https://msmemon.wordpress.com/scmlab/
Replacement Models
and
Maintenance Analysis
Dr. M. S. Memon
Department of Industrial Engineering & Management
Mehran University of Engineering & Technology,
Jamshoro, Pakistan
• Organizations providing goods/services use several facilities like equipment
and machinery which are directly required in their operations.
• In addition to these facilities, there are several other items which are
necessary to facilitate the functioning of organizations.
• All such facilities should be continuously monitored for their efficient
functioning; otherwise, the quality of service will be poor. Besides the
quality of service of the facilities, the cost of their operation and
maintenance would increase with the passage of time.
• Hence, it is an absolute necessity to maintain the equipment in good
operating conditions with economical cost.
• Thus, we need an integrated approach to minimize the cost of maintenance.
In certain cases, the equipment will be obsolete over a period of time.
INTRODUCTION
• If a firm wants to be in the same business competitively, it has
to take decision on whether to replace the old equipment or to
retain it by taking the cost of maintenance and operation into
account.
• There are two basic reasons for considering the replacement of
an equipment—physical impairment of the various parts or
obsolescence of the equipment.
INTRODUCTION
• Sometimes, the capacity of existing facilities may be inadequate
to meet the current demand. Under such situation, the following
alternatives will be considered.
– Replacement of the existing equipment with a new one.
– Augmenting the existing one with an additional equipment.
INTRODUCTION
• Maintenance activity can be classified into two types:
preventive maintenance and breakdown maintenance.
– Preventive maintenance (PM) is the periodical inspection and service
activities which are aimed to detect potential failures and perform
minor adjustments or repairs which will prevent major operating
problems in future.
– Breakdown maintenance is the repair which is generally done after the
equipment has attained down state. It is often of an emergency nature
which will have associated penalty in terms of expediting cost of
maintenance and down time cost of equipment.
TYPES OF MAINTENANCE
• Preventive maintenance will reduce such cost up to a point. Beyond
that point, the cost of preventive maintenance will be more when
compared to the breakdown maintenance cost.
• The total cost, which is the sum of the preventive maintenance cost
and the breakdown maintenance cost, will go on decreasing with an
increase in the level of maintenance up to a point.
• Beyond that point, the total cost will start increasing.
• The level of maintenance corresponding to the minimum total cost
is the optimal level of maintenance.
• The concepts are demonstrated in Fig. 8.1.
TYPES OF MAINTENANCE
TYPES OF MAINTENANCE
• Replacement study can be classified into two categories:
a) Replacement of assets that deteriorate with time (Replacement due to
gradual failure, or wear and tear of the components of the machines).
• This can be further classified into the following types:
i. Determination of economic life of an asset.
ii. Replacement of an existing asset with a new asset.
b) Simple probabilistic model for assets which fail completely
(replacement due to sudden failure).
TYPES OF REPLACEMENT PROBLEM
• Any asset will have the following cost components:
– Capital recovery cost (average first cost), computed from the first
cost (purchase price) of the machine.
– Average operating and maintenance cost (O & M cost)
– Total cost which is the sum of capital recovery cost (average first
cost) and average maintenance cost.
DETERMINATION OF ECONOMIC LIFE OF AN ASSET
DETERMINATION OF ECONOMIC LIFE OF AN ASSET
DETERMINATION OF ECONOMIC LIFE OF AN ASSET
• From Fig. it is clear that the capital recovery cost (average first
cost) goes on decreasing with the life of the machine and the
average operating and maintenance cost goes on increasing with the
life of the machine.
• From the beginning, the total cost continues to decrease up to a
particular life and then it starts increasing.
• The point where the total cost is minimum is called the economic
life of the machine.
• If the interest rate is more than zero per cent, then we use interest
formulas to determine the economic life.
• A firm is considering replacement of an equipment, whose first
cost is Rs. 4,000 and the scrap value is negligible at the end of
any year.
• Based on experience, it was found that the maintenance cost is
zero during the first year and it increases by Rs. 200 every year
thereafter.
a) When should the equipment be replaced if i = 0%?
b) When should the equipment be replaced if i = 12%?
EXAMPLE 8.1
EXAMPLE 8.1
EXAMPLE 8.1
EXAMPLE 8.1
EXAMPLE 8.1
• The following table gives the operation cost, maintenance cost and salvage value
at the end of every year of a machine whose purchase value is Rs. 20,000.
• Find the economic life of the machine assuming interest rate, i = 15%.
EXAMPLE 8.2
EXAMPLE 8.2
EXAMPLE 8.2
EXAMPLE 8.2
• In this section, the concept of comparison of replacement of an
existing asset with a new asset is presented.
• In this analysis, the annual equivalent cost of each alternative
should be computed first.
• Then the alternative which has the least cost should be selected
as the best alternative. Before discussing details, some
preliminary concepts which are essential for this type of
replacement analysis are presented.
REPLACEMENT OF EXISTING ASSET WITH A NEW ASSET
Capital Recovery with Return
Capital Recovery with Return
• If an existing equipment is considered for replacement with a new
equipment, then the existing equipment is known as the defender and the
new equipment is known as challenger.
• Assume that an equipment has been purchased about three years back for
Rs. 5,00,000 and it is considered for replacement with a new equipment.
The supplier of the new equipment will take the old one for some money,
say, Rs. 3,00,000.
• This should be treated as the present value of the existing Equipment and it
should be considered for all further economic analysis. The purchase value
of the existing equipment before three years is now known as sunk cost, and
it should not be considered for further analysis.
Concept of Challenger and Defender
• Two years ago, a machine was purchased at a cost of Rs.
2,00,000 to be useful for eight years. Its salvage value at the
end of its life is Rs. 25,000. The annual maintenance cost is Rs.
25,000. The market value of the present machine is Rs.
1,20,000. Now, a new machine to cater to the need of the
present machine is available at Rs. 1,50,000 to be useful for six
years. Its annual maintenance cost is Rs. 14,000. The salvage
value of the new machine is Rs. 20,000. Using an interest rate
of 12%, find whether it is worth replacing the present machine
with the new machine.
EXAMPLE 8.3
EXAMPLE 8.3
• The cash flow diagram of the present machine is illustrated in
Fig. 8.4. The annual maintenance cost for the preceding periods
are not shown in this figure.
EXAMPLE 8.3
EXAMPLE 8.3
EXAMPLE 8.3
• A diesel engine was installed 10 years ago at a cost of Rs. 50,000. It has a
present realizable market value of Rs. 15,000.
• If kept, it can be expected to last five years more, with operating and
maintenance cost of Rs. 14,000 per year and to have a salvage value of Rs.
8,000 at the end of the fifth year. This engine can be replaced with an
improved version costing Rs. 65,000 which has an expected life of 20
years.
• This improved version will have an estimated annual operating and
maintenance cost of Rs. 9,000 and ultimate salvage value of Rs. 13,000.
• Using an interest rate of 15%, make an annual equivalent cost analysis to
determine whether to keep or replace the old engine.
EXAMPLE 8.4

More Related Content

PPTX
Replacement analysis
PPT
Replacement analysis importance and application
PPTX
PPTX
Machine hour rate method
PPTX
What is replacement theory
PPTX
Replacement models in plant and operations
PPTX
Machine hour rate
PPTX
The key components for a production industry replacement Analysis
Replacement analysis
Replacement analysis importance and application
Machine hour rate method
What is replacement theory
Replacement models in plant and operations
Machine hour rate
The key components for a production industry replacement Analysis

What's hot (19)

PPT
Replacement Theory
PPTX
Machine hour reate
PDF
Replacement
PPTX
Chapter 8 The Procurement of Equipment
PDF
Elementary Economic Analysis
PPTX
MG6863 Engineering Economics
PPT
Choosing a Vehicle
PPT
OWNERSHIP COST OF CONSTRUCTION PLANT & EQUIPMENT
PPTX
Costcurves
PPTX
Replacement theory
PPTX
Concept of Efficiency- Engineering Economics
PPTX
Economic analysis
PPTX
A Model for Life-Cycle Benefit and Cost Analysis
PPTX
Engineering economics and finance
PPTX
COST ANALYSIS (Brief overview)
PPT
Vision of construction mechanizer
PPTX
Life cycle cost example
PPTX
Total cost of ownership1
PPTX
Cost and cost concepts (Engineering Economics and Management)
Replacement Theory
Machine hour reate
Replacement
Chapter 8 The Procurement of Equipment
Elementary Economic Analysis
MG6863 Engineering Economics
Choosing a Vehicle
OWNERSHIP COST OF CONSTRUCTION PLANT & EQUIPMENT
Costcurves
Replacement theory
Concept of Efficiency- Engineering Economics
Economic analysis
A Model for Life-Cycle Benefit and Cost Analysis
Engineering economics and finance
COST ANALYSIS (Brief overview)
Vision of construction mechanizer
Life cycle cost example
Total cost of ownership1
Cost and cost concepts (Engineering Economics and Management)
Ad

Similar to Chap5 engeco (20)

PPTX
Replacement models and maintenance analysis
PDF
Replacement and Maintenance Analysis
PDF
MG6863-Unit-4.pdf
PDF
unit-6 (1).pdf
PPTX
Operations REsearch
PDF
Replacement & Maintenance Analysis Unit IV MG 6863
PPT
REPLACEMENT DECISIONS.ppt
PPT
ISE 307 - CHAPTER 12.ppt
PPT
replacement_theory ppt slide in python .
PPTX
Replacement Theory. by Dr. Babasaheb. J. Mohite
PDF
PPTX
Replacement Problem
PPTX
Replacement Problem - Dr. Bhupender SOM - JIMS Rohini Faculty Presentation
PDF
Published 2
PDF
Lecture 5 - Replacement Problem for industrial equipments
PPTX
replacement model problems.pptx
PDF
Replacement Strategies
DOCX
Cost of Maintenancekmkm;m;lk'kl;m;m.docx
PDF
Replacement model
PPTX
Maintenance Management
Replacement models and maintenance analysis
Replacement and Maintenance Analysis
MG6863-Unit-4.pdf
unit-6 (1).pdf
Operations REsearch
Replacement & Maintenance Analysis Unit IV MG 6863
REPLACEMENT DECISIONS.ppt
ISE 307 - CHAPTER 12.ppt
replacement_theory ppt slide in python .
Replacement Theory. by Dr. Babasaheb. J. Mohite
Replacement Problem
Replacement Problem - Dr. Bhupender SOM - JIMS Rohini Faculty Presentation
Published 2
Lecture 5 - Replacement Problem for industrial equipments
replacement model problems.pptx
Replacement Strategies
Cost of Maintenancekmkm;m;lk'kl;m;m.docx
Replacement model
Maintenance Management
Ad

More from abidiqbal55 (18)

PDF
Lecture 1
PPT
Network theorems chapter 9
PPT
Method of analysis chapter 8
PPT
Method of analysis chapter 8 final
PPT
Inductors chapter 11
PPT
Capacitor chapter 10
PPT
Ac series parallel chapter 13
PDF
10 150316005543-conversion-gate01
PDF
9 150316005537-conversion-gate01
PDF
8 150316005531-conversion-gate01
PDF
7 150316005526-conversion-gate01
PDF
6 150316005521-conversion-gate01
PDF
5moreinterestformulas 150316005456-conversion-gate01
PDF
5 150316005456-conversion-gate01
PDF
4 interestandequivalence-150316005410-conversion-gate01
PDF
3 150316005311-conversion-gate01
PDF
2 decisionmakingandprofessionalethics-150316005212-conversion-gate01
PDF
1 introductiontoengineeringeconomics-150316005104-conversion-gate01
Lecture 1
Network theorems chapter 9
Method of analysis chapter 8
Method of analysis chapter 8 final
Inductors chapter 11
Capacitor chapter 10
Ac series parallel chapter 13
10 150316005543-conversion-gate01
9 150316005537-conversion-gate01
8 150316005531-conversion-gate01
7 150316005526-conversion-gate01
6 150316005521-conversion-gate01
5moreinterestformulas 150316005456-conversion-gate01
5 150316005456-conversion-gate01
4 interestandequivalence-150316005410-conversion-gate01
3 150316005311-conversion-gate01
2 decisionmakingandprofessionalethics-150316005212-conversion-gate01
1 introductiontoengineeringeconomics-150316005104-conversion-gate01

Recently uploaded (20)

PPTX
Chemical Technological Processes, Feasibility Study and Chemical Process Indu...
PDF
PREDICTION OF DIABETES FROM ELECTRONIC HEALTH RECORDS
PPTX
Amdahl’s law is explained in the above power point presentations
PDF
ChapteR012372321DFGDSFGDFGDFSGDFGDFGDFGSDFGDFGFD
PDF
Artificial Superintelligence (ASI) Alliance Vision Paper.pdf
PPTX
Fundamentals of Mechanical Engineering.pptx
PPTX
AUTOMOTIVE ENGINE MANAGEMENT (MECHATRONICS).pptx
PDF
Abrasive, erosive and cavitation wear.pdf
PDF
Exploratory_Data_Analysis_Fundamentals.pdf
PPTX
Graph Data Structures with Types, Traversals, Connectivity, and Real-Life App...
PDF
Design Guidelines and solutions for Plastics parts
PDF
null (2) bgfbg bfgb bfgb fbfg bfbgf b.pdf
PPTX
"Array and Linked List in Data Structures with Types, Operations, Implementat...
PDF
SMART SIGNAL TIMING FOR URBAN INTERSECTIONS USING REAL-TIME VEHICLE DETECTI...
PPTX
CyberSecurity Mobile and Wireless Devices
PPTX
Information Storage and Retrieval Techniques Unit III
PPTX
CURRICULAM DESIGN engineering FOR CSE 2025.pptx
PPTX
communication and presentation skills 01
PDF
Visual Aids for Exploratory Data Analysis.pdf
PDF
EXPLORING LEARNING ENGAGEMENT FACTORS INFLUENCING BEHAVIORAL, COGNITIVE, AND ...
Chemical Technological Processes, Feasibility Study and Chemical Process Indu...
PREDICTION OF DIABETES FROM ELECTRONIC HEALTH RECORDS
Amdahl’s law is explained in the above power point presentations
ChapteR012372321DFGDSFGDFGDFSGDFGDFGDFGSDFGDFGFD
Artificial Superintelligence (ASI) Alliance Vision Paper.pdf
Fundamentals of Mechanical Engineering.pptx
AUTOMOTIVE ENGINE MANAGEMENT (MECHATRONICS).pptx
Abrasive, erosive and cavitation wear.pdf
Exploratory_Data_Analysis_Fundamentals.pdf
Graph Data Structures with Types, Traversals, Connectivity, and Real-Life App...
Design Guidelines and solutions for Plastics parts
null (2) bgfbg bfgb bfgb fbfg bfbgf b.pdf
"Array and Linked List in Data Structures with Types, Operations, Implementat...
SMART SIGNAL TIMING FOR URBAN INTERSECTIONS USING REAL-TIME VEHICLE DETECTI...
CyberSecurity Mobile and Wireless Devices
Information Storage and Retrieval Techniques Unit III
CURRICULAM DESIGN engineering FOR CSE 2025.pptx
communication and presentation skills 01
Visual Aids for Exploratory Data Analysis.pdf
EXPLORING LEARNING ENGAGEMENT FACTORS INFLUENCING BEHAVIORAL, COGNITIVE, AND ...

Chap5 engeco

  • 1. https://msmemon.wordpress.com/scmlab/ Replacement Models and Maintenance Analysis Dr. M. S. Memon Department of Industrial Engineering & Management Mehran University of Engineering & Technology, Jamshoro, Pakistan
  • 2. • Organizations providing goods/services use several facilities like equipment and machinery which are directly required in their operations. • In addition to these facilities, there are several other items which are necessary to facilitate the functioning of organizations. • All such facilities should be continuously monitored for their efficient functioning; otherwise, the quality of service will be poor. Besides the quality of service of the facilities, the cost of their operation and maintenance would increase with the passage of time. • Hence, it is an absolute necessity to maintain the equipment in good operating conditions with economical cost. • Thus, we need an integrated approach to minimize the cost of maintenance. In certain cases, the equipment will be obsolete over a period of time. INTRODUCTION
  • 3. • If a firm wants to be in the same business competitively, it has to take decision on whether to replace the old equipment or to retain it by taking the cost of maintenance and operation into account. • There are two basic reasons for considering the replacement of an equipment—physical impairment of the various parts or obsolescence of the equipment. INTRODUCTION
  • 4. • Sometimes, the capacity of existing facilities may be inadequate to meet the current demand. Under such situation, the following alternatives will be considered. – Replacement of the existing equipment with a new one. – Augmenting the existing one with an additional equipment. INTRODUCTION
  • 5. • Maintenance activity can be classified into two types: preventive maintenance and breakdown maintenance. – Preventive maintenance (PM) is the periodical inspection and service activities which are aimed to detect potential failures and perform minor adjustments or repairs which will prevent major operating problems in future. – Breakdown maintenance is the repair which is generally done after the equipment has attained down state. It is often of an emergency nature which will have associated penalty in terms of expediting cost of maintenance and down time cost of equipment. TYPES OF MAINTENANCE
  • 6. • Preventive maintenance will reduce such cost up to a point. Beyond that point, the cost of preventive maintenance will be more when compared to the breakdown maintenance cost. • The total cost, which is the sum of the preventive maintenance cost and the breakdown maintenance cost, will go on decreasing with an increase in the level of maintenance up to a point. • Beyond that point, the total cost will start increasing. • The level of maintenance corresponding to the minimum total cost is the optimal level of maintenance. • The concepts are demonstrated in Fig. 8.1. TYPES OF MAINTENANCE
  • 8. • Replacement study can be classified into two categories: a) Replacement of assets that deteriorate with time (Replacement due to gradual failure, or wear and tear of the components of the machines). • This can be further classified into the following types: i. Determination of economic life of an asset. ii. Replacement of an existing asset with a new asset. b) Simple probabilistic model for assets which fail completely (replacement due to sudden failure). TYPES OF REPLACEMENT PROBLEM
  • 9. • Any asset will have the following cost components: – Capital recovery cost (average first cost), computed from the first cost (purchase price) of the machine. – Average operating and maintenance cost (O & M cost) – Total cost which is the sum of capital recovery cost (average first cost) and average maintenance cost. DETERMINATION OF ECONOMIC LIFE OF AN ASSET
  • 10. DETERMINATION OF ECONOMIC LIFE OF AN ASSET
  • 11. DETERMINATION OF ECONOMIC LIFE OF AN ASSET • From Fig. it is clear that the capital recovery cost (average first cost) goes on decreasing with the life of the machine and the average operating and maintenance cost goes on increasing with the life of the machine. • From the beginning, the total cost continues to decrease up to a particular life and then it starts increasing. • The point where the total cost is minimum is called the economic life of the machine. • If the interest rate is more than zero per cent, then we use interest formulas to determine the economic life.
  • 12. • A firm is considering replacement of an equipment, whose first cost is Rs. 4,000 and the scrap value is negligible at the end of any year. • Based on experience, it was found that the maintenance cost is zero during the first year and it increases by Rs. 200 every year thereafter. a) When should the equipment be replaced if i = 0%? b) When should the equipment be replaced if i = 12%? EXAMPLE 8.1
  • 17. • The following table gives the operation cost, maintenance cost and salvage value at the end of every year of a machine whose purchase value is Rs. 20,000. • Find the economic life of the machine assuming interest rate, i = 15%. EXAMPLE 8.2
  • 21. • In this section, the concept of comparison of replacement of an existing asset with a new asset is presented. • In this analysis, the annual equivalent cost of each alternative should be computed first. • Then the alternative which has the least cost should be selected as the best alternative. Before discussing details, some preliminary concepts which are essential for this type of replacement analysis are presented. REPLACEMENT OF EXISTING ASSET WITH A NEW ASSET
  • 24. • If an existing equipment is considered for replacement with a new equipment, then the existing equipment is known as the defender and the new equipment is known as challenger. • Assume that an equipment has been purchased about three years back for Rs. 5,00,000 and it is considered for replacement with a new equipment. The supplier of the new equipment will take the old one for some money, say, Rs. 3,00,000. • This should be treated as the present value of the existing Equipment and it should be considered for all further economic analysis. The purchase value of the existing equipment before three years is now known as sunk cost, and it should not be considered for further analysis. Concept of Challenger and Defender
  • 25. • Two years ago, a machine was purchased at a cost of Rs. 2,00,000 to be useful for eight years. Its salvage value at the end of its life is Rs. 25,000. The annual maintenance cost is Rs. 25,000. The market value of the present machine is Rs. 1,20,000. Now, a new machine to cater to the need of the present machine is available at Rs. 1,50,000 to be useful for six years. Its annual maintenance cost is Rs. 14,000. The salvage value of the new machine is Rs. 20,000. Using an interest rate of 12%, find whether it is worth replacing the present machine with the new machine. EXAMPLE 8.3
  • 27. • The cash flow diagram of the present machine is illustrated in Fig. 8.4. The annual maintenance cost for the preceding periods are not shown in this figure. EXAMPLE 8.3
  • 30. • A diesel engine was installed 10 years ago at a cost of Rs. 50,000. It has a present realizable market value of Rs. 15,000. • If kept, it can be expected to last five years more, with operating and maintenance cost of Rs. 14,000 per year and to have a salvage value of Rs. 8,000 at the end of the fifth year. This engine can be replaced with an improved version costing Rs. 65,000 which has an expected life of 20 years. • This improved version will have an estimated annual operating and maintenance cost of Rs. 9,000 and ultimate salvage value of Rs. 13,000. • Using an interest rate of 15%, make an annual equivalent cost analysis to determine whether to keep or replace the old engine. EXAMPLE 8.4