      Practical Experience Report: Application of Project
       Management areas from CMMI model in an Agile
                  development environment

                                   Author: Ahmed Mahdy
                       Senior Software Quality Engineer, Agile Coach
                                  Raya Corporation, Egypt
                                   aamahdys@gmail.com
                               ahmed_mahdy@rayacorp.com


                                 Reviewer: Sree Yellayi
     SCAMPI Lead Appraiser, SEI Authorized CMMI® Instructor, Certified Scrum Master
                         Siemens, Greater New York City Area
                               sree.yellayi@siemens.com
                             sreeramamurthy@yahoo.com




Abstract

The Capability Maturity Model Integration (CMMI) has been broadly used for assessing
organizational maturity and process capability throughout the world. Although most of the
customers give priority to CMMI certified organizations over others for guaranteeing the
quality, the nature of their rapid market change can no longer accept heavyweight plans,
requirements specification, change requests, contract negotiation, and other
documentation. Moreover, the rapid change in information technology has caused
increasing the frustration more, especially that there are new competitors started using
lightweight processes that invite to customer collaboration over contract negotiation and
working software over comprehensive documentation that is called “Agile” methodologies
that have been adopted to tackle this challenge. Agile development methods and CMMI are
often perceived to be at odds with each other. In fact, it’s possible to embrace both to
dramatically improve business performance. This paper focuses on the verification of
implementing CMMI Project Management process areas in agile organizations based on a
real and practical experience in Agile and CMMI successful projects.
The authors are going to share their practical experiences in interpreting the CMMI model's
project management practices in an Agile environment to address the model intent and not
compromising on the credibility or value of the practices.




                                              1
2009
               CMMI® 9th Technology Conference and User Group www.ndia.org/meetings/0110


Agile CMMI
Why Agile CMMI?
Most of the promising objectives of any software development method or process are delivering
working software on time, quality and budget. Software Engineering Institute (SEI) has paid a lot
of efforts to mostly satisfy these objectives in its process improvement models, and version 1.3
of CMMI Development will be released soon.
Nevertheless, the world becomes convinced with adding another objective, which was somehow
neglected more than highly considered, which is delivering a business value to the customer. [1]

Agile Scrum methodology
I assume that the readers know what CMMI is, or/and has experience in its implementation.
Scrum is a software development methodology that teams can adopt quickly to plan and
manage their daily work. Every Scrum activity has enough detail to plan, design, build and
test output, while tracking team progress. There are multiple planning levels and its strength
is that it is straightforward and easy to use. The risk is that some scrum implementers may
focus on generating components regardless of the complete integrated system, and this risk
is managed. The paper will not go through explaining what scrum or CMMI is in detail and
how to implement it, online materials are more than enough for that. Let us jump to explain
how we could embrace both.


CMMI Project Management process areas:

Project Management process areas cover the project management activities related to
planning, monitoring, and controlling the project.
The Project Management process areas of CMMI are as follows:
• Project Planning
• Project Monitoring and Control
• Integrated Project Management
• Risk Management


The Basic Project Management process areas address the activities related to establishing
and maintaining the project plan, establishing and maintaining commitments, monitoring
progress against the plan, taking corrective action, and managing supplier agreements.

Project Planning

The purpose of Project Planning (PP) is to establish and maintain plans that define
project activities.

SP CMMI Practice                                                  Agile Practice
1.1 Establish a top-level work breakdown structure (WBS) to       High level user stories (i.e. the
     estimate the scope of the project.                           parent of user stories)

1.2 Establish and maintain estimates of the attributes of the     Story points, used to estimate the


                                               2
2009
                CMMI® 9th Technology Conference and User Group www.ndia.org/meetings/0110


     work products and tasks.                                     difficulty/complexity (or relative size)
                                                                  of a Story (feature).

1.3 Define the project life-cycle phases upon which to scope      The Scrum process.
     the planning effort.

1.4 Estimate the project effort and cost for the work products    Scrum Ideal Time estimate (similar
     and tasks based on estimation rationale.                     to billable hours or Full-time
                                                                  Equivalents).

2.1 Establish and maintain the project’s budget and               Scrum estimates (in Ideal Time).
     schedule.                                                    Estimates of what work will be in
                                                                  each release.
                                                                  Iteration Backlog.
                                                                  Project Task board.

2.2 Identify and analyze project risks.                           Iteration Retrospective

2.3 Plan for the management of project data.                      Project Internal Chartering
2.4 Plan for necessary resources to perform the project.          Scrum estimates in Ideal Time
                                                                  Release plan, Iteration Backlog and
                                                                  assignments.

2.5 Plan for knowledge and skills needed to perform the           Project Internal Chartering
     project.                                                     Release Planning (synchronized
                                                                  with the internal chartering)
2.6 Plan the involvement of identified stakeholders.              Scrum process roles
                                                                  External and Internal Chartering

2.7 Establish and maintain the overall project plan content.      Scrum release plan.
                                                                  Iteration Backlog.
                                                                     Project Taskboard.
                                                                     [Note: The term “plan” in CMMI
                                                                  refers to additional plan
                                                                  components (such as risks and data
                                                                  management) that are not
                                                                  called out specifically in Scrum.]

3.1 Review all plans that affect the project to understand        Iteration planning meeting.
     project commitments.                                         Daily Scrum meeting.

3.2 Reconcile the project plan to reflect available and           Iteration planning meeting.
     estimated resources.                                         Daily Scrum meeting.

3.3 Obtain commitment from relevant stakeholders                  Iteration planning meeting.
     responsible for performing and supporting plan               Daily Scrum meeting.
     execution.                                                   [Note: The stakeholders listed in
                                                                  Scrum might not be the complete list


                                                3
2009
               CMMI® 9th Technology Conference and User Group www.ndia.org/meetings/0110


                                                                 of stakeholders for the project.]


The column of “Agile Practice” means either a previously defined practice in agile community or
a new proposed practice that does contradict with agile principles.

Project Monitoring and Control

The purpose of Project Monitoring and Control (PMC) is to provide an understanding of
the project’s progress so that appropriate corrective actions can be taken when the
project’s performance deviates significantly from the plan.


SP      CMMI Specific Practice                              Agile Practice
SP1.1 Monitor the actual values of the project planning     Iteration burndown chart that tracks effort
      parameters against the project plan.                  remaining.
                                                            Release burndown chart that tracks
                                                            completed story points. This shows how
                                                            much of the product functionality is left to
                                                            complete.
                                                            Project Task Board used to track stories
                                                            (requirements) that are done, in progress,
                                                            or ones that need verification.

        Monitor commitments against those identified in
        the project plan.

SP      Monitor commitments against those                   Discussions on team commitments at the:
        identified in the project plan.                     − Daily Scrum meeting.
                                                            − Iteration review meeting.
                                                            • Iteration burndown chart that tracks
                                                            effort remaining.
                                                            • Release burndown chart that tracks
                                                            story points that have been
                                                            completed. This shows how much of the
                                                            product functionality is left to complete.
SP      Monitor stakeholder involvement against the         Discussions at the:
        project plan.                                       − Daily Scrum meeting.
                                                            − Iteration review meeting.
                                                            • [Note: The stakeholders listed in Scrum
                                                            might not be the
                                                            complete list of stakeholders for the
                                                            project, e.g., customers, other impacted
                                                            teams.]
        Periodically review the project's progress,         Daily Scrum meeting.
        performance, and issues.                            Iteration review meeting.
                                                            Retrospectives.
        Review the accomplishments and results of the       Iteration review meeting.

                                                4
2009
               CMMI® 9th Technology Conference and User Group www.ndia.org/meetings/0110


        project at selected project milestones.
        Collect and analyze the issues and determine the      Notes from the:
        corrective actions necessary to address the           − Daily Scrum meeting.
        issues.                                               − Iteration review meeting.
                                                              [Note: Some teams track their
                                                              outstanding actions on the Product
                                                              Backlog. It doesn’t matter where or how
                                                              the items are tracked, as long as they
                                                              are.]

        Take corrective action on identified issues.          Actions from the:
                                                              − Daily Scrum meeting.
                                                              − Iteration review meeting.

        Manage corrective actions to closure.                 Tracking of actions from:
                                                              − Daily Scrum meeting.
                                                              − Iteration review meeting.
                                                              • [Note: This assumes that teams will
                                                              track (and not lose) actions.]

Integrated Project Management

The purpose of Integrated Project Management (IPM) is to establish and manage the project and the
involvement of the relevant stakeholders according to an integrated and defined process that is
tailored from the organization’s set of standard processes.
Assumption:
There is an established Guidelines and Strategy of Agile Standards (GSAS) for agile projects:
     - Data Management Strategy
     - Lifecycle roadmap strategy (Agile roadmap or workflow with the connection dependencies,
         conditions, input/output)
     - People Management Plan:
             - Agile People Roles, Skills and Responsibilities
             - Any constraints


SP    CMMI Practice                                                Agile Practice
1.1   Establish and maintain the project's defined process from    OPF and OPD is a reference for this
      project startup through the life of the project.             practice
                                                                   Project process can be stated from
                                                                   the internal/external chartering
                                                                   meetings (it can be updated with re-
                                                                   meeting the stakeholders throughout
                                                                   the work because the nature of
                                                                   software process is empirical)
1.2   Use the organizational process assets and measurement        Given the Guidelines and Strategy of
      repository for estimating and planning the project’s         Agile Standards:
      activities.                                                  Roadmap (Scope of Work)
                                                                   Release Planning
                                                                   Iteration Planning
                                                                   (the estimation of stories – both high

                                                 5
2009
               CMMI® 9th Technology Conference and User Group www.ndia.org/meetings/0110


                                                                       and low level)
1.3   Establish and maintain the project's work environment            Given the Guidelines and Strategy of
      based on the organization's work environment standards.          Agile Standards:
                                                                       List of required tools for agile or scrum
                                                                       activities
                                                                       Other requirements for work
                                                                       environment that are standardized in
1.4   Integrate the project plan and the other plans that affect the   Project Integrated Plan which
      project to describe the project’s defined process.               includes:
                                                                       Roadmap (Scope of Work over the
                                                                       releases)
                                                                       Release Plan
                                                                       Iteration Plan
                                                                       ( it’s important to integrate these plans
                                                                       to be synchronized due to the
                                                                       expected updates throughout the
                                                                       work)
                                                                       Using Rally, VersionOne, TFS 2010 or
                                                                       any other similar tools definitely help
                                                                       you in achieving that easily.
1.5   Manage the project using the project plan, the other plans       Project Integrated plan
      that affect the project, and the project’s defined process.      Review meetings that may update
                                                                       requirements and plans
1.6   Contribute work products, measures, and documented               Iteration Retrospectives
      experiences to the organizational process assets.                Release Retrospectives
                                                                       Project Lessons learned
2.1   Manage the involvement of the relevant stakeholders in the       Updatable Schedule of the coming
      project.                                                         events (Release planning and
                                                                       retrospectives, Iteration planning and
                                                                       retrospectives, customer meetings)
                                                                       Roles and Responsibilities in GSAS
2.2   Participate with relevant stakeholders to identify, negotiate,   Action items from standup meetings,
      and track critical dependencies.                                 iteration and release retrospectives
                                                                       Story slicing that can show
                                                                       dependencies
                                                                       Senior Management meetings and its
                                                                       action items
                                                                       Action items should be assigned and
                                                                       tracked in whatever tool
2.3   Resolve issues with relevant stakeholders.                       The tool of action items tracking
                                                                       should show the status of all action
                                                                       items, and all issues.
                                                                       Results of action items’ tracking


Risk Management

The purpose of Risk Management (RSKM) is to identify potential problems before they occur so that
risk-handling activities can be planned and invoked as needed across the life of the product or
project to mitigate adverse impacts on achieving objectives.


                                                   6
2009
               CMMI® 9th Technology Conference and User Group www.ndia.org/meetings/0110


Important Notes:
                   -   It’s really *important* to manage your risks
                   -   Early risk identification (discovering and exploring)
                   -   Consider both internal and external chartering risks (cost, schedule,
                       performance, technical and other risks)
                   -   Discuss any new risk
                   -   Prepare a mitigation for the identified risk with the collaboration of other
                       stakeholders
                   -   Assign the responsibility of such mitigation actions to people
                   -   Monitor and follow up these mitigations in the agile meetings in your process
                   -   I personally prefer using any tracking tool that help you in adding/updating
                       risks

SP    CMMI Practice                                                    Agile Practice
1.1   Determine risk sources and categories.                           Risk Categories in iteration and
                                                                       release retrospectives
1.2   Define the parameters used to analyze and categorize             Discuss each risk in iteration and
      risks, and the parameters used to control the risk               release retrospectives , define the
      management effort.                                               parameters for risks, and not to
                                                                       involve the management in all risks,
                                                                       you can define threshold for
                                                                       management involvement other than
                                                                       the relevant risks by nature.
1.3   Establish and maintain the strategy to be used for risk          Discuss the mitigation for each risk
      management.                                                      with the stakeholders in iteration and
                                                                       release retrospectives, identify
                                                                       assigned action items and how to
                                                                       monitored with due dates if possible.
2.1   Identify and document the risks.                                 Here the call to use any tool for
                                                                       documenting and monitoring the risks.
2.2   Evaluate and categorize each identified risk using the           Discuss and analyze each risk with
      defined risk categories and parameters, and determine its        evaluating its defined parameters
      relative                                                         (priority, impact, probability and any
      priority.                                                        other parameter you need for your
                                                                       organization)
3.1   Develop a risk mitigation plan for the most important risks to   Discuss the actions for each identified
      the project as defined by the risk management strategy.          risk mitigation and plan for its follow
                                                                       up and handling
3.2   Monitor the status of each risk periodically and implement       Iteration and release retrospective can
      the risk mitigation plan as appropriate.                         perform these actions:
                                                                       Update the risks with additional risks,
                                                                       status of old risks, status of actions
                                                                       and mitigations,


References:

[1] Neil Potter and Mary Sakry, Process Group Newsletter Volume 16 No 2, March 2009
[2] CMMI Product Team, CMMI for Development Ver 1.2, Nov 2007
[3] Agile CMMI Workshop by Ahmed Sidky, Marian Tadros, Sree Yellayi , Egypt 2008
[4] Software Process Improvement Community Meetings, Egypt
                                                  7
2009
          CMMI® 9th Technology Conference and User Group www.ndia.org/meetings/0110


IMPORTANT NOTES:



  • These practices are proposed and they may not be
    the best practices for your organization,

  • These practices are only for a proof of
    AgileCMMI,

  • Do NOT implement these proposed practices If
    you think there are other practices that ADD
    more value,

  • Explore more practices !




                                          8

More Related Content

DOC
0569 project management-beenish
PPT
Ch3 proj.mgt
PPT
Project management in Agile Way
PDF
Macrosolutions Consulting Service: Resources and Investment Optimization thro...
PDF
Macrosolutions Consulting Service: Projects accelerated planning through the ...
PDF
Agile Project Manager
PDF
Macrosolutions Consulting Service: Project Maturity Assessment and Diagnosis
PPTX
T carlson mbontrager_wtippin_lsinger_v2
0569 project management-beenish
Ch3 proj.mgt
Project management in Agile Way
Macrosolutions Consulting Service: Resources and Investment Optimization thro...
Macrosolutions Consulting Service: Projects accelerated planning through the ...
Agile Project Manager
Macrosolutions Consulting Service: Project Maturity Assessment and Diagnosis
T carlson mbontrager_wtippin_lsinger_v2

What's hot (20)

PDF
2008 Fiatech Ceti Awards Smccv
PPTX
Ch22-Software Engineering 9
PDF
Wbs Building Use This
PDF
Macrosolutions Consulting Service: Support and Consulting for Specific Projec...
PDF
Agile Importance in Pharmaceutical Industry
PDF
Macrosolutions Consulting Service: Communication, Management and Recovery Pla...
DOC
Dan Drew Resume
PDF
Macrosolutions Consulting Service: Applying Quantitative Methods and Risks Si...
KEY
Agile Project Management for elearning development
PDF
Murphy.dar jean.jean
PDF
SCL Aug Sep 2010 Software Development How Agile Are You
PPT
Rational collaborative-lifecycle-management-2012
PDF
Aceicon epm software
PDF
Louis.cioletti
PPTX
Agile Business Rhythm
PDF
Capm time 150 question final key
PDF
The Evolving Agile Development Process at Srijan
DOC
The project will be deemed successful when all the objectives have been met
PDF
Moser.bryan
2008 Fiatech Ceti Awards Smccv
Ch22-Software Engineering 9
Wbs Building Use This
Macrosolutions Consulting Service: Support and Consulting for Specific Projec...
Agile Importance in Pharmaceutical Industry
Macrosolutions Consulting Service: Communication, Management and Recovery Pla...
Dan Drew Resume
Macrosolutions Consulting Service: Applying Quantitative Methods and Risks Si...
Agile Project Management for elearning development
Murphy.dar jean.jean
SCL Aug Sep 2010 Software Development How Agile Are You
Rational collaborative-lifecycle-management-2012
Aceicon epm software
Louis.cioletti
Agile Business Rhythm
Capm time 150 question final key
The Evolving Agile Development Process at Srijan
The project will be deemed successful when all the objectives have been met
Moser.bryan
Ad

Viewers also liked (18)

PPTX
Project Management: Knowledge Areas
PPT
PM Knowledge Areas
PPTX
1.3 project management process groups & knowledge areas 1
PPS
The Project Management Knowledge Areas ITTOs
PDF
TPG PSLink - Integration of Financial and Project Data (Integration of Micros...
PPTX
Ingenio eng presentation
PPT
Project managemenet knowledge areas
PPTX
Project Management Knowledge Areas
PDF
PMBOK 5th Edition Project Management Processes and Knowledge Areas
PPT
Introduction to-project-management
PPTX
Project management chapter 4 - project integration management-1
PPTX
Project management fundamentals
PPS
Project Management Process Groups And Knowledge Areas
PDF
Pmbok 4th edition chapter 5 - Project Scope Management
PPT
3.3 Types of Business Ownership 1
PPTX
Introduction to Project Management (workshop) - v.1
PDF
Agile Project Management - An introduction to Agile and the new PMI-ACP
PPSX
Project management
Project Management: Knowledge Areas
PM Knowledge Areas
1.3 project management process groups & knowledge areas 1
The Project Management Knowledge Areas ITTOs
TPG PSLink - Integration of Financial and Project Data (Integration of Micros...
Ingenio eng presentation
Project managemenet knowledge areas
Project Management Knowledge Areas
PMBOK 5th Edition Project Management Processes and Knowledge Areas
Introduction to-project-management
Project management chapter 4 - project integration management-1
Project management fundamentals
Project Management Process Groups And Knowledge Areas
Pmbok 4th edition chapter 5 - Project Scope Management
3.3 Types of Business Ownership 1
Introduction to Project Management (workshop) - v.1
Agile Project Management - An introduction to Agile and the new PMI-ACP
Project management
Ad

Similar to [AgileCMMI] Practical Experience Report: Application of Project Management areas from CMMI model in an Agile development environment (20)

PPT
Project Management Foundations Series Course 104 - Agile Project Management C...
PPTX
PMI-ACP - Agile Framework
PPTX
CMMI and Agile
PPTX
Project management in pharmaceutical generic industry basics and standards
PPTX
Metodologia scrum actualizada qa
DOC
Project Management
PDF
Managing Scope Time Cost And Team In Agile
PPTX
Agile, PMI and PMBOK
KEY
Agile product development
PDF
110605=holy grail cmmi_scrum
PDF
Scrum group7 20120213
PPTX
Project management
PDF
Agile Certified Practitioner Workshop
PPTX
Agile Project Management using Scrum
PPTX
PPTX
system analysis and design Class 3
PPTX
PPTX
Brief introduction to project management and project management tools
PDF
Pmbok 4th edition chapter 3 - Project Management Processes for a Project
PDF
Presentation The 360°Project Manager @ PMI UK South West Event Swindon 13th ...
Project Management Foundations Series Course 104 - Agile Project Management C...
PMI-ACP - Agile Framework
CMMI and Agile
Project management in pharmaceutical generic industry basics and standards
Metodologia scrum actualizada qa
Project Management
Managing Scope Time Cost And Team In Agile
Agile, PMI and PMBOK
Agile product development
110605=holy grail cmmi_scrum
Scrum group7 20120213
Project management
Agile Certified Practitioner Workshop
Agile Project Management using Scrum
system analysis and design Class 3
Brief introduction to project management and project management tools
Pmbok 4th edition chapter 3 - Project Management Processes for a Project
Presentation The 360°Project Manager @ PMI UK South West Event Swindon 13th ...

Recently uploaded (20)

PDF
How UI/UX Design Impacts User Retention in Mobile Apps.pdf
PDF
Encapsulation_ Review paper, used for researhc scholars
PDF
The Rise and Fall of 3GPP – Time for a Sabbatical?
PPTX
Understanding_Digital_Forensics_Presentation.pptx
PDF
7 ChatGPT Prompts to Help You Define Your Ideal Customer Profile.pdf
PDF
TokAI - TikTok AI Agent : The First AI Application That Analyzes 10,000+ Vira...
PDF
Architecting across the Boundaries of two Complex Domains - Healthcare & Tech...
PDF
Bridging biosciences and deep learning for revolutionary discoveries: a compr...
PPTX
MYSQL Presentation for SQL database connectivity
PDF
Machine learning based COVID-19 study performance prediction
PDF
Build a system with the filesystem maintained by OSTree @ COSCUP 2025
PDF
Electronic commerce courselecture one. Pdf
PDF
Dropbox Q2 2025 Financial Results & Investor Presentation
PPTX
Cloud computing and distributed systems.
PPTX
Effective Security Operations Center (SOC) A Modern, Strategic, and Threat-In...
PDF
Mobile App Security Testing_ A Comprehensive Guide.pdf
PPTX
Digital-Transformation-Roadmap-for-Companies.pptx
DOCX
The AUB Centre for AI in Media Proposal.docx
PDF
Spectral efficient network and resource selection model in 5G networks
PDF
Network Security Unit 5.pdf for BCA BBA.
How UI/UX Design Impacts User Retention in Mobile Apps.pdf
Encapsulation_ Review paper, used for researhc scholars
The Rise and Fall of 3GPP – Time for a Sabbatical?
Understanding_Digital_Forensics_Presentation.pptx
7 ChatGPT Prompts to Help You Define Your Ideal Customer Profile.pdf
TokAI - TikTok AI Agent : The First AI Application That Analyzes 10,000+ Vira...
Architecting across the Boundaries of two Complex Domains - Healthcare & Tech...
Bridging biosciences and deep learning for revolutionary discoveries: a compr...
MYSQL Presentation for SQL database connectivity
Machine learning based COVID-19 study performance prediction
Build a system with the filesystem maintained by OSTree @ COSCUP 2025
Electronic commerce courselecture one. Pdf
Dropbox Q2 2025 Financial Results & Investor Presentation
Cloud computing and distributed systems.
Effective Security Operations Center (SOC) A Modern, Strategic, and Threat-In...
Mobile App Security Testing_ A Comprehensive Guide.pdf
Digital-Transformation-Roadmap-for-Companies.pptx
The AUB Centre for AI in Media Proposal.docx
Spectral efficient network and resource selection model in 5G networks
Network Security Unit 5.pdf for BCA BBA.

[AgileCMMI] Practical Experience Report: Application of Project Management areas from CMMI model in an Agile development environment

  • 1. 2009 CMMI® 9th Technology Conference and User Group www.ndia.org/meetings/0110 Practical Experience Report: Application of Project Management areas from CMMI model in an Agile development environment Author: Ahmed Mahdy Senior Software Quality Engineer, Agile Coach Raya Corporation, Egypt aamahdys@gmail.com ahmed_mahdy@rayacorp.com Reviewer: Sree Yellayi SCAMPI Lead Appraiser, SEI Authorized CMMI® Instructor, Certified Scrum Master Siemens, Greater New York City Area sree.yellayi@siemens.com sreeramamurthy@yahoo.com Abstract The Capability Maturity Model Integration (CMMI) has been broadly used for assessing organizational maturity and process capability throughout the world. Although most of the customers give priority to CMMI certified organizations over others for guaranteeing the quality, the nature of their rapid market change can no longer accept heavyweight plans, requirements specification, change requests, contract negotiation, and other documentation. Moreover, the rapid change in information technology has caused increasing the frustration more, especially that there are new competitors started using lightweight processes that invite to customer collaboration over contract negotiation and working software over comprehensive documentation that is called “Agile” methodologies that have been adopted to tackle this challenge. Agile development methods and CMMI are often perceived to be at odds with each other. In fact, it’s possible to embrace both to dramatically improve business performance. This paper focuses on the verification of implementing CMMI Project Management process areas in agile organizations based on a real and practical experience in Agile and CMMI successful projects. The authors are going to share their practical experiences in interpreting the CMMI model's project management practices in an Agile environment to address the model intent and not compromising on the credibility or value of the practices. 1
  • 2. 2009 CMMI® 9th Technology Conference and User Group www.ndia.org/meetings/0110 Agile CMMI Why Agile CMMI? Most of the promising objectives of any software development method or process are delivering working software on time, quality and budget. Software Engineering Institute (SEI) has paid a lot of efforts to mostly satisfy these objectives in its process improvement models, and version 1.3 of CMMI Development will be released soon. Nevertheless, the world becomes convinced with adding another objective, which was somehow neglected more than highly considered, which is delivering a business value to the customer. [1] Agile Scrum methodology I assume that the readers know what CMMI is, or/and has experience in its implementation. Scrum is a software development methodology that teams can adopt quickly to plan and manage their daily work. Every Scrum activity has enough detail to plan, design, build and test output, while tracking team progress. There are multiple planning levels and its strength is that it is straightforward and easy to use. The risk is that some scrum implementers may focus on generating components regardless of the complete integrated system, and this risk is managed. The paper will not go through explaining what scrum or CMMI is in detail and how to implement it, online materials are more than enough for that. Let us jump to explain how we could embrace both. CMMI Project Management process areas: Project Management process areas cover the project management activities related to planning, monitoring, and controlling the project. The Project Management process areas of CMMI are as follows: • Project Planning • Project Monitoring and Control • Integrated Project Management • Risk Management The Basic Project Management process areas address the activities related to establishing and maintaining the project plan, establishing and maintaining commitments, monitoring progress against the plan, taking corrective action, and managing supplier agreements. Project Planning The purpose of Project Planning (PP) is to establish and maintain plans that define project activities. SP CMMI Practice Agile Practice 1.1 Establish a top-level work breakdown structure (WBS) to High level user stories (i.e. the estimate the scope of the project. parent of user stories) 1.2 Establish and maintain estimates of the attributes of the Story points, used to estimate the 2
  • 3. 2009 CMMI® 9th Technology Conference and User Group www.ndia.org/meetings/0110 work products and tasks. difficulty/complexity (or relative size) of a Story (feature). 1.3 Define the project life-cycle phases upon which to scope The Scrum process. the planning effort. 1.4 Estimate the project effort and cost for the work products Scrum Ideal Time estimate (similar and tasks based on estimation rationale. to billable hours or Full-time Equivalents). 2.1 Establish and maintain the project’s budget and Scrum estimates (in Ideal Time). schedule. Estimates of what work will be in each release. Iteration Backlog. Project Task board. 2.2 Identify and analyze project risks. Iteration Retrospective 2.3 Plan for the management of project data. Project Internal Chartering 2.4 Plan for necessary resources to perform the project. Scrum estimates in Ideal Time Release plan, Iteration Backlog and assignments. 2.5 Plan for knowledge and skills needed to perform the Project Internal Chartering project. Release Planning (synchronized with the internal chartering) 2.6 Plan the involvement of identified stakeholders. Scrum process roles External and Internal Chartering 2.7 Establish and maintain the overall project plan content. Scrum release plan. Iteration Backlog. Project Taskboard. [Note: The term “plan” in CMMI refers to additional plan components (such as risks and data management) that are not called out specifically in Scrum.] 3.1 Review all plans that affect the project to understand Iteration planning meeting. project commitments. Daily Scrum meeting. 3.2 Reconcile the project plan to reflect available and Iteration planning meeting. estimated resources. Daily Scrum meeting. 3.3 Obtain commitment from relevant stakeholders Iteration planning meeting. responsible for performing and supporting plan Daily Scrum meeting. execution. [Note: The stakeholders listed in Scrum might not be the complete list 3
  • 4. 2009 CMMI® 9th Technology Conference and User Group www.ndia.org/meetings/0110 of stakeholders for the project.] The column of “Agile Practice” means either a previously defined practice in agile community or a new proposed practice that does contradict with agile principles. Project Monitoring and Control The purpose of Project Monitoring and Control (PMC) is to provide an understanding of the project’s progress so that appropriate corrective actions can be taken when the project’s performance deviates significantly from the plan. SP CMMI Specific Practice Agile Practice SP1.1 Monitor the actual values of the project planning Iteration burndown chart that tracks effort parameters against the project plan. remaining. Release burndown chart that tracks completed story points. This shows how much of the product functionality is left to complete. Project Task Board used to track stories (requirements) that are done, in progress, or ones that need verification. Monitor commitments against those identified in the project plan. SP Monitor commitments against those Discussions on team commitments at the: identified in the project plan. − Daily Scrum meeting. − Iteration review meeting. • Iteration burndown chart that tracks effort remaining. • Release burndown chart that tracks story points that have been completed. This shows how much of the product functionality is left to complete. SP Monitor stakeholder involvement against the Discussions at the: project plan. − Daily Scrum meeting. − Iteration review meeting. • [Note: The stakeholders listed in Scrum might not be the complete list of stakeholders for the project, e.g., customers, other impacted teams.] Periodically review the project's progress, Daily Scrum meeting. performance, and issues. Iteration review meeting. Retrospectives. Review the accomplishments and results of the Iteration review meeting. 4
  • 5. 2009 CMMI® 9th Technology Conference and User Group www.ndia.org/meetings/0110 project at selected project milestones. Collect and analyze the issues and determine the Notes from the: corrective actions necessary to address the − Daily Scrum meeting. issues. − Iteration review meeting. [Note: Some teams track their outstanding actions on the Product Backlog. It doesn’t matter where or how the items are tracked, as long as they are.] Take corrective action on identified issues. Actions from the: − Daily Scrum meeting. − Iteration review meeting. Manage corrective actions to closure. Tracking of actions from: − Daily Scrum meeting. − Iteration review meeting. • [Note: This assumes that teams will track (and not lose) actions.] Integrated Project Management The purpose of Integrated Project Management (IPM) is to establish and manage the project and the involvement of the relevant stakeholders according to an integrated and defined process that is tailored from the organization’s set of standard processes. Assumption: There is an established Guidelines and Strategy of Agile Standards (GSAS) for agile projects: - Data Management Strategy - Lifecycle roadmap strategy (Agile roadmap or workflow with the connection dependencies, conditions, input/output) - People Management Plan: - Agile People Roles, Skills and Responsibilities - Any constraints SP CMMI Practice Agile Practice 1.1 Establish and maintain the project's defined process from OPF and OPD is a reference for this project startup through the life of the project. practice Project process can be stated from the internal/external chartering meetings (it can be updated with re- meeting the stakeholders throughout the work because the nature of software process is empirical) 1.2 Use the organizational process assets and measurement Given the Guidelines and Strategy of repository for estimating and planning the project’s Agile Standards: activities. Roadmap (Scope of Work) Release Planning Iteration Planning (the estimation of stories – both high 5
  • 6. 2009 CMMI® 9th Technology Conference and User Group www.ndia.org/meetings/0110 and low level) 1.3 Establish and maintain the project's work environment Given the Guidelines and Strategy of based on the organization's work environment standards. Agile Standards: List of required tools for agile or scrum activities Other requirements for work environment that are standardized in 1.4 Integrate the project plan and the other plans that affect the Project Integrated Plan which project to describe the project’s defined process. includes: Roadmap (Scope of Work over the releases) Release Plan Iteration Plan ( it’s important to integrate these plans to be synchronized due to the expected updates throughout the work) Using Rally, VersionOne, TFS 2010 or any other similar tools definitely help you in achieving that easily. 1.5 Manage the project using the project plan, the other plans Project Integrated plan that affect the project, and the project’s defined process. Review meetings that may update requirements and plans 1.6 Contribute work products, measures, and documented Iteration Retrospectives experiences to the organizational process assets. Release Retrospectives Project Lessons learned 2.1 Manage the involvement of the relevant stakeholders in the Updatable Schedule of the coming project. events (Release planning and retrospectives, Iteration planning and retrospectives, customer meetings) Roles and Responsibilities in GSAS 2.2 Participate with relevant stakeholders to identify, negotiate, Action items from standup meetings, and track critical dependencies. iteration and release retrospectives Story slicing that can show dependencies Senior Management meetings and its action items Action items should be assigned and tracked in whatever tool 2.3 Resolve issues with relevant stakeholders. The tool of action items tracking should show the status of all action items, and all issues. Results of action items’ tracking Risk Management The purpose of Risk Management (RSKM) is to identify potential problems before they occur so that risk-handling activities can be planned and invoked as needed across the life of the product or project to mitigate adverse impacts on achieving objectives. 6
  • 7. 2009 CMMI® 9th Technology Conference and User Group www.ndia.org/meetings/0110 Important Notes: - It’s really *important* to manage your risks - Early risk identification (discovering and exploring) - Consider both internal and external chartering risks (cost, schedule, performance, technical and other risks) - Discuss any new risk - Prepare a mitigation for the identified risk with the collaboration of other stakeholders - Assign the responsibility of such mitigation actions to people - Monitor and follow up these mitigations in the agile meetings in your process - I personally prefer using any tracking tool that help you in adding/updating risks SP CMMI Practice Agile Practice 1.1 Determine risk sources and categories. Risk Categories in iteration and release retrospectives 1.2 Define the parameters used to analyze and categorize Discuss each risk in iteration and risks, and the parameters used to control the risk release retrospectives , define the management effort. parameters for risks, and not to involve the management in all risks, you can define threshold for management involvement other than the relevant risks by nature. 1.3 Establish and maintain the strategy to be used for risk Discuss the mitigation for each risk management. with the stakeholders in iteration and release retrospectives, identify assigned action items and how to monitored with due dates if possible. 2.1 Identify and document the risks. Here the call to use any tool for documenting and monitoring the risks. 2.2 Evaluate and categorize each identified risk using the Discuss and analyze each risk with defined risk categories and parameters, and determine its evaluating its defined parameters relative (priority, impact, probability and any priority. other parameter you need for your organization) 3.1 Develop a risk mitigation plan for the most important risks to Discuss the actions for each identified the project as defined by the risk management strategy. risk mitigation and plan for its follow up and handling 3.2 Monitor the status of each risk periodically and implement Iteration and release retrospective can the risk mitigation plan as appropriate. perform these actions: Update the risks with additional risks, status of old risks, status of actions and mitigations, References: [1] Neil Potter and Mary Sakry, Process Group Newsletter Volume 16 No 2, March 2009 [2] CMMI Product Team, CMMI for Development Ver 1.2, Nov 2007 [3] Agile CMMI Workshop by Ahmed Sidky, Marian Tadros, Sree Yellayi , Egypt 2008 [4] Software Process Improvement Community Meetings, Egypt 7
  • 8. 2009 CMMI® 9th Technology Conference and User Group www.ndia.org/meetings/0110 IMPORTANT NOTES: • These practices are proposed and they may not be the best practices for your organization, • These practices are only for a proof of AgileCMMI, • Do NOT implement these proposed practices If you think there are other practices that ADD more value, • Explore more practices ! 8