REPLACEMENT THEORY
Prof.P.D.Devan
Asst Professor
Department of Mechanical Engineering
Kumaraguru College of Technology
Coimbatore
Replacement Model
The problem of replacement arises when any one of the
components of productive resources, such as machinery, building and
men deteriorates due to time or usage.
Ex:
 A machine, which is purchased and installed in a production system, due to usage
some of its components wear out and its efficiency is reduced.
 A building in which production activities are carried out, may leave cracks in
walls, roof etc, and needs repair.
 A worker, when he is young, will work efficiently, as the time passes becomes old
and his work efficiency falls down and after some time he will become unable to
work.
Efficiency Vs Time
 At the beginning the operating efficiency id 95% and it is reduced to 50% at final
stage.
 When the efficiency is too low its not advisable to use the facility further, as the
maintenance cost will be very high and unit production cost also will increase.
 Hence the replacement of the facility is due at this stage.
Decision Types
 We may decide whether to wait for complete failure of the item .
 The expensive item may be considered individually to decide whether we should
replace now or, if not, when it should be reconsidered for replacement.
 Whether the item is to be replaced by similar type of item or by different.
The main objective of replacement is to help the organization for maximizing
its profit or to minimize the cost.
Failure Mechanism of Items
Nature of
Failure
Gradual
Progressive
Retrogressive
RandomSudden
Gradual Failure
 As the life of the machine increases or due continuous usage, due to wear and tear of
components of the facility, its efficiency deteriorates due to which the management
can experience.
a) Progressive Increase in maintenance expenditure or operating costs,
b) Decreased productivity of the equipment
c) Decrease in the value of the equipment (resale value) of the equipment/facility
decreases.
Ex: Automobile, Machine Tool
Sudden Failure
 The items ultimately fail suddenly after a period of time.
 The life of the equipment cannot be predicted and is some sort of random variable
 The period between installation and failure is not constant for any particular type
of equipment but will follow some frequency distribution
Progressive Failure
 In this case probability of failure increases with the increase in life of an item.
Ex: Electrical bulbs and computer components
Retrogressive failure
 Some items will have higher probability of failure in the beginning of their life,
and as the time passes chances of failure becomes less.
 That is the ability of the item to survive in the initial period of life increases its
expected life.
Ex: Newly installed machines and new vehicles
Random Failure
 Constant probability of failure is associated with items that fail from random
causes such as physical shocks, not related to age.
 In such cases all items fail before aging has any effect.
Ex: Vacuum Tubes
Stages of Maintenance
Costs Associated with Maintenance
 Purchase or Capital Cost (C)
 Salvage value / Scrap value / Resale value / Depreciation (S)
 Running costs including maintenance, Repair and Operating costs
Types of Replacement Problems
 Replacement of items that deteriorate with time (value of money not changing
with time)
 Replacement of items that deteriorate with time (Value of money changing with
time)
 Replacement of items that fail suddenly (individual and group replacement
policies)
 Staff Replacement
General Approach to Replacement Problem
 The information necessary to formulate optimum replacement policy is:
 (i) Objective assessment of the probability of the item failing at a particular point
of time
 (ii) Assessments of the cost of replacement in terms of:
(a) Actual cost of the item,
(b) Direct costs of labour involved in replacement,
(c) Costs of disruption in terms of lost production, lost orders etc.,
Replacement of items that deteriorate with time
(Value of money not changing with time)
 Certain equipment/parts are deteriorate gradually with respect to time.
 After a certain period the efficiency of the item will reduce and maintenance cost
increases.
 Then the old item must be replaced by new one.
Ex: Automobile part wear out with age and the owner needs to replace the old
part at suitable time by a new one
Costs to be Considered
 Capital/Purchase cost =(C)
 Scrap value after ‘t’ years= S(t)
 Operating cost at time ‘t’ = M(t)
 Optimal replacement period = n
 Depreciation cost
 Operating cost
Optimal replacement period is corresponding to which the minimum average cost
Replacement of items that deteriorate with time
(Value of money changing with time)
 This problem is complicated as the money value changes with time. This can be
dealt under two different conditions:
(a) The maintenance cost goes on increasing with usage or age or time and then
we have to find out optimum time of replacing the item. Here the value of money
decreases with a constant rate which is known as its depreciation ratio or
discounted factor.
(b) If a businessman takes a loan for a certain period at a given interest rate and
agrees to pay it in a number of instalments, then we have to find the most suitable
period during which the loan would be repaid.
Replacement of items that fail suddenly
 There are certain items or systems or products, whose probability of failure
increases with time. They may work with designed efficiency throughout their life
and if they fail to act they fail suddenly.
 The nature of these items is they are costly to replace at the same time and their
failure affect the functioning of entire system.
 For example, resistors, components of air conditioning unit and certain electrical
components. If we do not replace the item immediately, then loss of production,
idle labour; idle raw materials, etc are the results. It is evident failure of such
items causes heavy losses to the organization.
Individual Replacement Policy
 This policy states that replace the item soon after its failure. Here the cost of
replacement will be somewhat greater as the item is to be purchased individually
from the seller as and when it fails.
 From the time of failure to the replacement, the system remains idle. More than
that, as the item is purchased individually, the cost of the item may be more.
 In case, the component or the item is not available in the local market, we have to
get it from other places, where the procurement cost may be higher for individual
purchase.
Ex: Bearing in a machine
Group Replacement Policy
 If the organization has got the statistics of failure of the item, it can calculate the
average life of the item and replace the item before it fails, so that the system can
work without break.
 In this case, all the items, even they are in good working condition, are replaced at
a stipulated period as calculated by the organization by using the group
replacement policy.
 In case any item fails, before the calculated group replacement period, it is
replaced individually immediately after failure. Hence this policy utilizes the
strategy of both individual replacement and group replacement.
Ex: Street Lights, Electronic Parts and etc
THANK YOU

More Related Content

PPTX
Replacement Problem
PPTX
Applied Operation Research (AOR) Replacement Theory
PPTX
Replacement Theory. by Dr. Babasaheb. J. Mohite
PPTX
Replacement theory
PPTX
Replacement theory
PPTX
Replacement Model - Types and Problem
PPTX
Replacement Theory Models in Operations Research by Dr. Rajesh Timane
PDF
Assignment problems
Replacement Problem
Applied Operation Research (AOR) Replacement Theory
Replacement Theory. by Dr. Babasaheb. J. Mohite
Replacement theory
Replacement theory
Replacement Model - Types and Problem
Replacement Theory Models in Operations Research by Dr. Rajesh Timane
Assignment problems

What's hot (20)

PPTX
Operational research queuing theory
PPTX
Operations Research - Models
PPTX
Elements of cost
PDF
Queuing Theory - Operation Research
PPTX
Just In Time (JIT)
PPTX
History of Operations Research
PPTX
METHODS OF DEPRECIATION -PPT.pptx
PPTX
Methods of depreciation
PPT
Work measurement
PPT
Plant layout Production Management
PPTX
Economic Order Quantity Models
PPTX
Economic order quantity (eoq)
PPT
Sequencing problems in Operations Research
PPTX
Machine hour rate
PPTX
What is Replacement Theory.pptx
PPT
Inventory models
PDF
Operation research-Network analysis (Critical Path Method)
PPT
Plant layout
PPTX
KAIZEN COSTING
Operational research queuing theory
Operations Research - Models
Elements of cost
Queuing Theory - Operation Research
Just In Time (JIT)
History of Operations Research
METHODS OF DEPRECIATION -PPT.pptx
Methods of depreciation
Work measurement
Plant layout Production Management
Economic Order Quantity Models
Economic order quantity (eoq)
Sequencing problems in Operations Research
Machine hour rate
What is Replacement Theory.pptx
Inventory models
Operation research-Network analysis (Critical Path Method)
Plant layout
KAIZEN COSTING
Ad

Similar to Replacement model (20)

PPTX
Replacement models in plant and operations
PPTX
Replacement theory
PPTX
Replacement theory
PPTX
Replacement theory
PPTX
PPTX
replacementtheory.pptx
PDF
Replacement
PPTX
Operations REsearch
PPT
Replacement Theory
PPT
replacement_theory ppt slide in python .
PDF
Lecture 5 - Replacement Problem for industrial equipments
PPTX
Operations research : Decision Theory, Dynamic Programming, and Replacement a...
PPTX
replacement model problems.pptx
PDF
Replacement & Maintenance Analysis Unit IV MG 6863
PDF
Chap5 engeco
PPTX
Replacement theory
PDF
MG6863-Unit-4.pdf
PPTX
Replacement Problem - Dr. Bhupender SOM - JIMS Rohini Faculty Presentation
PDF
Unit iv replacement and maintenence analysis
PPTX
Unit iv replacement and maintenence analysis
Replacement models in plant and operations
Replacement theory
Replacement theory
Replacement theory
replacementtheory.pptx
Replacement
Operations REsearch
Replacement Theory
replacement_theory ppt slide in python .
Lecture 5 - Replacement Problem for industrial equipments
Operations research : Decision Theory, Dynamic Programming, and Replacement a...
replacement model problems.pptx
Replacement & Maintenance Analysis Unit IV MG 6863
Chap5 engeco
Replacement theory
MG6863-Unit-4.pdf
Replacement Problem - Dr. Bhupender SOM - JIMS Rohini Faculty Presentation
Unit iv replacement and maintenence analysis
Unit iv replacement and maintenence analysis
Ad

More from Devan P.D (16)

PPTX
Cam and follower
PDF
Basics of kinematics mechanism
PPTX
Engineering Graphics
PDF
Single Rotor, Two Rotor and Three Rotor Torsional Vibration System
PDF
Dynamics of Machinery - Engine gas force analysis
PPTX
Static and dynamic force analysis
PDF
Static and dynamic force analysis
PDF
Design of belt drives
PDF
Roller contact bearing
PDF
Material Selection for Product Development
PDF
Queueing theory
PDF
Inventory management
PDF
Sequencing model
PDF
Design of Transmission Systems
PPT
Operations research
PDF
Mechatronics
Cam and follower
Basics of kinematics mechanism
Engineering Graphics
Single Rotor, Two Rotor and Three Rotor Torsional Vibration System
Dynamics of Machinery - Engine gas force analysis
Static and dynamic force analysis
Static and dynamic force analysis
Design of belt drives
Roller contact bearing
Material Selection for Product Development
Queueing theory
Inventory management
Sequencing model
Design of Transmission Systems
Operations research
Mechatronics

Recently uploaded (20)

PPTX
Sustainable Sites - Green Building Construction
DOCX
573137875-Attendance-Management-System-original
PPTX
CYBER-CRIMES AND SECURITY A guide to understanding
PPTX
Foundation to blockchain - A guide to Blockchain Tech
PPT
Project quality management in manufacturing
PDF
composite construction of structures.pdf
PPTX
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
PDF
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
PDF
Operating System & Kernel Study Guide-1 - converted.pdf
PPTX
bas. eng. economics group 4 presentation 1.pptx
PDF
TFEC-4-2020-Design-Guide-for-Timber-Roof-Trusses.pdf
PDF
PPT on Performance Review to get promotions
PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PDF
PRIZ Academy - 9 Windows Thinking Where to Invest Today to Win Tomorrow.pdf
PDF
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
PDF
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
PPTX
UNIT-1 - COAL BASED THERMAL POWER PLANTS
PPTX
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
PDF
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
PPTX
CH1 Production IntroductoryConcepts.pptx
Sustainable Sites - Green Building Construction
573137875-Attendance-Management-System-original
CYBER-CRIMES AND SECURITY A guide to understanding
Foundation to blockchain - A guide to Blockchain Tech
Project quality management in manufacturing
composite construction of structures.pdf
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
Operating System & Kernel Study Guide-1 - converted.pdf
bas. eng. economics group 4 presentation 1.pptx
TFEC-4-2020-Design-Guide-for-Timber-Roof-Trusses.pdf
PPT on Performance Review to get promotions
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PRIZ Academy - 9 Windows Thinking Where to Invest Today to Win Tomorrow.pdf
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
UNIT-1 - COAL BASED THERMAL POWER PLANTS
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
CH1 Production IntroductoryConcepts.pptx

Replacement model

  • 1. REPLACEMENT THEORY Prof.P.D.Devan Asst Professor Department of Mechanical Engineering Kumaraguru College of Technology Coimbatore
  • 2. Replacement Model The problem of replacement arises when any one of the components of productive resources, such as machinery, building and men deteriorates due to time or usage. Ex:  A machine, which is purchased and installed in a production system, due to usage some of its components wear out and its efficiency is reduced.  A building in which production activities are carried out, may leave cracks in walls, roof etc, and needs repair.  A worker, when he is young, will work efficiently, as the time passes becomes old and his work efficiency falls down and after some time he will become unable to work.
  • 3. Efficiency Vs Time  At the beginning the operating efficiency id 95% and it is reduced to 50% at final stage.  When the efficiency is too low its not advisable to use the facility further, as the maintenance cost will be very high and unit production cost also will increase.  Hence the replacement of the facility is due at this stage.
  • 4. Decision Types  We may decide whether to wait for complete failure of the item .  The expensive item may be considered individually to decide whether we should replace now or, if not, when it should be reconsidered for replacement.  Whether the item is to be replaced by similar type of item or by different. The main objective of replacement is to help the organization for maximizing its profit or to minimize the cost.
  • 5. Failure Mechanism of Items Nature of Failure Gradual Progressive Retrogressive RandomSudden
  • 6. Gradual Failure  As the life of the machine increases or due continuous usage, due to wear and tear of components of the facility, its efficiency deteriorates due to which the management can experience. a) Progressive Increase in maintenance expenditure or operating costs, b) Decreased productivity of the equipment c) Decrease in the value of the equipment (resale value) of the equipment/facility decreases. Ex: Automobile, Machine Tool
  • 7. Sudden Failure  The items ultimately fail suddenly after a period of time.  The life of the equipment cannot be predicted and is some sort of random variable  The period between installation and failure is not constant for any particular type of equipment but will follow some frequency distribution
  • 8. Progressive Failure  In this case probability of failure increases with the increase in life of an item. Ex: Electrical bulbs and computer components
  • 9. Retrogressive failure  Some items will have higher probability of failure in the beginning of their life, and as the time passes chances of failure becomes less.  That is the ability of the item to survive in the initial period of life increases its expected life. Ex: Newly installed machines and new vehicles
  • 10. Random Failure  Constant probability of failure is associated with items that fail from random causes such as physical shocks, not related to age.  In such cases all items fail before aging has any effect. Ex: Vacuum Tubes
  • 12. Costs Associated with Maintenance  Purchase or Capital Cost (C)  Salvage value / Scrap value / Resale value / Depreciation (S)  Running costs including maintenance, Repair and Operating costs
  • 13. Types of Replacement Problems  Replacement of items that deteriorate with time (value of money not changing with time)  Replacement of items that deteriorate with time (Value of money changing with time)  Replacement of items that fail suddenly (individual and group replacement policies)  Staff Replacement
  • 14. General Approach to Replacement Problem  The information necessary to formulate optimum replacement policy is:  (i) Objective assessment of the probability of the item failing at a particular point of time  (ii) Assessments of the cost of replacement in terms of: (a) Actual cost of the item, (b) Direct costs of labour involved in replacement, (c) Costs of disruption in terms of lost production, lost orders etc.,
  • 15. Replacement of items that deteriorate with time (Value of money not changing with time)  Certain equipment/parts are deteriorate gradually with respect to time.  After a certain period the efficiency of the item will reduce and maintenance cost increases.  Then the old item must be replaced by new one. Ex: Automobile part wear out with age and the owner needs to replace the old part at suitable time by a new one
  • 16. Costs to be Considered  Capital/Purchase cost =(C)  Scrap value after ‘t’ years= S(t)  Operating cost at time ‘t’ = M(t)  Optimal replacement period = n  Depreciation cost  Operating cost Optimal replacement period is corresponding to which the minimum average cost
  • 17. Replacement of items that deteriorate with time (Value of money changing with time)  This problem is complicated as the money value changes with time. This can be dealt under two different conditions: (a) The maintenance cost goes on increasing with usage or age or time and then we have to find out optimum time of replacing the item. Here the value of money decreases with a constant rate which is known as its depreciation ratio or discounted factor. (b) If a businessman takes a loan for a certain period at a given interest rate and agrees to pay it in a number of instalments, then we have to find the most suitable period during which the loan would be repaid.
  • 18. Replacement of items that fail suddenly  There are certain items or systems or products, whose probability of failure increases with time. They may work with designed efficiency throughout their life and if they fail to act they fail suddenly.  The nature of these items is they are costly to replace at the same time and their failure affect the functioning of entire system.  For example, resistors, components of air conditioning unit and certain electrical components. If we do not replace the item immediately, then loss of production, idle labour; idle raw materials, etc are the results. It is evident failure of such items causes heavy losses to the organization.
  • 19. Individual Replacement Policy  This policy states that replace the item soon after its failure. Here the cost of replacement will be somewhat greater as the item is to be purchased individually from the seller as and when it fails.  From the time of failure to the replacement, the system remains idle. More than that, as the item is purchased individually, the cost of the item may be more.  In case, the component or the item is not available in the local market, we have to get it from other places, where the procurement cost may be higher for individual purchase. Ex: Bearing in a machine
  • 20. Group Replacement Policy  If the organization has got the statistics of failure of the item, it can calculate the average life of the item and replace the item before it fails, so that the system can work without break.  In this case, all the items, even they are in good working condition, are replaced at a stipulated period as calculated by the organization by using the group replacement policy.  In case any item fails, before the calculated group replacement period, it is replaced individually immediately after failure. Hence this policy utilizes the strategy of both individual replacement and group replacement. Ex: Street Lights, Electronic Parts and etc