Here are the steps to solve the case studies:
Case Study 1:
- PV = 4 weeks * 100 sqft/week = 400 sqft
- EV = 45% of 1000 sqft = 450 sqft
- AC = $250,000
- CV = EV - AC = $50,000
- SV = EV - PV = 50 sqft
- CPI = EV/AC = 1.8
- SPI = EV/PV = 1.125
Case Study 2:
- BAC = $500,000
- PV = 8 weeks * 25 fixtures/week = 200 fixtures
- EV = 110 rooms * 5 fixtures/room = 550 fixtures
- AC