T. Schulthess 3
Centro Svizzero di Calcolo Scientifico (CSCS)
The Swiss National Supercomputing Center
• Established in 1991 as a unit of ETH Zurich
• Located in Lugano, Ticino
• 115 highly qualified staff (25f) from 26 nations
• Flexible Infrastructure: Power/cooling: 12MW, upgradable to 25MW
• Develops & operates the key supercomputing capabilities required to solve important problems to science and/or society
• A research infrastructure with ~2000 users, 200 projects
• Leads the national strategy for High-Performance Computing and Networking (HPCN) that was passed by Swiss Parliament in 2009
• Has a dedicated User Laboratory for supercomputing since 2011
(i.e. research infrastructure funded by the ETH Domain on a programmatic basis)
• From 2017, tier-0 system of the “Partnership for Advanced Computing in Europe” (PRACE)
T. Schulthess
User Lab allocations 2018 – by research fields
4
node hours storage
T. Schulthess
User Lab allocations 2018 – by institutions
5
T. Schulthess
“Piz Daint” 2017 fact sheet
6
http://www.cscs.ch/publications/fact_sheets/index.html
~5’000 NVIDIA P100 GPU accelerated nodes
~1’400 Dual multi-core socket nodes
Institutions using Piz Daint (in 2019)
•User Lab (including PRACE Tier-0 allocations)
•University of Zurich, USI, PSI, EMPA
•NCCR MARVEL and HBP (EPFL)
•CHIPP (Swiss LHC Grid sine Aug. 2017)
•Others (exploratory)
T. Schulthess 7
CSCS vision for next generation systems
•Performance goal: develop a general purpose system (for all domains) with enough
performance to run “exascale weather and climate simulations” by 2022, specifically,
•Run global model with 1 km horizontal resolution at one simulated year per day
throughput on a system with similar footprint at Piz Daint;
•Functional goal: converged Cloud and HPC services in one infrastructure
•Support most native Cloud services on supercomputer replacing Piz Daint in 2022
•In particular, focus on software defined infrastructure (networking, storage and
compute) and service orientation
Pursue clear and ambitious goals for successor of Piz Daint
T. Schulthess 8
September 15, 2015
Today’s Outlook: GPU-accelerated Weather Forecasting
John Russell
“Piz Kesch”
Since April 2016, the Swiss version* of the COSMO model is running operationally on GPUs
(*) Swiss version of the COSMO model is running at
1km horizontal resolution over Alpine region and was
(in 2016) ~10x more efficient than the state of the art
T. Schulthess
MeteoSwiss’ performance ambitions in 2013
9
1
5
10
15
20
25
30
35
40
Constant budget for investments and operations
24x
Ensemble with multiple forecasts
Grid 2.2 km → 1.1 km
10x
Requirements from MeteoSwiss
Data assimilation
6x
We need a 40x improvement between 2012 and 2015 at constant cost
?
T. Schulthess
COSMO: old and new (refactored) code
10
main (current / Fortran)
physics
(Fortran)
dynamics (Fortran)
MPI
system
main (new / Fortran)
physics
(Fortran)
with OpenMP /
OpenACC
dynamics (C++)
MPI or whatever
system
Generic Comm.
Library
boundary
conditions & halo
exchg.
stencil library
X86* CUDA
Shared Infrastructure
ROCmPhi*
* two different OpenMP backends
T. Schulthess
Where the factor 40 improvement came from
11
1
5
10
15
20
25
30
35
40
Constant budget for investments and operations
Grid 2.2 km → 1.1 km
24x
Ensemble with multiple forecasts
Data assimilation
10x
1.7x from software refactoring (old vs. new implementation on x86)
2.8x Mathematical improvements (resource utilisation, precision)
2.8x Moore’s Law & arch. improvements on x86
2.3x Change in architecture (CPU → GPU)
1.3x additional processors
Requirements from MeteoSwiss
6x
Investment in software allowed mathematical improvements and change in architecture
There is no silver bullet!
Bonus: reduction in power!
T. Schulthess
Leadership in weather and climate
12
European model may be the best – but far away from
sufficient accuracy and reliability!
Peter Bauer, ECMWF
T. Schulthess
Structural convergence
Statistics of cloud ensemble:
E.g., spacing and size of convective clouds
Bulk convergence
Area-averaged bulk effects upon ambient flow:
E.g., heating and moistening of cloud layer
Resolving convective clouds (convergence?)
13
Source: Christoph Schär, ETH Zurich
T. Schulthess
Structural and bulk convergence
14
Source: Christoph Schär, ETH Zurich
Statistics of cloud area Statistics of up- & downdrafts
No structural convergence Bulk statistics of updrafts converges
Factor 4
(Panosetti et al. 2018)
T. Schulthess 15
Source: Christoph Schär, ETH Zurich, & Nils Wedi, ECMWF
Can the delivery of a 1km-scale
capability be pulled in by a decade?
T. Schulthess
Our “exascale” goal for 2022
16
Horizontal resolution 1 km (globally quasi-uniform)
Vertical resolution 180 levels (surface to ~100 km)
Time resolution Less than 1 minute
Coupled Land-surface/ocean/ocean-waves/sea-ice
Atmosphere Non-hydrostatic
Precision Single (32bit) or mixed precision
Compute rate 1 SYPD (simulated year wall-clock day)
T. Schulthess
Running COSMO 5.0 & IFS (“the European Model”) at global scale on Piz Daint
17
Scaling to full system size: ~5300 GPU accelerate nodes available
Running a near-global (±80º covering 97% of Earths surface) COSMO 5.0 simulation & IFS
> Either on the hosts processors: Intel Xeon E5 2690v3 (Haswell 12c).
> Or on the GPU accelerator: PCIe version of NVIDIA GP100 (Pascal) GPU
T. Schulthess
The baseline for COSMO-global and IFS
18
T. Schulthess
Memory use efficiency
19
Necessary data transfers
Actual data transfers
Fuhrer et al., Geosci. Model Dev. Discuss., https://doi.org/10.5194/gmd-2017-230, published 2018
Achieved BW
Max achievable BW
(STREAM)
0.88
0.76
= 0.67
2x lower than peak BW
0.55 w. regard to
peak BW
T. Schulthess
Can the 100x shortfall of a grid-based implementation like COSMO-global be overcome?
20
1. Icosahedral/octahedral grid (ICON/IFS) vs. Lat-long/Cartesian grid (COSMO)
2x fewer grid-columns
Time step of 10 ms instead of 5 ms
4x
2. Improving BW efficiency
Improve BW efficiency and peak BW 2x
(results on Volta show this is realistic)
3. Strong scaling
4x possible in COSMO, but we reduced
available parallelism by factor 1.33
3x
4. Remaining reduction in shortfall 4x
Numerical algorithms (larger time steps)
Further improved processors / memory
But we don’t want to increase the footprint of the 2022 system succeeding “Piz Daint”
100x
T. Schulthess
What about ensembles and throughput for climate?
(Remaining goals beyond 2022)
21
1. Improve the throughput to 5 SYPD
2. Reduce the footprint of a single simulation by up to factor 10-50
Necessary data transfers
Actual data transfers
Achieved BW
Max achievable BW
Change the architecture from control flow to data flow centric (reduce necessary data transfers)
We may have to change the footprint of machines to hyper scale!
T. Schulthess 22
LUMI Consortium
•Large consortium with strong national HPC centres and competence
provides a unique opportunity for
•knowledge transfer;
•synergies in operations; and
•regionally adaptable user support for extreme-scale systems
•National & EU investments (2020-2026)
Finland 50 M€
Belgium 15.5 M€
Czech Republic 5 M€
Denmark 6 M€
Estonia 2 M€
Norway 4 M€
Poland 5 M€
Sweden 7 M€
Switzerland 10 M€
EU 104 M€
Plus additional investments in applications development
T. Schulthess
Kajaani Data Center (LUMI)
23
100% hydroelectric energy up to 200 MW
2200 m2 floor space, expandable up to 4600 m2
Waste heat reuse: effective energy price 35 €/MWh,
negative CO2 footprint: 13500 tons reduced every year
One power grid outage in 36 years
100% free cooling @ PUE 1.03
Extreme connectivity:
Kajaani DC is a direct part of the Nordic backbone; 4x100
Gbit/s in place; can be easily scaled up to multi-terabit level
Zero network downtime since the establishment of the DC in 2012
T. Schulthess
Collaborators on Exascale (climate)
24
Tim Palmer (U. of Oxford)
Christoph Schar (ETH Zurich)
Oliver Fuhrer (MeteoSwiss)
Peter Bauer (ECMWF)
Bjorn Stevens (MPI-M)
Torsten Hoefler (ETH Zurich)Nils Wedi (ECMWF)
T. Schulthess 25
Thank you!

More Related Content

PDF
DSD-INT 2015 - 3Di pilot application in Taiwan - Jhih-Cyuan Shen, Geert Prinsen
PDF
Fog Computing for Dummies
PDF
Access to Open Earth Observation Data, an Overview and Outlook Raymond Sluit...
PPTX
Raster processing
PDF
Using a Widely Distributed Federated Cloud System to Support Multiple Dispara...
PPTX
Watershed Delineation in ArcGIS
PPT
Introduction to STILT – an on-demand CO2 footprint calculator service
PDF
DSD-INT 2015 - 3Di pilot application in Taiwan - Jhih-Cyuan Shen, Geert Prinsen
Fog Computing for Dummies
Access to Open Earth Observation Data, an Overview and Outlook Raymond Sluit...
Raster processing
Using a Widely Distributed Federated Cloud System to Support Multiple Dispara...
Watershed Delineation in ArcGIS
Introduction to STILT – an on-demand CO2 footprint calculator service

What's hot (17)

PPTX
AHM 2014: The Flow Simulation Tools on VHub
PPTX
Inspire Compliant Weather Data
PDF
Nuclear emergency response and Big Data technologies
PPTX
SmartMet Server OSGeo
PPTX
069MSW405_Devendra Tamrakar_Presentation
PPTX
1 catchment delineation.ppt
PPTX
Producing INSPIRE compliant datasets
PDF
Optimising Service Deployment and Infrastructure Resource Configuration
PDF
Software for the Hydrographic ocean
PDF
Accès ouvert aux données météorologiques d’Environnement Canada
PPTX
Possibilities of Open Source Code
PDF
Fibre footprint-for-research-infrastructures
PPTX
Watershed Delineation Using ArcMap
PPTX
FMI Open Data Interface and Usage
PPT
Change detection
PDF
Big Linked Data Querying - ExtremeEarth Open Workshop
PPT
3D Analyst - Cut and Fill
AHM 2014: The Flow Simulation Tools on VHub
Inspire Compliant Weather Data
Nuclear emergency response and Big Data technologies
SmartMet Server OSGeo
069MSW405_Devendra Tamrakar_Presentation
1 catchment delineation.ppt
Producing INSPIRE compliant datasets
Optimising Service Deployment and Infrastructure Resource Configuration
Software for the Hydrographic ocean
Accès ouvert aux données météorologiques d’Environnement Canada
Possibilities of Open Source Code
Fibre footprint-for-research-infrastructures
Watershed Delineation Using ArcMap
FMI Open Data Interface and Usage
Change detection
Big Linked Data Querying - ExtremeEarth Open Workshop
3D Analyst - Cut and Fill
Ad

Similar to An Update on CSCS (20)

PPTX
Gergely Sipos (EGI): Exploiting scientific data in the international context ...
PDF
Overview of the FlexPlan project. Focus on EU regulatory analysis and TSO-DSO...
PDF
CloudLightning - Project and Architecture Overview
PDF
LCG project description
PDF
Data analytics and downscaling for climate research in a big data world
PDF
Using the Open Science Data Cloud for Data Science Research
PDF
IoT Meetup Budapest - The Open-CPS approach
PDF
This Helix Nebula Science Cloud Pilot Phase Open Session
PDF
Designing HPC Architectures at the Barcelona Supercomputing Center
PPTX
Volunteer Crowd Computing and Federated Cloud developments
PDF
Linking EUDAT services to the EGI Fed-Cloud - EUDAT Summer School (Hans van P...
PPTX
Jorge gomes
PPTX
Jorge gomes
PPTX
Jorge gomes
PDF
ICT4S - Green cloud? the current and future development of energy consumption...
PPTX
eROSA Policy WS2: European Open Science Cloud (EOSC) - The Perspective of e-I...
PDF
CloudLightning and the OPM-based Use Case
PDF
El nuevo superordenador Mare Nostrum y el futuro procesador europeo
PDF
Flexibility needs at system level and how RD&I projects are leveraging these ...
PPT
SomeSlides
Gergely Sipos (EGI): Exploiting scientific data in the international context ...
Overview of the FlexPlan project. Focus on EU regulatory analysis and TSO-DSO...
CloudLightning - Project and Architecture Overview
LCG project description
Data analytics and downscaling for climate research in a big data world
Using the Open Science Data Cloud for Data Science Research
IoT Meetup Budapest - The Open-CPS approach
This Helix Nebula Science Cloud Pilot Phase Open Session
Designing HPC Architectures at the Barcelona Supercomputing Center
Volunteer Crowd Computing and Federated Cloud developments
Linking EUDAT services to the EGI Fed-Cloud - EUDAT Summer School (Hans van P...
Jorge gomes
Jorge gomes
Jorge gomes
ICT4S - Green cloud? the current and future development of energy consumption...
eROSA Policy WS2: European Open Science Cloud (EOSC) - The Perspective of e-I...
CloudLightning and the OPM-based Use Case
El nuevo superordenador Mare Nostrum y el futuro procesador europeo
Flexibility needs at system level and how RD&I projects are leveraging these ...
SomeSlides
Ad

More from inside-BigData.com (20)

PDF
Major Market Shifts in IT
PDF
Preparing to program Aurora at Exascale - Early experiences and future direct...
PPTX
Transforming Private 5G Networks
PDF
The Incorporation of Machine Learning into Scientific Simulations at Lawrence...
PDF
How to Achieve High-Performance, Scalable and Distributed DNN Training on Mod...
PDF
Evolving Cyberinfrastructure, Democratizing Data, and Scaling AI to Catalyze ...
PDF
HPC Impact: EDA Telemetry Neural Networks
PDF
Biohybrid Robotic Jellyfish for Future Applications in Ocean Monitoring
PDF
Machine Learning for Weather Forecasts
PPTX
HPC AI Advisory Council Update
PDF
Fugaku Supercomputer joins fight against COVID-19
PDF
Energy Efficient Computing using Dynamic Tuning
PDF
HPC at Scale Enabled by DDN A3i and NVIDIA SuperPOD
PDF
State of ARM-based HPC
PDF
Versal Premium ACAP for Network and Cloud Acceleration
PDF
Zettar: Moving Massive Amounts of Data across Any Distance Efficiently
PDF
Scaling TCO in a Post Moore's Era
PDF
CUDA-Python and RAPIDS for blazing fast scientific computing
PDF
Introducing HPC with a Raspberry Pi Cluster
PDF
Overview of HPC Interconnects
Major Market Shifts in IT
Preparing to program Aurora at Exascale - Early experiences and future direct...
Transforming Private 5G Networks
The Incorporation of Machine Learning into Scientific Simulations at Lawrence...
How to Achieve High-Performance, Scalable and Distributed DNN Training on Mod...
Evolving Cyberinfrastructure, Democratizing Data, and Scaling AI to Catalyze ...
HPC Impact: EDA Telemetry Neural Networks
Biohybrid Robotic Jellyfish for Future Applications in Ocean Monitoring
Machine Learning for Weather Forecasts
HPC AI Advisory Council Update
Fugaku Supercomputer joins fight against COVID-19
Energy Efficient Computing using Dynamic Tuning
HPC at Scale Enabled by DDN A3i and NVIDIA SuperPOD
State of ARM-based HPC
Versal Premium ACAP for Network and Cloud Acceleration
Zettar: Moving Massive Amounts of Data across Any Distance Efficiently
Scaling TCO in a Post Moore's Era
CUDA-Python and RAPIDS for blazing fast scientific computing
Introducing HPC with a Raspberry Pi Cluster
Overview of HPC Interconnects

Recently uploaded (20)

PDF
Network Security Unit 5.pdf for BCA BBA.
PDF
A comparative analysis of optical character recognition models for extracting...
PDF
Architecting across the Boundaries of two Complex Domains - Healthcare & Tech...
PDF
Advanced methodologies resolving dimensionality complications for autism neur...
PPTX
Cloud computing and distributed systems.
PDF
Diabetes mellitus diagnosis method based random forest with bat algorithm
PPTX
sap open course for s4hana steps from ECC to s4
PDF
Empathic Computing: Creating Shared Understanding
PPTX
KOM of Painting work and Equipment Insulation REV00 update 25-dec.pptx
PPTX
Digital-Transformation-Roadmap-for-Companies.pptx
PDF
Encapsulation theory and applications.pdf
PPTX
MYSQL Presentation for SQL database connectivity
PPTX
Machine Learning_overview_presentation.pptx
PDF
Building Integrated photovoltaic BIPV_UPV.pdf
PPT
Teaching material agriculture food technology
PDF
7 ChatGPT Prompts to Help You Define Your Ideal Customer Profile.pdf
DOCX
The AUB Centre for AI in Media Proposal.docx
PDF
Build a system with the filesystem maintained by OSTree @ COSCUP 2025
PDF
Per capita expenditure prediction using model stacking based on satellite ima...
PPTX
VMware vSphere Foundation How to Sell Presentation-Ver1.4-2-14-2024.pptx
Network Security Unit 5.pdf for BCA BBA.
A comparative analysis of optical character recognition models for extracting...
Architecting across the Boundaries of two Complex Domains - Healthcare & Tech...
Advanced methodologies resolving dimensionality complications for autism neur...
Cloud computing and distributed systems.
Diabetes mellitus diagnosis method based random forest with bat algorithm
sap open course for s4hana steps from ECC to s4
Empathic Computing: Creating Shared Understanding
KOM of Painting work and Equipment Insulation REV00 update 25-dec.pptx
Digital-Transformation-Roadmap-for-Companies.pptx
Encapsulation theory and applications.pdf
MYSQL Presentation for SQL database connectivity
Machine Learning_overview_presentation.pptx
Building Integrated photovoltaic BIPV_UPV.pdf
Teaching material agriculture food technology
7 ChatGPT Prompts to Help You Define Your Ideal Customer Profile.pdf
The AUB Centre for AI in Media Proposal.docx
Build a system with the filesystem maintained by OSTree @ COSCUP 2025
Per capita expenditure prediction using model stacking based on satellite ima...
VMware vSphere Foundation How to Sell Presentation-Ver1.4-2-14-2024.pptx

An Update on CSCS

  • 1. T. Schulthess Thomas C. Schulthess 1 An update on CSCS
  • 2. T. Schulthess ETH Domain 2 Lausanne Basel Thoune Villigen Birmensdorf Zürich Dübendorf St. Gallen Kastanienbaum Bellinzona Lugano- Cornaredo Davos Neuchâtel Sion ETH Zurich EPFL, Lausanne PSI WSL Empa Eawag
  • 3. T. Schulthess 3 Centro Svizzero di Calcolo Scientifico (CSCS) The Swiss National Supercomputing Center • Established in 1991 as a unit of ETH Zurich • Located in Lugano, Ticino • 115 highly qualified staff (25f) from 26 nations • Flexible Infrastructure: Power/cooling: 12MW, upgradable to 25MW • Develops & operates the key supercomputing capabilities required to solve important problems to science and/or society • A research infrastructure with ~2000 users, 200 projects • Leads the national strategy for High-Performance Computing and Networking (HPCN) that was passed by Swiss Parliament in 2009 • Has a dedicated User Laboratory for supercomputing since 2011 (i.e. research infrastructure funded by the ETH Domain on a programmatic basis) • From 2017, tier-0 system of the “Partnership for Advanced Computing in Europe” (PRACE)
  • 4. T. Schulthess User Lab allocations 2018 – by research fields 4 node hours storage
  • 5. T. Schulthess User Lab allocations 2018 – by institutions 5
  • 6. T. Schulthess “Piz Daint” 2017 fact sheet 6 http://www.cscs.ch/publications/fact_sheets/index.html ~5’000 NVIDIA P100 GPU accelerated nodes ~1’400 Dual multi-core socket nodes Institutions using Piz Daint (in 2019) •User Lab (including PRACE Tier-0 allocations) •University of Zurich, USI, PSI, EMPA •NCCR MARVEL and HBP (EPFL) •CHIPP (Swiss LHC Grid sine Aug. 2017) •Others (exploratory)
  • 7. T. Schulthess 7 CSCS vision for next generation systems •Performance goal: develop a general purpose system (for all domains) with enough performance to run “exascale weather and climate simulations” by 2022, specifically, •Run global model with 1 km horizontal resolution at one simulated year per day throughput on a system with similar footprint at Piz Daint; •Functional goal: converged Cloud and HPC services in one infrastructure •Support most native Cloud services on supercomputer replacing Piz Daint in 2022 •In particular, focus on software defined infrastructure (networking, storage and compute) and service orientation Pursue clear and ambitious goals for successor of Piz Daint
  • 8. T. Schulthess 8 September 15, 2015 Today’s Outlook: GPU-accelerated Weather Forecasting John Russell “Piz Kesch” Since April 2016, the Swiss version* of the COSMO model is running operationally on GPUs (*) Swiss version of the COSMO model is running at 1km horizontal resolution over Alpine region and was (in 2016) ~10x more efficient than the state of the art
  • 9. T. Schulthess MeteoSwiss’ performance ambitions in 2013 9 1 5 10 15 20 25 30 35 40 Constant budget for investments and operations 24x Ensemble with multiple forecasts Grid 2.2 km → 1.1 km 10x Requirements from MeteoSwiss Data assimilation 6x We need a 40x improvement between 2012 and 2015 at constant cost ?
  • 10. T. Schulthess COSMO: old and new (refactored) code 10 main (current / Fortran) physics (Fortran) dynamics (Fortran) MPI system main (new / Fortran) physics (Fortran) with OpenMP / OpenACC dynamics (C++) MPI or whatever system Generic Comm. Library boundary conditions & halo exchg. stencil library X86* CUDA Shared Infrastructure ROCmPhi* * two different OpenMP backends
  • 11. T. Schulthess Where the factor 40 improvement came from 11 1 5 10 15 20 25 30 35 40 Constant budget for investments and operations Grid 2.2 km → 1.1 km 24x Ensemble with multiple forecasts Data assimilation 10x 1.7x from software refactoring (old vs. new implementation on x86) 2.8x Mathematical improvements (resource utilisation, precision) 2.8x Moore’s Law & arch. improvements on x86 2.3x Change in architecture (CPU → GPU) 1.3x additional processors Requirements from MeteoSwiss 6x Investment in software allowed mathematical improvements and change in architecture There is no silver bullet! Bonus: reduction in power!
  • 12. T. Schulthess Leadership in weather and climate 12 European model may be the best – but far away from sufficient accuracy and reliability! Peter Bauer, ECMWF
  • 13. T. Schulthess Structural convergence Statistics of cloud ensemble: E.g., spacing and size of convective clouds Bulk convergence Area-averaged bulk effects upon ambient flow: E.g., heating and moistening of cloud layer Resolving convective clouds (convergence?) 13 Source: Christoph Schär, ETH Zurich
  • 14. T. Schulthess Structural and bulk convergence 14 Source: Christoph Schär, ETH Zurich Statistics of cloud area Statistics of up- & downdrafts No structural convergence Bulk statistics of updrafts converges Factor 4 (Panosetti et al. 2018)
  • 15. T. Schulthess 15 Source: Christoph Schär, ETH Zurich, & Nils Wedi, ECMWF Can the delivery of a 1km-scale capability be pulled in by a decade?
  • 16. T. Schulthess Our “exascale” goal for 2022 16 Horizontal resolution 1 km (globally quasi-uniform) Vertical resolution 180 levels (surface to ~100 km) Time resolution Less than 1 minute Coupled Land-surface/ocean/ocean-waves/sea-ice Atmosphere Non-hydrostatic Precision Single (32bit) or mixed precision Compute rate 1 SYPD (simulated year wall-clock day)
  • 17. T. Schulthess Running COSMO 5.0 & IFS (“the European Model”) at global scale on Piz Daint 17 Scaling to full system size: ~5300 GPU accelerate nodes available Running a near-global (±80º covering 97% of Earths surface) COSMO 5.0 simulation & IFS > Either on the hosts processors: Intel Xeon E5 2690v3 (Haswell 12c). > Or on the GPU accelerator: PCIe version of NVIDIA GP100 (Pascal) GPU
  • 18. T. Schulthess The baseline for COSMO-global and IFS 18
  • 19. T. Schulthess Memory use efficiency 19 Necessary data transfers Actual data transfers Fuhrer et al., Geosci. Model Dev. Discuss., https://doi.org/10.5194/gmd-2017-230, published 2018 Achieved BW Max achievable BW (STREAM) 0.88 0.76 = 0.67 2x lower than peak BW 0.55 w. regard to peak BW
  • 20. T. Schulthess Can the 100x shortfall of a grid-based implementation like COSMO-global be overcome? 20 1. Icosahedral/octahedral grid (ICON/IFS) vs. Lat-long/Cartesian grid (COSMO) 2x fewer grid-columns Time step of 10 ms instead of 5 ms 4x 2. Improving BW efficiency Improve BW efficiency and peak BW 2x (results on Volta show this is realistic) 3. Strong scaling 4x possible in COSMO, but we reduced available parallelism by factor 1.33 3x 4. Remaining reduction in shortfall 4x Numerical algorithms (larger time steps) Further improved processors / memory But we don’t want to increase the footprint of the 2022 system succeeding “Piz Daint” 100x
  • 21. T. Schulthess What about ensembles and throughput for climate? (Remaining goals beyond 2022) 21 1. Improve the throughput to 5 SYPD 2. Reduce the footprint of a single simulation by up to factor 10-50 Necessary data transfers Actual data transfers Achieved BW Max achievable BW Change the architecture from control flow to data flow centric (reduce necessary data transfers) We may have to change the footprint of machines to hyper scale!
  • 22. T. Schulthess 22 LUMI Consortium •Large consortium with strong national HPC centres and competence provides a unique opportunity for •knowledge transfer; •synergies in operations; and •regionally adaptable user support for extreme-scale systems •National & EU investments (2020-2026) Finland 50 M€ Belgium 15.5 M€ Czech Republic 5 M€ Denmark 6 M€ Estonia 2 M€ Norway 4 M€ Poland 5 M€ Sweden 7 M€ Switzerland 10 M€ EU 104 M€ Plus additional investments in applications development
  • 23. T. Schulthess Kajaani Data Center (LUMI) 23 100% hydroelectric energy up to 200 MW 2200 m2 floor space, expandable up to 4600 m2 Waste heat reuse: effective energy price 35 €/MWh, negative CO2 footprint: 13500 tons reduced every year One power grid outage in 36 years 100% free cooling @ PUE 1.03 Extreme connectivity: Kajaani DC is a direct part of the Nordic backbone; 4x100 Gbit/s in place; can be easily scaled up to multi-terabit level Zero network downtime since the establishment of the DC in 2012
  • 24. T. Schulthess Collaborators on Exascale (climate) 24 Tim Palmer (U. of Oxford) Christoph Schar (ETH Zurich) Oliver Fuhrer (MeteoSwiss) Peter Bauer (ECMWF) Bjorn Stevens (MPI-M) Torsten Hoefler (ETH Zurich)Nils Wedi (ECMWF)