SlideShare a Scribd company logo
“Big Dig” Project
THE CENTRAL ARTERY/TUNNEL PROJECT (CA/T)
A CASE STUDY ON PROJECT COMPLEXITY.
Project Description
Located in Boston, MA, on the
northeast coast of the United
States.
 Includes tunnels, highway
interchange connections, bridges
and pedestrian facilities
Project Map
Project Description
Rerouted the Central Artery (Interstate 93),
into a 3.5-mile (5.6-km) tunnel.
 Construction of the Ted Williams Tunnel.
 Construction of the Leonard P. Zakim Bunker
Hill Memorial Bridge over the Charles River.
 Construction of the Rose Kennedy
Greenway in the space vacated by the
previous I-93 elevated roadway.
Project Description
 Planning Phase started in 1982
 Construction work – 1991-2006
 Estimated Completion - 1998
 Actual Completion – Dec 31, 2007
Estimated Cost - $2.8 billion
Final Cost - $14.6 billion
Cost over run – 190%
Official project owner - Massachusetts
Turnpike Authority
 Joint venture of Bechtel and Parson
Brinkerhoff
Source: http://www.roadtraffic-technology.com
Why Boston Needed the Big Dig?
Traffic improvements and
substantial reductions in
congestion
 Improving mobility in
downtown Boston
 Reconnect neighborhoods
severed by the old elevated
highway
Source: http://www.massdot.state.ma.us
Central Artery: Before and After
Source:http://www.bigdig.com
Problems faced
Escalating costs
Scheduling overruns
Design flaws
Charges of poor execution and use of
substandard materials
Fatal Ceiling Collapse
Criminal arrests and one death
Source: http://www.roadtraffic-technology.com
Complexity Factors - Cost
Contingency Usage
◦ Construction Contracts
◦ Management Contingency
◦ Massachusetts Turnpike Authority CEO Contingency
Risk Analysis
◦ Location
◦ Utilities
Estimate Formation
◦ Ted Williams Tunnel
◦ Zakim Bunker Hill Bridge
◦ Center Artery (I-93)
Complexity Factors - Cost
Figure. Big Dig Project Cost Growth (National Research Council 2003)
55%
15%
8%
7%
5%
3%
2%
5% Inflation
Environmental/Mitigation
Scope Growth
Accounting Changes
Traffic
Schedule Maintenance
Contingency for Unknowns
Other
Complexity Factors - Schedule
Timeline Requirements
◦ Community Conflicts
Milestones
Schedule Control
◦ Software Programs
Complexity Factors - Technical
Scope of Project
Owner’s Internal Structure
Design Method
Complexity Factors - Context
Public
◦ Economic Value of Boston
Utility Coordination
◦ 29 Miles of Underground Utility Relocation and Updating
Land Use Impact
◦ 300 acres of Green Space
Complexity Factors - Financing
Federal Funding
State Funding
Borrowing Against Future Funding
Project Dimension Complexity
Ranking
DIMENSION RANK
Context 5
Cost 4
Technical 3
Financing 2
Schedule 1
Project Dimension Complexity
Rating
DIMENSIONS SCALE (0 – 100)
Cost Dimension
Complexity
99
Schedule Dimension
Complexity
90
Technical Dimension Complexity 95
Context
Dimension Complexity
100
Financing Dimension Complexity 92
Complexity Map
The Big Dig Project
0
10
20
30
40
50
60
70
80
90
100
Technical
Cost
FinancingContext
Schedule
Critical Planning and
Analysis Methods
Method 1: Define Critical Success Factors
◦ Community Needs
◦ Political Restrictions
◦ Federal and State Funding
◦ Major Project Components
◦ Center Artery (I-93)
◦ Ted Williams Tunnel
◦ Zakim Bunker Hill Bridge
Method 2: Assemble Project Team
Communication
Collaboration
◦ Example
◦ Ted Williams Tunnel Ceiling Panel Collapse
Method 3: Project Arrangements
Design-Bid-Build
Value Engineering
Dispute Resolution
Dispute Resolution Board
Method 4: Early Cost Model
and Finance Plan
Incorrect Initial Cost Model and Finance Plan
The cost model would have included
◦ Inflation
◦ Project Risk- Account for Cost Overruns
◦ More detail over Design Costs
Method 5: Develop
Project Action Plans
Major Obstacles
◦ Restrictive Legislation
◦ Acquisition of ROW
◦ Cooperation of Utilities
◦ Community Support
Tools for Managing Complex Projects
The following tools were used in the Big Dig Project:
•Public involvement plan
•Critical permit issues
•Offsite fabrication
•Co-locate team
•Dispute resolution plan
Public Involvement Plan
◦ Project planners worked with community groups, government & business leaders to
create a consensus of how the project would be built
◦ Mitigation: The process of keeping the city open and making certain all
affected groups would be treated fairly
◦ Informed, organized interest groups press for their demands
◦ Public involvement plan produces early project wins of consensus but at the
expense of late project soaring project costs
Critical Permit Issues
◦ Bechtel/Parsons Brinkerhoff (B/PB):
◦ Engineering authority that approved, permitted, and released designs for construction
◦ Construction managers in charge of contractors & sub-contractors
◦ B/PB operated the project with the philosophy of getting this done, ask questions later
◦ Many plans that were permitted and released for construction were incomplete, contained
numerous errors, and lacked proper subsurface exploration
◦ The lax oversight produced an estimated $750 million in construction over-runs
Offsite Fabrication
◦ Utilized successfully on the CA/T project
◦ Several examples are:
◦ Immersed steel tubes for the Ted Williams Tunnel
◦ Steel box girder sections for the Bunker Hill Bridge
◦ Utilized successfully on the CA/T project
◦ Offsite fabrication of box girders and steel tubes produced accurate sections per specification that could
be test connected at the factory to insure smooth and timely installation
◦ Quicker assembly time at the job site with smaller construction crews as compared to onsite fabrication
◦ Exposure of construction workers to difficult job environments was reduced as compared to onsite
fabrication
Co-Locate Team
◦ Co-Locate elements of the project team to produce a cohesive team effort to complete a project
◦ Perhaps the most controversial tool
◦ In 1998, State of Massachusetts combined B/PB with state workers into one integrated project
organization
◦ Massachusetts Turnpike Authority was at the top of the organization chart
◦ State of Massachusetts designated B/PB as “owner’s representative” in several instances
◦ Who is in charge?
Dispute Resolution Plan
◦ Two noteworthy dispute resolution plan techniques were utilized on the CA/T project:
◦ Partnering
◦ Mediation
◦ Partnering was practiced on the CA/T project for construction projects with a duration of least
one year and a value of $1 million or more
◦ Mediation was utilized to resolve the dispute of responsibility for leaks at the Fort Point
Channel tunnel area
References
◦ Bartlett School of Planning (UCL). (2011). “The Central Artery/Third Harbor Tunnel Project (‘The Big Dig’), Omega Centre.” Bloomsbury, London.
◦ Gelinas, N. (2007). “Lessons of Boston’s Big Dig.” City Journal Autumn. New York, New York.
◦ Greirman, V. (2010). “The Big Dig: Learning from a Mega Project.” NASA, <http://appel.nasa.gov/2010/07/15/the-big-dig-learning-from-a-mega-project/>
(November 13, 2013).
◦ Hsu, J. Mckay, S., McKnight, M. (2003). “Cost-Benefit Analysis of Boston’s Central Artery/Tunnel Project” Carnegie Mello University. Pittsburgh, PA.
◦ Lewis, R. and Murphy, S. (2003). “Artery Errors Cost More Than $1b.” The Boston Globe, <http://www.boston.com/globe/metro/packages/bechtel/>
(November 13, 2013).
◦ Massachusetts Department of Transportation (MassDOT). (2013). “The Central Artery/Tunnel Project-The Big Dig.” MassDOT Highway Division.
<http://www.massdot.state.ma.us/highway/TheBigDig.aspx> (October 5, 2013).
◦ National Research Council. “Completing the "Big Dig": Managing the Final Stages of Boston's Central Artery/Tunnel Project. Washington, DC: The National
Academies Press, 2003.
◦ Poole, R.W., Samuel, P. (2011). “Transportation Mega-Projects and Risk.” Reason Foundation Policy Brief 97. Los Angeles, CA.
◦ Saltzman, J. (2009). “Big Dig Contractor Modern Continental Pleads Guilty.” Boston Globe.
<http://www.boston.com/news/local/breaking_news/2009/05/modern_continen_2.html> (October 5, 2013).
◦ Salvucci, F. P. (2008). “Unearthing the Big Dig.” Massachusetts Institute of Technology. Cambridge, MA.
◦ Wood, D. (2001). “Learning From the Big Dig.” Federal Highway Administration: Public Roads,
<http://www.fhwa.dot.gov/publications/publicroads/01julaug/bigdig.cfm> (November 13, 2013).

More Related Content

PDF
STANDARD REVETMENT, RETAINING WALL DO_100_s2020.pdf
PDF
Concrete and steel bridges
PPTX
Construction Supply Chain Management
PPTX
Multi criteria decision making in spatial data analysis
PPTX
cfst columns
PPTX
Nuclear wastes and its disposal my ppt
PDF
Crusher and Its Types
PPTX
Conveyors and types
STANDARD REVETMENT, RETAINING WALL DO_100_s2020.pdf
Concrete and steel bridges
Construction Supply Chain Management
Multi criteria decision making in spatial data analysis
cfst columns
Nuclear wastes and its disposal my ppt
Crusher and Its Types
Conveyors and types

What's hot (20)

PPTX
Big dig powerpoint
PPTX
BP's Deepwater Oil Spill Case Study Analysis - Business Ethics
PDF
What can we learn from the hoover dam
PPT
Planning of materials in Construction Project management
PPTX
case study on failed construction projects
PPTX
Presentation on Cost Overrun ( Project Management)
DOCX
PROJECT MANAGEMENT - ASSIGNMENT ON BRIDGE CONSTRUCTION PLAYS A ROLE OF PROJEC...
PPTX
BP case study
PPTX
Evolution of project management
PPT
Challenges Of Project Management
PPTX
Summary chunnel tunnel project management
PDF
Sea Port Construction, Project Execution Plan
PDF
Contract payment and variation
PDF
Extension of Time (EoT) in Construction Project presentation
DOCX
Procurement Methods
PPTX
Quality management
PDF
General technical specification for construction
DOCX
Site visit report
PPTX
Construction Project Process Flow
PPTX
Construction site supervision aalecture one.
Big dig powerpoint
BP's Deepwater Oil Spill Case Study Analysis - Business Ethics
What can we learn from the hoover dam
Planning of materials in Construction Project management
case study on failed construction projects
Presentation on Cost Overrun ( Project Management)
PROJECT MANAGEMENT - ASSIGNMENT ON BRIDGE CONSTRUCTION PLAYS A ROLE OF PROJEC...
BP case study
Evolution of project management
Challenges Of Project Management
Summary chunnel tunnel project management
Sea Port Construction, Project Execution Plan
Contract payment and variation
Extension of Time (EoT) in Construction Project presentation
Procurement Methods
Quality management
General technical specification for construction
Site visit report
Construction Project Process Flow
Construction site supervision aalecture one.
Ad

Similar to Project Complexity (Case study) (20)

PDF
BigDig_KeyFacts_Dec2006
PDF
ANALYSIS OF VIADUCT REHABILITATION PROJECTS IN MASSACHUSETTS AND CALIFORNIA: ...
DOCX
PDF
Walton Boulevard Reconstruction, APWA Project of the Year
PPTX
Torrey pines road corridor study final
PPTX
2024 Constructability.pptx test test test
PDF
060626_Temple_Mills_Bridge_Reconstruction_Javad_Akhtar
DOC
Resume pe civil
PDF
2016-07-28 Martin Jacobs
PDF
megaprojects, SPUR 2022.pdf
PPTX
Final acec design summit pres 2017
DOCX
LEADERSHIP ROLES With a project of this magnitude, it .docx
PDF
Proposal to reclaim Chicago's lakefront from the highway using immersed tunnels
PDF
Deh Cho Bridge
DOC
Tim McAnallen - Construction Inspector 2104
PDF
Cover Letter & Resume
PDF
WALID_TANBEDAWY_2016 R Dom Comp
PPTX
OTEC Presentation: Complete Streets for Akron's East End Development
PDF
228 congressparkway overview_jan2010
PDF
Congress Parkway Construction Overview, January 2010
BigDig_KeyFacts_Dec2006
ANALYSIS OF VIADUCT REHABILITATION PROJECTS IN MASSACHUSETTS AND CALIFORNIA: ...
Walton Boulevard Reconstruction, APWA Project of the Year
Torrey pines road corridor study final
2024 Constructability.pptx test test test
060626_Temple_Mills_Bridge_Reconstruction_Javad_Akhtar
Resume pe civil
2016-07-28 Martin Jacobs
megaprojects, SPUR 2022.pdf
Final acec design summit pres 2017
LEADERSHIP ROLES With a project of this magnitude, it .docx
Proposal to reclaim Chicago's lakefront from the highway using immersed tunnels
Deh Cho Bridge
Tim McAnallen - Construction Inspector 2104
Cover Letter & Resume
WALID_TANBEDAWY_2016 R Dom Comp
OTEC Presentation: Complete Streets for Akron's East End Development
228 congressparkway overview_jan2010
Congress Parkway Construction Overview, January 2010
Ad

More from Sunny Mahajan (7)

PPTX
Usage of RAP on gravel roads
PPTX
Off site fabrication
PPTX
Frugal innovation-sankalp
PPTX
Marketing101-The Geek
PPTX
Optimal RAP content for Minnesota Roads
PPTX
BIM case study
PPTX
Burj al arab (Cofferdam&Rigging)
Usage of RAP on gravel roads
Off site fabrication
Frugal innovation-sankalp
Marketing101-The Geek
Optimal RAP content for Minnesota Roads
BIM case study
Burj al arab (Cofferdam&Rigging)

Recently uploaded (20)

PDF
Digital Logic Computer Design lecture notes
PDF
Operating System & Kernel Study Guide-1 - converted.pdf
PPTX
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
PPTX
Sustainable Sites - Green Building Construction
PPTX
additive manufacturing of ss316l using mig welding
PPTX
Strings in CPP - Strings in C++ are sequences of characters used to store and...
DOCX
573137875-Attendance-Management-System-original
PDF
PRIZ Academy - 9 Windows Thinking Where to Invest Today to Win Tomorrow.pdf
PPTX
Geodesy 1.pptx...............................................
PDF
Model Code of Practice - Construction Work - 21102022 .pdf
PDF
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
PPTX
MCN 401 KTU-2019-PPE KITS-MODULE 2.pptx
PPT
Mechanical Engineering MATERIALS Selection
PDF
Structs to JSON How Go Powers REST APIs.pdf
PPTX
Internet of Things (IOT) - A guide to understanding
PPTX
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
PPTX
Recipes for Real Time Voice AI WebRTC, SLMs and Open Source Software.pptx
PDF
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
PPTX
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx
PDF
Arduino robotics embedded978-1-4302-3184-4.pdf
Digital Logic Computer Design lecture notes
Operating System & Kernel Study Guide-1 - converted.pdf
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
Sustainable Sites - Green Building Construction
additive manufacturing of ss316l using mig welding
Strings in CPP - Strings in C++ are sequences of characters used to store and...
573137875-Attendance-Management-System-original
PRIZ Academy - 9 Windows Thinking Where to Invest Today to Win Tomorrow.pdf
Geodesy 1.pptx...............................................
Model Code of Practice - Construction Work - 21102022 .pdf
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
MCN 401 KTU-2019-PPE KITS-MODULE 2.pptx
Mechanical Engineering MATERIALS Selection
Structs to JSON How Go Powers REST APIs.pdf
Internet of Things (IOT) - A guide to understanding
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
Recipes for Real Time Voice AI WebRTC, SLMs and Open Source Software.pptx
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx
Arduino robotics embedded978-1-4302-3184-4.pdf

Project Complexity (Case study)

  • 1. “Big Dig” Project THE CENTRAL ARTERY/TUNNEL PROJECT (CA/T) A CASE STUDY ON PROJECT COMPLEXITY.
  • 2. Project Description Located in Boston, MA, on the northeast coast of the United States.  Includes tunnels, highway interchange connections, bridges and pedestrian facilities
  • 4. Project Description Rerouted the Central Artery (Interstate 93), into a 3.5-mile (5.6-km) tunnel.  Construction of the Ted Williams Tunnel.  Construction of the Leonard P. Zakim Bunker Hill Memorial Bridge over the Charles River.  Construction of the Rose Kennedy Greenway in the space vacated by the previous I-93 elevated roadway.
  • 5. Project Description  Planning Phase started in 1982  Construction work – 1991-2006  Estimated Completion - 1998  Actual Completion – Dec 31, 2007 Estimated Cost - $2.8 billion Final Cost - $14.6 billion Cost over run – 190% Official project owner - Massachusetts Turnpike Authority  Joint venture of Bechtel and Parson Brinkerhoff Source: http://www.roadtraffic-technology.com
  • 6. Why Boston Needed the Big Dig? Traffic improvements and substantial reductions in congestion  Improving mobility in downtown Boston  Reconnect neighborhoods severed by the old elevated highway Source: http://www.massdot.state.ma.us
  • 7. Central Artery: Before and After Source:http://www.bigdig.com
  • 8. Problems faced Escalating costs Scheduling overruns Design flaws Charges of poor execution and use of substandard materials Fatal Ceiling Collapse Criminal arrests and one death Source: http://www.roadtraffic-technology.com
  • 9. Complexity Factors - Cost Contingency Usage ◦ Construction Contracts ◦ Management Contingency ◦ Massachusetts Turnpike Authority CEO Contingency Risk Analysis ◦ Location ◦ Utilities Estimate Formation ◦ Ted Williams Tunnel ◦ Zakim Bunker Hill Bridge ◦ Center Artery (I-93)
  • 10. Complexity Factors - Cost Figure. Big Dig Project Cost Growth (National Research Council 2003) 55% 15% 8% 7% 5% 3% 2% 5% Inflation Environmental/Mitigation Scope Growth Accounting Changes Traffic Schedule Maintenance Contingency for Unknowns Other
  • 11. Complexity Factors - Schedule Timeline Requirements ◦ Community Conflicts Milestones Schedule Control ◦ Software Programs
  • 12. Complexity Factors - Technical Scope of Project Owner’s Internal Structure Design Method
  • 13. Complexity Factors - Context Public ◦ Economic Value of Boston Utility Coordination ◦ 29 Miles of Underground Utility Relocation and Updating Land Use Impact ◦ 300 acres of Green Space
  • 14. Complexity Factors - Financing Federal Funding State Funding Borrowing Against Future Funding
  • 15. Project Dimension Complexity Ranking DIMENSION RANK Context 5 Cost 4 Technical 3 Financing 2 Schedule 1
  • 16. Project Dimension Complexity Rating DIMENSIONS SCALE (0 – 100) Cost Dimension Complexity 99 Schedule Dimension Complexity 90 Technical Dimension Complexity 95 Context Dimension Complexity 100 Financing Dimension Complexity 92
  • 17. Complexity Map The Big Dig Project 0 10 20 30 40 50 60 70 80 90 100 Technical Cost FinancingContext Schedule
  • 18. Critical Planning and Analysis Methods Method 1: Define Critical Success Factors ◦ Community Needs ◦ Political Restrictions ◦ Federal and State Funding ◦ Major Project Components ◦ Center Artery (I-93) ◦ Ted Williams Tunnel ◦ Zakim Bunker Hill Bridge
  • 19. Method 2: Assemble Project Team Communication Collaboration ◦ Example ◦ Ted Williams Tunnel Ceiling Panel Collapse
  • 20. Method 3: Project Arrangements Design-Bid-Build Value Engineering Dispute Resolution Dispute Resolution Board
  • 21. Method 4: Early Cost Model and Finance Plan Incorrect Initial Cost Model and Finance Plan The cost model would have included ◦ Inflation ◦ Project Risk- Account for Cost Overruns ◦ More detail over Design Costs
  • 22. Method 5: Develop Project Action Plans Major Obstacles ◦ Restrictive Legislation ◦ Acquisition of ROW ◦ Cooperation of Utilities ◦ Community Support
  • 23. Tools for Managing Complex Projects The following tools were used in the Big Dig Project: •Public involvement plan •Critical permit issues •Offsite fabrication •Co-locate team •Dispute resolution plan
  • 24. Public Involvement Plan ◦ Project planners worked with community groups, government & business leaders to create a consensus of how the project would be built ◦ Mitigation: The process of keeping the city open and making certain all affected groups would be treated fairly ◦ Informed, organized interest groups press for their demands ◦ Public involvement plan produces early project wins of consensus but at the expense of late project soaring project costs
  • 25. Critical Permit Issues ◦ Bechtel/Parsons Brinkerhoff (B/PB): ◦ Engineering authority that approved, permitted, and released designs for construction ◦ Construction managers in charge of contractors & sub-contractors ◦ B/PB operated the project with the philosophy of getting this done, ask questions later ◦ Many plans that were permitted and released for construction were incomplete, contained numerous errors, and lacked proper subsurface exploration ◦ The lax oversight produced an estimated $750 million in construction over-runs
  • 26. Offsite Fabrication ◦ Utilized successfully on the CA/T project ◦ Several examples are: ◦ Immersed steel tubes for the Ted Williams Tunnel ◦ Steel box girder sections for the Bunker Hill Bridge ◦ Utilized successfully on the CA/T project ◦ Offsite fabrication of box girders and steel tubes produced accurate sections per specification that could be test connected at the factory to insure smooth and timely installation ◦ Quicker assembly time at the job site with smaller construction crews as compared to onsite fabrication ◦ Exposure of construction workers to difficult job environments was reduced as compared to onsite fabrication
  • 27. Co-Locate Team ◦ Co-Locate elements of the project team to produce a cohesive team effort to complete a project ◦ Perhaps the most controversial tool ◦ In 1998, State of Massachusetts combined B/PB with state workers into one integrated project organization ◦ Massachusetts Turnpike Authority was at the top of the organization chart ◦ State of Massachusetts designated B/PB as “owner’s representative” in several instances ◦ Who is in charge?
  • 28. Dispute Resolution Plan ◦ Two noteworthy dispute resolution plan techniques were utilized on the CA/T project: ◦ Partnering ◦ Mediation ◦ Partnering was practiced on the CA/T project for construction projects with a duration of least one year and a value of $1 million or more ◦ Mediation was utilized to resolve the dispute of responsibility for leaks at the Fort Point Channel tunnel area
  • 29. References ◦ Bartlett School of Planning (UCL). (2011). “The Central Artery/Third Harbor Tunnel Project (‘The Big Dig’), Omega Centre.” Bloomsbury, London. ◦ Gelinas, N. (2007). “Lessons of Boston’s Big Dig.” City Journal Autumn. New York, New York. ◦ Greirman, V. (2010). “The Big Dig: Learning from a Mega Project.” NASA, <http://appel.nasa.gov/2010/07/15/the-big-dig-learning-from-a-mega-project/> (November 13, 2013). ◦ Hsu, J. Mckay, S., McKnight, M. (2003). “Cost-Benefit Analysis of Boston’s Central Artery/Tunnel Project” Carnegie Mello University. Pittsburgh, PA. ◦ Lewis, R. and Murphy, S. (2003). “Artery Errors Cost More Than $1b.” The Boston Globe, <http://www.boston.com/globe/metro/packages/bechtel/> (November 13, 2013). ◦ Massachusetts Department of Transportation (MassDOT). (2013). “The Central Artery/Tunnel Project-The Big Dig.” MassDOT Highway Division. <http://www.massdot.state.ma.us/highway/TheBigDig.aspx> (October 5, 2013). ◦ National Research Council. “Completing the "Big Dig": Managing the Final Stages of Boston's Central Artery/Tunnel Project. Washington, DC: The National Academies Press, 2003. ◦ Poole, R.W., Samuel, P. (2011). “Transportation Mega-Projects and Risk.” Reason Foundation Policy Brief 97. Los Angeles, CA. ◦ Saltzman, J. (2009). “Big Dig Contractor Modern Continental Pleads Guilty.” Boston Globe. <http://www.boston.com/news/local/breaking_news/2009/05/modern_continen_2.html> (October 5, 2013). ◦ Salvucci, F. P. (2008). “Unearthing the Big Dig.” Massachusetts Institute of Technology. Cambridge, MA. ◦ Wood, D. (2001). “Learning From the Big Dig.” Federal Highway Administration: Public Roads, <http://www.fhwa.dot.gov/publications/publicroads/01julaug/bigdig.cfm> (November 13, 2013).