5 Broadgate
A Collaboration between;
UBS, ISG, IBSECAD &
ARC:BIM
Fit-Out Case Study
5 Broadgate Project
BIM in Action at UBS
#BSL2015
5 Broadgate
Your speakers today
Richard Baglow
Business
Development
Director
IBSECAD
Paul Field
Division Director
ARC:BIM
Jason Clark
Director
UBS
Steve Bagland
Project Director
ISG
#BSL2015
5 Broadgate
 Background
 Project BIM Map
 Preparation
 Stage 1 – Spatial Design
 Stage 2 & 3 Continues
 Stage 4 – Soft Landing
 Summary
 Questions & Answers
Agenda
#BSL2015
5 Broadgate
Background
 UBS is a global firm providing financial services to
private, corporate and institutional clients.
 Headquartered in Zurich and Basel,
 UBS is present in all major financial centres and has
offices in over 50 countries.
 UBS employs more than 65,000 people around the
world.
 In the UK, UBS employs around 8,500 people
 UBS as a property portfolio of 7 buildings in the
London area
 A portfolio that equates to approximately
1,000,000 Sqft
#BSL2015
5 Broadgate
Background
Specific objectives…
 Maximum flexibility and cost efficiency for London real estate portfolio
 Enhanced client experience through world-class facilities
 Productive and flexible working environment for our staff
 Secure and reliable infrastructure to minimise operational risk
 Excellent sustainability characteristics and energy efficiencies
Delivering a flexible world-class office facility for the
integrated Firm
#BSL2015
5 Broadgate
Background
 Twelve occupied floors above ground and three levels
of basement
 Basement: Plant plus extensive bicycle (520 spaces)
and motorcycle facilities, limited car parking (16
spaces)
 Ground & L1: Reception, 250 seat auditorium,
client/staff event space, staff restaurant, medical
centre and gym
 L2-5: Trading floors, enhanced structural height, large
floors 5,800m2 up to 3,000 trading positions
 L6: IT infrastructure CER rooms & office space
 L7: Meeting room suite with winter gardens
 L8: Office space, dining/meeting and executive suite
 L9-12: Office floors 5,000m2 ; daylight from atria
 Roof: Heat rejection plant, solar thermal and photo
voltaic panels
Twelve floors and a net internal area of circa 700,000 Sqft
#BSL2015
5 Broadgate
Preparation
Why would you build a building of the Future without BIM ?
 Synchronisation with following
databases with a common data set:
 Asset Management
 Space Management
 Asset Lifecycle Planning
 O&M
Moves and
Changes CAFM
Capital Expenditure
Cost Management
Asset Management
CMMS
Engineering / Fabric
O&M Records
Drawings and
Data
Drawings and
Data
Drawings and
Data
Drawings and
Data
 One-time’ updates to centralised BIM
model in single/multiple repositories
 Improve change management
process providing reliable validated
data
 Inform maintenance access and
asset replacement strategy
 Asset validation and data ownership
 User visualisation tool throughout the
process
 Holistic O&M (not just M&E)
ISO 9001 (ISO 55000)
#BSL2015
5 Broadgate
Preparation
Opportunities
 Benchmarking costs, energy efficiencies and lifecycle modelling
 Staff training tool for maintenance, health, safety and security
 Parametric data make physical change management more
efficient
 Interface with: -
 Physical Security Information Management PSIM Systems
 UBS Business Unit (BU) cost /HR database
 Asset management hand held technology
 Management Information Systems MIS
 Graphical User Interface GUI
 e.g. fire alarms, BMS, Lighting etc.
#BSL2015
5 Broadgate
Programme
GOVERNMENT
BIM STRATEGY
#BSL2015
5 Broadgate
Project BIM Map
#BSL2015
5 Broadgate
Project BIM Map
#BSL2015
5 Broadgate
Project BIM Map
Soft Landing (database population)
#BSL2015
5 Broadgate
Objectives
 To provide a data rich model (in Revit) and database for UBS to
use an FM management
 To ensure best fit and quality to facilitate safe and efficient
future maintenance
 To develop the detailed co-ordination of the fit-out designs and
their integration with shell & core structure, fabric and systems,
which will in turn…
 …enable the procurement of robust and comprehensive
tenders so that…
 …the construction phase co-ordination, programme and cost
risks are minimised.
#BSL2015
5 Broadgate
Challenges
 Limited 3D Design
(only Architectural)
 Information Gaps
 base build Steel & Structure
 base build Fabric & Services
Translate 2D MEP fit-
out design into 3D
Procure base build
information & stich
together
Design & Modelling
FEDERATE
#BSL2015
5 Broadgate
Challenges
 Risk of Errors, omissions,
inaccuracies, creep
during Shell & Core
construction
 Risk of changes in base
build Information
 Clashes
Validate by
inspection and laser
surveys
Monitor during the
base build phase
Identify, workaround
or change process
Design & Modelling
#BSL2015
5 Broadgate
BIM Strategy
• Capturing the strategy in
the BIM Execution Plan
ready for procurement.
• The Project BEP was issued
as part of the Tender packs.
#BSL2015
5 Broadgate
Testing the Market: Knowledge
 What LOD should the model
be taken to pre-procurement
& appointment?
 Revit or FABMep?
 Model Ownership?
= LOD 300
- 80/20 principle
- Identify known co-ord risks
= FABMep
= Adoption/Novation after
review/validation
Feedback incorporated into the BIM Strategy
MEP Supply Chain Engagement
#BSL2015
5 Broadgate
Testing the Market: Process
Review &
Preparation
Tender
9 Weeks
Post Tender 9
Weeks
Pre-Construction
27 Weeks
Trade Contractor Co-ordinated
Design- 8-9 Months
STAGE F TENDER ISSUE TENDER RETURN APPOINTMENT START
ON SITE
2WKS-MOBILISE
CO-ORD/MODEL/SIGN-OFF
15 WKS
FABRICATION
10 WKS
STANDARD OPTION
 Design Development & co-
ordination frozen for 6 months.
 3D Model frozen
 Wait for Trade Contractor
appointment to start co-
ordinating 3D Spatial design.
#BSL2015
5 Broadgate
Testing the Market: Process
Trade
Contractor
Development
STAGE F APPOINTMENT START ON SITE
2WKS-MOBILISE
FINALISE/SIGN-OFF
15 WKS
APPROXIMATE 20-24
WEEKS BENEFIT
ALTERNATIVE OPTION
Co-ordinated 3D Design (LOD 350)
24 Weeks
THE FM DATA BASE BUILD
PROCESS CAN START
MUCH EARLIER IN THIS
SCENARIO Mitigates cost and programme risk.
 More control of the management of
this risk to Construction Manager and
Project team.
#BSL2015
5 Broadgate
Solution was chosen;
 REVIT for Architecture
 FABMep for Services
 Navisworks for Co-ordination
 Buzzsaw for Collaboration
Testing the Market: 3D Software
 Trades were asked what they prefer if advanced co-ordination started.
#BSL2015
5 Broadgate
Testing the Market: FM Software
 Archibus directly interfaces with Revit
Space Planning tool
 Import of structured data
Asset Management
#BSL2015
5 Broadgate
Preparation Complete
Summary & Learnings
 Define the objectives as a team
 Spend quality time in this phase and face up to
the future and PLAN
 Be prepared to change course
 Engage with the Supply Chain
 Accept that not everyone gets BIM – spend time
and energy building awareness and knowledge
#BSL2015
5 Broadgate
Stage 1 – Spatial Design
ISG appointed single
source modeller for BIM
co-ordination.
#BSL2015
5 Broadgate
 Base build Integration
 Design Validation
 Reduce Risk
 Early Co-ordination
 Collaboration
 Constructability
Objectives
#BSL2015
5 Broadgate
Team Buy-in & Willingness
One team philosophy…
#BSL2015
5 Broadgate
Collaboration
Collaborative workshops to drive solutions were
held weekly at Ibsecad offices.
#BSL2015
5 Broadgate
Collaboration
All stakeholders had representation at meetings
#BSL2015
5 Broadgate
Design Validation
 Technical Queries were
utilised for challenging
design issues
 This system allowed the
design team to focus on
key areas.
 Total Ibsecad TQ’s = 125
 93% resolved pre-
procurement
 98% solved post
procurement.
#BSL2015
5 Broadgate
Design Validation
A – GRILLES UNDER STEELWORK/PRIMARY SERVICES
 Design Layout shows grille line located beneath steelwork &
Primary services distribution.
 Only 150mm from underside of ceiling to steel work.
 Not possible to locate grilles even a reduced ceiling height (red)
 Redesign of Ventilation & RCP required to resolve.
#BSL2015
5 Broadgate
Base Build Integration
Integration of the Base
Build information was
key to ensure Fit out
delivery.
Mace were leading the
Shell & Core Installation.
Point Cloud provided by
XYZ Surveys appointed
by ISG.
Utilisation of Recap with
“Real View” data.
#BSL2015
5 Broadgate
Base Build Integration
 Existing Rainwater
systems installed by
Base build team.
 XYZ Surveys
commenced Laser
scan point cloud.
 Recap files supplied for
Model federation.
Recap “Real View” output
#BSL2015
5 Broadgate
Base Build Integration
Clash Management
process for Base
Build
#BSL2015
5 Broadgate
Base Build Integration
 Impact of RWP
reviewed in the
BIM workshop.
 Informed
decisions could
be made to suit
Fit out and Base
build install’s.
 Amendments
absorbed into
programmed
works.
#BSL2015
5 Broadgate
Base Build Integration
 Fully Co-ordinated Solutions
#BSL2015
5 Broadgate
BIM Output
 Advanced BIM Co-ordination completed – September 2014
 24 Week programme
 Team peaked @ 28 People
#BSL2015
5 Broadgate
BIM Output
 Full set of Co-ordinated “MEP Installation Drawings” prior to Trade
Contractor appointment, for incorporation into tender process.
 Outstanding TQ’s enabled risks to be managed.
 Minimal Trade contractor co-ordination required thereafter.
#BSL2015
5 Broadgate
Constructability
 Trading Floor – Low Level
MODELPROTOTYPEVISION
#BSL2015
5 Broadgate
MODELPROTOTYPE
Constructability
 Trading Floor – High Level
VISION
#BSL2015
5 Broadgate
Constructability
 Meeting Room MODELPROTOTYPEVISION
#BSL2015
5 Broadgate
Constructability
FABRICATE & BUILD WITH CONFIDENCE
– PROGRAMME
– QUALITY
– CO-ORDINATION
– FUNCTION
– COST
MODELPROTOTYPEVISION
#BSL2015
5 Broadgate
Stage 1 Complete
Summary & Learnings
 Keeping and managing the risk makes sense.
 Change management
 Clash management
 Procurement benefits
 Don’t underestimate the value of Laser Scanning for
continual validation.
 Prototyping still has a big part to play.
#BSL2015
5 Broadgate
Stage 2 & 3 continues
 Trades are now appointed.
 Site Mobilised.
 Further prototyping and mock up with
trades.
 Ibsecad novated to continue the final
detailing with the Mechanical
Contractor.
 As Co-ordination has been completed
Trades are focusing on Sequencing,
Final procurement & Model enrichment.
#BSL2015
5 Broadgate
Workflows
Architecture / Non-MEP MEP
Revit model to remain intact for
Space planning tools
Process to allow for multiple
Architectural trades inputting
simultaneously
Model enriched with data in
accordance with BEP
Use of Stage 1 models for all MEP
Trades
Models developed with final
equipment selection
Generation of Master Revit file for
Fit-out
Model enriched with data in
accordance with BEP
#BSL2015
5 Broadgate
Team Buy-in & Willingness
#BSL2015
5 Broadgate
Model enrichment
 Analysis of FM integration between platformsEIR
COBie
#BSL2015
5 Broadgate
Model enrichment
 Development of UBS Structured Data Template
 Enables data to be passed to CMMS and Space
planning solutions with no data duplication.
Output = Universal Golden Rules
#BSL2015
5 Broadgate
Integration for FM
 Delivering Information enriched Revit Architecture model
 Delivering Asset referenced MEP Models
 Delivering Structured database for all existing FM platforms
 Tested the market for Integration of model with O&Ms
#BSL2015
5 Broadgate
Stage 2 & 3 Summary
Summary & Learnings to date
 Mixed capability in the supply chain
 Need help, guidance & support.
 Trade contractors are engaged on data input and
generating feedback
 The work completed now is informing the soft
landings in Stage 4.
#BSL2015
5 Broadgate
Stage 4 – Soft Landing
Development of Business Change Management
 Process Mapping
 Operation & Management efficiencies
 Improved Information management
 Upskilling & re-deployment
 Operational execution plan
 Integrated asset management –
o Not only MEP…
 Improve response times to business needs
MOVING TOWARDS AN INTELLIGENT
BUILDING WITH INFORMED CLIENTS
#BSL2015
5 Broadgate
 Start with the end in mind…
 Be prepared to change course…
 Keeping and managing the risk makes sense…
 Early co-ordination massively de risks the construction phase…
 Engage with the supply chain at every opportunity…
 If you are not effective and managing data / information in
operations now, BIM will not solve this for you.
 HAVE FUN
Summary
#BSL2015
5 Broadgate
Questions & Answers

More Related Content

PPSX
BIM SHOW LIVE 14 - Story of BIM from design to use
PDF
BIM Show Live 2015: Single or Multiple Models
PDF
How to Create a Rock Star BIM Execution Plan (BEP) and MPDT* (Responsibility ...
PDF
MTECH BIM project case study
PDF
BIM Show Live 2015: 110 Queen Street – A BIM exemplar
PDF
4th Qatar BIM User Day, Pragmatic Use of COBie As-Built BIM for FM
PDF
Digital & BIM in Total Architecture
PPTX
Change Management For Building Information Modelling (BIM)
BIM SHOW LIVE 14 - Story of BIM from design to use
BIM Show Live 2015: Single or Multiple Models
How to Create a Rock Star BIM Execution Plan (BEP) and MPDT* (Responsibility ...
MTECH BIM project case study
BIM Show Live 2015: 110 Queen Street – A BIM exemplar
4th Qatar BIM User Day, Pragmatic Use of COBie As-Built BIM for FM
Digital & BIM in Total Architecture
Change Management For Building Information Modelling (BIM)

What's hot (20)

PDF
BIM project execution
PPTX
The NBS BIM Toolkit and Digital Plan of Work
PDF
11.30 uur thomas vandenbergh - uitdagingen bij de introductie van bim binne...
PPT
Bim level-2 information-management
PPTX
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...
PDF
BIM Execution plan
PDF
5th Qatar BIM User Day, Understanding stakeholder roles in BIM
PDF
5th Qatar BIM User Day, Expanding BIM into Augmented and Virtual Reality
PPTX
BIM Execution Plan
PPT
IMPLEMENTATION OF BIM IN CONSTRUCTION - Experience Sharing by Mr. Kevin...
PPTX
BIM for Local Government - Presentation by John Lorimer, Local Government BIM...
PDF
4th Qatar BIM User Day, BIM Solutions and Strategies
PPTX
Virtual Design and Construction
PDF
BIM (Building Information Modeling) Services | Revit Architecture | Revit Str...
PDF
The future of BIM is open - or - Is proprietary BIM unsustainable
PDF
Pre and Post Contract BIM Execution Plans
PPTX
BIM - Changing Perceptions of Design-Build
PDF
Ramboll - BIM - Now It's Serious
PDF
Build Source-Company_Profile
PPT
BASIC TERMS IN BIM-REVIT
BIM project execution
The NBS BIM Toolkit and Digital Plan of Work
11.30 uur thomas vandenbergh - uitdagingen bij de introductie van bim binne...
Bim level-2 information-management
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...
BIM Execution plan
5th Qatar BIM User Day, Understanding stakeholder roles in BIM
5th Qatar BIM User Day, Expanding BIM into Augmented and Virtual Reality
BIM Execution Plan
IMPLEMENTATION OF BIM IN CONSTRUCTION - Experience Sharing by Mr. Kevin...
BIM for Local Government - Presentation by John Lorimer, Local Government BIM...
4th Qatar BIM User Day, BIM Solutions and Strategies
Virtual Design and Construction
BIM (Building Information Modeling) Services | Revit Architecture | Revit Str...
The future of BIM is open - or - Is proprietary BIM unsustainable
Pre and Post Contract BIM Execution Plans
BIM - Changing Perceptions of Design-Build
Ramboll - BIM - Now It's Serious
Build Source-Company_Profile
BASIC TERMS IN BIM-REVIT
Ad

Viewers also liked (20)

PDF
Sponda Financial Results Q2 2014 presentation 010814
PPTX
Evolución de la web mapa
PPTX
Enterprise Threat Management
PPTX
презентація опера
PPTX
Shooting
PPTX
Comparatives and Superlatives
PDF
FINAL PR Portfolio Slides
PPTX
Whole Person Risk Modeling
PPTX
Haystax Carbon for Insider Threat Management
PDF
Results presentation q3 2016
PDF
StimulusWk13
PDF
Sponda Results presentation Q4 2015
PDF
Haystax Technology Machine learning white paper
PPTX
Importance pdhpe
PPTX
Processing Events in Probabilistic Risk Assessment
PPTX
Evaluation Q7
PDF
Exploiting inference to improve temporal RDF annotations and queries for mach...
PPTX
Major events
PPT
Mega Holdings prasentation
PPTX
Haystax - Analytic Products and Enterprise Network Services
Sponda Financial Results Q2 2014 presentation 010814
Evolución de la web mapa
Enterprise Threat Management
презентація опера
Shooting
Comparatives and Superlatives
FINAL PR Portfolio Slides
Whole Person Risk Modeling
Haystax Carbon for Insider Threat Management
Results presentation q3 2016
StimulusWk13
Sponda Results presentation Q4 2015
Haystax Technology Machine learning white paper
Importance pdhpe
Processing Events in Probabilistic Risk Assessment
Evaluation Q7
Exploiting inference to improve temporal RDF annotations and queries for mach...
Major events
Mega Holdings prasentation
Haystax - Analytic Products and Enterprise Network Services
Ad

Similar to BIM Show Live 2015: Fit-out case study (20)

PPTX
Innovation in practice presentation 10 06-15
PPT
Sustainability In Government - Bim Webinar
PDF
BIFM North Region Key Learning Event - BIM & Soft Landings
PDF
From 3D to 6D Managing the Information Labyrinth of BIM.pdf
PPTX
BuildingSmart COBie presentation March 2014
PPTX
Software Applications
PPTX
Software Application Presentation Slide
PPT
Corporate member event September 2015, BIM and Soft Landings
PDF
BIM_BROCHURE.PDF
PDF
Recent developments in BIM in geotechnics
PDF
Recent developments in BIM in geotechnics
PDF
bim and project controls
PPTX
Use of BIM in planning and construction and implementation in real project
PPTX
Cape Cod Networking-BIM_MDESK
PPTX
What is bim, building information modeling
PPT
BIM model analysis
PDF
5 peter trebilcock, balfour beattie
PDF
NW BIM 2018 3 Mabey
PPTX
Delivering Projects Better with BIM
Innovation in practice presentation 10 06-15
Sustainability In Government - Bim Webinar
BIFM North Region Key Learning Event - BIM & Soft Landings
From 3D to 6D Managing the Information Labyrinth of BIM.pdf
BuildingSmart COBie presentation March 2014
Software Applications
Software Application Presentation Slide
Corporate member event September 2015, BIM and Soft Landings
BIM_BROCHURE.PDF
Recent developments in BIM in geotechnics
Recent developments in BIM in geotechnics
bim and project controls
Use of BIM in planning and construction and implementation in real project
Cape Cod Networking-BIM_MDESK
What is bim, building information modeling
BIM model analysis
5 peter trebilcock, balfour beattie
NW BIM 2018 3 Mabey
Delivering Projects Better with BIM

More from BuiltEnvironmentUBM (16)

PDF
BIM Show Live 2015: Man City Stadium Construction
PPTX
Collaborative design and engineering with IFC in the Netherlands
PDF
BIM Show Live 2015: BIM HEALTH & SAFETY FOR VIRTUALLY SORTED
PDF
BIM Show Live 2015: The challenges and the wins of Information Management on...
PDF
BIM Show Live 2015: BIM for SMEs #BSLSME
PDF
BIM Show Live 2015: Link between BIM and Energy Simulation
PDF
BIM SHOW LIVE 14: Big BIM Theory
PDF
BIM SHOW LIVE 14 - IFC: the developers perspective
PPTX
BIM SHOW LIVE 14 - 4D BIM: successful implementation at Gravesened Railway St...
PPTX
BIM SHOW LIVE 14 - SME architectural BIM journey
PPTX
BIM SHOW LIVE 14 - Attempting to comply Level 2 BIM as an SME QS working on s...
PPTX
BIM SHOW LIVE 14 - BIM for manufacturers
PPTX
BIM SHOW LIVE 14 - Same, same but different
PDF
BIM SHOW LIVE 14 - Reference models inside a BIM-authoring program
PDF
BIM SHOW LIVE 14 - Lego to Minecraft: from 3D CAD to BIM
PPSX
BIM SHOW LIVE 14 - BIM for residential
BIM Show Live 2015: Man City Stadium Construction
Collaborative design and engineering with IFC in the Netherlands
BIM Show Live 2015: BIM HEALTH & SAFETY FOR VIRTUALLY SORTED
BIM Show Live 2015: The challenges and the wins of Information Management on...
BIM Show Live 2015: BIM for SMEs #BSLSME
BIM Show Live 2015: Link between BIM and Energy Simulation
BIM SHOW LIVE 14: Big BIM Theory
BIM SHOW LIVE 14 - IFC: the developers perspective
BIM SHOW LIVE 14 - 4D BIM: successful implementation at Gravesened Railway St...
BIM SHOW LIVE 14 - SME architectural BIM journey
BIM SHOW LIVE 14 - Attempting to comply Level 2 BIM as an SME QS working on s...
BIM SHOW LIVE 14 - BIM for manufacturers
BIM SHOW LIVE 14 - Same, same but different
BIM SHOW LIVE 14 - Reference models inside a BIM-authoring program
BIM SHOW LIVE 14 - Lego to Minecraft: from 3D CAD to BIM
BIM SHOW LIVE 14 - BIM for residential

Recently uploaded (20)

PPTX
LITERATURE CASE STUDY DESIGN SEMESTER 5.pptx
PPTX
VERNACULAR_DESIGN_PPT FINAL WITH PROPOSED PLAN.pptx
PDF
1 Introduction to Networking (06).pdfbsbsbsb
PPTX
Evolution_of_Computing_Presentation (1).pptx
PPTX
Final Presentation of Reportttttttttttttttt
PPTX
Presentation.pptx anemia in pregnancy in
PDF
analisis snsistem etnga ahrfahfffffffffffffffffffff
PPT
robotS AND ROBOTICSOF HUMANS AND MACHINES
PPTX
Media And Information Literacy for Grade 12
PPTX
UNIT III - GRAPHICS AND AUDIO FOR MOBILE
PDF
trenching-standard-drawings procedure rev
PPTX
Acoustics new a better way to learn sound science
PPT
EthicsNotesSTUDENTCOPYfghhnmncssssx sjsjsj
PPTX
PROPOSAL tentang PLN di metode pelaksanaan.pptx
PPTX
Introduction to Building Information Modeling
PPTX
a group casestudy on architectural aesthetic and beauty
PPTX
URBAN FINANCEnhynhynnnytnynnnynynyynynynyn
PDF
Trends That Shape Graphic Design Services
PPTX
Presentation1.pptxnmnmnmnjhjhkjkjkkjkjjk
PDF
Chalkpiece Annual Report from 2019 To 2025
LITERATURE CASE STUDY DESIGN SEMESTER 5.pptx
VERNACULAR_DESIGN_PPT FINAL WITH PROPOSED PLAN.pptx
1 Introduction to Networking (06).pdfbsbsbsb
Evolution_of_Computing_Presentation (1).pptx
Final Presentation of Reportttttttttttttttt
Presentation.pptx anemia in pregnancy in
analisis snsistem etnga ahrfahfffffffffffffffffffff
robotS AND ROBOTICSOF HUMANS AND MACHINES
Media And Information Literacy for Grade 12
UNIT III - GRAPHICS AND AUDIO FOR MOBILE
trenching-standard-drawings procedure rev
Acoustics new a better way to learn sound science
EthicsNotesSTUDENTCOPYfghhnmncssssx sjsjsj
PROPOSAL tentang PLN di metode pelaksanaan.pptx
Introduction to Building Information Modeling
a group casestudy on architectural aesthetic and beauty
URBAN FINANCEnhynhynnnytnynnnynynyynynynyn
Trends That Shape Graphic Design Services
Presentation1.pptxnmnmnmnjhjhkjkjkkjkjjk
Chalkpiece Annual Report from 2019 To 2025

BIM Show Live 2015: Fit-out case study

  • 1. #BSL2015 5 Broadgate A Collaboration between; UBS, ISG, IBSECAD & ARC:BIM Fit-Out Case Study 5 Broadgate Project BIM in Action at UBS
  • 2. #BSL2015 5 Broadgate Your speakers today Richard Baglow Business Development Director IBSECAD Paul Field Division Director ARC:BIM Jason Clark Director UBS Steve Bagland Project Director ISG
  • 3. #BSL2015 5 Broadgate  Background  Project BIM Map  Preparation  Stage 1 – Spatial Design  Stage 2 & 3 Continues  Stage 4 – Soft Landing  Summary  Questions & Answers Agenda
  • 4. #BSL2015 5 Broadgate Background  UBS is a global firm providing financial services to private, corporate and institutional clients.  Headquartered in Zurich and Basel,  UBS is present in all major financial centres and has offices in over 50 countries.  UBS employs more than 65,000 people around the world.  In the UK, UBS employs around 8,500 people  UBS as a property portfolio of 7 buildings in the London area  A portfolio that equates to approximately 1,000,000 Sqft
  • 5. #BSL2015 5 Broadgate Background Specific objectives…  Maximum flexibility and cost efficiency for London real estate portfolio  Enhanced client experience through world-class facilities  Productive and flexible working environment for our staff  Secure and reliable infrastructure to minimise operational risk  Excellent sustainability characteristics and energy efficiencies Delivering a flexible world-class office facility for the integrated Firm
  • 6. #BSL2015 5 Broadgate Background  Twelve occupied floors above ground and three levels of basement  Basement: Plant plus extensive bicycle (520 spaces) and motorcycle facilities, limited car parking (16 spaces)  Ground & L1: Reception, 250 seat auditorium, client/staff event space, staff restaurant, medical centre and gym  L2-5: Trading floors, enhanced structural height, large floors 5,800m2 up to 3,000 trading positions  L6: IT infrastructure CER rooms & office space  L7: Meeting room suite with winter gardens  L8: Office space, dining/meeting and executive suite  L9-12: Office floors 5,000m2 ; daylight from atria  Roof: Heat rejection plant, solar thermal and photo voltaic panels Twelve floors and a net internal area of circa 700,000 Sqft
  • 7. #BSL2015 5 Broadgate Preparation Why would you build a building of the Future without BIM ?  Synchronisation with following databases with a common data set:  Asset Management  Space Management  Asset Lifecycle Planning  O&M Moves and Changes CAFM Capital Expenditure Cost Management Asset Management CMMS Engineering / Fabric O&M Records Drawings and Data Drawings and Data Drawings and Data Drawings and Data  One-time’ updates to centralised BIM model in single/multiple repositories  Improve change management process providing reliable validated data  Inform maintenance access and asset replacement strategy  Asset validation and data ownership  User visualisation tool throughout the process  Holistic O&M (not just M&E) ISO 9001 (ISO 55000)
  • 8. #BSL2015 5 Broadgate Preparation Opportunities  Benchmarking costs, energy efficiencies and lifecycle modelling  Staff training tool for maintenance, health, safety and security  Parametric data make physical change management more efficient  Interface with: -  Physical Security Information Management PSIM Systems  UBS Business Unit (BU) cost /HR database  Asset management hand held technology  Management Information Systems MIS  Graphical User Interface GUI  e.g. fire alarms, BMS, Lighting etc.
  • 12. #BSL2015 5 Broadgate Project BIM Map Soft Landing (database population)
  • 13. #BSL2015 5 Broadgate Objectives  To provide a data rich model (in Revit) and database for UBS to use an FM management  To ensure best fit and quality to facilitate safe and efficient future maintenance  To develop the detailed co-ordination of the fit-out designs and their integration with shell & core structure, fabric and systems, which will in turn…  …enable the procurement of robust and comprehensive tenders so that…  …the construction phase co-ordination, programme and cost risks are minimised.
  • 14. #BSL2015 5 Broadgate Challenges  Limited 3D Design (only Architectural)  Information Gaps  base build Steel & Structure  base build Fabric & Services Translate 2D MEP fit- out design into 3D Procure base build information & stich together Design & Modelling FEDERATE
  • 15. #BSL2015 5 Broadgate Challenges  Risk of Errors, omissions, inaccuracies, creep during Shell & Core construction  Risk of changes in base build Information  Clashes Validate by inspection and laser surveys Monitor during the base build phase Identify, workaround or change process Design & Modelling
  • 16. #BSL2015 5 Broadgate BIM Strategy • Capturing the strategy in the BIM Execution Plan ready for procurement. • The Project BEP was issued as part of the Tender packs.
  • 17. #BSL2015 5 Broadgate Testing the Market: Knowledge  What LOD should the model be taken to pre-procurement & appointment?  Revit or FABMep?  Model Ownership? = LOD 300 - 80/20 principle - Identify known co-ord risks = FABMep = Adoption/Novation after review/validation Feedback incorporated into the BIM Strategy MEP Supply Chain Engagement
  • 18. #BSL2015 5 Broadgate Testing the Market: Process Review & Preparation Tender 9 Weeks Post Tender 9 Weeks Pre-Construction 27 Weeks Trade Contractor Co-ordinated Design- 8-9 Months STAGE F TENDER ISSUE TENDER RETURN APPOINTMENT START ON SITE 2WKS-MOBILISE CO-ORD/MODEL/SIGN-OFF 15 WKS FABRICATION 10 WKS STANDARD OPTION  Design Development & co- ordination frozen for 6 months.  3D Model frozen  Wait for Trade Contractor appointment to start co- ordinating 3D Spatial design.
  • 19. #BSL2015 5 Broadgate Testing the Market: Process Trade Contractor Development STAGE F APPOINTMENT START ON SITE 2WKS-MOBILISE FINALISE/SIGN-OFF 15 WKS APPROXIMATE 20-24 WEEKS BENEFIT ALTERNATIVE OPTION Co-ordinated 3D Design (LOD 350) 24 Weeks THE FM DATA BASE BUILD PROCESS CAN START MUCH EARLIER IN THIS SCENARIO Mitigates cost and programme risk.  More control of the management of this risk to Construction Manager and Project team.
  • 20. #BSL2015 5 Broadgate Solution was chosen;  REVIT for Architecture  FABMep for Services  Navisworks for Co-ordination  Buzzsaw for Collaboration Testing the Market: 3D Software  Trades were asked what they prefer if advanced co-ordination started.
  • 21. #BSL2015 5 Broadgate Testing the Market: FM Software  Archibus directly interfaces with Revit Space Planning tool  Import of structured data Asset Management
  • 22. #BSL2015 5 Broadgate Preparation Complete Summary & Learnings  Define the objectives as a team  Spend quality time in this phase and face up to the future and PLAN  Be prepared to change course  Engage with the Supply Chain  Accept that not everyone gets BIM – spend time and energy building awareness and knowledge
  • 23. #BSL2015 5 Broadgate Stage 1 – Spatial Design ISG appointed single source modeller for BIM co-ordination.
  • 24. #BSL2015 5 Broadgate  Base build Integration  Design Validation  Reduce Risk  Early Co-ordination  Collaboration  Constructability Objectives
  • 25. #BSL2015 5 Broadgate Team Buy-in & Willingness One team philosophy…
  • 26. #BSL2015 5 Broadgate Collaboration Collaborative workshops to drive solutions were held weekly at Ibsecad offices.
  • 27. #BSL2015 5 Broadgate Collaboration All stakeholders had representation at meetings
  • 28. #BSL2015 5 Broadgate Design Validation  Technical Queries were utilised for challenging design issues  This system allowed the design team to focus on key areas.  Total Ibsecad TQ’s = 125  93% resolved pre- procurement  98% solved post procurement.
  • 29. #BSL2015 5 Broadgate Design Validation A – GRILLES UNDER STEELWORK/PRIMARY SERVICES  Design Layout shows grille line located beneath steelwork & Primary services distribution.  Only 150mm from underside of ceiling to steel work.  Not possible to locate grilles even a reduced ceiling height (red)  Redesign of Ventilation & RCP required to resolve.
  • 30. #BSL2015 5 Broadgate Base Build Integration Integration of the Base Build information was key to ensure Fit out delivery. Mace were leading the Shell & Core Installation. Point Cloud provided by XYZ Surveys appointed by ISG. Utilisation of Recap with “Real View” data.
  • 31. #BSL2015 5 Broadgate Base Build Integration  Existing Rainwater systems installed by Base build team.  XYZ Surveys commenced Laser scan point cloud.  Recap files supplied for Model federation. Recap “Real View” output
  • 32. #BSL2015 5 Broadgate Base Build Integration Clash Management process for Base Build
  • 33. #BSL2015 5 Broadgate Base Build Integration  Impact of RWP reviewed in the BIM workshop.  Informed decisions could be made to suit Fit out and Base build install’s.  Amendments absorbed into programmed works.
  • 34. #BSL2015 5 Broadgate Base Build Integration  Fully Co-ordinated Solutions
  • 35. #BSL2015 5 Broadgate BIM Output  Advanced BIM Co-ordination completed – September 2014  24 Week programme  Team peaked @ 28 People
  • 36. #BSL2015 5 Broadgate BIM Output  Full set of Co-ordinated “MEP Installation Drawings” prior to Trade Contractor appointment, for incorporation into tender process.  Outstanding TQ’s enabled risks to be managed.  Minimal Trade contractor co-ordination required thereafter.
  • 37. #BSL2015 5 Broadgate Constructability  Trading Floor – Low Level MODELPROTOTYPEVISION
  • 40. #BSL2015 5 Broadgate Constructability FABRICATE & BUILD WITH CONFIDENCE – PROGRAMME – QUALITY – CO-ORDINATION – FUNCTION – COST MODELPROTOTYPEVISION
  • 41. #BSL2015 5 Broadgate Stage 1 Complete Summary & Learnings  Keeping and managing the risk makes sense.  Change management  Clash management  Procurement benefits  Don’t underestimate the value of Laser Scanning for continual validation.  Prototyping still has a big part to play.
  • 42. #BSL2015 5 Broadgate Stage 2 & 3 continues  Trades are now appointed.  Site Mobilised.  Further prototyping and mock up with trades.  Ibsecad novated to continue the final detailing with the Mechanical Contractor.  As Co-ordination has been completed Trades are focusing on Sequencing, Final procurement & Model enrichment.
  • 43. #BSL2015 5 Broadgate Workflows Architecture / Non-MEP MEP Revit model to remain intact for Space planning tools Process to allow for multiple Architectural trades inputting simultaneously Model enriched with data in accordance with BEP Use of Stage 1 models for all MEP Trades Models developed with final equipment selection Generation of Master Revit file for Fit-out Model enriched with data in accordance with BEP
  • 45. #BSL2015 5 Broadgate Model enrichment  Analysis of FM integration between platformsEIR COBie
  • 46. #BSL2015 5 Broadgate Model enrichment  Development of UBS Structured Data Template  Enables data to be passed to CMMS and Space planning solutions with no data duplication. Output = Universal Golden Rules
  • 47. #BSL2015 5 Broadgate Integration for FM  Delivering Information enriched Revit Architecture model  Delivering Asset referenced MEP Models  Delivering Structured database for all existing FM platforms  Tested the market for Integration of model with O&Ms
  • 48. #BSL2015 5 Broadgate Stage 2 & 3 Summary Summary & Learnings to date  Mixed capability in the supply chain  Need help, guidance & support.  Trade contractors are engaged on data input and generating feedback  The work completed now is informing the soft landings in Stage 4.
  • 49. #BSL2015 5 Broadgate Stage 4 – Soft Landing Development of Business Change Management  Process Mapping  Operation & Management efficiencies  Improved Information management  Upskilling & re-deployment  Operational execution plan  Integrated asset management – o Not only MEP…  Improve response times to business needs MOVING TOWARDS AN INTELLIGENT BUILDING WITH INFORMED CLIENTS
  • 50. #BSL2015 5 Broadgate  Start with the end in mind…  Be prepared to change course…  Keeping and managing the risk makes sense…  Early co-ordination massively de risks the construction phase…  Engage with the supply chain at every opportunity…  If you are not effective and managing data / information in operations now, BIM will not solve this for you.  HAVE FUN Summary

Editor's Notes