Acceptance that it is not a MBT system
• Passengers will be expected to stand on buses during peak demands
• Transfers between routes to complete a desired trip
• Mixed fleet in an operation
• If a safe, reliable, accessible service where timetables are integrated and adhered
to, passengers will learn to trust and adapt to the system
• System is required to be continuously monitored and evaluated to minimise
operational costs
Industry Engagements
• Commenced in 2007, with the 3 associations and local bus operator
• MOA – prior to formal negotiation process
• Under the NLTTA this negotiation was not possible, but the introduction of the
NLTA, under Section 41 allowed for this
• Formal negotiation process
• Operator Contract
• Bus fleet ownership
• Compensation Model – relinquishment of operating licenses
• MBT industry can be persuaded to convert from the informal to the informal
operations
• Benefits include secure employment, fixed working hours, pension fund, etc
Operating License Holders and Affected
Persons
• NLTA indicated negotiations can only be with persons holding valid operating
licenses
• establishing valid OLs through the Provincial Regulating Entity records took
considerable time, with a number of engagement and appeals process
• GIPTN
• operators with local George based OL’s.
• Long distance and chartered OLs could remain
• All operators and affected persons were requested to register their interest to
keep informed of the process
• Registration process was run a few times, given the stop start nature of the project
• List started at 400 people but now has risen to 1300 people
• Managing the process and expectations remain a challenge
Infrastructure Light Approach
• GIPTN
• Conventional bus system, using existing
road network , attractive as there is no
demand for priority operations
• Provision of minimal up front
infrastructure
• 4 stage infrastructure approach
• Bus Depot, Minimal starter stops,
upgrading of roads and provision of bus
turning facilities
• Advantages – minimised abortive and
wasteful expenditure
• Disadvantages –
• necessary to play catch up once the
services become operational
• Passengers disadvantaged by limited
supply of bus shelters and other facilities
• Significant impact of existing road
network
Bus Supply Dilemma
• Universal Access
• Accommodate passengers with special
categories of need through universal design
• Provision of universally accessible vehicles
• Condition of PTNG grant
• Current bus market
• Limited supply of suitable mini, midi and
conventional low floor or low entry buses
• GIPTN
• Mixed fleet
• Developed accessible minibus with a wheel
chair hoist, Midi buses are shortened
conventional bus (10.5m) – too wide for
certain roadways
• Wider range of universally accessible
buses to cater for different demand
environments, especially in non- metro
areas
Conclusions and Recommendations
• GIPTN – flagship project for non-metro areas
• Project has demonstrated that
• MBT operators and bus operators can be encouraged to participate, and take up the
challenge if they are supported and there is measure of compensation
• Provision of the service should focus on user needs and if so, will be utilised
• Fare policy and structure must reduce share of household expenditure on transport
• System must be accessible from a spatial, cost and time and must be seen as safe
• Operating costs can be minimised though effective use of a mixed fleet and service
delivery matched to passenger temporal demand
• Target must be Quality Public Transport service delivery
A quality Public Transport System, elements for consideration

More Related Content

PPT
5 route network rs final
PPT
Securing modal shift to bus FINAL - Nick Phillips, Borough of Poole
PDF
LA City Planning Commission Parking Workshop
PPTX
Brett herron
PPT
3 industry reform rtm final
PPTX
Estimating residential public transport trip generation rates
PDF
Community Networks: Kenya Telecoop Project Concept
PPTX
Dachs itssa march 2012 pp ps financing transport infrastructure
5 route network rs final
Securing modal shift to bus FINAL - Nick Phillips, Borough of Poole
LA City Planning Commission Parking Workshop
Brett herron
3 industry reform rtm final
Estimating residential public transport trip generation rates
Community Networks: Kenya Telecoop Project Concept
Dachs itssa march 2012 pp ps financing transport infrastructure

What's hot (20)

PPTX
2040 RTP Leadership Symposium II 3.13.13
PPTX
City Bus Service Modernisation "BusKaroPlus" - Anjum Parwez, IAS
PDF
First – Last Mile_MBPJ_2015
PDF
Singapore MRT
PPTX
Access to Opportunities Event Presentation
PDF
John Howe - Metrolinx - Smart Transportation: Strategic Approaches
PPTX
Geraldo Abranches
PPTX
Bhubaneswar E-Mobility Plan
PPTX
Eetp 170900713008 2721307_bhavya
PPT
Richard Williams - state aid presentation inca
PDF
mpo fiscal priorities committee - ptp then and now
PDF
Fbe Transport presentation
PPTX
Rmtsp 2721303 170900713008_bhavya
PDF
Assessing impact of metro stations integrating commercial landuse & trans...
PDF
Public Private Partnership in Railways - A New Approach_IMR March 2008
PPTX
Electromagnetic Frequency Spectrum Presentation
PPTX
Ppp case study in nigeria second niger bridge (world bank ppp mooc final pr...
PDF
Managing Systems Development Term Paper Leap integrated ticketing system
PDF
PlaceEXPO: City Region Investment Strategies: High Speed 2
DOCX
Anne James CV 1117 - full
2040 RTP Leadership Symposium II 3.13.13
City Bus Service Modernisation "BusKaroPlus" - Anjum Parwez, IAS
First – Last Mile_MBPJ_2015
Singapore MRT
Access to Opportunities Event Presentation
John Howe - Metrolinx - Smart Transportation: Strategic Approaches
Geraldo Abranches
Bhubaneswar E-Mobility Plan
Eetp 170900713008 2721307_bhavya
Richard Williams - state aid presentation inca
mpo fiscal priorities committee - ptp then and now
Fbe Transport presentation
Rmtsp 2721303 170900713008_bhavya
Assessing impact of metro stations integrating commercial landuse & trans...
Public Private Partnership in Railways - A New Approach_IMR March 2008
Electromagnetic Frequency Spectrum Presentation
Ppp case study in nigeria second niger bridge (world bank ppp mooc final pr...
Managing Systems Development Term Paper Leap integrated ticketing system
PlaceEXPO: City Region Investment Strategies: High Speed 2
Anne James CV 1117 - full
Ad

Similar to A quality Public Transport System, elements for consideration (20)

PDF
RTPI 2013 David Hytch
PPTX
Moving from Bus Rapid Transit to Integrated Public Transport
PDF
Crowd Conscious Internet of Things Enabled Smart Bus Navigation System
PPT
Building a Better Metro: Possibilities for BRT
PDF
The Design of a Simulation for the Modeling and Analysis of Public Transporta...
PDF
LS3: Implementing bus reform - Institutional dimensions
PPT
Improving transport in Malta using GIS and LBS
PDF
2013 RMIT Guest Lecture in Integrated Transport Accessibility: GIS Tools for ...
PPTX
Public Vs Private Transportation Systems
PPT
Public Transit 101 - Making Transit the Better Way
PPTX
Workshop Innovation in Africa - Manifesto for BRT Lite
PDF
Road Based Public Transport V1
PDF
Mountain View AGT
PPT
Transit Operations - The Basics
PPTX
Re engineering process of sri lankan national transport service
PDF
Urban Data Challenge - Christopher A. Pangilinan
PPTX
Public Transport Policy in Singapore (a long view)
PPTX
transitFinal
PDF
Smart integrated public transport network for the smart city
PDF
Peter Albert - City & County of San Francisco - The Connected Bus Project
RTPI 2013 David Hytch
Moving from Bus Rapid Transit to Integrated Public Transport
Crowd Conscious Internet of Things Enabled Smart Bus Navigation System
Building a Better Metro: Possibilities for BRT
The Design of a Simulation for the Modeling and Analysis of Public Transporta...
LS3: Implementing bus reform - Institutional dimensions
Improving transport in Malta using GIS and LBS
2013 RMIT Guest Lecture in Integrated Transport Accessibility: GIS Tools for ...
Public Vs Private Transportation Systems
Public Transit 101 - Making Transit the Better Way
Workshop Innovation in Africa - Manifesto for BRT Lite
Road Based Public Transport V1
Mountain View AGT
Transit Operations - The Basics
Re engineering process of sri lankan national transport service
Urban Data Challenge - Christopher A. Pangilinan
Public Transport Policy in Singapore (a long view)
transitFinal
Smart integrated public transport network for the smart city
Peter Albert - City & County of San Francisco - The Connected Bus Project
Ad

More from https://logisticscompanies.co.za (20)

PDF
Business Fleet Africa Magazine: March 2025.pdf
PDF
RTMS Case Study Mining - New Era Commerce - 12 February 2025.pdf
PPSX
RTMS Case Study Mining - Mr Duhan du Plessis - 12 February 2025.ppsx
PDF
RTMS Case Study - Measurement and Compliance - Mr Oliver Naidoo - 12 February...
PDF
PBS-Smart Truck pilot project - Dr Paul Nordengen - 12 February 2025.pdf
PDF
NLCC and BUSA Feedback - Mr Ian Bird - 12 February 2025.pdf
PDF
INControl RTMS Road Safety Reports - Ms Antoinette van Graan - 12 February 20...
PDF
Economic Challenges in the Mining Sector and the Role of RTMS - Insights by C...
PDF
ATT: South Africa's Leading Tyre Solutions Provider - Comprehensive Profile 2025
PDF
CCBSA RTMS Case Study 2025: Advancing Road Safety and Smart Trucking in South...
PDF
AFRIT: Africa's Leading Trailer Manufacturing & Solutions - Complete Product ...
PDF
AMS: Comprehensive Mining Solutions Provider - Tyres, Rims, and Services Over...
PDF
AfCFTA-anchored Pharmaceutical Initiative: Building Africa's Healthcare Resil...
PDF
Data Meets Culture: Understanding South African Trade Flows Through a Cultura...
PDF
Digital Transformation Success: Leveraging Lean to Beat the 70% Failure Rate
PDF
Legal Liability in Customs Clearing: A Comprehensive Guide for Clearing Agents
PDF
Advancing Logistics Management in South Africa: A Strategic Framework for Mod...
PDF
Warehouse Rescue 911: Crisis Management & Recovery for Distribution Centres
PDF
Innovation Approaches to Mitigating Human Factors in Road Transport - Ms Lera...
PDF
Daimler Trucks and the Drive to move the Heavy Truck Industry Sustainably for...
Business Fleet Africa Magazine: March 2025.pdf
RTMS Case Study Mining - New Era Commerce - 12 February 2025.pdf
RTMS Case Study Mining - Mr Duhan du Plessis - 12 February 2025.ppsx
RTMS Case Study - Measurement and Compliance - Mr Oliver Naidoo - 12 February...
PBS-Smart Truck pilot project - Dr Paul Nordengen - 12 February 2025.pdf
NLCC and BUSA Feedback - Mr Ian Bird - 12 February 2025.pdf
INControl RTMS Road Safety Reports - Ms Antoinette van Graan - 12 February 20...
Economic Challenges in the Mining Sector and the Role of RTMS - Insights by C...
ATT: South Africa's Leading Tyre Solutions Provider - Comprehensive Profile 2025
CCBSA RTMS Case Study 2025: Advancing Road Safety and Smart Trucking in South...
AFRIT: Africa's Leading Trailer Manufacturing & Solutions - Complete Product ...
AMS: Comprehensive Mining Solutions Provider - Tyres, Rims, and Services Over...
AfCFTA-anchored Pharmaceutical Initiative: Building Africa's Healthcare Resil...
Data Meets Culture: Understanding South African Trade Flows Through a Cultura...
Digital Transformation Success: Leveraging Lean to Beat the 70% Failure Rate
Legal Liability in Customs Clearing: A Comprehensive Guide for Clearing Agents
Advancing Logistics Management in South Africa: A Strategic Framework for Mod...
Warehouse Rescue 911: Crisis Management & Recovery for Distribution Centres
Innovation Approaches to Mitigating Human Factors in Road Transport - Ms Lera...
Daimler Trucks and the Drive to move the Heavy Truck Industry Sustainably for...

Recently uploaded (20)

PPTX
368455847-Relibility RJS-Relibility-PPT-1.pptx
PPTX
building_blocks.pptxdcsDVabdbzfbtydtyyjtj67
PPTX
Zeem: Transition Your Fleet, Seamlessly by Margaret Boelter
PDF
EC290C NL EC290CNL - Volvo Service Repair Manual.pdf
PPTX
internal combustion engine renewable new
PDF
GMPL auto injector molding toollllllllllllllll
PPTX
Intro to ISO 9001 2015.pptx for awareness
PDF
Volvo ec17c specs Service Manual Download
PDF
Honda Dealership SNS Evaluation pdf/ppts
PPTX
Lecture 3b C Library xnxjxjxjxkx_ ESP32.pptx
PDF
6. Chapter Twenty_Managing Mass Communications Advertising Sales Promotions E...
PPTX
description of motor equipments and its process.pptx
PDF
Volvo EC290C NL EC290CNL Excavator Service Repair Manual Instant Download.pdf
PPT
ACCOMPLISHMENT REPOERTS AND FILE OF GRADE 12 2021.ppt
PDF
Volvo EC20C Excavator Step-by-step Maintenance Instructions pdf
PPTX
deforestation.ppt[1]bestpptondeforestation.pptx
PPTX
Independence_Day_Patriotic theme (1).pptx
PDF
Volvo EC20C Excavator Service maintenance schedules.pdf
PDF
Marketing project 2024 for marketing students
PDF
Journal Meraj.pdfuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuu
368455847-Relibility RJS-Relibility-PPT-1.pptx
building_blocks.pptxdcsDVabdbzfbtydtyyjtj67
Zeem: Transition Your Fleet, Seamlessly by Margaret Boelter
EC290C NL EC290CNL - Volvo Service Repair Manual.pdf
internal combustion engine renewable new
GMPL auto injector molding toollllllllllllllll
Intro to ISO 9001 2015.pptx for awareness
Volvo ec17c specs Service Manual Download
Honda Dealership SNS Evaluation pdf/ppts
Lecture 3b C Library xnxjxjxjxkx_ ESP32.pptx
6. Chapter Twenty_Managing Mass Communications Advertising Sales Promotions E...
description of motor equipments and its process.pptx
Volvo EC290C NL EC290CNL Excavator Service Repair Manual Instant Download.pdf
ACCOMPLISHMENT REPOERTS AND FILE OF GRADE 12 2021.ppt
Volvo EC20C Excavator Step-by-step Maintenance Instructions pdf
deforestation.ppt[1]bestpptondeforestation.pptx
Independence_Day_Patriotic theme (1).pptx
Volvo EC20C Excavator Service maintenance schedules.pdf
Marketing project 2024 for marketing students
Journal Meraj.pdfuuuuuuuuuuuuuuuuuuuuuuuuuuuuuuu

A quality Public Transport System, elements for consideration

  • 1. Go George – GIPTN A Quality Public Transport System, Elements for Consideration SATC Conference 2016 7 July 2016 Safiyyah Aboo – Aurecon EJ Robertson – EJ Robertson Consultants
  • 2. Aim and Scope • Provide a high level introduction to certain elements in IPTN development • More detailed experience on certain elements in the development of the GIPTN • Development Process • The Network • Industry Engagements • Infrastructure Light Approach • Bus supply dilemma • Not covered is • Institutional arrangements • Role of consultants/advisors • GIPTN Management and Operations • Capacity Building - overall
  • 3. Project History • Commenced in 2003 as the Sandkraal Road Corridor Mobility Strategy • Converted to George Integrated Public Transport Network or known to the public as the GO GEORGE System • ‘Flagship’ or pilot project • Project was initiated by the Province of the Western Cape (DTPW), partnered with George Municipality through and IGA and FA – in terms of Section 12 of the NLTA • Engagement with existing local taxi and bus operators commenced in 2007 with the aim of establishing them into a private company, and • Awarding them a 12 year negotiated bus contract as per the Section 41 of the NLTA
  • 4. Concept&Strategy Started in 2005 Project Scoping Travel surveys conducted MBT studies Economic Assessments conducted for George Engagement Engagement with the Taxi Industry Public Consultation Planning Operational Planning: Infrastructure, systems & technology Institutional Assessment Establishment Formalisation of operator company Signing the IGA between DTPW & MoG Developed institutional arrangements Engage in detailed negotiations with industry Implementation Operator Contract signed in November 2014 Services commences on 8 December 2014 Phases 1-3 have rolled out 2005 2006/7 – 2009/10 Introduction of the NLTA 2011-2013 2014-2016 Development Process
  • 5. The Network System Design System Roll-out Phases • Includes both the urban and rural areas of George Municipality • Services are operational in Rosemoor, Loerie Park, Denneoord, Blanco, Pacaltsdorp and the CBD • Remaining areas are to be implemented in late 2016 and 2017
  • 6. Salient Features of the System • Routes • Main • Community or feeder type • Intersuburb – linking rural settlements • Intertown - services between George and neighbouring towns (planned) • Demand responsive service for rural communities (planned) • Present sedan taxi operators converted to metered taxi to compliment the service (planned) • Minimum policy level of service • Spatial and temporal coverage • Operating hours of service – 14-18 hours, 7 days a week • Walking distances – 400m to 600m to most of the urban population of George • Mixed Fleet • Selection of appropriate vehicle for the respective demand level, mix of urban and rural environment, mixed topography
  • 7. Design Philosophy and Intended Benefits • Understanding that virtually all formal PT operations require some form of government subsidy • ‘user pay’ principle is unrealistic • given the high portion of poor and unemployed persons • amplifies by apartheid legacy • Any IPTN must be established and maintained in manner that will minimise the financial burden on both user and government • Should provide the urban poor with less costly access to employment to reduce the household disposable income spent on transport • GIPTN • Fare and policy structure based on user affordability criteria – linked to the minimum gazetted labour rate for the urban domestic worker • Not linked to operations cost recovery model
  • 8. Design Philosophy and Intended Benefits Public Contracting Authority Vehicle Operating Company QualityCharter RespondingtoUserNeeds PassengerCharter DeliveredServices Contract Operating Obligations • Quality triangle • Governments role in consulting with and providing the public with public transport services • Government contracts a service provider to provide the service • Government then makes the decision as to the quality of service provided • Once the quality of service is set and maintained at an appropriate quality level • Encourage car owners to use the PT system • Introduction of car use restraints as a future consideration • TDM measures
  • 9. Replicating MBT operations • Fallacy in the belief that IPTN operations should in some way replicate the replaced MBT and bus operations– reality is that it will be inefficient and ultimately non-sustainable • IPTN demand profile must draw on a wide range of sources to ensure adequate capacity provision including CPTR, census, household surveys, on the ground surveys etc • Shift to a structured network presents specific challenges since the negotiating status of the existing taxi industry and their advisors will change • GIPTN • Strongly association linked – 3 associations • Single bus operating contract – initially prior to NLTA, Province would be the Contracting Authority, however GIPTN now functions under Section 12 of the NLTA for joint controls - GM and DTPW (WC) • Removal of racial bias or competition between associations • After the 12 year contract, can be split up into more than one contract
  • 10. Scheduled Bus System • Acceptance that it is not a MBT system • Passengers will be expected to stand on buses during peak demands • Transfers between routes to complete a desired trip • Mixed fleet in an operation • If a safe, reliable, accessible service where timetables are integrated and adhered to, passengers will learn to trust and adapt to the system • System is required to be continuously monitored and evaluated to minimise operational costs
  • 11. Industry Engagements • Commenced in 2007, with the 3 associations and local bus operator • MOA – prior to formal negotiation process • Under the NLTTA this negotiation was not possible, but the introduction of the NLTA, under Section 41 allowed for this • Formal negotiation process • Operator Contract • Bus fleet ownership • Compensation Model – relinquishment of operating licenses • MBT industry can be persuaded to convert from the informal to the informal operations • Benefits include secure employment, fixed working hours, pension fund, etc
  • 12. Operating License Holders and Affected Persons • NLTA indicated negotiations can only be with persons holding valid operating licenses • establishing valid OLs through the Provincial Regulating Entity records took considerable time, with a number of engagement and appeals process • GIPTN • operators with local George based OL’s. • Long distance and chartered OLs could remain • All operators and affected persons were requested to register their interest to keep informed of the process • Registration process was run a few times, given the stop start nature of the project • List started at 400 people but now has risen to 1300 people • Managing the process and expectations remain a challenge
  • 13. Infrastructure Light Approach • GIPTN • Conventional bus system, using existing road network , attractive as there is no demand for priority operations • Provision of minimal up front infrastructure • 4 stage infrastructure approach • Bus Depot, Minimal starter stops, upgrading of roads and provision of bus turning facilities • Advantages – minimised abortive and wasteful expenditure • Disadvantages – • necessary to play catch up once the services become operational • Passengers disadvantaged by limited supply of bus shelters and other facilities • Significant impact of existing road network
  • 14. Bus Supply Dilemma • Universal Access • Accommodate passengers with special categories of need through universal design • Provision of universally accessible vehicles • Condition of PTNG grant • Current bus market • Limited supply of suitable mini, midi and conventional low floor or low entry buses • GIPTN • Mixed fleet • Developed accessible minibus with a wheel chair hoist, Midi buses are shortened conventional bus (10.5m) – too wide for certain roadways • Wider range of universally accessible buses to cater for different demand environments, especially in non- metro areas
  • 15. Conclusions and Recommendations • GIPTN – flagship project for non-metro areas • Project has demonstrated that • MBT operators and bus operators can be encouraged to participate, and take up the challenge if they are supported and there is measure of compensation • Provision of the service should focus on user needs and if so, will be utilised • Fare policy and structure must reduce share of household expenditure on transport • System must be accessible from a spatial, cost and time and must be seen as safe • Operating costs can be minimised though effective use of a mixed fleet and service delivery matched to passenger temporal demand • Target must be Quality Public Transport service delivery