Simplified Agile EVM
The Art Of Managing Triple Constraint
Presenter: Dinesh Sharma
ABOUT ME
DINESH SHARMA
Delivery Head
Over 26 years of experience in IT Industry with more than 15
years in Project management. Extensive Project, Program and
Delivery Management and more than 10 years into Agile Based
Models.
Worked with a number of organizations both product based and
service based across the globe. Experience working with wide
range of domains and technologies. Exceptional track record of
delivering a high number of projects and programs with 100%
success rate. Authored and published a large number of articles
and whitepapers on many topics in Agile and Project
Management.
Wunderman Thompson
Commerce and Technology
(A WPP Company)
AGENDA
INTRODUCTION THE SAEVM
MODEL
CASE STUDIES CONCLUSION
Why
Simplified
Agile EVM?
Our Technological environment is rapidly evolving
The Businesses environment is getting excessively competitive
Role of IT increasing yet success rate of IT projects still very low
Need for more innovation – SAEVM a possible solution
Why Projects
Fail – Some
Facts
• Change in the organization’s
priorities (39%)
• Change in project objectives
(37%)
• Inaccurate requirements
gathering (35%)
• Inadequate vision (29%)
• Poor communication (29%)
Facts
Success Rate?
Traditional Approach Vs Agile Approach – The Challenge
• Inability to change with the dynamic and ever-
changing market requirements
• Remain relevant and to keep up with the competitive
pressures is enormous
• Gain a competitive advantage the Project Management
group must constantly look for innovation, latest tools
and techniques, to gain newness, add value and
customer benefits.
• Adaptability and Change Management sometime being
misunderstood and misused leading to reduced
effectiveness of teams
• Challenge of cost overrun and schedule delays, due to
lack of supporting processes
• Operating with the approach in a non-agile or hybrid
environment, most projects fall in this category
Traditional Approach
Phases are clearly planned before hand; focus on
formal processes; extensive documentation; less
customer involvement
Agile Approach
Projects defined into small tasks; interactive
input system of continuous delivery
The Challenge
Is there a one size that fits all?
The Challenge
Choosing the
correct Project
Management
Technique
A PM’s
Dilemma
Selecting the right Project Management
Technique is critical to successfully
deliver projects on time and budget
based on the two Lifecycle models -
Traditional Vs Agile based
From the Traditional to Agile; there are a
wide range of project management
techniques and practices that can be
leveraged to maximize success.
A Possible Solution – SAEVM
Model
Introduces a new way of working on projects to bring in the power of EVM to the agile
world and help managing triple constraint effectively towards project success
SAEVM Model
SACPI SASPI SARPI SAQPI
Quality
Cost
Scope Time
Quality
It is based on the traditional EVM applied to the projects with an agile context. Although the projects
can be very different and the agile maturity and application also varied, but this model can still be
applicable in most scenarios
Overview
SCOPE
What do we have to accomplish?
TIME
How much time do we have?
COST
How much can we spend?
Sizing
Function Points
Use Case Points
Story Points
Complexity Points
Ideal Hours
QUALITY
Any Quality Considerations?
Base Metrics
Don’t Miss this metric
Budget
Effort
Dollar Value
Team Size
Mandatorily Available
Target Date(s)
No. of Days
No. of Sprints
No. of months
Usually Available
No. of weeks
Defects
No. of UAT Defects
No. of Internal Defects
Usually Not Specified
No. of Post Production Defects
Count
Cost Performance - SACPI
Planned/Replan
ned Size
(PSP)
Actual
Completed Size
(ASP)
Work
Completed %
(EV [ASP/PSP])
Total Budgeted
Cost
(TBC)
Total Incurred
Cost
(TIC)
Actual Cost
Consumed %
(AC [TIC/TBC])
Offtrack
Cost
Performance
(SACPI [EV/AC])
Slightly
Offtrack
On
Track
1.0
SP/FP/UCP
or Ideal
Hours
Currency
Value or
Person
Days/Hours
1.0
Schedule (Time) Performance - SASPI
Planned/Replan
ned Size
(PSP)
Actual
Completed Size
(ASP)
Work
Completed %
(EV [ASP/PSP])
Total Duration
(TST)
Completed
Duration
(CST)
Work Expected
Till Date %
(PV [CST/TST])
Schedule
Performance
(SACPI [EV/PV])
SP/FP/UCP
or Ideal
Hours
Sprints or
Weeks or
Days
1.0
1.0
Offtrack
Slightly
Offtrack
On
Track
Scope Performance - SARPI
Planned/Replan
ned Size
(PSP)
In Sprint Scope
Change
(RSP)
Scope Change
%
(SC [RSP/PSP])
Scope
Performance
(SARPI [1 - SC])
SP/FP/UCP
or Ideal
Hours
0.9X
0.9X
1.0
1.0
Offtrack
Slightly
Offtrack
On
Track
Quality Performance - SAQPI
Actual
Completed Size
(ASP)
Delivered
Defect Count
(UDC)
Delivered
Defect Density
(DDD
[UDC/ASP])
Quality
Performance
(SAQPI [1 –
DDD/BDD])
SP/FP/UCP
or Ideal
Hours
0.XX
0.XX
Baseline Defect
Density
(BDD)
1.0
1.0
Offtrack
Slightly
Offtrack
On
Track
Beyond Agile Metrics and Tools
Burn-down/
Burn-up
Velocity
Sprint Goal
Compliance
Increased Effectiveness and better managed projects
SAEVM – Implementation
How to Apply?
Project Focused
These are projects where the
expectation is to manage the project
delivery at overall project level.
Sprint/Time Bucket Focused
These are projects where the expectation
is to manage the delivery at sprint or time
bucket level.
Categorise Calculate Analyse Implement
How to Apply?
Calculate Derived Metrics
These are Calculated Metrics
and derived from base
metrics
Calculate Base Metrics
These are the data points
to be collected based on
the categorization
Categorise Calculate Analyse Implement
Calculate Core KPIs
These are KPIs for all core
areas – Cost, Time, Scope and
Quality calculated from
derived metrics
How to Apply?
Categorise Calculate Analyse Implement
Identify Root Cause
Why the KPIs are showing the
current value, identify
underlying causes
Inference
What does the KPI value
and trend mean
Draw an Action Plan
Identify actions to bring the
KPIs on track if not on track
How to Apply?
Repeat last 3 steps
Identify the tracking frequency and
repeat last 3 steps
Implement Actions
Implement the identified actions
Categorise Calculate Analyse Implement
SAEVM – Case Study – I
Project Focused
This project was for one of our European clients. After a few initial
discussions with the customer, it was understood that the requirements
were very fluid and non-structured.
We started applying SAEVM to the project with two-week sprint cycle and
annual release roadmap with releases spread throughout the year.
The project started with Quality slightly below par, Scope Performance
also slightly below par, other core KPIs completely offset to low value with
SACPI at 0.72 and SASPI at 0.55.
Case Insight
Cost Time Scope Quality
Stage III: This was the final stage of the
project. This stage was relatively smooth
as the core project performance was
gradually settling down. All essential
project performance parameters reached
a healthy levels with SACPI at 1.02 and
SASPI at 1.0.
Implementation
Stage I: The initial stage of
the project involved a lot
of struggle. The SASPI and
SACPI clearly indicated
the productivity of the
team was low
Stage II: At mid stage our project
started showing satisfactory cost and
schedule indicators, yet quality
parameters showed no signs of
improvement. The team was augmented
to support our delivery quality.
The project
can be
considered in
three stages
of
performance
SAEVM – Case Study – II
Sprint Focused
Case Insight
Cost Time Scope Quality
All other core KPIs completely offset with high variations on sprint-on-
sprint basis. SACPI remained around 0.5 and SASPI around 1 with
variation from 0.5 to 2.0.
The project was Driven by a competitive and ever-changing business
landscape, the requirements coming from the customer were extremely
unclear at the start.
The project started with quality maintained at healthy level with one
spike at the initial stage. The scope performance remained at a healthy
level with one spike.
Implementation
Stage I: At the initial stage the project
suffered high variation in SASPI and SACPI
which clearly indicated that the predictability
of the sprints were low. The low average
value of SACPI indicated that clearly team
was incurring more efforts than budget
Stage III: This was the
final stage which was
relatively smooth,
previous process
improvements seem to
have paid off
Stage II: At the mid stage,
project showed overall improvement
in SACPI and SASPI variations but
started getting some spikes on SARPI
and SAQPI.
The project
can be
considered in
three stages
of
performance
Inference and
Takeaways
• Although the execution of the model was
very different in two different categories but
we could establish effectiveness and overall
performance improvement in both
scenarios.
• The model’s effectiveness lies in the actions
taken based on the measures provided, as
with any other data driven models.
• Since model is heavily dependent on data it
would be crucial to have a good data quality
and care should be taken for the same for
effective implementation and positive results
from the model.
CONCLUSION
The rapidly evolving landscape of technology and
business mandates the importance of successful IT
project.
Future-Forward Strategy
Integrating Simplified Agile EVM (Earned Value
Management) can enhance project success,
complementing traditional Agile metrics and tools.
Thank You
Your Questions?

More Related Content

PDF
Dinesh Sharma and Jayeeta Dutta: Simplified Agile EVM - The Art Of Managing T...
PPTX
Project Management Framework
PPTX
2.SDLC . (1).pptxyuyhhgfbhsdfgsrsgwtrgtrgt
PDF
Session 5
PPT
Agile Cafe Boulder - Panelist and keynote slides
PDF
Webinar - Integrating InEight Hard Dollar and Oracle Primavera P6
PDF
Scaled agile implementation
PPT
Agile adoption julen c. mohanty
Dinesh Sharma and Jayeeta Dutta: Simplified Agile EVM - The Art Of Managing T...
Project Management Framework
2.SDLC . (1).pptxyuyhhgfbhsdfgsrsgwtrgtrgt
Session 5
Agile Cafe Boulder - Panelist and keynote slides
Webinar - Integrating InEight Hard Dollar and Oracle Primavera P6
Scaled agile implementation
Agile adoption julen c. mohanty

Similar to Agile Gurugram 2023 I Simplified Agile EVM - The Art of Managing Triple Constraint (20)

PDF
Lean Discussions About Agile and MVP
PDF
Lean discussions about agile and mvp
PDF
Why agile?
PDF
Michigan Agile Presentation
PPT
Northern Finishing School: IT Project Managment
DOCX
Foods Case StudyWhat to coverExecuti.docx
PDF
#Fundamental understanding of agile - By SN Panigrahi
PPTX
Applying both of waterfall and iterative development
PPT
Using Earned Value Management Concepts to Improve Commercial Project Performance
PPT
Agile project management PMI-ACP
PPT
Management by Objectives from the views of Project Management and Coordination
PPTX
Microsoft Dynamics AX Implementation Stabilization Case Studies
PPTX
SPM presentation.pptx
PPTX
Is your project not going well this will help you get it back on track
PPT
ASAP Methodology in Implementing ERP
PPS
Zero Defects Through Lean six Sigma
PPS
Zero Defects Through Lean Six Sigma
PPT
Strategic Project Selection in Oil & Gas Industry
PPT
Asap implementation methodology (2)
PDF
Agile Transformation
Lean Discussions About Agile and MVP
Lean discussions about agile and mvp
Why agile?
Michigan Agile Presentation
Northern Finishing School: IT Project Managment
Foods Case StudyWhat to coverExecuti.docx
#Fundamental understanding of agile - By SN Panigrahi
Applying both of waterfall and iterative development
Using Earned Value Management Concepts to Improve Commercial Project Performance
Agile project management PMI-ACP
Management by Objectives from the views of Project Management and Coordination
Microsoft Dynamics AX Implementation Stabilization Case Studies
SPM presentation.pptx
Is your project not going well this will help you get it back on track
ASAP Methodology in Implementing ERP
Zero Defects Through Lean six Sigma
Zero Defects Through Lean Six Sigma
Strategic Project Selection in Oil & Gas Industry
Asap implementation methodology (2)
Agile Transformation
Ad

More from AgileNetwork (20)

PDF
ANIn Mumbai 2025 | Measuring Business Value during Agile Transformation by Pr...
PPTX
ANIn Ahmedabad 2025 | Quality as Foundation of Business Agility: How QA Enabl...
PPTX
ANIn Ahmedabad 2025 | Beyond Survival: Enabling Growth Mindset by Abhishek Bh...
PPTX
Agile Chennai 18-19 July 2025 | Emerging patterns in Agentic AI by Bharani Su...
PPTX
Agile Chennai 18-19 July 2025 Ideathon | AI Powered Microfinance Literacy Gui...
PPTX
Agile Chennai 18-19 July 2025 Ideathon | Crypton- an AI driven, Quantum Resis...
PPTX
Agile Chennai 18-19 July 2025 | Leading with Integrity in the Age of AI – A C...
PDF
Agile Chennai 18-19 July 2025 | Workshop - Leadership in an Uncertain World: ...
PPTX
Agile Chennai 18-19 July 2025 | The Human Metrics of Agile: Building Resilien...
PPTX
Agile Chennai 18-19 July 2025 | Adaptive Organizations: Built to Learn, Ready...
PPTX
Agile Chennai 18-19 July 2025 | Workshop - Enhancing Agile Collaboration with...
PPTX
Agile Chennai 18-19 July 2025 | The Purpose Playbook: Building AI that Solves...
PDF
Agile Chennai 18-19 July 2025 | The Story of KM Implementation for enabling V...
PPTX
Agile Chennai 18-19 July 2025 | Beyond Survival: Resilience Through Agility a...
PPTX
Agile Chennai 18-19 July 2025 | Kanban: The Shop Floor’s Secret to Smooth Wor...
PDF
Agile Chennai 18-19 July 2025 | Unpacking OKRs: A Guide to Strategic Sophisti...
PPTX
Agile Chennai 18-19 July 2025 | Agility for Resilience - Adaptive Systems & C...
PPTX
Agile Chennai 18-19 July 2025 | Redefining Customer Centricity by Aarthi Ramesh
PDF
ANIn Bengaluru 2025 | Workshop- Innovate For Business Agility: Idea Generatio...
PPTX
ANIn Bengaluru 2025 | Working Smarter: The Fusion of Agile Mindsets and AI Mi...
ANIn Mumbai 2025 | Measuring Business Value during Agile Transformation by Pr...
ANIn Ahmedabad 2025 | Quality as Foundation of Business Agility: How QA Enabl...
ANIn Ahmedabad 2025 | Beyond Survival: Enabling Growth Mindset by Abhishek Bh...
Agile Chennai 18-19 July 2025 | Emerging patterns in Agentic AI by Bharani Su...
Agile Chennai 18-19 July 2025 Ideathon | AI Powered Microfinance Literacy Gui...
Agile Chennai 18-19 July 2025 Ideathon | Crypton- an AI driven, Quantum Resis...
Agile Chennai 18-19 July 2025 | Leading with Integrity in the Age of AI – A C...
Agile Chennai 18-19 July 2025 | Workshop - Leadership in an Uncertain World: ...
Agile Chennai 18-19 July 2025 | The Human Metrics of Agile: Building Resilien...
Agile Chennai 18-19 July 2025 | Adaptive Organizations: Built to Learn, Ready...
Agile Chennai 18-19 July 2025 | Workshop - Enhancing Agile Collaboration with...
Agile Chennai 18-19 July 2025 | The Purpose Playbook: Building AI that Solves...
Agile Chennai 18-19 July 2025 | The Story of KM Implementation for enabling V...
Agile Chennai 18-19 July 2025 | Beyond Survival: Resilience Through Agility a...
Agile Chennai 18-19 July 2025 | Kanban: The Shop Floor’s Secret to Smooth Wor...
Agile Chennai 18-19 July 2025 | Unpacking OKRs: A Guide to Strategic Sophisti...
Agile Chennai 18-19 July 2025 | Agility for Resilience - Adaptive Systems & C...
Agile Chennai 18-19 July 2025 | Redefining Customer Centricity by Aarthi Ramesh
ANIn Bengaluru 2025 | Workshop- Innovate For Business Agility: Idea Generatio...
ANIn Bengaluru 2025 | Working Smarter: The Fusion of Agile Mindsets and AI Mi...
Ad

Recently uploaded (20)

PDF
Encapsulation_ Review paper, used for researhc scholars
PDF
Architecting across the Boundaries of two Complex Domains - Healthcare & Tech...
PDF
Per capita expenditure prediction using model stacking based on satellite ima...
PDF
Optimiser vos workloads AI/ML sur Amazon EC2 et AWS Graviton
PPTX
MYSQL Presentation for SQL database connectivity
PPTX
1. Introduction to Computer Programming.pptx
PDF
cuic standard and advanced reporting.pdf
PDF
Dropbox Q2 2025 Financial Results & Investor Presentation
PDF
Diabetes mellitus diagnosis method based random forest with bat algorithm
PDF
A comparative analysis of optical character recognition models for extracting...
PPTX
Machine Learning_overview_presentation.pptx
PDF
gpt5_lecture_notes_comprehensive_20250812015547.pdf
PPTX
Tartificialntelligence_presentation.pptx
PPT
“AI and Expert System Decision Support & Business Intelligence Systems”
PDF
Approach and Philosophy of On baking technology
PDF
Empathic Computing: Creating Shared Understanding
PPTX
A Presentation on Artificial Intelligence
PDF
Encapsulation theory and applications.pdf
PDF
Mobile App Security Testing_ A Comprehensive Guide.pdf
PPTX
Spectroscopy.pptx food analysis technology
Encapsulation_ Review paper, used for researhc scholars
Architecting across the Boundaries of two Complex Domains - Healthcare & Tech...
Per capita expenditure prediction using model stacking based on satellite ima...
Optimiser vos workloads AI/ML sur Amazon EC2 et AWS Graviton
MYSQL Presentation for SQL database connectivity
1. Introduction to Computer Programming.pptx
cuic standard and advanced reporting.pdf
Dropbox Q2 2025 Financial Results & Investor Presentation
Diabetes mellitus diagnosis method based random forest with bat algorithm
A comparative analysis of optical character recognition models for extracting...
Machine Learning_overview_presentation.pptx
gpt5_lecture_notes_comprehensive_20250812015547.pdf
Tartificialntelligence_presentation.pptx
“AI and Expert System Decision Support & Business Intelligence Systems”
Approach and Philosophy of On baking technology
Empathic Computing: Creating Shared Understanding
A Presentation on Artificial Intelligence
Encapsulation theory and applications.pdf
Mobile App Security Testing_ A Comprehensive Guide.pdf
Spectroscopy.pptx food analysis technology

Agile Gurugram 2023 I Simplified Agile EVM - The Art of Managing Triple Constraint

  • 1. Simplified Agile EVM The Art Of Managing Triple Constraint Presenter: Dinesh Sharma
  • 2. ABOUT ME DINESH SHARMA Delivery Head Over 26 years of experience in IT Industry with more than 15 years in Project management. Extensive Project, Program and Delivery Management and more than 10 years into Agile Based Models. Worked with a number of organizations both product based and service based across the globe. Experience working with wide range of domains and technologies. Exceptional track record of delivering a high number of projects and programs with 100% success rate. Authored and published a large number of articles and whitepapers on many topics in Agile and Project Management. Wunderman Thompson Commerce and Technology (A WPP Company)
  • 4. Why Simplified Agile EVM? Our Technological environment is rapidly evolving The Businesses environment is getting excessively competitive Role of IT increasing yet success rate of IT projects still very low Need for more innovation – SAEVM a possible solution
  • 5. Why Projects Fail – Some Facts • Change in the organization’s priorities (39%) • Change in project objectives (37%) • Inaccurate requirements gathering (35%) • Inadequate vision (29%) • Poor communication (29%) Facts Success Rate?
  • 6. Traditional Approach Vs Agile Approach – The Challenge • Inability to change with the dynamic and ever- changing market requirements • Remain relevant and to keep up with the competitive pressures is enormous • Gain a competitive advantage the Project Management group must constantly look for innovation, latest tools and techniques, to gain newness, add value and customer benefits. • Adaptability and Change Management sometime being misunderstood and misused leading to reduced effectiveness of teams • Challenge of cost overrun and schedule delays, due to lack of supporting processes • Operating with the approach in a non-agile or hybrid environment, most projects fall in this category Traditional Approach Phases are clearly planned before hand; focus on formal processes; extensive documentation; less customer involvement Agile Approach Projects defined into small tasks; interactive input system of continuous delivery The Challenge Is there a one size that fits all? The Challenge
  • 7. Choosing the correct Project Management Technique A PM’s Dilemma Selecting the right Project Management Technique is critical to successfully deliver projects on time and budget based on the two Lifecycle models - Traditional Vs Agile based From the Traditional to Agile; there are a wide range of project management techniques and practices that can be leveraged to maximize success.
  • 8. A Possible Solution – SAEVM Model
  • 9. Introduces a new way of working on projects to bring in the power of EVM to the agile world and help managing triple constraint effectively towards project success SAEVM Model SACPI SASPI SARPI SAQPI Quality Cost Scope Time Quality It is based on the traditional EVM applied to the projects with an agile context. Although the projects can be very different and the agile maturity and application also varied, but this model can still be applicable in most scenarios Overview
  • 10. SCOPE What do we have to accomplish? TIME How much time do we have? COST How much can we spend? Sizing Function Points Use Case Points Story Points Complexity Points Ideal Hours QUALITY Any Quality Considerations? Base Metrics Don’t Miss this metric Budget Effort Dollar Value Team Size Mandatorily Available Target Date(s) No. of Days No. of Sprints No. of months Usually Available No. of weeks Defects No. of UAT Defects No. of Internal Defects Usually Not Specified No. of Post Production Defects Count
  • 11. Cost Performance - SACPI Planned/Replan ned Size (PSP) Actual Completed Size (ASP) Work Completed % (EV [ASP/PSP]) Total Budgeted Cost (TBC) Total Incurred Cost (TIC) Actual Cost Consumed % (AC [TIC/TBC]) Offtrack Cost Performance (SACPI [EV/AC]) Slightly Offtrack On Track 1.0 SP/FP/UCP or Ideal Hours Currency Value or Person Days/Hours 1.0
  • 12. Schedule (Time) Performance - SASPI Planned/Replan ned Size (PSP) Actual Completed Size (ASP) Work Completed % (EV [ASP/PSP]) Total Duration (TST) Completed Duration (CST) Work Expected Till Date % (PV [CST/TST]) Schedule Performance (SACPI [EV/PV]) SP/FP/UCP or Ideal Hours Sprints or Weeks or Days 1.0 1.0 Offtrack Slightly Offtrack On Track
  • 13. Scope Performance - SARPI Planned/Replan ned Size (PSP) In Sprint Scope Change (RSP) Scope Change % (SC [RSP/PSP]) Scope Performance (SARPI [1 - SC]) SP/FP/UCP or Ideal Hours 0.9X 0.9X 1.0 1.0 Offtrack Slightly Offtrack On Track
  • 14. Quality Performance - SAQPI Actual Completed Size (ASP) Delivered Defect Count (UDC) Delivered Defect Density (DDD [UDC/ASP]) Quality Performance (SAQPI [1 – DDD/BDD]) SP/FP/UCP or Ideal Hours 0.XX 0.XX Baseline Defect Density (BDD) 1.0 1.0 Offtrack Slightly Offtrack On Track
  • 15. Beyond Agile Metrics and Tools Burn-down/ Burn-up Velocity Sprint Goal Compliance Increased Effectiveness and better managed projects
  • 17. How to Apply? Project Focused These are projects where the expectation is to manage the project delivery at overall project level. Sprint/Time Bucket Focused These are projects where the expectation is to manage the delivery at sprint or time bucket level. Categorise Calculate Analyse Implement
  • 18. How to Apply? Calculate Derived Metrics These are Calculated Metrics and derived from base metrics Calculate Base Metrics These are the data points to be collected based on the categorization Categorise Calculate Analyse Implement Calculate Core KPIs These are KPIs for all core areas – Cost, Time, Scope and Quality calculated from derived metrics
  • 19. How to Apply? Categorise Calculate Analyse Implement Identify Root Cause Why the KPIs are showing the current value, identify underlying causes Inference What does the KPI value and trend mean Draw an Action Plan Identify actions to bring the KPIs on track if not on track
  • 20. How to Apply? Repeat last 3 steps Identify the tracking frequency and repeat last 3 steps Implement Actions Implement the identified actions Categorise Calculate Analyse Implement
  • 21. SAEVM – Case Study – I Project Focused
  • 22. This project was for one of our European clients. After a few initial discussions with the customer, it was understood that the requirements were very fluid and non-structured. We started applying SAEVM to the project with two-week sprint cycle and annual release roadmap with releases spread throughout the year. The project started with Quality slightly below par, Scope Performance also slightly below par, other core KPIs completely offset to low value with SACPI at 0.72 and SASPI at 0.55. Case Insight Cost Time Scope Quality
  • 23. Stage III: This was the final stage of the project. This stage was relatively smooth as the core project performance was gradually settling down. All essential project performance parameters reached a healthy levels with SACPI at 1.02 and SASPI at 1.0. Implementation Stage I: The initial stage of the project involved a lot of struggle. The SASPI and SACPI clearly indicated the productivity of the team was low Stage II: At mid stage our project started showing satisfactory cost and schedule indicators, yet quality parameters showed no signs of improvement. The team was augmented to support our delivery quality. The project can be considered in three stages of performance
  • 24. SAEVM – Case Study – II Sprint Focused
  • 25. Case Insight Cost Time Scope Quality All other core KPIs completely offset with high variations on sprint-on- sprint basis. SACPI remained around 0.5 and SASPI around 1 with variation from 0.5 to 2.0. The project was Driven by a competitive and ever-changing business landscape, the requirements coming from the customer were extremely unclear at the start. The project started with quality maintained at healthy level with one spike at the initial stage. The scope performance remained at a healthy level with one spike.
  • 26. Implementation Stage I: At the initial stage the project suffered high variation in SASPI and SACPI which clearly indicated that the predictability of the sprints were low. The low average value of SACPI indicated that clearly team was incurring more efforts than budget Stage III: This was the final stage which was relatively smooth, previous process improvements seem to have paid off Stage II: At the mid stage, project showed overall improvement in SACPI and SASPI variations but started getting some spikes on SARPI and SAQPI. The project can be considered in three stages of performance
  • 27. Inference and Takeaways • Although the execution of the model was very different in two different categories but we could establish effectiveness and overall performance improvement in both scenarios. • The model’s effectiveness lies in the actions taken based on the measures provided, as with any other data driven models. • Since model is heavily dependent on data it would be crucial to have a good data quality and care should be taken for the same for effective implementation and positive results from the model.
  • 28. CONCLUSION The rapidly evolving landscape of technology and business mandates the importance of successful IT project. Future-Forward Strategy Integrating Simplified Agile EVM (Earned Value Management) can enhance project success, complementing traditional Agile metrics and tools.