SlideShare a Scribd company logo
GROUP 4
Chris Miner
Sabah Tasnuva
Tingting Liu
Nicholas Johnson
PROJECT
0
What Is The Big Dig?
OLD CENTRAL ARTERY (I-
93)
NEW CENTRAL ARTERY (I-93)
6 Lane Elevated Artery 8-10 Lane State of the Art
Underground Highway
“Largest, most complex, and technologically challenging highway
project in the history of the United States”
-Solution To Boston’s Traffic Problem
-Reconnect Waterfront Towns To Downtown
BRIDGES TUNNELS
Leonard P. Zakim Bunker Hill Ted Williams Tunnel
Leverett Circle Connector Thomas P. O’Neill Jr.
Widest Cable-Stayed Bridge
WHY WE CHOSE “THE BIG DIG”
TRANSPORTATION LOCAL PROJECT
Tunnels Classmates Can Relate
Bridges Classmates Have Seen It
Highways Classmates Have Used It
A Big Part of Civil Engineering Involves Transportation
WHAT DID IT TAKE TO COMPLETE “THE BIG
DIG”?
1982-Environmental Impact Documents
2007- Restoration of City Streets
7.8 miles of highway, 161 lanes miles
3.8 million cubic yards of concrete
More than 16 million cubic yards of soil excavated
1999 through 2002, about $3 million of work completed each day
About 5,000 construction workers were on the job
Jay Cashman, Modern Continental
118 separate construction contracts, with 26 geotechnical drilling contracts.
22 billion
Bigdig project
CONSTRUCTION PROBLEMS
Faulty Loose Fixtures:
September 2004
- Water seeps through traffic barriers in Interstate 93 tunnel
-Workers sandbagged one wall
-Independent engineers hired to study problem
-Reported that the tunnels may have more than 400 leaks
July 2006
-39-year-old woman killed after 12 tons of cement ceiling panels fell
on car.
-Lead to investigation where federal and state officials uncovered
additional problems almost on a daily basis
Bechtel: engineering, construction and management company’s reputation damaged
FINANCIAL PROBLEMS
- Over the course of the Project, costs kept increasing
- 2.6 Billion to 22 Billion
- Taxpayers ended up paying half of the project’s cost
ENVIRONMENTAL ISSUES
-Downtown area through which the tunnels were to be dug
was largely landfill and included existing subway lines as
well as innumerable pipes and utility lines that would have
to be replaced or moved.
-Tunnel workers encountered many unexpected geological
and archaeological barriers
-Glacial debris
- Foundations of buried houses and sunken
ships

More Related Content

PPTX
Project Complexity (Case study)
PDF
BigDig_KeyFacts_Dec2006
PPTX
Rick presentation about central artery for stephaine pollocks class
PPTX
Big dig powerpoint
PPTX
LYNX Blue Line Extension Construction Update
PDF
Story_2_Kosciuszko_Bridge
PPTX
Lee Highway, U.S. Route 29 Phase III Widening
PPTX
Innovations of civil engineering
Project Complexity (Case study)
BigDig_KeyFacts_Dec2006
Rick presentation about central artery for stephaine pollocks class
Big dig powerpoint
LYNX Blue Line Extension Construction Update
Story_2_Kosciuszko_Bridge
Lee Highway, U.S. Route 29 Phase III Widening
Innovations of civil engineering

What's hot (20)

PPTX
Advancement in infrastructure
PDF
Construction Choreography
PPT
A+DS Sustainable Placemaking 3 - Placemaking Briefs by design: Dundee Design ...
PPT
Civil engineering
PDF
Greening of concrete trends & priorities
PPTX
Miami-Dade MPO 2015 Transportation Summit Presentation
PPTX
Civil engineering
PDF
LTC_Lovell_SAME_E&S_Webinar_FEB_16_Final
PPTX
History of road
PDF
Bridge
PPTX
Challenges for civil engineers
PPTX
Introduction to Civil Engineering
PPTX
Introduction to Civil Engineering
PPTX
Tempe Town Lake Pedestrian Bridge
PPTX
Civil10
PDF
Societal Impact of the Seismic Retrofit Project of the Dumbarton Bridge, CA
PPTX
Njf redevelopment forum 2018 heydt ignite
PPTX
Advanced Type Civil Engineering Structures
PPTX
progress in civil engg by aatif sadiq
PDF
[PDF]PROJECT ON HIGHWAY BY SUBHENDU SAMUI
Advancement in infrastructure
Construction Choreography
A+DS Sustainable Placemaking 3 - Placemaking Briefs by design: Dundee Design ...
Civil engineering
Greening of concrete trends & priorities
Miami-Dade MPO 2015 Transportation Summit Presentation
Civil engineering
LTC_Lovell_SAME_E&S_Webinar_FEB_16_Final
History of road
Bridge
Challenges for civil engineers
Introduction to Civil Engineering
Introduction to Civil Engineering
Tempe Town Lake Pedestrian Bridge
Civil10
Societal Impact of the Seismic Retrofit Project of the Dumbarton Bridge, CA
Njf redevelopment forum 2018 heydt ignite
Advanced Type Civil Engineering Structures
progress in civil engg by aatif sadiq
[PDF]PROJECT ON HIGHWAY BY SUBHENDU SAMUI
Ad

Similar to Bigdig project (20)

PPTX
Big dig powerpoint
PPTX
Interstate Highway
PPTX
Project 2 north central expy-high 5 interchange 092210
PPTX
Underground construction
PPT
Bernstein Street History
PDF
Priority List Infrastructure Projects
PDF
Priority List Infrastructure Projects
PDF
UNDERGROUND STRUCTURES AND IT'S ENVIRONMENTAL IMPACTS.IT'S
PDF
NORTH AMERICAN TUNNELING 2004 1st Edition Levent. Ozdemir
PDF
Water_Intrusion
PPTX
UNDERGROUND-CONSTRUCTION.pptx
PPTX
Tunneling
PDF
NORTH AMERICAN TUNNELING 2004 1st Edition Levent. Ozdemir
PDF
PPT-Civil-Engineering-Introduction-Global-Socital-Impact.pdf
PDF
PPT-Civil-Engineering-Introduction-Global-Socital-Impact.pdf
DOC
Henn, Ray (LONG) w-o PhD 2014 (NEW)
PPTX
History & Theory of Planning: Postmodern Critiques of Modernism
PPTX
Final acec design summit pres 2017
PPT
Extension of Metro's Purple line.
PPTX
History of civil engineering
Big dig powerpoint
Interstate Highway
Project 2 north central expy-high 5 interchange 092210
Underground construction
Bernstein Street History
Priority List Infrastructure Projects
Priority List Infrastructure Projects
UNDERGROUND STRUCTURES AND IT'S ENVIRONMENTAL IMPACTS.IT'S
NORTH AMERICAN TUNNELING 2004 1st Edition Levent. Ozdemir
Water_Intrusion
UNDERGROUND-CONSTRUCTION.pptx
Tunneling
NORTH AMERICAN TUNNELING 2004 1st Edition Levent. Ozdemir
PPT-Civil-Engineering-Introduction-Global-Socital-Impact.pdf
PPT-Civil-Engineering-Introduction-Global-Socital-Impact.pdf
Henn, Ray (LONG) w-o PhD 2014 (NEW)
History & Theory of Planning: Postmodern Critiques of Modernism
Final acec design summit pres 2017
Extension of Metro's Purple line.
History of civil engineering
Ad

Recently uploaded (20)

PPTX
VERNACULAR_DESIGN_PPT FINAL WITH PROPOSED PLAN.pptx
PPTX
8086.pptx microprocessor and microcontroller
PPTX
Introduction to Building Information Modeling
PDF
trenching-standard-drawings procedure rev
PPTX
Acoustics new for. Sound insulation and absorber
PPTX
22CDO02-IMGD-UNIT-I-MOBILE GAME DESIGN PROCESS
PDF
Architecture Design Portfolio- VICTOR OKUTU
PPTX
22CDH01-V3-UNIT-I INTRODUCITON TO EXTENDED REALITY
PPTX
CLASS_11_BUSINESS_STUDIES_PPT_CHAPTER_1_Business_Trade_Commerce.pptx
PDF
Chalkpiece Annual Report from 2019 To 2025
PPTX
Final Presentation of Reportttttttttttttttt
PDF
The Complete Guide to Buying Verified Stripe Accounts 2025.pdf
PDF
Test slideshare presentation for blog post
PDF
intro_to_rust.pptx_123456789012446789.pdf
PPT
WHY_R12 Uaafafafpgradeaffafafafaffff.ppt
PDF
1 Introduction to Networking (06).pdfbsbsbsb
PPTX
Evolution_of_Computing_Presentation (1).pptx
PPTX
URBAN FINANCEnhynhynnnytnynnnynynyynynynyn
PPTX
Necrosgwjskdnbsjdmdndmkdndndnmdndndkdmdndkdkndmdmis.pptx
PPT
robotS AND ROBOTICSOF HUMANS AND MACHINES
VERNACULAR_DESIGN_PPT FINAL WITH PROPOSED PLAN.pptx
8086.pptx microprocessor and microcontroller
Introduction to Building Information Modeling
trenching-standard-drawings procedure rev
Acoustics new for. Sound insulation and absorber
22CDO02-IMGD-UNIT-I-MOBILE GAME DESIGN PROCESS
Architecture Design Portfolio- VICTOR OKUTU
22CDH01-V3-UNIT-I INTRODUCITON TO EXTENDED REALITY
CLASS_11_BUSINESS_STUDIES_PPT_CHAPTER_1_Business_Trade_Commerce.pptx
Chalkpiece Annual Report from 2019 To 2025
Final Presentation of Reportttttttttttttttt
The Complete Guide to Buying Verified Stripe Accounts 2025.pdf
Test slideshare presentation for blog post
intro_to_rust.pptx_123456789012446789.pdf
WHY_R12 Uaafafafpgradeaffafafafaffff.ppt
1 Introduction to Networking (06).pdfbsbsbsb
Evolution_of_Computing_Presentation (1).pptx
URBAN FINANCEnhynhynnnytnynnnynynyynynynyn
Necrosgwjskdnbsjdmdndmkdndndnmdndndkdmdndkdkndmdmis.pptx
robotS AND ROBOTICSOF HUMANS AND MACHINES

Bigdig project

  • 1. GROUP 4 Chris Miner Sabah Tasnuva Tingting Liu Nicholas Johnson PROJECT 0
  • 2. What Is The Big Dig? OLD CENTRAL ARTERY (I- 93) NEW CENTRAL ARTERY (I-93) 6 Lane Elevated Artery 8-10 Lane State of the Art Underground Highway “Largest, most complex, and technologically challenging highway project in the history of the United States” -Solution To Boston’s Traffic Problem -Reconnect Waterfront Towns To Downtown
  • 3. BRIDGES TUNNELS Leonard P. Zakim Bunker Hill Ted Williams Tunnel Leverett Circle Connector Thomas P. O’Neill Jr. Widest Cable-Stayed Bridge
  • 4. WHY WE CHOSE “THE BIG DIG” TRANSPORTATION LOCAL PROJECT Tunnels Classmates Can Relate Bridges Classmates Have Seen It Highways Classmates Have Used It A Big Part of Civil Engineering Involves Transportation
  • 5. WHAT DID IT TAKE TO COMPLETE “THE BIG DIG”? 1982-Environmental Impact Documents 2007- Restoration of City Streets 7.8 miles of highway, 161 lanes miles 3.8 million cubic yards of concrete More than 16 million cubic yards of soil excavated 1999 through 2002, about $3 million of work completed each day About 5,000 construction workers were on the job Jay Cashman, Modern Continental 118 separate construction contracts, with 26 geotechnical drilling contracts. 22 billion
  • 7. CONSTRUCTION PROBLEMS Faulty Loose Fixtures: September 2004 - Water seeps through traffic barriers in Interstate 93 tunnel -Workers sandbagged one wall -Independent engineers hired to study problem -Reported that the tunnels may have more than 400 leaks
  • 8. July 2006 -39-year-old woman killed after 12 tons of cement ceiling panels fell on car. -Lead to investigation where federal and state officials uncovered additional problems almost on a daily basis Bechtel: engineering, construction and management company’s reputation damaged
  • 9. FINANCIAL PROBLEMS - Over the course of the Project, costs kept increasing - 2.6 Billion to 22 Billion - Taxpayers ended up paying half of the project’s cost ENVIRONMENTAL ISSUES -Downtown area through which the tunnels were to be dug was largely landfill and included existing subway lines as well as innumerable pipes and utility lines that would have to be replaced or moved. -Tunnel workers encountered many unexpected geological and archaeological barriers -Glacial debris - Foundations of buried houses and sunken ships