SlideShare a Scribd company logo
Chapter 15
Methods of
Compensation
15-1
Key Concepts
• Introduction to compensation agreements
• Contract cost risk appraisal
» Technical risk
» Contract schedule risk
• General types of contract compensation
agreements
» Fixed price contracts
» Incentive contracts
» Cost-type contracts
15-2
Key Concepts
• Specific types of compensation agreements
» Fixed price compensation arrangements:
– Firm fixed price contracts
– Fixed price with economic adjustment contracts
– Fixed price redetermination contracts
» Incentive arrangements
– Fixed price incentive
– Cost plus incentive fee arrangements
» Cost-type arrangements:
– Cost reimbursement
– Cost sharing
– Time and materials
– Cost plus fixed fee arrangements
– Cost plus award fee arrangements
– Cost without fee
• Considerations when selecting contract types
15-3
Introduction to Compensation Agreements
• The compensation arrangement
determines:
» Degree and timing of the cost responsibility
assumed by the supplier
» Amount of profit or fee available to the
supplier
» Motivational implications of the fee portion of
the compensation arrangements
15-4
Example 1: Low Level of Uncertainty
Potential
Outcomes Seller’s Cost Seller’s Price Seller’s Profit
Low $950,000 $1,100,000 $150,000
Most Likely 1,000,000 1,100,000 100,000
High 1,050,000 1,100,000 50,000
Firm Fixed Price Contract
15-5
Example 2: High Level of Uncertainty
Potential
Outcomes Seller’s Cost Seller’s Price Seller’s Profit
Low $500,000 $1,100,000 $600,000
Most Likely 1,000,000 1,100,000 100,000
High 1,500,000 1,100,000 (-400,000)
Same FFP Contract as 19-1
15-6
Example 2: Continued
• Most sellers are unwilling to large risks
» The supplier will not want to offer the contract
at $1,100,000 due to this additional uncertainty
• In this case, the seller studies the
distribution of likely cost outcomes and
concludes that, 9 times out of 10, the
actual cost will be $1,400,000 or less
• Based on the risk aversion, the seller may
demand a firm fixed price of $1,540,000
» $1,400,000 plus $140,000 (10 percent profit on
this cost)
» The supplier will not lose money on the
contract 15-7
Example 2: Continued
Potential
Outcomes Seller’s Cost Seller’s Price Seller’s Profit
Low $500,000 $1,540,000 $1,040,000
Most Likely 1,000,000 1,540,000 540,000
90% Level 1,400,000 1,540,000 140,000
High 1,500,000 1,540,000 40,000
Firm Fixed Price Contract
15-8
Example 2: Continued
Potential
Outcomes Seller’s Cost Seller’s Price Seller’s Profit
Low $500,000 $550,000 $50,000
Most Likely 1,000,000 1,050,000 50,000
90% Level 1,400,000 1,450,000 50,000
High 1,500,000 1,550,000 50,000
Cost Plus $50,000 Fixed Fee
15-9
Example 2: Continued
Potential
Outcomes Seller’s Cost Seller’s Price Seller’s Profit
Low $500,000 $550,000 $50,000
Most Likely 1,000,000 1,100,000 100,000
90% Level 1,400,000 1,540,000 140,000
High 1,500,000 1,650,000 150,000
Cost Plus Fixed 10% Fee
15-10
Contract Cost Risk Appraisal
• Technical Risk
» Risk associated with the nature of the item
» Technical risk appraisal:
– Type and complexity of the item or service
– Stability of design specifications or statement of
work
– Availability of historical pricing data
– Prior production experience
• Contract Schedule Risk
» Anticipate material and labor cost increases
– Forward pricing is common
» Anticipate possible schedule slippages
15-11
General Types of Contract Compensation
Arrangements
• Fixed Price Contracts
• Incentive Contracts
• Cost-Type Contracts
Buyer Risk
Supplier Risk
Low
High
High
Low
Fixed
Price
Contracts
Cost
Type
Contracts
Incentive Contracts
15-12
Firm Fixed Price Contracts
• A firm fixed price (FFP) contract is an
agreement to pay a specified price when
the items (services) specified by the
contract have been delivered (completed)
and accepted
• Common types:
» Firm fixed price
» Fixed price with economic price adjustment
» Fixed price redetermination
15-13
When to Use FFP
• Specifications are well defined
• Cost risk is low
• Schedule risk is low
• Technical risk is low
• Competition has established pricing
15-14
Firm Fixed Price Contract Example
Figure 19-3
15-15
Reasons Why Firm Fixed Price Contracts Do Not
Always Remained Fixed
• A supplier losing money may request
relief if:
» Customer contributed to the loss
» Customer badly needs the items
– Assumes other suppliers are not available
» Supplier has unique facilities and time is short
» Customers representatives do not employ
sound supply management practices
15-16
Fixed Price and Economic
Price Adjustment Contracts (FPEPA)
• (FPEPA) contracts are used to recognize
economic contingencies, such as unstable
labor or market conditions
• FPEPA is an FFP contract that includes
economic price adjustment clauses
» Escalator clauses are for price increases
» De-escalator clauses are for price decreases
15-17
Rules for Selecting Indexes for Price Adjustment
Clauses
• Select from the appropriate Bureau of Labor
Statistics category
• Avoid broad indexes; use the lowest-level
classification
• Develop a weighted index for materials in a
product
• Select labor rate indexes by type and location
• Define energy indexes by fuel type and location
• Analyze the past history of each index versus
actual price change of the item being indexed
15-18
Fixed Price Redetermination Contracts (FPR)
• A FFP is set for an initial contract period
• A redetermination (upward or downward)
occurs at a stated time during the contract
• FPR prospective
» Occurs at a stated time during the contract
» Used where a fair and reasonable price can be
developed for initial periods but not subsequent periods
• FPR retroactive
» Occurs at the end of the contract
» Used when uncertainty exists as in the prospective, but
the amount of the contract is small and/or the
performance period is short
15-19
Incentive Arrangements
• Used to motivate the supplier to:
» Control costs
» Encourage good supplier performance
• Contract price will usually be higher
• Ceiling price is usually fixed during
negotiations
• Cost responsibility is shared
• Two primary types:
» Fixed price incentive
» Cost plus incentive fee
15-20
Elements of a Simplified Incentive Contract
• Target cost
» Cost outcome both buyer and supplier feel is
the most likely outcome
• Target profit
» Amount considered fair and reasonable
• Allocating costs above or below target
» Recognizes the target most likely will not be
met
» A sharing arrangement is agreed upon that
reflects the sharing of the cost responsibility
15-21
Fixed Price Incentive Fee Example
15-22
Cost Plus Incentive Fee Arrangements
• Combine the incentive arrangement and
the cost plus fixed fee arrangement
• Under a CPIF arrangement, an incentive
applies over part of the range of cost
outcomes
• The fee structure resembles a cost plus
fixed fee contract at both the low-cost and
high-cost ends of the range
15-23
Cost Plus Incentive Fee Example
• Target cost = $1,000,000
• Target profit = $70,000
• Optimistic cost = $800,000
• Optimistic and maximum profit = $120,000
• Pessimistic cost = $1,400,000
• Pessimistic and minimum profit = $20,000
• Sharing below target (customer/supplier)
= 75/25
• Sharing above target (cust./supplier) =
87.5/12.5 15-24
CPIF Contract Example Continued
• Target cost = $1,000,000
• Target profit = $70,000
• Maximum fee = $120,000
• Minimum fee = $20,000
• Cost savings = target cost - final cost
» $300,000 = $1,000,000 - $700,000
• Supplier’s savings = cost savings × supplier
share
» 75,000 = $300,000 × 0.25
• Computed fee = savings fee + target fee
» $145,000 = $75,000 + $70,000
• Final price = final cost + maximum fee
» $820,000 = $700,000 + $120,000 15-25
Cost Plus Incentive Fee Arrangements
• Cost savings = target cost - final cost
• Supplier’s share of cost savings = cost
savings × supplier share
• Computed fee = savings fee + target fee
• Final price = final cost + maximum fee
15-26
Cost Plus Incentive Fee Example
15-27
Cost-type Arrangements
• Used when:
» Research and development increases technical risk
» Project completion is in doubt
» Product specifications are incomplete
» High-dollar, highly uncertain procurements are involved
• Common types are:
» Cost reimbursement
» Cost plus fixed fee
» Cost plus award fee
» Cost without fee
» Cost sharing
» Time and materials
15-28
Cost Plus Fixed Fee Arrangements (CPFF)
• Buying firm pays a fixed fee and all costs
beyond fee
• Fee is for specified scope of work
• Supplier has no incentive to control costs
• Characterized by low supplier profit
• A total liability limit is usually established
Optimistic Most likely Pessimistic
Final cost $800 $1,000 $1,200
Fixed fee 50 50 50
Price $850 $1,050 $1,250
CPFF Example
(not in text)
15-29
Cost Plus Award Fee (CPAF)
• The award fee is a pool of money
established by the buyer to reward the
supplier in meeting the buyer’s stated
needs
• Receipt of the fee is based on the buying
firm’s subjective evaluation
• CPAF works as a flexible tool
15-30
Cost Without Fee
• Used primarily by nonprofit institutions
• Used for research work without the
objective of making a profit
• Institutions recover all overhead costs
• In recent years, high-technology firms
have increased their use of this contract
type
15-31
Cost Sharing
• In some situations, a firm doing research
under a cost type of contract stands to
benefit if the product developed can be
used in its own product line
• Under such circumstances, the buyer and
the seller agree on what they consider to
be a fair basis to share the costs (most
often it is 50-50)
• The electronics industry has found this
type of contract especially useful
15-32
Considerations When Selecting Contract Types
• Unstable labor conditions
• Unstable market conditions
• Improvement in production is required
• Complexity of product or service
• Product or service requires development
• Design is not completed or may change
• Learning must take place
• Short time to prepare for a bid or negotiation
• Short delivery period
» Which may require additional resources to meet
deadlines
15-33
Concluding Remarks
• Sound application of the compensation
methods presented will significantly
reduce expenditures when cost risk is
present
• Compensation agreements must result in
a reasonable allocation of the cost risk
• Agreements should also provide adequate
motivation to the supplier to assure
effective performance
15-34

More Related Content

PPTX
Chapter 16 Negotiation
PPTX
Chapter 10 Outsourcing
PPTX
Chapter 13 Total Cost of Ownership
PPTX
Chapter 14 Price and Cost Analysis
PPTX
Chapter 18 Contract and Relationship Management
PPTX
Chapter 20 Production and Inventory Control
PPTX
Effective Procurement - Doyle Club Feb 2014
PPTX
Purchase cost reduction
Chapter 16 Negotiation
Chapter 10 Outsourcing
Chapter 13 Total Cost of Ownership
Chapter 14 Price and Cost Analysis
Chapter 18 Contract and Relationship Management
Chapter 20 Production and Inventory Control
Effective Procurement - Doyle Club Feb 2014
Purchase cost reduction

What's hot (20)

PPTX
Indirect Procurement - Mr. Ashwani Singh (Watson Pharma)
PDF
Procurement Cost Saving Strategy " Procurement dari cost centre menjadi profit...
PPTX
Mba ii pmom_unit-2.6 purchase management a
PPTX
Project Procurment Management
PPTX
Types of purchasing system
PPT
purchasing process
PPT
Top 10 Procurement KPI\'s
PPTX
What Is The Difference Between Procurement and Purchasing?
PPTX
The purchasing process
PPTX
Project Procurement Management
PPTX
Procurement management by- Prateek kumar
PDF
Finance cost reduction
PPT
How to Effectively Measure a Procurement Organization Sample
PPS
Centralized purchase
PDF
Measuring Procurement's Performance
PPTX
L 12 strategic outsourcing, defensive strategies etc
PPT
Supplier Relations
PPT
Cost Management
PPTX
UC Berkeley Final Deliverable
PPS
Purchase Presentation 1
Indirect Procurement - Mr. Ashwani Singh (Watson Pharma)
Procurement Cost Saving Strategy " Procurement dari cost centre menjadi profit...
Mba ii pmom_unit-2.6 purchase management a
Project Procurment Management
Types of purchasing system
purchasing process
Top 10 Procurement KPI\'s
What Is The Difference Between Procurement and Purchasing?
The purchasing process
Project Procurement Management
Procurement management by- Prateek kumar
Finance cost reduction
How to Effectively Measure a Procurement Organization Sample
Centralized purchase
Measuring Procurement's Performance
L 12 strategic outsourcing, defensive strategies etc
Supplier Relations
Cost Management
UC Berkeley Final Deliverable
Purchase Presentation 1
Ad

Similar to Chapter 15 Methods of Compensation (20)

PPTX
201 Marketing Management Unit 2.2 Setting PRICE .ppt.pptx
PPTX
procurement Management
PPTX
12 projectprocurementmanagement
PPTX
Pm session11
PPTX
M5 Pricing and Channels.pptx
PDF
Pmp procurement chapter 12
PPTX
Pricing in marketing Management
PPTX
Chapter 10 (pricing) (customer perceptions of value) visual bee
PPTX
Lec 09 Two Sessions (Pricing Model).pptx
PPT
How should a company set prices intially for products and services.
PDF
Pricing Strategy for the third year- Updated.pdf
PPTX
Merchandise management
PPTX
Chapter 14 - Developing Pricing Strategies and Programs
PDF
Bmgt 411 week_8
PPTX
CHAPTER 3- COSTING AND PRICING.pptx
PPT
Pricing ppt.ppt for 1 st year business students
PPT
Pricing ppt.ppt good for 1st year students
PPT
Pricing ppt.ppt good for 1st year students
PPTX
B to B - 6- SCM & Pricing.pptxmmmmmmmmmm
PPTX
Pricing
201 Marketing Management Unit 2.2 Setting PRICE .ppt.pptx
procurement Management
12 projectprocurementmanagement
Pm session11
M5 Pricing and Channels.pptx
Pmp procurement chapter 12
Pricing in marketing Management
Chapter 10 (pricing) (customer perceptions of value) visual bee
Lec 09 Two Sessions (Pricing Model).pptx
How should a company set prices intially for products and services.
Pricing Strategy for the third year- Updated.pdf
Merchandise management
Chapter 14 - Developing Pricing Strategies and Programs
Bmgt 411 week_8
CHAPTER 3- COSTING AND PRICING.pptx
Pricing ppt.ppt for 1 st year business students
Pricing ppt.ppt good for 1st year students
Pricing ppt.ppt good for 1st year students
B to B - 6- SCM & Pricing.pptxmmmmmmmmmm
Pricing
Ad

More from Tran Thang (20)

PPTX
Chapter 21 Demand Management and Logistics
PPTX
Chapter 19 Ethics and Social Responsibilities
PPTX
Chapter 17 Contract Formation and Legal Issues
PPTX
Chapter 11 Sourcing
PPTX
Chapter 9 Purchasing Services
PPTX
Chapter 8 The Procurement of Equipment
PPTX
Chapter 6 Purchasing Descriptions and Specifications
PPTX
Chapter 5 New Product Development
PPTX
Chapter 4 A Portfolio of Relationships
PPTX
Chapter 3 Supply Management: An Organization Spanning Activity
PPTX
Chapter 2 Organizational Issues
PPTX
Chapter 1 The Progression to Professional Supply Management
PDF
A management thinking to solving material outsourcing problems
DOCX
Research report the driver of supply management capability
DOCX
The effects of quality management practices on and employees’ well-being
DOCX
The impact of service quality on customer satisfaction and loyalty
PPTX
Routing in Ad hoc networks
PPTX
IP networks and mutlimedia
PPTX
Globalisation
DOCX
FINANCIAL REPORT ANALYSIS: BECAMEX TRADE AND DEVELOPMENT JOIN STOCK COMPANY
Chapter 21 Demand Management and Logistics
Chapter 19 Ethics and Social Responsibilities
Chapter 17 Contract Formation and Legal Issues
Chapter 11 Sourcing
Chapter 9 Purchasing Services
Chapter 8 The Procurement of Equipment
Chapter 6 Purchasing Descriptions and Specifications
Chapter 5 New Product Development
Chapter 4 A Portfolio of Relationships
Chapter 3 Supply Management: An Organization Spanning Activity
Chapter 2 Organizational Issues
Chapter 1 The Progression to Professional Supply Management
A management thinking to solving material outsourcing problems
Research report the driver of supply management capability
The effects of quality management practices on and employees’ well-being
The impact of service quality on customer satisfaction and loyalty
Routing in Ad hoc networks
IP networks and mutlimedia
Globalisation
FINANCIAL REPORT ANALYSIS: BECAMEX TRADE AND DEVELOPMENT JOIN STOCK COMPANY

Recently uploaded (20)

PDF
Unit 1 Cost Accounting - Cost sheet
PPT
Lecture 3344;;,,(,(((((((((((((((((((((((
PPTX
svnfcksanfskjcsnvvjknsnvsdscnsncxasxa saccacxsax
PDF
Solara Labs: Empowering Health through Innovative Nutraceutical Solutions
PDF
COST SHEET- Tender and Quotation unit 2.pdf
PDF
Deliverable file - Regulatory guideline analysis.pdf
PDF
Stem Cell Market Report | Trends, Growth & Forecast 2025-2034
PPTX
HR Introduction Slide (1).pptx on hr intro
DOCX
unit 2 cost accounting- Tender and Quotation & Reconciliation Statement
PDF
Daniels 2024 Inclusive, Sustainable Development
PDF
Cours de Système d'information about ERP.pdf
PPTX
3. HISTORICAL PERSPECTIVE UNIIT 3^..pptx
DOCX
Business Management - unit 1 and 2
PDF
Ôn tập tiếng anh trong kinh doanh nâng cao
PPTX
Belch_12e_PPT_Ch18_Accessible_university.pptx
PDF
Chapter 5_Foreign Exchange Market in .pdf
PDF
NISM Series V-A MFD Workbook v December 2024.khhhjtgvwevoypdnew one must use ...
PDF
Power and position in leadershipDOC-20250808-WA0011..pdf
PDF
BsN 7th Sem Course GridNNNNNNNN CCN.pdf
PPTX
Principles of Marketing, Industrial, Consumers,
Unit 1 Cost Accounting - Cost sheet
Lecture 3344;;,,(,(((((((((((((((((((((((
svnfcksanfskjcsnvvjknsnvsdscnsncxasxa saccacxsax
Solara Labs: Empowering Health through Innovative Nutraceutical Solutions
COST SHEET- Tender and Quotation unit 2.pdf
Deliverable file - Regulatory guideline analysis.pdf
Stem Cell Market Report | Trends, Growth & Forecast 2025-2034
HR Introduction Slide (1).pptx on hr intro
unit 2 cost accounting- Tender and Quotation & Reconciliation Statement
Daniels 2024 Inclusive, Sustainable Development
Cours de Système d'information about ERP.pdf
3. HISTORICAL PERSPECTIVE UNIIT 3^..pptx
Business Management - unit 1 and 2
Ôn tập tiếng anh trong kinh doanh nâng cao
Belch_12e_PPT_Ch18_Accessible_university.pptx
Chapter 5_Foreign Exchange Market in .pdf
NISM Series V-A MFD Workbook v December 2024.khhhjtgvwevoypdnew one must use ...
Power and position in leadershipDOC-20250808-WA0011..pdf
BsN 7th Sem Course GridNNNNNNNN CCN.pdf
Principles of Marketing, Industrial, Consumers,

Chapter 15 Methods of Compensation

  • 2. Key Concepts • Introduction to compensation agreements • Contract cost risk appraisal » Technical risk » Contract schedule risk • General types of contract compensation agreements » Fixed price contracts » Incentive contracts » Cost-type contracts 15-2
  • 3. Key Concepts • Specific types of compensation agreements » Fixed price compensation arrangements: – Firm fixed price contracts – Fixed price with economic adjustment contracts – Fixed price redetermination contracts » Incentive arrangements – Fixed price incentive – Cost plus incentive fee arrangements » Cost-type arrangements: – Cost reimbursement – Cost sharing – Time and materials – Cost plus fixed fee arrangements – Cost plus award fee arrangements – Cost without fee • Considerations when selecting contract types 15-3
  • 4. Introduction to Compensation Agreements • The compensation arrangement determines: » Degree and timing of the cost responsibility assumed by the supplier » Amount of profit or fee available to the supplier » Motivational implications of the fee portion of the compensation arrangements 15-4
  • 5. Example 1: Low Level of Uncertainty Potential Outcomes Seller’s Cost Seller’s Price Seller’s Profit Low $950,000 $1,100,000 $150,000 Most Likely 1,000,000 1,100,000 100,000 High 1,050,000 1,100,000 50,000 Firm Fixed Price Contract 15-5
  • 6. Example 2: High Level of Uncertainty Potential Outcomes Seller’s Cost Seller’s Price Seller’s Profit Low $500,000 $1,100,000 $600,000 Most Likely 1,000,000 1,100,000 100,000 High 1,500,000 1,100,000 (-400,000) Same FFP Contract as 19-1 15-6
  • 7. Example 2: Continued • Most sellers are unwilling to large risks » The supplier will not want to offer the contract at $1,100,000 due to this additional uncertainty • In this case, the seller studies the distribution of likely cost outcomes and concludes that, 9 times out of 10, the actual cost will be $1,400,000 or less • Based on the risk aversion, the seller may demand a firm fixed price of $1,540,000 » $1,400,000 plus $140,000 (10 percent profit on this cost) » The supplier will not lose money on the contract 15-7
  • 8. Example 2: Continued Potential Outcomes Seller’s Cost Seller’s Price Seller’s Profit Low $500,000 $1,540,000 $1,040,000 Most Likely 1,000,000 1,540,000 540,000 90% Level 1,400,000 1,540,000 140,000 High 1,500,000 1,540,000 40,000 Firm Fixed Price Contract 15-8
  • 9. Example 2: Continued Potential Outcomes Seller’s Cost Seller’s Price Seller’s Profit Low $500,000 $550,000 $50,000 Most Likely 1,000,000 1,050,000 50,000 90% Level 1,400,000 1,450,000 50,000 High 1,500,000 1,550,000 50,000 Cost Plus $50,000 Fixed Fee 15-9
  • 10. Example 2: Continued Potential Outcomes Seller’s Cost Seller’s Price Seller’s Profit Low $500,000 $550,000 $50,000 Most Likely 1,000,000 1,100,000 100,000 90% Level 1,400,000 1,540,000 140,000 High 1,500,000 1,650,000 150,000 Cost Plus Fixed 10% Fee 15-10
  • 11. Contract Cost Risk Appraisal • Technical Risk » Risk associated with the nature of the item » Technical risk appraisal: – Type and complexity of the item or service – Stability of design specifications or statement of work – Availability of historical pricing data – Prior production experience • Contract Schedule Risk » Anticipate material and labor cost increases – Forward pricing is common » Anticipate possible schedule slippages 15-11
  • 12. General Types of Contract Compensation Arrangements • Fixed Price Contracts • Incentive Contracts • Cost-Type Contracts Buyer Risk Supplier Risk Low High High Low Fixed Price Contracts Cost Type Contracts Incentive Contracts 15-12
  • 13. Firm Fixed Price Contracts • A firm fixed price (FFP) contract is an agreement to pay a specified price when the items (services) specified by the contract have been delivered (completed) and accepted • Common types: » Firm fixed price » Fixed price with economic price adjustment » Fixed price redetermination 15-13
  • 14. When to Use FFP • Specifications are well defined • Cost risk is low • Schedule risk is low • Technical risk is low • Competition has established pricing 15-14
  • 15. Firm Fixed Price Contract Example Figure 19-3 15-15
  • 16. Reasons Why Firm Fixed Price Contracts Do Not Always Remained Fixed • A supplier losing money may request relief if: » Customer contributed to the loss » Customer badly needs the items – Assumes other suppliers are not available » Supplier has unique facilities and time is short » Customers representatives do not employ sound supply management practices 15-16
  • 17. Fixed Price and Economic Price Adjustment Contracts (FPEPA) • (FPEPA) contracts are used to recognize economic contingencies, such as unstable labor or market conditions • FPEPA is an FFP contract that includes economic price adjustment clauses » Escalator clauses are for price increases » De-escalator clauses are for price decreases 15-17
  • 18. Rules for Selecting Indexes for Price Adjustment Clauses • Select from the appropriate Bureau of Labor Statistics category • Avoid broad indexes; use the lowest-level classification • Develop a weighted index for materials in a product • Select labor rate indexes by type and location • Define energy indexes by fuel type and location • Analyze the past history of each index versus actual price change of the item being indexed 15-18
  • 19. Fixed Price Redetermination Contracts (FPR) • A FFP is set for an initial contract period • A redetermination (upward or downward) occurs at a stated time during the contract • FPR prospective » Occurs at a stated time during the contract » Used where a fair and reasonable price can be developed for initial periods but not subsequent periods • FPR retroactive » Occurs at the end of the contract » Used when uncertainty exists as in the prospective, but the amount of the contract is small and/or the performance period is short 15-19
  • 20. Incentive Arrangements • Used to motivate the supplier to: » Control costs » Encourage good supplier performance • Contract price will usually be higher • Ceiling price is usually fixed during negotiations • Cost responsibility is shared • Two primary types: » Fixed price incentive » Cost plus incentive fee 15-20
  • 21. Elements of a Simplified Incentive Contract • Target cost » Cost outcome both buyer and supplier feel is the most likely outcome • Target profit » Amount considered fair and reasonable • Allocating costs above or below target » Recognizes the target most likely will not be met » A sharing arrangement is agreed upon that reflects the sharing of the cost responsibility 15-21
  • 22. Fixed Price Incentive Fee Example 15-22
  • 23. Cost Plus Incentive Fee Arrangements • Combine the incentive arrangement and the cost plus fixed fee arrangement • Under a CPIF arrangement, an incentive applies over part of the range of cost outcomes • The fee structure resembles a cost plus fixed fee contract at both the low-cost and high-cost ends of the range 15-23
  • 24. Cost Plus Incentive Fee Example • Target cost = $1,000,000 • Target profit = $70,000 • Optimistic cost = $800,000 • Optimistic and maximum profit = $120,000 • Pessimistic cost = $1,400,000 • Pessimistic and minimum profit = $20,000 • Sharing below target (customer/supplier) = 75/25 • Sharing above target (cust./supplier) = 87.5/12.5 15-24
  • 25. CPIF Contract Example Continued • Target cost = $1,000,000 • Target profit = $70,000 • Maximum fee = $120,000 • Minimum fee = $20,000 • Cost savings = target cost - final cost » $300,000 = $1,000,000 - $700,000 • Supplier’s savings = cost savings × supplier share » 75,000 = $300,000 × 0.25 • Computed fee = savings fee + target fee » $145,000 = $75,000 + $70,000 • Final price = final cost + maximum fee » $820,000 = $700,000 + $120,000 15-25
  • 26. Cost Plus Incentive Fee Arrangements • Cost savings = target cost - final cost • Supplier’s share of cost savings = cost savings × supplier share • Computed fee = savings fee + target fee • Final price = final cost + maximum fee 15-26
  • 27. Cost Plus Incentive Fee Example 15-27
  • 28. Cost-type Arrangements • Used when: » Research and development increases technical risk » Project completion is in doubt » Product specifications are incomplete » High-dollar, highly uncertain procurements are involved • Common types are: » Cost reimbursement » Cost plus fixed fee » Cost plus award fee » Cost without fee » Cost sharing » Time and materials 15-28
  • 29. Cost Plus Fixed Fee Arrangements (CPFF) • Buying firm pays a fixed fee and all costs beyond fee • Fee is for specified scope of work • Supplier has no incentive to control costs • Characterized by low supplier profit • A total liability limit is usually established Optimistic Most likely Pessimistic Final cost $800 $1,000 $1,200 Fixed fee 50 50 50 Price $850 $1,050 $1,250 CPFF Example (not in text) 15-29
  • 30. Cost Plus Award Fee (CPAF) • The award fee is a pool of money established by the buyer to reward the supplier in meeting the buyer’s stated needs • Receipt of the fee is based on the buying firm’s subjective evaluation • CPAF works as a flexible tool 15-30
  • 31. Cost Without Fee • Used primarily by nonprofit institutions • Used for research work without the objective of making a profit • Institutions recover all overhead costs • In recent years, high-technology firms have increased their use of this contract type 15-31
  • 32. Cost Sharing • In some situations, a firm doing research under a cost type of contract stands to benefit if the product developed can be used in its own product line • Under such circumstances, the buyer and the seller agree on what they consider to be a fair basis to share the costs (most often it is 50-50) • The electronics industry has found this type of contract especially useful 15-32
  • 33. Considerations When Selecting Contract Types • Unstable labor conditions • Unstable market conditions • Improvement in production is required • Complexity of product or service • Product or service requires development • Design is not completed or may change • Learning must take place • Short time to prepare for a bid or negotiation • Short delivery period » Which may require additional resources to meet deadlines 15-33
  • 34. Concluding Remarks • Sound application of the compensation methods presented will significantly reduce expenditures when cost risk is present • Compensation agreements must result in a reasonable allocation of the cost risk • Agreements should also provide adequate motivation to the supplier to assure effective performance 15-34