Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 1
BUILDING CONSTRUCTION 1
Project 2: Construction Activities and Process
AIMI RUZANNA BINTI DATUADZMAN
0306177
Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 2
WEEK 1
ConstructionActivity : Site Clearance
Duration: 6 Days
Materials:Steel Fencing
Equipment: Excavator, BumpTruck, Dozer, SurveyEquipment
Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 3
SkilledWorker: 5 General Workers,2 Truck/DozerOperators
Technical Information:
 Contractor needsto establishthe site boundary due tothe commencementof the site
clearing
 Contractor shall produce asafety signboardtonotifyandalertthe publicaboutthe
constructionworksconducted
 Contractorsshall alsosubmittheirproposed dumpingsite forapproval due tosite clearingto
the superintendingofficer
WEEK 2
ConstructionActivity : Excavationand Earth Works
Duration: 6 Days
Materials:Natural Soil
Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 4
Equipment:Excavator,Pay loader,Six Wheel Truck,BobCat,Shovel,MeterTape,Rollers,Dump
Truck, Backhoes
SkilledWorker: 5 General Workers,TruckDriver,ExcavatorOperator,Contractor
Technical Information:
• Before beginningthe site clearingwork,the areatobe excavatedshall be properly
markedand cleared.
• The surveyorneedtoperiodicallycheckthe depthof excavation toavoidover
excavation
WEEK 3
ConstructionActivity: Pile boringandreinforcementinstallation
Duration: 7 days
Materials:Steel Bore,Reinforcementbar,bar bender
Equipment:Rebar Bendingmachine,BoringMachine
SkilledWorker:5 General Workers,BoringMachine Operator,BarBendingMachine
Technical Information:
• Surveyandrecord the existinggroundlevelateachpile location.
• Setout the pile locationinaccordance withthe Engineer’sworkingdrawingsusinga
theodolitewiththe accuracyrequiredinthe specifications.
• All settingoutshouldrefertothe reference pointsandthe relatedContractDrawings.
Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 5
WEEK 4
ConstructionActivity : Pile boringandreinforcementinstallation
Duration: 6 days
Materials:Steel Bore,Reinforcementbar,bar bender
Equipment:Rebar Bendingmachine,BoringMachine
SkilledWorker: 5 General Workers,BoringMachine Operator,BarBendingMachine
Technical Information:
The locationof the centerof each boredpile willbe setoutbyreference tothe workingdrawings
and the site boundarymarkers.The shaftwill be excavatedwithinaheavytemporarysteel casing
withan outside diameterof 1.5m.The casingiscomposedof sectionsof 6 to 8m single lengthswith
50mm wall thickness.Thereisaspecial cuttingshoe atthe toe of the casingfor the bottomsection.
The casing sectionisconnectedtogetherusingspecial casingjoints.The casingwill be drivenusing
hydrauliccasingoscillatorconnectedtoa crawler crane.
Aftersetting-upthe casingoscillatoroverthe pilinglocation,the firstsectionof the casingwill be
insertedintothe oscillatoranditspositionandverticallyshall be checkedpriortocommencing
excavationandregularityduringconstruction.The pile shaftexcavationwillbe carriedoutusinga
single orhammergrab supportedfroma crawlercrane.The casing will be advancedbymeansof the
hydrauliccasingoscillatorandthe toe of the temporarycasingwill be keptinfrontof the excavated
level.
The water level withinthe pile shaftwillbe maintainedatorabove the surroundinggroundwater
level toensure thatthere isnodifferential headencouragingpipingof the soil atthe base of the
excavation.
Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 6
WEEK 5
ConstructionActivity : Pile Filling
Duration: 6 days
Materials:Concrete
Equipment:Concrete mixer,Concrete dispenser,Concrete vibrator
SkilledWorker:4 General Workers
Technical Information:
Concretingtothe pile will be carriedoutunderwaterbytremie techniquesmaintainingthe water
headinside the casingator above existinggroundwaterlevel atall times. 6.5.2 The workabilityof
the concrete will be testedbyslumptestsonsamplestaken fromeachbatch.A setof two cubeswill
be made for each 25m3 of concrete fortestingat28 daysas specifiedinthe particularspecifications.
Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 7
WEEK 6
ConstructionActivity : Pile Capconstruction
Duration: 6 days
Materials:Concrete,Reinforcement,Timberformwork
Equipment:Bar BendingMachine,Saw,VibratingMachine,Concrete Mixer
SkilledWorker:3 General Workers,3Bar benders,2carpenters
Technical Information:
• Formworkiserectedaccordingto the design
• Fix pile capreinforcementinthe framework
• Applysufficientvibration
Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 8
• Pile capsdistributesthe loadfromthe above structure evenlythroughtothe piles
below.
WEEK 7
ConstructionActivity 1 : Pile Capconstruction
Duration: 5 days
Materials:Concrete,Reinforcement,Timberformwork
Equipment:Bar BendingMachine,Saw,VibratingMachine,Concrete Mixer
SkilledWorker:3 General Workers,3Bar benders,2carpenters
Technical Information:
• Formworkiserected accordingto the design
• Fix pile capreinforcementinthe framework
• Applysufficientvibration
Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 9
• Pile capsdistributesthe loadfromthe above structure evenlythroughtothe pilesbelow.
ConstructionActivity 2 : Stumpon Pile Cap
Duration: 5 days
Materials:Concrete,Reinforcement,Timberformwork
Equipment:Bar BendingMachine,Saw,VibratingMachine
SkilledWorker:4 General Workers,3Bar benders,2carpenters
Technical Information:
• To realignthe level of the substructure toensure the groundfloorand corresponding
floorsare leve
WEEK 8
ConstructionActivity 1 : Ground BeamConstruction
Duration: 6 days
Materials:Concrete,reinforcements,timberformworks
Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer
SkilledWorker:3 General Workers,3 Bar benders,2carpenters
Technical Information :
Afterconstructingthe foundation,the groundbeamwill fill upthe excavatedareawithearth.
A groundbeamnormallyshouldconsistof reinforcements,concrete andlinkers. The reinforcements
can be placedatcenterof that beam. The sizesof mainreinforcementplayimportantrole in
determine the strengthof abeam.
Ground beamusuallydoes nothave secondarybeam, onlyhasprimarybeam. The groundbeam
constructionwill be startedafteracolumnstumphas finish.Afterthe columnstumphasingrainedin
foundationandhascorpulentonlevel aswanted.
Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 10
ConstructionActivity 2 : Stumpon Pile Cap(Gridd-i)
Duration: 5 days
Materials:Concrete,Reinforcement,Timberformwork
Equipment:Bar BendingMachine,Saw,VibratingMachine
SkilledWorker:3 General Workers,3Bar benders,2carpenters
Technical Information:
To realignthe level of the substructure toensure the groundfloorand correspondingfloorsare
level
WEEK 9
ConstructionActivity: Ground BeamConstruction
Duration: 7 days
Materials:Concrete,reinforcements,timberformworks
Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer
SkilledWorker:3General Workers,3 Bar benders,2carpenters
Technical Information:
Beam frameworkwill putandpointedstake setinthe groundwithtidysothatlooktoughand
strength.Strengthof frameworkisimportanttoensure thatframeworknotexpandwhenaconcrete
will instill.If frameworknotgood,itwill give aproblemandthe constructionworkhave muchtime.
Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 11
Afterthat,linkconcrete islainouton groundsurface intothe framework.The reinforcements
will be puttedwithspacerblockonbelow andbeside reinforcement.Purposethatputtedthe spacer
blockisto protect the reinforcementforavoidfromrust.
WEEK 10
ConstructionActivity: Ground FloorSlabConstruction
Duration: 7 days
Materials:Concrete,reinforcementbars,timberformworks,DampProof Membrane (DPM),Rigid
FloorInsulation
Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer
SkilledWorker:5 General Workers,3Bar benders,2carpenters
Technical Information:
Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 12
Firstcondition- isbuiltwhenthe groundisgoodenoughtocarry the loadfrom the building.Inthis
condition,the slabisdesignedtocarry the loadof the buildingwiththe helpfromthe ground
support.
Secondcondition- isbuildingwhenthe groundisnotgoodenoughtocarry the loadfrom the
building.Inthiscondition,the slabisdesignjustlikethe floorof upperfloorthatcancarry the load
withoutthe helpfromthe groundsupport.Inthiscase,more costis needed.
Functionof groundslab
• To supportcolumnand stump
• To receive the loadfromthe building
• To reduce the pressure onthe columnand stump
• The main base of constructionto ensure that the constructionwill done well
• Make iteasierforfloorfinishes
WEEK 11
ConstructionActivity: Ground FloorSlabConstruction
Duration: 7 day
Materials:Concrete,reinforcementbars,timberformworks,DampProof Membrane (DPM),Rigid
FloorInsulation
Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer
SkilledWorker:5General Workers,3 Bar benders,2carpenters
Technical Information:
Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 13
• Have the slabreinforcingtiedintothe foundationwallreinforcing.
• Incorporate a damp-proof membrane (DPM) underthe concrete slab.
• Damp proofingof newconcrete slabsisbestcarriedoutas for a standard house
• slab,withthe polyethylene DPMor proprietaryconcrete underlaylaidoversand
blinding(nominal minimumthicknessof 5mm or a maximum.thicknessof 25mm)
before the slabislaid.
• Jointsshouldbe tapedandthe DPM protectedfromdamage duringthe placingof
reinforcingandconcreting.
• Have the finishedfloorlevelatleast100 mm above the highestadjacentgroundlevel.
• Have concrete well vibratedandfree of voidsandcavities,asthese are potentialweak
spotswhenthe floorisloaded.
• Have a minimumslabthicknessof 100 mm.
• Be laidovera minimumof 75 mm thick(maximumpermitted600 mm) well compacted
hard fill.Whenover150 mm thick,compact in150 mm maximumlayersusinga
vibratingplate compactor.
WEEK 12
ConstructionActivity: Ground FloorColumns(grida-c)
Duration: 6 days
Materials:Concrete,reinforcement,timberformwork
Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer
SkilledWorker:5 General Workers,3Bar benders,2carpenters
Technical Information:
Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 14
• Layingcementconcrete infoundation
• Placingsteel barnetinfootingasper designandalsoplacingvertical barsof columninfootingon
the steel barnet as perdesign.
• Layingformworkin footing.
• Layingcementconcrete 1: 2:4 or 1:1-1/2:3 infootingupto requiredheightasperdesign.
• Curingworkand refillingof eartharoundfooting
WEEK 13
ConstructionActivity: Ground FloorColumns
Duration: 6 days
Materials:Concrete,reinforcement,timberformwork
Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer
SkilledWorker:5 General Workers,3Bar benders,2carpenters
Technical Information:
Afterthe constructionof footingandpedestal the constructionof columnisstarted.The processof
constructionisfollowing.
Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 15
• Tie upall ringsaroundand intovertical steel barsaccordingtodesign.
•Fix formwork of requiredsize withvertical steelbars.
• Lay cementconcrete informworkaccordingto design.
• Take propercuringof RCC column
WEEK 14
ConstructionActivity: FirstFloorBeam
Duration: 5 days
Materials:Concrete,reinforcement,timberformwork
Equipment:Concrete Vibrator, Rebarbendingmachine,table saw,concrete mixer
SkilledWorker:5 General Workers,3Bar benders,2carpenters
Technical Information:
The firstflooris supportedbythe foundation. –Completionof the lowerfloor(usuallyjustafterthe
Concretingwhichwascarriedouton the day before) Removingof the wall formpanel andlifttothe
upperfloorforerection. Innerwall panel erectedwithreinforcingbarbeingfixed.
Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 16
Completionof the wall formworkandthe reinforcement(includinginspectionof the reinforcing
bars)Erectionof the floorformworkincludingthe proppingandjoistgridframe (alsothe beam
formworkif there isbeamsinthe structural design)
Completionof the floorreinforcement.Final re-adjustandsecure the wall andfloorformworkready
for the concretion.
The completedwall andfloorformworkwiththe floorreinforcementbeingfixed.Workstodo
before concretingare:
 Final inspectionof the steelfixing,
 checkthe shape,level,verticality,andalignmentof all the formworkelements,
 checkwhetherthe conditionof formworkisfirmandsecure enoughtowithstandthe
concretingprocess,
 provide andinstall the equipmentreadyforthe carryingout of concretingworks.
WEEK 15
ConstructionActivity: FirstFloorSlab
Duration: 5 days
Materials:Concrete,reinforcement,timberformwork,DPM
Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 17
Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer
SkilledWorker:5 General Workers,3Bar benders,2carpenters
Technical Information:
The slab iscast integrally withthe beamswhichprovide supportintwodirection.Beamsare
supportedoninnerleaf of cavitywall.Closure blockbedded. Twobeamsgroutedtogetherto
supportblockpartition. Beamisadjacenttosupportwall and groutedsolid.CoursingSlipwithblock
out frombeamintoadjacent supportwall beddedoncoursingslip. Closure Blockoninternal
support. Sharedbearingoninternal supportwall lessthan200mmthick.
WEEK 16
ConstructionActivity: First FloorColumns
Duration: 5 days
Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 18
Materials:Concrete,reinforcement,timberformwork
Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer
SkilledWorker:4 General Workers,3Bar benders,2carpenters
Technical Information:
Structural columnsare builtto bearthe load fromsuperstructure above and transferit
downwardsintofoundation.
The processof constructionisfollowing:
• Tie upall ringsaroundand intovertical steel barsaccordingtodesign.
• Fix formworkof requiredsize withvertical steel bars.
• Lay cementconcrete informworkaccordingto design.
• Take propercuringof RCC column
WEEK 17
ConstructionActivity: First FloorColumns
Duration: 5 days
Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 19
Materials:Concrete,reinforcement,timberformwork
Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer
SkilledWorker:4 General Workers,3Bar benders,2carpenters
Technical Information:
Structural columnsare builtto bearthe load fromsuperstructure above and transferit
downwardsintofoundation
The processof constructionisfollowing.
• Tie upall ringsaroundand intovertical steel barsaccordingtodesign.
• Fix formworkof requiredsize withvertical steel bars.
• Lay cementconcrete informworkaccordingto design.
• Take propercuringof RCC column
WEEK 18
ConstructionActivity: FirstFloorBeam
Duration: 5 days
Materials:Concrete,reinforcement,timberformwork
Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer
SkilledWorker:4 General Workers,3Bar benders,2carpenters
Technical Information: Superstructure columnsare connecttogetherviabeams, theyresistapplied
loadswitha rebar fromthe columns.
• Completionof the lowerfloor(usuallyjustafterthe
Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 20
• Concretingwhichwascarriedouton the day before) Removingof the wall formpanel
and lifttothe upperfloorfor erection.
• Innerwall panel erectedwithreinforcingbarbeingfixed.
• Completionof the wall formworkandthe reinforcement(includinginspectionof the
reinforcingbars)
• Erectionof the floorformworkincludingthe proppingandjoistgridframe (alsothe
beamformworkif there isbeamsinthe structural design)
• Completionof the floorreinforcement.Final re-adjustandsecure the wall andfloor
formworkreadyforthe concretion.
• The completedwall andfloorformworkwiththe floorreinforcementbeingfixed.Works
to do before concretingare:
- Final inspectionof the steelfixing,
- checkthe shape,level,verticality,andalignmentof all the formworkelements,
- checkwhetherthe conditionof formworkisfirmandsecure enoughtowithstand
the concretingprocess,
- provide andinstall the equipmentreadyforthe carryingout of concretingworks.
WEEK 19
ConstructionActivity: SecondFloorSlab
Duration: 5 days
Materials:Concrete,reinforcement,timberformwork,DPM
Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer
Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 21
SkilledWorker:5 General Workers,3Bar benders,2carpenters
Technical Information:
The slab iscast integrally withthe beamswhichprovide supportintwodirection
• Have the slabreinforcingtiedintothe foundationwallreinforcing.
• Incorporate a damp-proof membrane (DPM) underthe concrete slab.
• Damp proofingof newconcrete slabsisbestcarriedoutas for a standard house
• slab,withthe polyethylene DPMor proprietaryconcrete underlaylaidoversand
blinding(nominal minimumthicknessof 5mm or a maximum.thicknessof 25mm)
before the slabislaid.
• Jointsshouldbe tapedandthe DPM protectedfromdamage duringthe placingof
reinforcingandconcreting.
• Have the finishedfloorlevelatleast100 mm above the highestadjacentgroundlevel.
• Have concrete well vibratedandfree of voidsandcavities,asthese are potentialweak
spotswhenthe floorisloaded.
• Have a minimumslabthickness of 100 mm.
• Be laidovera minimumof 75 mm thick(maximumpermitted600 mm) well compacted
hard fill.Whenover150 mm thick,compact in150 mm maximumlayersusinga
vibratingplate compactor.
WEEK 20
ConstructionActivity: Second FloorColumns(grida-c)
Duration: 5 days
Materials:Concrete,reinforcement,timberformwork
Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 22
Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer
SkilledWorker:5 General Workers,3Bar benders,2carpenters
Technical Information:
Structural columnsare builttobear the loadfromsuperstructure above and transferit
downwardsintofoundation
The processof constructionisfollowing:
• Tie upall ringsaroundand intovertical steel barsaccordingtodesign.
• Fix formworkof requiredsize withvertical steel bars.
• Lay cementconcrete informworkaccordingto design.
• Take propercuringof RCC column
WEEK 21
ConstructionActivity: Second FloorColumns
Duration: 5 days
Materials:Concrete,reinforcement,timberformwork
Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer
Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 23
SkilledWorker:5 General Workers,3Bar benders,2carpenters
Technical Information: Structural columnsare builtto bearthe load fromsuperstructure above and
transferit downwardsintofoundation
WEEK 22
ConstructionActivity : Ground FloorStairs
Duration: 6 days
Materials:Concrete,reinforcement,timberformwork
Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer
Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 24
SkilledWorker:5 General Workers,3Bar benders,2carpenters
Technical Information:
Stairsconnectindividual floorstogetherbymeansof a seriesof incremental stepsthatallow a
humanto graduallyclimb.The stairsisbuiltfroma starterbox,whichisa seriesof starterbars
protrudingfromthe groundfloorslab.Thentimberformworkis make at the desiredpitch.The
tread(depth) andriser(height) iscarefullymade toa uniformspecifications.The half turnstairsturns
180 degreesthrough tworightanglesatan interveninglanding.Thisspace floorspace onthe
relevantfloorplans.
WEEK 23
ConstructionActivity 1: FirstFloorStairs
Duration: 6 days
Materials:Concrete,reinforcement,timberformwork
Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer
SkilledWorker:5 General Workers,3Bar benders,2carpenters
Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 25
Technical Information:
Stairsconnectindividual floorstogetherbymeansof a seriesof incremental stepsthatallow a
humanto graduallyclimb.The stairsisbuiltfroma starterbox,whichisa seriesof starterbars
protrudingfromthe groundfloorslab.Thentimberformworkis make at the desiredpitch.The
tread(depth) andriser(height) iscarefullymade toa uniformspecifications.The half turnstairsturns
180 degreesthrough tworightanglesatan interveninglanding.Thisspace floorspace onthe
relevantfloorplans.
WEEK 24
ConstructionActivity : Ground FloorWall
Duration: 5 days
Materials:Concrete,reinforcement,timberformwork
Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer
SkilledWorker:4 General Workers,3Bar benders,2carpenters
Technical Information:
A wall constructionprocessforbuildingawall comprisingthe stepsof:
a) providingaconcrete footinghavingapluralityof vertical dowelseachextendingupwardly
therefromtoa pointpasta top of the wall to be constructed;
Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 26
b) Constructinga reinforcingscreenbyattachingscreenreinforcingbarstoandacross said plurality
of vertical dowelsandprovidingapluralityof spacers;
c) Placingsaidpluralityof spacersadjacenttosaidreinforcingscreeninamannersuchthat said
spacersdefine aplane againstwhichasubstantiallyplanarsurface maybe positioned;
d) Providingapluralityof sheetsof afoam insulatingmaterial havingafirstand secondsubstantially
planarsurface;
e) Positioningone of saidfirstandsecondsurfacesagainstsaidspacers;
f) Providingapluralityof sheetsof sheet-formlathe;
g) positioningsaidpluralityof sheetsof sheet-formlathe againstsaidremainingfirstandsecond
surfacesof saidfoam insulationthatare notagainstsaidspacers;
h) fasteningsaidpluralityof sheetsof sheet-formlathe,saidpluralityof sheetsof foaminsulation
material,saidspacers,andsaidreinforcingscreentogetherinamannersuchthat each sheetof said
pluralityof sheetsof foaminsulationmaterial isincontactwithat leastone spacer;and
j) Blowinga blownconcrete mixtureagainstsaidpluralityof sheetsof foaminsulationmaterial from
a directionwhereinsaidreinforcingscreenispositionedbetweensaidpluralityof sheetsof foam
insulationmaterial andsaidnozzle fromwhichsaidblownconcrete isdischarged.
WEEK 25
Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 27
ConstructionActivity : Ground FloorWall & FirstFloorWall
Duration: 5 days
Materials:Concrete,reinforcement,timberformwork
Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer
SkilledWorker:4 General Workers,3Bar benders,2carpenters
WEEK 26
Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 28
ConstructionActivity : Ground FloorWall & FirstFloorWall
Duration: 7 days
Materials:Concrete,reinforcement,timberformwork
Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer
SkilledWorker:4 General Workers,3Bar benders,2carpenters
WEEK 27
Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 29
ConstructionActivity1 : GroundFloorWall
Duration: 7 days
Materials:Concrete,reinforcement,timberformwork
Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer
SkilledWorker:4 General Workers,3Bar benders,2carpenters
ConstructionActivity 2: GroundFloordoor framingandinstallation
Duration: 2 days
Materials:Hollowsingle rabbetmetal frame
Equipment:Wrench,Level,ScrewDriver,measuringtape,marker
SkilledWorker:2 General Workers,1Special Worker
Technical Information:
:Doors are openingsbetweenexteriorandinterior,andbetweenrooms.Theyare carefully
positionedbetweencolumnswherethe wall will eventuallybe made.Doorsare correctlyorientedas
to whethertheyopeninorout and stoodupright withwoodtemporarilynailedtocolumnsand
beams.
ConstructionActivity 3: GroundFloorwindow framingandinstallation
Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 30
Duration: 3 days
Materials:Aluminumcasementframe,glasswindow,screws
Equipment:Wrench,Level,ScrewDriver,measuringtape,marker
SkilledWorker:2 General Workers,1Special Worker
Technical Information:
: : Windowsprovide ventilationforabuilding,acasementwindow provides100% ventilation.A
windowframe isfirstinstalled,followedbythe twosmallerwindowsandtheirpivotbrackets,the
unitistoppedoff withtrimmingforaesthetics
Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 31
WEEK 28
ConstructionActivity 1 : SecondFloorBeam
Duration: 4 days
Materials:Concrete,reinforcement,timberformwork
Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer
SkilledWorker: 4 General Workers,3 Bar benders,2carpenters
ConstructionActivity 2: GroundFloordoor framingand installation
Duration: 2 days
Materials:Hollowsingle rabbetmetal frame
Equipment:Wrench,Level,ScrewDriver,measuringtape,marker
SkilledWorker:2 General Workers,1Special Worker
Technical Information:
:Doors are openingsbetweenexteriorandinterior,andbetweenrooms.Theyare carefully
positionedbetweencolumnswherethe wall will eventuallybe made.Doorsare correctlyorientedas
to whethertheyopeninorout and stoodupright withwoodtemporarilynailedtocolumnsand
beams.
Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 32
ConstructionActivity 3: GroundFloorwindow framingandinstallation
Duration: 3 days
Materials:Aluminumcasementframe,glasswindow,screws
Equipment:Wrench,Level,ScrewDriver,measuringtape,marker
SkilledWorker:2 General Workers,1Special Worker
Technical Information:
: : Windowsprovide ventilationforabuilding,acasementwindow provides100% ventilation.A
windowframe isfirstinstalled,followedbythe twosmallerwindowsandtheirpivotbrackets,the
unitistoppedoff withtrimmingforaesthetics
Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 33
WEEK 29
ConstructionActivity : SecondFloorWall,Railing
Duration: 6 days
Materials:Concrete,reinforcement,timberformwork
Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer
SkilledWorker: 4 General Workers,3 Bar benders,2carpenters
ConstructionActivity 2: GroundFloordoor framingand installation
Duration: 2 days
Materials:Hollowsingle rabbetmetal frame
Equipment:Wrench,Level,ScrewDriver,measuringtape,marker
SkilledWorker:2 General Workers,1Special Worker
Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 34
Technical Information:
:Doors are openingsbetweenexteriorandinterior,andbetweenrooms.Theyare carefully
positionedbetweencolumnswherethe wall will eventuallybe made.Doorsare correctlyoriented as
to whethertheyopeninorout and stoodupright withwoodtemporarilynailedtocolumnsand
beams.
ConstructionActivity 3: GroundFloorwindow framingandinstallation
Duration: 3 days
Materials:Aluminumcasementframe,glasswindow,screws
Equipment:Wrench,Level,ScrewDriver,measuringtape,marker
SkilledWorker:2 General Workers,1Special Worker
Technical Information:
: : Windowsprovide ventilationforabuilding,acasementwindow provides100% ventilation.A
windowframe isfirst installed,followedbythe twosmallerwindowsandtheirpivotbrackets,the
unitistoppedoff withtrimmingforaesthetics
Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 35
WEEK 30
ConstructionActivity : Roof Trusses
Duration: 5 days
Materials:Concrete,reinforcement,timberformwork
Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer
SkilledWorker: 4 General Workers,3 Bar benders,2carpenters
Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 36
Technical Information:
The firststepin coveringroof isto erecta scaffoldtoa heightwhichwill bring
the eavesaboutwaist-hightoaman standingonthe scaffold.
Before anyroof coveringisapplied,the roof sheathing mustbe sweptcleanand
carefullyinspectedforirregularities,cracks,holes,orotherdefects.Noroofingshouldbe applied
unlessthe sheathingboardsare absolutelydry.
An underlayof roofingfeltisfirstappliedtothe sheathing.Roofingfeltusuallycomesin
3-foot-widerollsandshouldbe laidwitha2-inchtoplap and a 4-inchside lap.
Bundlesof shinglesshouldbe distributedalongthe scaffoldbeforeworkbegins.There
are 27 stripsina bundle of 1 x 3 asphaltstripshingles.Three bundleswillcover100square feet.
Afterthe firstcourse at the eaves(the startercourse) islaidbyinvertingthe first
Course of shinglesorthe starterstripof mineral-surfacedroll roofing,eachcourse
that followsisbegunbystretchingaguidelineorbysnappinga chalkline from
edge to edge.Thispositionsthe course.
Stripshinglesshouldbe nailedwith1-inchcopperorhot-dipped,galvanizedroofingnails,twoto
each tab;this meanssix nailstoeachfull strip.Nailsshouldbe placedabout61/2 inchesfromthe
butt edgestoensure thateachnail will be coveredbythe nextcourse (blind-nailing)anddriven
throughtwo courses.
An asbestos-cementroof islaidinaboutthe same way as the asphaltstripshingles.
A binderisusedtobondthe roofingfelttogetherandforma watertightseal.Asphaltand
coal tar are the two maintypesof bituminousbindersused.
Dryingout of the bindercausesdeteriorationof built-uproofs.
If this didnothappen,a built-uproof wouldlastindefinitely.Asphaltisthe preferred
binder.Itisusedon roofsslopingupto 6 inchesperfoot(1/4 pitch).Asphalthasamelting
pointof 350' to 41 0°F. A roof coveredwithasphaltshouldbe protectedwithacoveringof
slag,gravel,or otherprotective material.Tarhasa lowermeltingpoint(300°to 350°F)
than asphalt,soit will move more easily;therefore,itisnotrecommendedforroofshavinga
slope of more than 3 inchesperfoot(1/8 pitch).
Aggregate,crushedstone,orgravel from1/4 to 5/8 inchin diameteris embeddedinacoat of
asphaltor tar to holdthe roof coveringdown.Italsopreventsthe bindingfromdisintegrating
because of the weather.
Gravel stopson slagor gravel-surfacedroofs,andmetal-edge stripsonsmooth-surfaced
built-uproofsare usedto finishall exposededgesandeavestopreventwindfromgetting
underthe edgesandcausingblowoffs.The gravel stopalsopreventsthe lossof gravel or
slagoff the edge of the roof.The flashingflange of the gravel stoporedge stripisplaced
overthe last plyof felt.Itshouldbe nailedsecurelytothe roof deckand double feltstripped.
Thenthe finishedcoatof bitumenandsurfacingorcap sheetshouldbe applied.The lipof the
gravel stopshouldextendaminimumof 3/4inch above the roof deck. The lipof the edge strip
shouldbe a maximumof 1/2 inch above the deck.Bothshouldbe securelyfastenedtothe fascia
board
Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 37
WEEK 31
ConstructionActivity : Roof
Duration: 4 days
Materials:Concrete,reinforcement,timberformwork
Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer
SkilledWorker: 4 General Workers,3 Bar benders,2carpenters
Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 38
Week 32
ConstructionActivity: Electrical Wiring
Duration: 7 days
Materials:insulatedcooperwires,electrical tape,andconnector
Equipment:Testpen,voltage meter
SkilledWorker:2 electricians
Technical Information: Electrical cablesare pulledthroughPVCpipe ambeddedinthe concrete
wallsoralong the wall surface.
Week 33:
ConstructionActivity: Plumbing
Duration: 7 days
Materials:assorteddimensionsof PVCpipe,connectors,PVCglue
Equipment:Saw,measuringtape
SkilledWorker:Plumber
Technical Information: Plumbingisessential forbringingincleanwaterintoabuildingandtaking
waste productsaway.PVCpipesare piecedtogether,inordertoconnectvarioussystemstogether.
Week 34:
Construction Activity:SanitaryFittings
Duration: 5 days
Materials:Ceramics
Equipment:Saw,Measuringtape,drill
SkilledWorker:Special Worker,2 General Workers
Technical Information: Sanitaryfittingssuchassick,waterclosetand showerare usuallyboughtas
modularunitsandare easilyinstalled.Justconnectthe plumbingtothe inletandoutlet,andensure
the fasteningissecure.
Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 39
Week 35:
ConstructionActivity: Tiling (GroundFloor)
Duration: 5 days
Materials:Mortar, Grout, homogeneousceramictiles
Equipment:Puttyknife,spacers,level
SkilledWorker:2 Tilers
Technical Information: Tilesare a durable,easytocleanmodularfinishthatrequirescareful
installationinordertolasta longtime.A tilingpatternisfirstdeterminedandthe tilerspreadmortar
on the floorsurface.The tilesare uniformlyspacedandalignwiththe aidof spacers.The gapsare
made to allowforexpansionandare filledwithgrout.
Week 36:
ConstructionActivity : Tiling(SecondFloor)
Duration: 5 days
Materials:Mortar, Grout, homogeneousceramictiles
Equipment:Puttyknife,spacers,level
SkilledWorker:2 Tilers
Technical Information: Tilesare a durable,easytocleanmodularfinishthatrequirescareful
installationin ordertolasta longtime.A tilingpatternisfirstdeterminedandthe tilerspreadmortar
on the floorsurface.The tilesare uniformlyspacedandalignwiththe aidof spacers.The gapsare
made to allowforexpansionandare filledwithgrout.
Week 37:
ConstructionActivity : Tiling (Second Floor)
Duration: 5 days
Materials:Mortar, Grout, homogeneousceramictiles
Equipment:Puttyknife,spacers,level
SkilledWorker:2 Tilers
Technical Information: Tilesare a durable,easytocleanmodular finishthatrequirescareful
installationinordertolasta longtime.A tilingpatternisfirstdeterminedandthe tilerspreadmortar
on the floorsurface.The tilesare uniformlyspacedandalignwiththe aidof spacers.The gapsare
made to allowforexpansionandare filledwithgrout.
Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 40
Week 38:
ConstructionActivity : Plastering(GroundFloor)
Duration: 5 days
Materials:PlasterBoard
Equipment:Ramsetconcrete nailer,Makitaconcrete driller,LaserLevelmachine, Plumbs,Basic
handtools,Makita steel benchcutters,Ceilinggun,Ladder,Steel square ruler,DrillingMachine
SkilledWorker:3 General Workers
Technical Information: All levelingsetoutcoordinatesshall be basedonthe settingoutlevels
providedondesign.
Week 39:
ConstructionActivity: Plastering(firstFloor)
Duration: 5 days
Materials:PlasterBoard
Equipment:Ramsetconcrete nailer,Makitaconcrete driller,LaserLevelmachine,Plumbs,Basic
handtools,Makita steel benchcutters,Ceilinggun,Ladder,Steel square ruler, DrillingMachine
SkilledWorker:3 General Workers
Technical Information: All levelingsetoutcoordinatesshall be basedonthe settingoutlevels
providedondesign.
Week 40:
ConstructionActivity : Plastering(firstFloor)
Duration: 5 days
Materials:PlasterBoard
Equipment:Ramsetconcrete nailer,Makitaconcrete driller,LaserLevelmachine, Plumbs,Basic
handtools,Makita steel benchcutters,Ceilinggun,Ladder,Steel square ruler,DrillingMachine
SkilledWorker:3 General Workers
Technical Information: All levelingsetoutcoordinatesshall be basedonthe settingoutlevels
providedondesign.
Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 41

More Related Content

PDF
Moving Forward with Digital Communications
DOC
Pengurusan kurikulum sk penajis 2012
PPTX
Apprentice cake powerpoint ( runa in charge)
PPTX
Target audience final
DOCX
Transit pbsdst3
PPT
My life with Lifebushido
PDF
Contra quienes tendran que competir nuestro hijos y nietos
PPT
My life with Lifebushido
Moving Forward with Digital Communications
Pengurusan kurikulum sk penajis 2012
Apprentice cake powerpoint ( runa in charge)
Target audience final
Transit pbsdst3
My life with Lifebushido
Contra quienes tendran que competir nuestro hijos y nietos
My life with Lifebushido

Viewers also liked (20)

PPTX
Magnesium & nitrogen
PPTX
Cerpen capa rengat
PPT
Caracteres 2
PPS
Safety managers and engineers histories
DOC
Program upsr2014
DOC
Pasca upsr 2013
DOC
Pengurusan kurikulum sk penajis 2014
PDF
The Phisher's Guide To Building A Website: How Design Live 2015
DOCX
DOCX
Rpt matematik kssr tahun 4
PPTX
Culture & Civilization E-Portfolio
PDF
Residential bulding
PPS
Fabula LA HORMIGA FELIZ
PDF
Masjid negara Publication Book
DOC
Mesyuarat guru 1 2014
DOC
Program Perkhemahan Kanak-kanak
DOCX
History Culture 2 Project 1 : Falling Water by Frank Lloyd Wright
DOC
Post mortem 2013edited
DOC
Soal semester gasal adm. kepegawaian kelas xi
DOCX
consumer preference towards organized retail to unorganized retail
Magnesium & nitrogen
Cerpen capa rengat
Caracteres 2
Safety managers and engineers histories
Program upsr2014
Pasca upsr 2013
Pengurusan kurikulum sk penajis 2014
The Phisher's Guide To Building A Website: How Design Live 2015
Rpt matematik kssr tahun 4
Culture & Civilization E-Portfolio
Residential bulding
Fabula LA HORMIGA FELIZ
Masjid negara Publication Book
Mesyuarat guru 1 2014
Program Perkhemahan Kanak-kanak
History Culture 2 Project 1 : Falling Water by Frank Lloyd Wright
Post mortem 2013edited
Soal semester gasal adm. kepegawaian kelas xi
consumer preference towards organized retail to unorganized retail
Ad

Similar to Building Construction Project 2 Report (7)

PDF
Construction activities and Process
PDF
Bungalow
DOCX
Bcon final report
DOCX
Construction Activities and Process
DOCX
Building Construction 1 - Final Project
PDF
Building Construction process
PDF
Construction Activities and Process
Construction activities and Process
Bungalow
Bcon final report
Construction Activities and Process
Building Construction 1 - Final Project
Building Construction process
Construction Activities and Process
Ad

More from appleManiac (19)

PDF
22 slabs.compressed
PDF
21 superstructure5.compressed
PDF
20 superstructure4.compressed
PDF
19 superstructure3.compressed
PDF
18 superstructure2.compressed
PDF
17 superstructure.compressed
PDF
16 foundation5.compressed
PDF
15 foundation4.compressed
PDF
14 foundation3.compressed
PDF
13 foundation2.compressed
PDF
12 foundation1.compressed
PDF
11 external%20works3.compressed
PDF
10 external%20works2.compressed
PDF
9 external%20works.compressed
PDF
8 bcons%20plants%20and%20machinery%20(pg%202).compressed
PDF
3 intro%20bcons%20first%20site.compressed
PDF
33 bcons%20references%20.compressed
22 slabs.compressed
21 superstructure5.compressed
20 superstructure4.compressed
19 superstructure3.compressed
18 superstructure2.compressed
17 superstructure.compressed
16 foundation5.compressed
15 foundation4.compressed
14 foundation3.compressed
13 foundation2.compressed
12 foundation1.compressed
11 external%20works3.compressed
10 external%20works2.compressed
9 external%20works.compressed
8 bcons%20plants%20and%20machinery%20(pg%202).compressed
3 intro%20bcons%20first%20site.compressed
33 bcons%20references%20.compressed

Recently uploaded (20)

PPTX
Qualitative Qantitative and Mixed Methods.pptx
PPTX
IMPACT OF LANDSLIDE.....................
PPTX
Introduction to Inferential Statistics.pptx
PDF
168300704-gasification-ppt.pdfhghhhsjsjhsuxush
PPT
ISS -ESG Data flows What is ESG and HowHow
PPTX
Acceptance and paychological effects of mandatory extra coach I classes.pptx
PPTX
Copy of 16 Timeline & Flowchart Templates – HubSpot.pptx
PPTX
AI Strategy room jwfjksfksfjsjsjsjsjfsjfsj
PPTX
Managing Community Partner Relationships
PPTX
IBA_Chapter_11_Slides_Final_Accessible.pptx
PPTX
01_intro xxxxxxxxxxfffffffffffaaaaaaaaaaafg
DOCX
Factor Analysis Word Document Presentation
PDF
REAL ILLUMINATI AGENT IN KAMPALA UGANDA CALL ON+256765750853/0705037305
PPTX
modul_python (1).pptx for professional and student
PDF
[EN] Industrial Machine Downtime Prediction
PDF
Global Data and Analytics Market Outlook Report
PPTX
retention in jsjsksksksnbsndjddjdnFPD.pptx
PPTX
CYBER SECURITY the Next Warefare Tactics
PPTX
A Complete Guide to Streamlining Business Processes
PDF
Transcultural that can help you someday.
Qualitative Qantitative and Mixed Methods.pptx
IMPACT OF LANDSLIDE.....................
Introduction to Inferential Statistics.pptx
168300704-gasification-ppt.pdfhghhhsjsjhsuxush
ISS -ESG Data flows What is ESG and HowHow
Acceptance and paychological effects of mandatory extra coach I classes.pptx
Copy of 16 Timeline & Flowchart Templates – HubSpot.pptx
AI Strategy room jwfjksfksfjsjsjsjsjfsjfsj
Managing Community Partner Relationships
IBA_Chapter_11_Slides_Final_Accessible.pptx
01_intro xxxxxxxxxxfffffffffffaaaaaaaaaaafg
Factor Analysis Word Document Presentation
REAL ILLUMINATI AGENT IN KAMPALA UGANDA CALL ON+256765750853/0705037305
modul_python (1).pptx for professional and student
[EN] Industrial Machine Downtime Prediction
Global Data and Analytics Market Outlook Report
retention in jsjsksksksnbsndjddjdnFPD.pptx
CYBER SECURITY the Next Warefare Tactics
A Complete Guide to Streamlining Business Processes
Transcultural that can help you someday.

Building Construction Project 2 Report

  • 1. Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 1 BUILDING CONSTRUCTION 1 Project 2: Construction Activities and Process AIMI RUZANNA BINTI DATUADZMAN 0306177
  • 2. Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 2 WEEK 1 ConstructionActivity : Site Clearance Duration: 6 Days Materials:Steel Fencing Equipment: Excavator, BumpTruck, Dozer, SurveyEquipment
  • 3. Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 3 SkilledWorker: 5 General Workers,2 Truck/DozerOperators Technical Information:  Contractor needsto establishthe site boundary due tothe commencementof the site clearing  Contractor shall produce asafety signboardtonotifyandalertthe publicaboutthe constructionworksconducted  Contractorsshall alsosubmittheirproposed dumpingsite forapproval due tosite clearingto the superintendingofficer WEEK 2 ConstructionActivity : Excavationand Earth Works Duration: 6 Days Materials:Natural Soil
  • 4. Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 4 Equipment:Excavator,Pay loader,Six Wheel Truck,BobCat,Shovel,MeterTape,Rollers,Dump Truck, Backhoes SkilledWorker: 5 General Workers,TruckDriver,ExcavatorOperator,Contractor Technical Information: • Before beginningthe site clearingwork,the areatobe excavatedshall be properly markedand cleared. • The surveyorneedtoperiodicallycheckthe depthof excavation toavoidover excavation WEEK 3 ConstructionActivity: Pile boringandreinforcementinstallation Duration: 7 days Materials:Steel Bore,Reinforcementbar,bar bender Equipment:Rebar Bendingmachine,BoringMachine SkilledWorker:5 General Workers,BoringMachine Operator,BarBendingMachine Technical Information: • Surveyandrecord the existinggroundlevelateachpile location. • Setout the pile locationinaccordance withthe Engineer’sworkingdrawingsusinga theodolitewiththe accuracyrequiredinthe specifications. • All settingoutshouldrefertothe reference pointsandthe relatedContractDrawings.
  • 5. Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 5 WEEK 4 ConstructionActivity : Pile boringandreinforcementinstallation Duration: 6 days Materials:Steel Bore,Reinforcementbar,bar bender Equipment:Rebar Bendingmachine,BoringMachine SkilledWorker: 5 General Workers,BoringMachine Operator,BarBendingMachine Technical Information: The locationof the centerof each boredpile willbe setoutbyreference tothe workingdrawings and the site boundarymarkers.The shaftwill be excavatedwithinaheavytemporarysteel casing withan outside diameterof 1.5m.The casingiscomposedof sectionsof 6 to 8m single lengthswith 50mm wall thickness.Thereisaspecial cuttingshoe atthe toe of the casingfor the bottomsection. The casing sectionisconnectedtogetherusingspecial casingjoints.The casingwill be drivenusing hydrauliccasingoscillatorconnectedtoa crawler crane. Aftersetting-upthe casingoscillatoroverthe pilinglocation,the firstsectionof the casingwill be insertedintothe oscillatoranditspositionandverticallyshall be checkedpriortocommencing excavationandregularityduringconstruction.The pile shaftexcavationwillbe carriedoutusinga single orhammergrab supportedfroma crawlercrane.The casing will be advancedbymeansof the hydrauliccasingoscillatorandthe toe of the temporarycasingwill be keptinfrontof the excavated level. The water level withinthe pile shaftwillbe maintainedatorabove the surroundinggroundwater level toensure thatthere isnodifferential headencouragingpipingof the soil atthe base of the excavation.
  • 6. Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 6 WEEK 5 ConstructionActivity : Pile Filling Duration: 6 days Materials:Concrete Equipment:Concrete mixer,Concrete dispenser,Concrete vibrator SkilledWorker:4 General Workers Technical Information: Concretingtothe pile will be carriedoutunderwaterbytremie techniquesmaintainingthe water headinside the casingator above existinggroundwaterlevel atall times. 6.5.2 The workabilityof the concrete will be testedbyslumptestsonsamplestaken fromeachbatch.A setof two cubeswill be made for each 25m3 of concrete fortestingat28 daysas specifiedinthe particularspecifications.
  • 7. Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 7 WEEK 6 ConstructionActivity : Pile Capconstruction Duration: 6 days Materials:Concrete,Reinforcement,Timberformwork Equipment:Bar BendingMachine,Saw,VibratingMachine,Concrete Mixer SkilledWorker:3 General Workers,3Bar benders,2carpenters Technical Information: • Formworkiserectedaccordingto the design • Fix pile capreinforcementinthe framework • Applysufficientvibration
  • 8. Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 8 • Pile capsdistributesthe loadfromthe above structure evenlythroughtothe piles below. WEEK 7 ConstructionActivity 1 : Pile Capconstruction Duration: 5 days Materials:Concrete,Reinforcement,Timberformwork Equipment:Bar BendingMachine,Saw,VibratingMachine,Concrete Mixer SkilledWorker:3 General Workers,3Bar benders,2carpenters Technical Information: • Formworkiserected accordingto the design • Fix pile capreinforcementinthe framework • Applysufficientvibration
  • 9. Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 9 • Pile capsdistributesthe loadfromthe above structure evenlythroughtothe pilesbelow. ConstructionActivity 2 : Stumpon Pile Cap Duration: 5 days Materials:Concrete,Reinforcement,Timberformwork Equipment:Bar BendingMachine,Saw,VibratingMachine SkilledWorker:4 General Workers,3Bar benders,2carpenters Technical Information: • To realignthe level of the substructure toensure the groundfloorand corresponding floorsare leve WEEK 8 ConstructionActivity 1 : Ground BeamConstruction Duration: 6 days Materials:Concrete,reinforcements,timberformworks Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer SkilledWorker:3 General Workers,3 Bar benders,2carpenters Technical Information : Afterconstructingthe foundation,the groundbeamwill fill upthe excavatedareawithearth. A groundbeamnormallyshouldconsistof reinforcements,concrete andlinkers. The reinforcements can be placedatcenterof that beam. The sizesof mainreinforcementplayimportantrole in determine the strengthof abeam. Ground beamusuallydoes nothave secondarybeam, onlyhasprimarybeam. The groundbeam constructionwill be startedafteracolumnstumphas finish.Afterthe columnstumphasingrainedin foundationandhascorpulentonlevel aswanted.
  • 10. Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 10 ConstructionActivity 2 : Stumpon Pile Cap(Gridd-i) Duration: 5 days Materials:Concrete,Reinforcement,Timberformwork Equipment:Bar BendingMachine,Saw,VibratingMachine SkilledWorker:3 General Workers,3Bar benders,2carpenters Technical Information: To realignthe level of the substructure toensure the groundfloorand correspondingfloorsare level WEEK 9 ConstructionActivity: Ground BeamConstruction Duration: 7 days Materials:Concrete,reinforcements,timberformworks Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer SkilledWorker:3General Workers,3 Bar benders,2carpenters Technical Information: Beam frameworkwill putandpointedstake setinthe groundwithtidysothatlooktoughand strength.Strengthof frameworkisimportanttoensure thatframeworknotexpandwhenaconcrete will instill.If frameworknotgood,itwill give aproblemandthe constructionworkhave muchtime.
  • 11. Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 11 Afterthat,linkconcrete islainouton groundsurface intothe framework.The reinforcements will be puttedwithspacerblockonbelow andbeside reinforcement.Purposethatputtedthe spacer blockisto protect the reinforcementforavoidfromrust. WEEK 10 ConstructionActivity: Ground FloorSlabConstruction Duration: 7 days Materials:Concrete,reinforcementbars,timberformworks,DampProof Membrane (DPM),Rigid FloorInsulation Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer SkilledWorker:5 General Workers,3Bar benders,2carpenters Technical Information:
  • 12. Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 12 Firstcondition- isbuiltwhenthe groundisgoodenoughtocarry the loadfrom the building.Inthis condition,the slabisdesignedtocarry the loadof the buildingwiththe helpfromthe ground support. Secondcondition- isbuildingwhenthe groundisnotgoodenoughtocarry the loadfrom the building.Inthiscondition,the slabisdesignjustlikethe floorof upperfloorthatcancarry the load withoutthe helpfromthe groundsupport.Inthiscase,more costis needed. Functionof groundslab • To supportcolumnand stump • To receive the loadfromthe building • To reduce the pressure onthe columnand stump • The main base of constructionto ensure that the constructionwill done well • Make iteasierforfloorfinishes WEEK 11 ConstructionActivity: Ground FloorSlabConstruction Duration: 7 day Materials:Concrete,reinforcementbars,timberformworks,DampProof Membrane (DPM),Rigid FloorInsulation Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer SkilledWorker:5General Workers,3 Bar benders,2carpenters Technical Information:
  • 13. Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 13 • Have the slabreinforcingtiedintothe foundationwallreinforcing. • Incorporate a damp-proof membrane (DPM) underthe concrete slab. • Damp proofingof newconcrete slabsisbestcarriedoutas for a standard house • slab,withthe polyethylene DPMor proprietaryconcrete underlaylaidoversand blinding(nominal minimumthicknessof 5mm or a maximum.thicknessof 25mm) before the slabislaid. • Jointsshouldbe tapedandthe DPM protectedfromdamage duringthe placingof reinforcingandconcreting. • Have the finishedfloorlevelatleast100 mm above the highestadjacentgroundlevel. • Have concrete well vibratedandfree of voidsandcavities,asthese are potentialweak spotswhenthe floorisloaded. • Have a minimumslabthicknessof 100 mm. • Be laidovera minimumof 75 mm thick(maximumpermitted600 mm) well compacted hard fill.Whenover150 mm thick,compact in150 mm maximumlayersusinga vibratingplate compactor. WEEK 12 ConstructionActivity: Ground FloorColumns(grida-c) Duration: 6 days Materials:Concrete,reinforcement,timberformwork Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer SkilledWorker:5 General Workers,3Bar benders,2carpenters Technical Information:
  • 14. Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 14 • Layingcementconcrete infoundation • Placingsteel barnetinfootingasper designandalsoplacingvertical barsof columninfootingon the steel barnet as perdesign. • Layingformworkin footing. • Layingcementconcrete 1: 2:4 or 1:1-1/2:3 infootingupto requiredheightasperdesign. • Curingworkand refillingof eartharoundfooting WEEK 13 ConstructionActivity: Ground FloorColumns Duration: 6 days Materials:Concrete,reinforcement,timberformwork Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer SkilledWorker:5 General Workers,3Bar benders,2carpenters Technical Information: Afterthe constructionof footingandpedestal the constructionof columnisstarted.The processof constructionisfollowing.
  • 15. Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 15 • Tie upall ringsaroundand intovertical steel barsaccordingtodesign. •Fix formwork of requiredsize withvertical steelbars. • Lay cementconcrete informworkaccordingto design. • Take propercuringof RCC column WEEK 14 ConstructionActivity: FirstFloorBeam Duration: 5 days Materials:Concrete,reinforcement,timberformwork Equipment:Concrete Vibrator, Rebarbendingmachine,table saw,concrete mixer SkilledWorker:5 General Workers,3Bar benders,2carpenters Technical Information: The firstflooris supportedbythe foundation. –Completionof the lowerfloor(usuallyjustafterthe Concretingwhichwascarriedouton the day before) Removingof the wall formpanel andlifttothe upperfloorforerection. Innerwall panel erectedwithreinforcingbarbeingfixed.
  • 16. Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 16 Completionof the wall formworkandthe reinforcement(includinginspectionof the reinforcing bars)Erectionof the floorformworkincludingthe proppingandjoistgridframe (alsothe beam formworkif there isbeamsinthe structural design) Completionof the floorreinforcement.Final re-adjustandsecure the wall andfloorformworkready for the concretion. The completedwall andfloorformworkwiththe floorreinforcementbeingfixed.Workstodo before concretingare:  Final inspectionof the steelfixing,  checkthe shape,level,verticality,andalignmentof all the formworkelements,  checkwhetherthe conditionof formworkisfirmandsecure enoughtowithstandthe concretingprocess,  provide andinstall the equipmentreadyforthe carryingout of concretingworks. WEEK 15 ConstructionActivity: FirstFloorSlab Duration: 5 days Materials:Concrete,reinforcement,timberformwork,DPM
  • 17. Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 17 Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer SkilledWorker:5 General Workers,3Bar benders,2carpenters Technical Information: The slab iscast integrally withthe beamswhichprovide supportintwodirection.Beamsare supportedoninnerleaf of cavitywall.Closure blockbedded. Twobeamsgroutedtogetherto supportblockpartition. Beamisadjacenttosupportwall and groutedsolid.CoursingSlipwithblock out frombeamintoadjacent supportwall beddedoncoursingslip. Closure Blockoninternal support. Sharedbearingoninternal supportwall lessthan200mmthick. WEEK 16 ConstructionActivity: First FloorColumns Duration: 5 days
  • 18. Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 18 Materials:Concrete,reinforcement,timberformwork Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer SkilledWorker:4 General Workers,3Bar benders,2carpenters Technical Information: Structural columnsare builtto bearthe load fromsuperstructure above and transferit downwardsintofoundation. The processof constructionisfollowing: • Tie upall ringsaroundand intovertical steel barsaccordingtodesign. • Fix formworkof requiredsize withvertical steel bars. • Lay cementconcrete informworkaccordingto design. • Take propercuringof RCC column WEEK 17 ConstructionActivity: First FloorColumns Duration: 5 days
  • 19. Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 19 Materials:Concrete,reinforcement,timberformwork Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer SkilledWorker:4 General Workers,3Bar benders,2carpenters Technical Information: Structural columnsare builtto bearthe load fromsuperstructure above and transferit downwardsintofoundation The processof constructionisfollowing. • Tie upall ringsaroundand intovertical steel barsaccordingtodesign. • Fix formworkof requiredsize withvertical steel bars. • Lay cementconcrete informworkaccordingto design. • Take propercuringof RCC column WEEK 18 ConstructionActivity: FirstFloorBeam Duration: 5 days Materials:Concrete,reinforcement,timberformwork Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer SkilledWorker:4 General Workers,3Bar benders,2carpenters Technical Information: Superstructure columnsare connecttogetherviabeams, theyresistapplied loadswitha rebar fromthe columns. • Completionof the lowerfloor(usuallyjustafterthe
  • 20. Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 20 • Concretingwhichwascarriedouton the day before) Removingof the wall formpanel and lifttothe upperfloorfor erection. • Innerwall panel erectedwithreinforcingbarbeingfixed. • Completionof the wall formworkandthe reinforcement(includinginspectionof the reinforcingbars) • Erectionof the floorformworkincludingthe proppingandjoistgridframe (alsothe beamformworkif there isbeamsinthe structural design) • Completionof the floorreinforcement.Final re-adjustandsecure the wall andfloor formworkreadyforthe concretion. • The completedwall andfloorformworkwiththe floorreinforcementbeingfixed.Works to do before concretingare: - Final inspectionof the steelfixing, - checkthe shape,level,verticality,andalignmentof all the formworkelements, - checkwhetherthe conditionof formworkisfirmandsecure enoughtowithstand the concretingprocess, - provide andinstall the equipmentreadyforthe carryingout of concretingworks. WEEK 19 ConstructionActivity: SecondFloorSlab Duration: 5 days Materials:Concrete,reinforcement,timberformwork,DPM Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer
  • 21. Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 21 SkilledWorker:5 General Workers,3Bar benders,2carpenters Technical Information: The slab iscast integrally withthe beamswhichprovide supportintwodirection • Have the slabreinforcingtiedintothe foundationwallreinforcing. • Incorporate a damp-proof membrane (DPM) underthe concrete slab. • Damp proofingof newconcrete slabsisbestcarriedoutas for a standard house • slab,withthe polyethylene DPMor proprietaryconcrete underlaylaidoversand blinding(nominal minimumthicknessof 5mm or a maximum.thicknessof 25mm) before the slabislaid. • Jointsshouldbe tapedandthe DPM protectedfromdamage duringthe placingof reinforcingandconcreting. • Have the finishedfloorlevelatleast100 mm above the highestadjacentgroundlevel. • Have concrete well vibratedandfree of voidsandcavities,asthese are potentialweak spotswhenthe floorisloaded. • Have a minimumslabthickness of 100 mm. • Be laidovera minimumof 75 mm thick(maximumpermitted600 mm) well compacted hard fill.Whenover150 mm thick,compact in150 mm maximumlayersusinga vibratingplate compactor. WEEK 20 ConstructionActivity: Second FloorColumns(grida-c) Duration: 5 days Materials:Concrete,reinforcement,timberformwork
  • 22. Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 22 Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer SkilledWorker:5 General Workers,3Bar benders,2carpenters Technical Information: Structural columnsare builttobear the loadfromsuperstructure above and transferit downwardsintofoundation The processof constructionisfollowing: • Tie upall ringsaroundand intovertical steel barsaccordingtodesign. • Fix formworkof requiredsize withvertical steel bars. • Lay cementconcrete informworkaccordingto design. • Take propercuringof RCC column WEEK 21 ConstructionActivity: Second FloorColumns Duration: 5 days Materials:Concrete,reinforcement,timberformwork Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer
  • 23. Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 23 SkilledWorker:5 General Workers,3Bar benders,2carpenters Technical Information: Structural columnsare builtto bearthe load fromsuperstructure above and transferit downwardsintofoundation WEEK 22 ConstructionActivity : Ground FloorStairs Duration: 6 days Materials:Concrete,reinforcement,timberformwork Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer
  • 24. Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 24 SkilledWorker:5 General Workers,3Bar benders,2carpenters Technical Information: Stairsconnectindividual floorstogetherbymeansof a seriesof incremental stepsthatallow a humanto graduallyclimb.The stairsisbuiltfroma starterbox,whichisa seriesof starterbars protrudingfromthe groundfloorslab.Thentimberformworkis make at the desiredpitch.The tread(depth) andriser(height) iscarefullymade toa uniformspecifications.The half turnstairsturns 180 degreesthrough tworightanglesatan interveninglanding.Thisspace floorspace onthe relevantfloorplans. WEEK 23 ConstructionActivity 1: FirstFloorStairs Duration: 6 days Materials:Concrete,reinforcement,timberformwork Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer SkilledWorker:5 General Workers,3Bar benders,2carpenters
  • 25. Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 25 Technical Information: Stairsconnectindividual floorstogetherbymeansof a seriesof incremental stepsthatallow a humanto graduallyclimb.The stairsisbuiltfroma starterbox,whichisa seriesof starterbars protrudingfromthe groundfloorslab.Thentimberformworkis make at the desiredpitch.The tread(depth) andriser(height) iscarefullymade toa uniformspecifications.The half turnstairsturns 180 degreesthrough tworightanglesatan interveninglanding.Thisspace floorspace onthe relevantfloorplans. WEEK 24 ConstructionActivity : Ground FloorWall Duration: 5 days Materials:Concrete,reinforcement,timberformwork Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer SkilledWorker:4 General Workers,3Bar benders,2carpenters Technical Information: A wall constructionprocessforbuildingawall comprisingthe stepsof: a) providingaconcrete footinghavingapluralityof vertical dowelseachextendingupwardly therefromtoa pointpasta top of the wall to be constructed;
  • 26. Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 26 b) Constructinga reinforcingscreenbyattachingscreenreinforcingbarstoandacross said plurality of vertical dowelsandprovidingapluralityof spacers; c) Placingsaidpluralityof spacersadjacenttosaidreinforcingscreeninamannersuchthat said spacersdefine aplane againstwhichasubstantiallyplanarsurface maybe positioned; d) Providingapluralityof sheetsof afoam insulatingmaterial havingafirstand secondsubstantially planarsurface; e) Positioningone of saidfirstandsecondsurfacesagainstsaidspacers; f) Providingapluralityof sheetsof sheet-formlathe; g) positioningsaidpluralityof sheetsof sheet-formlathe againstsaidremainingfirstandsecond surfacesof saidfoam insulationthatare notagainstsaidspacers; h) fasteningsaidpluralityof sheetsof sheet-formlathe,saidpluralityof sheetsof foaminsulation material,saidspacers,andsaidreinforcingscreentogetherinamannersuchthat each sheetof said pluralityof sheetsof foaminsulationmaterial isincontactwithat leastone spacer;and j) Blowinga blownconcrete mixtureagainstsaidpluralityof sheetsof foaminsulationmaterial from a directionwhereinsaidreinforcingscreenispositionedbetweensaidpluralityof sheetsof foam insulationmaterial andsaidnozzle fromwhichsaidblownconcrete isdischarged. WEEK 25
  • 27. Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 27 ConstructionActivity : Ground FloorWall & FirstFloorWall Duration: 5 days Materials:Concrete,reinforcement,timberformwork Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer SkilledWorker:4 General Workers,3Bar benders,2carpenters WEEK 26
  • 28. Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 28 ConstructionActivity : Ground FloorWall & FirstFloorWall Duration: 7 days Materials:Concrete,reinforcement,timberformwork Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer SkilledWorker:4 General Workers,3Bar benders,2carpenters WEEK 27
  • 29. Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 29 ConstructionActivity1 : GroundFloorWall Duration: 7 days Materials:Concrete,reinforcement,timberformwork Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer SkilledWorker:4 General Workers,3Bar benders,2carpenters ConstructionActivity 2: GroundFloordoor framingandinstallation Duration: 2 days Materials:Hollowsingle rabbetmetal frame Equipment:Wrench,Level,ScrewDriver,measuringtape,marker SkilledWorker:2 General Workers,1Special Worker Technical Information: :Doors are openingsbetweenexteriorandinterior,andbetweenrooms.Theyare carefully positionedbetweencolumnswherethe wall will eventuallybe made.Doorsare correctlyorientedas to whethertheyopeninorout and stoodupright withwoodtemporarilynailedtocolumnsand beams. ConstructionActivity 3: GroundFloorwindow framingandinstallation
  • 30. Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 30 Duration: 3 days Materials:Aluminumcasementframe,glasswindow,screws Equipment:Wrench,Level,ScrewDriver,measuringtape,marker SkilledWorker:2 General Workers,1Special Worker Technical Information: : : Windowsprovide ventilationforabuilding,acasementwindow provides100% ventilation.A windowframe isfirstinstalled,followedbythe twosmallerwindowsandtheirpivotbrackets,the unitistoppedoff withtrimmingforaesthetics
  • 31. Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 31 WEEK 28 ConstructionActivity 1 : SecondFloorBeam Duration: 4 days Materials:Concrete,reinforcement,timberformwork Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer SkilledWorker: 4 General Workers,3 Bar benders,2carpenters ConstructionActivity 2: GroundFloordoor framingand installation Duration: 2 days Materials:Hollowsingle rabbetmetal frame Equipment:Wrench,Level,ScrewDriver,measuringtape,marker SkilledWorker:2 General Workers,1Special Worker Technical Information: :Doors are openingsbetweenexteriorandinterior,andbetweenrooms.Theyare carefully positionedbetweencolumnswherethe wall will eventuallybe made.Doorsare correctlyorientedas to whethertheyopeninorout and stoodupright withwoodtemporarilynailedtocolumnsand beams.
  • 32. Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 32 ConstructionActivity 3: GroundFloorwindow framingandinstallation Duration: 3 days Materials:Aluminumcasementframe,glasswindow,screws Equipment:Wrench,Level,ScrewDriver,measuringtape,marker SkilledWorker:2 General Workers,1Special Worker Technical Information: : : Windowsprovide ventilationforabuilding,acasementwindow provides100% ventilation.A windowframe isfirstinstalled,followedbythe twosmallerwindowsandtheirpivotbrackets,the unitistoppedoff withtrimmingforaesthetics
  • 33. Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 33 WEEK 29 ConstructionActivity : SecondFloorWall,Railing Duration: 6 days Materials:Concrete,reinforcement,timberformwork Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer SkilledWorker: 4 General Workers,3 Bar benders,2carpenters ConstructionActivity 2: GroundFloordoor framingand installation Duration: 2 days Materials:Hollowsingle rabbetmetal frame Equipment:Wrench,Level,ScrewDriver,measuringtape,marker SkilledWorker:2 General Workers,1Special Worker
  • 34. Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 34 Technical Information: :Doors are openingsbetweenexteriorandinterior,andbetweenrooms.Theyare carefully positionedbetweencolumnswherethe wall will eventuallybe made.Doorsare correctlyoriented as to whethertheyopeninorout and stoodupright withwoodtemporarilynailedtocolumnsand beams. ConstructionActivity 3: GroundFloorwindow framingandinstallation Duration: 3 days Materials:Aluminumcasementframe,glasswindow,screws Equipment:Wrench,Level,ScrewDriver,measuringtape,marker SkilledWorker:2 General Workers,1Special Worker Technical Information: : : Windowsprovide ventilationforabuilding,acasementwindow provides100% ventilation.A windowframe isfirst installed,followedbythe twosmallerwindowsandtheirpivotbrackets,the unitistoppedoff withtrimmingforaesthetics
  • 35. Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 35 WEEK 30 ConstructionActivity : Roof Trusses Duration: 5 days Materials:Concrete,reinforcement,timberformwork Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer SkilledWorker: 4 General Workers,3 Bar benders,2carpenters
  • 36. Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 36 Technical Information: The firststepin coveringroof isto erecta scaffoldtoa heightwhichwill bring the eavesaboutwaist-hightoaman standingonthe scaffold. Before anyroof coveringisapplied,the roof sheathing mustbe sweptcleanand carefullyinspectedforirregularities,cracks,holes,orotherdefects.Noroofingshouldbe applied unlessthe sheathingboardsare absolutelydry. An underlayof roofingfeltisfirstappliedtothe sheathing.Roofingfeltusuallycomesin 3-foot-widerollsandshouldbe laidwitha2-inchtoplap and a 4-inchside lap. Bundlesof shinglesshouldbe distributedalongthe scaffoldbeforeworkbegins.There are 27 stripsina bundle of 1 x 3 asphaltstripshingles.Three bundleswillcover100square feet. Afterthe firstcourse at the eaves(the startercourse) islaidbyinvertingthe first Course of shinglesorthe starterstripof mineral-surfacedroll roofing,eachcourse that followsisbegunbystretchingaguidelineorbysnappinga chalkline from edge to edge.Thispositionsthe course. Stripshinglesshouldbe nailedwith1-inchcopperorhot-dipped,galvanizedroofingnails,twoto each tab;this meanssix nailstoeachfull strip.Nailsshouldbe placedabout61/2 inchesfromthe butt edgestoensure thateachnail will be coveredbythe nextcourse (blind-nailing)anddriven throughtwo courses. An asbestos-cementroof islaidinaboutthe same way as the asphaltstripshingles. A binderisusedtobondthe roofingfelttogetherandforma watertightseal.Asphaltand coal tar are the two maintypesof bituminousbindersused. Dryingout of the bindercausesdeteriorationof built-uproofs. If this didnothappen,a built-uproof wouldlastindefinitely.Asphaltisthe preferred binder.Itisusedon roofsslopingupto 6 inchesperfoot(1/4 pitch).Asphalthasamelting pointof 350' to 41 0°F. A roof coveredwithasphaltshouldbe protectedwithacoveringof slag,gravel,or otherprotective material.Tarhasa lowermeltingpoint(300°to 350°F) than asphalt,soit will move more easily;therefore,itisnotrecommendedforroofshavinga slope of more than 3 inchesperfoot(1/8 pitch). Aggregate,crushedstone,orgravel from1/4 to 5/8 inchin diameteris embeddedinacoat of asphaltor tar to holdthe roof coveringdown.Italsopreventsthe bindingfromdisintegrating because of the weather. Gravel stopson slagor gravel-surfacedroofs,andmetal-edge stripsonsmooth-surfaced built-uproofsare usedto finishall exposededgesandeavestopreventwindfromgetting underthe edgesandcausingblowoffs.The gravel stopalsopreventsthe lossof gravel or slagoff the edge of the roof.The flashingflange of the gravel stoporedge stripisplaced overthe last plyof felt.Itshouldbe nailedsecurelytothe roof deckand double feltstripped. Thenthe finishedcoatof bitumenandsurfacingorcap sheetshouldbe applied.The lipof the gravel stopshouldextendaminimumof 3/4inch above the roof deck. The lipof the edge strip shouldbe a maximumof 1/2 inch above the deck.Bothshouldbe securelyfastenedtothe fascia board
  • 37. Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 37 WEEK 31 ConstructionActivity : Roof Duration: 4 days Materials:Concrete,reinforcement,timberformwork Equipment:Concrete Vibrator,Rebarbendingmachine,table saw,concrete mixer SkilledWorker: 4 General Workers,3 Bar benders,2carpenters
  • 38. Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 38 Week 32 ConstructionActivity: Electrical Wiring Duration: 7 days Materials:insulatedcooperwires,electrical tape,andconnector Equipment:Testpen,voltage meter SkilledWorker:2 electricians Technical Information: Electrical cablesare pulledthroughPVCpipe ambeddedinthe concrete wallsoralong the wall surface. Week 33: ConstructionActivity: Plumbing Duration: 7 days Materials:assorteddimensionsof PVCpipe,connectors,PVCglue Equipment:Saw,measuringtape SkilledWorker:Plumber Technical Information: Plumbingisessential forbringingincleanwaterintoabuildingandtaking waste productsaway.PVCpipesare piecedtogether,inordertoconnectvarioussystemstogether. Week 34: Construction Activity:SanitaryFittings Duration: 5 days Materials:Ceramics Equipment:Saw,Measuringtape,drill SkilledWorker:Special Worker,2 General Workers Technical Information: Sanitaryfittingssuchassick,waterclosetand showerare usuallyboughtas modularunitsandare easilyinstalled.Justconnectthe plumbingtothe inletandoutlet,andensure the fasteningissecure.
  • 39. Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 39 Week 35: ConstructionActivity: Tiling (GroundFloor) Duration: 5 days Materials:Mortar, Grout, homogeneousceramictiles Equipment:Puttyknife,spacers,level SkilledWorker:2 Tilers Technical Information: Tilesare a durable,easytocleanmodularfinishthatrequirescareful installationinordertolasta longtime.A tilingpatternisfirstdeterminedandthe tilerspreadmortar on the floorsurface.The tilesare uniformlyspacedandalignwiththe aidof spacers.The gapsare made to allowforexpansionandare filledwithgrout. Week 36: ConstructionActivity : Tiling(SecondFloor) Duration: 5 days Materials:Mortar, Grout, homogeneousceramictiles Equipment:Puttyknife,spacers,level SkilledWorker:2 Tilers Technical Information: Tilesare a durable,easytocleanmodularfinishthatrequirescareful installationin ordertolasta longtime.A tilingpatternisfirstdeterminedandthe tilerspreadmortar on the floorsurface.The tilesare uniformlyspacedandalignwiththe aidof spacers.The gapsare made to allowforexpansionandare filledwithgrout. Week 37: ConstructionActivity : Tiling (Second Floor) Duration: 5 days Materials:Mortar, Grout, homogeneousceramictiles Equipment:Puttyknife,spacers,level SkilledWorker:2 Tilers Technical Information: Tilesare a durable,easytocleanmodular finishthatrequirescareful installationinordertolasta longtime.A tilingpatternisfirstdeterminedandthe tilerspreadmortar on the floorsurface.The tilesare uniformlyspacedandalignwiththe aidof spacers.The gapsare made to allowforexpansionandare filledwithgrout.
  • 40. Building Construction I Aimi Ruzanna binti Datu Adzman 0306177 Page 40 Week 38: ConstructionActivity : Plastering(GroundFloor) Duration: 5 days Materials:PlasterBoard Equipment:Ramsetconcrete nailer,Makitaconcrete driller,LaserLevelmachine, Plumbs,Basic handtools,Makita steel benchcutters,Ceilinggun,Ladder,Steel square ruler,DrillingMachine SkilledWorker:3 General Workers Technical Information: All levelingsetoutcoordinatesshall be basedonthe settingoutlevels providedondesign. Week 39: ConstructionActivity: Plastering(firstFloor) Duration: 5 days Materials:PlasterBoard Equipment:Ramsetconcrete nailer,Makitaconcrete driller,LaserLevelmachine,Plumbs,Basic handtools,Makita steel benchcutters,Ceilinggun,Ladder,Steel square ruler, DrillingMachine SkilledWorker:3 General Workers Technical Information: All levelingsetoutcoordinatesshall be basedonthe settingoutlevels providedondesign. Week 40: ConstructionActivity : Plastering(firstFloor) Duration: 5 days Materials:PlasterBoard Equipment:Ramsetconcrete nailer,Makitaconcrete driller,LaserLevelmachine, Plumbs,Basic handtools,Makita steel benchcutters,Ceilinggun,Ladder,Steel square ruler,DrillingMachine SkilledWorker:3 General Workers Technical Information: All levelingsetoutcoordinatesshall be basedonthe settingoutlevels providedondesign.