Project Delivery Methods
College of Engineering
Construction Technology and Management Department
Mada Walabu
University
Procurement Management and Contract Administration
CoTM 4242
Chapter Three
Instructor
Andualem Endris (M.Sc)
andu0117@yahoo.com
www.facebook.com/aendris1
www.linkedin.com/in/andualem-yadeta
www.twitter.com/andualemyadeta
Definition
Project Delivery Method: Is a system
used by an agency or owner for organizing
and financing design, construction,
operations, and maintenance services for a
project.
31 July 2021 COTM 4242 2
Construction Project Characteristics
Construction projects are different than other types of
projects due to the following characteristics;
 Construction projects are complex undertaking.
 Every construction project is unique.
 Construction projects involve a lot of uncertainties,
lack of information and variables.
 Therefore, parties and their role shall be pre-determined.
31 July 2021 3
COTM 4242
Traditional Vs Alternative Project
Delivery Methods
Traditional Approach (D-B-B):
The most common delivery system is called “the
traditional or standard approach” or “Design-Bid-
Build (D-B-B)”, in which the employer assigns the
design and construction phases to two different
firms (consultant/designer and contractor).
Constructing
Designing
Appointing
Consultant
Appointing Main
Contractor
31 July 2021 4
COTM 4242
Traditional Approach (D-B-B):
 For many years, DBB has been the most common
method of project delivery for public projects,
and for many private projects as well.
 Design-Bid-Build is effective on projects
 where the owner needs both professional
design services and construction services
 where the designer does not require detailed
knowledge of the means and methods of
construction.
 DBB provides the owner with a high degree of
control.
31 July 2021 5
COTM 4242
Traditional Approach (D-B-B) … Cont’d
 The owner defines project goals and objectives, secures the financing,
and specifies the standards and contract terms.
 The owner may perform planning, conceptual design and full design,
or may engage an outside design professional (designer) for some or
all of these tasks.
 During this planning and preliminary stage, owner and designer work
as a team to obtain required permits and conduct necessary site
investigations.
 The designer prepares the construction bid documents to reflect the
owner’s project goals and objectives.
 Prospective contractors prepare their bids from these complete and
specific bid documents.
 The bidders submit their proposals to the owner, who determines the
most responsive (typically the lowest) bid meeting project
requirements.
 In certain circumstances, owner may be justified in selecting a
contractor outright and negotiating contract terms directly.
31 July 2021 6
COTM 4242
Advantages of D-B-B Approach
 Applicable to a wide range of projects.
 Well established and easily understood.
 Clearly defined roles for all parties.
 Provides the lowest initial price that competitive
bidders can offer.
 Extensive litigation has resulted in well
established legal precedents.
 Insurance and bonding are well defined.
31 July 2021 7
COTM 4242
Disadvantages of D-B-B Approach
 Least-cost approach requires higher level of
inspection.
 Initial low bid might not result in ultimate lowest
cost or final best value.
 Designers may have limited knowledge of the
true cost and scheduling implication of design
decisions.
31 July 2021 8
COTM 4242
Alternative Approach (D-B)
Design-build (D-B) approach is regarded as an alternative
project delivery system
It involves a single contract between the project employer
and a design-build contractor covering both the
design and construction of a project.
The design-builder performs design and construction
according to design parameters and other
requirements established by the employer.
Constructing
Designing
Appointing design & construction
contractor
Tendering
31 July 2021 9
COTM 4242
Design-Build Approach
 The owner contracts with a single entity to provide the
design and to construct the project.
 The contract might be negotiated with a single design-
builder or result from competitive proposals.
 The selection can be based on low price or on a set of
value criteria (experience, staff, bonding capacity, etc).
 With the contractor playing a major role in design,
costs are typically defined and maintained to a greater
degree, and the coordination of fast-track management
to achieve early completion is greatly simplified.
 The design-builder makes many decisions that owner
would make under DBB, due to delegation of greatly
increased authority.
31 July 2021 10
COTM 4242
Design-Build Approach
 For many owners, delegation of responsibilities
leads to satisfactory projects. However, if the
parties are inexperienced and do not cooperate,
the transfer of control and risk can be
disappointing.
 The owner may need to restructure his/her
internal procedures to accommodate design-build
approach.
 Compared to DBB, this involves a significantly
different set of requirements and expectations for
process, timelines and communications.
 A clear understanding and documentation of
design-build processes enhances the quality of
design-build projects
31 July 2021 11
COTM 4242
Advantage of Design-Build Approach
Innovation and quality improvements through:
- Alternative designs and construction
methods
suited to the contractor’s capabilities
- Flexibility in the selection of design,
materials, and
construction methods.
• Earlier schedule and cost certainty
31 July 2021 12
COTM 4242
Disadvantage of Design-Build Approach
 Reduced opportunities for smaller, local construction
firms.
 Fewer competitors and increased risk may result in
higher initial costs.
 Elimination of traditional checks and balances. Quality
may be subordinated by cost or schedule
considerations.
 Less Engineer control over final design.
 Higher procurement costs.
 Traditional funding may not support fast-tracking
construction or may require accelerated cash flow.
 Accelerated construction can potentially overextend
the workforce.
31 July 2021 13
COTM 4242
Others
 Turnkey
 Turnkey Variations
 Direct Labor Approach
 Construction management.
31 July 2021 14
COTM 4242
Turnkey
 Turnkey adds to the design-builder’s
responsibilities the operation and/or
maintenance of the completed project.
 Turnkey delivery has the potential for bringing
a new project on line more quickly.
 Three forms of turnkey project delivery:
 Design-build-operate-transfer
 Design-build-operate-maintain
 Design-build-own-operate-transfer
31 July 2021 15
COTM 4242
Turnkey Variation
 Variations on turnkey add financing as a key
component. While financing arrangements are unique
for each project, developer financed projects
generally resemble one of the turnkey delivery
methods:
 FDBT (Finance, design, build, transfer)
 FDBOT (Finance, design, build, operate, transfer)
 FDBOOT (Finance, design, build ,own, operate,
transfer)
 In each case, the transfer of the project occurs only
after the developer’s interests and financial
obligations have been satisfied.
31 July 2021 16
COTM 4242
Thank You

More Related Content

PPT
Chapter 2- Contract Management
PPT
Chapter 6- Contract Management
PDF
Chapter 2 [compatibility mode]
PPT
Chapter 5- Contract Management
PPT
Chapter 4- Contract Management
PDF
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
PPT
Chapter 2- Construction Law
PPT
Construction contracts docuements_08092008
Chapter 2- Contract Management
Chapter 6- Contract Management
Chapter 2 [compatibility mode]
Chapter 5- Contract Management
Chapter 4- Contract Management
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Chapter 2- Construction Law
Construction contracts docuements_08092008

What's hot (20)

PDF
Chapter 3 [compatibility mode]
PDF
Contracts in professional practice
PPTX
Construction Documents
PPTX
Types of Contract in Construction Management
PDF
Considerations in Procurement Strategy - 2014 Olswang Construction Law Confer...
PPT
Estimating and Tendering methods for Construction Work
PPT
ACH 231 Lecture 07 (Contract Documents) Part 1
DOCX
Pp1 group assignment
DOCX
Professional Practice 1 Proposal Report
PPTX
Contracts and-tenders
DOCX
Traditional procurement method
PPT
ACH 231 Lecture 07 (Contract Documents) Part 3
PDF
A Report on Procurement Strategies - PP1
DOCX
Professional Practice 1 Assignment
PDF
Tendering-professional practices-jamia millia islamia
PDF
Procurement Strategies: A Seminar
PPTX
Contract and Arbitration
DOC
Single stage design and build method & construction project management
PPTX
Gcc vs scc
Chapter 3 [compatibility mode]
Contracts in professional practice
Construction Documents
Types of Contract in Construction Management
Considerations in Procurement Strategy - 2014 Olswang Construction Law Confer...
Estimating and Tendering methods for Construction Work
ACH 231 Lecture 07 (Contract Documents) Part 1
Pp1 group assignment
Professional Practice 1 Proposal Report
Contracts and-tenders
Traditional procurement method
ACH 231 Lecture 07 (Contract Documents) Part 3
A Report on Procurement Strategies - PP1
Professional Practice 1 Assignment
Tendering-professional practices-jamia millia islamia
Procurement Strategies: A Seminar
Contract and Arbitration
Single stage design and build method & construction project management
Gcc vs scc
Ad

Similar to Chapter 3- Contract Management (20)

PDF
Chapter 3 [compatibility mode]
PPT
CON_CONTRACTS_all_till_mid. bgf uggttyy ppt
 
PPTX
Lecture 1.pptx
PPTX
Lean Construction Background & Introduction.pptx
PPT
ACH 231 Lecture 06 (Project Delivery)
PPT
ACH 231 Lecture 06 (Project Delivery)
PPTX
Strategies in building procurement (summarized)
PPTX
Construction project delivery methods
PDF
Residential Design Build Whitepaper
PDF
Chapter 2 [compatibility mode]
PPTX
Chapter_2-Procurement and Contract management.pptx
PPTX
Chapter II: Pre- Contractual considerations and works.ppt
DOCX
PP1 assignment
PPT
ACH 216 Lecture 04c (Project Award)
PPTX
Preparation of boq
PPT
Tendering in construction introduction
PDF
Guide to Construction Procurement Strategies
PDF
Design Build Intro
PPTX
Procurement system
PDF
Professional practice 1 (QS)
Chapter 3 [compatibility mode]
CON_CONTRACTS_all_till_mid. bgf uggttyy ppt
 
Lecture 1.pptx
Lean Construction Background & Introduction.pptx
ACH 231 Lecture 06 (Project Delivery)
ACH 231 Lecture 06 (Project Delivery)
Strategies in building procurement (summarized)
Construction project delivery methods
Residential Design Build Whitepaper
Chapter 2 [compatibility mode]
Chapter_2-Procurement and Contract management.pptx
Chapter II: Pre- Contractual considerations and works.ppt
PP1 assignment
ACH 216 Lecture 04c (Project Award)
Preparation of boq
Tendering in construction introduction
Guide to Construction Procurement Strategies
Design Build Intro
Procurement system
Professional practice 1 (QS)
Ad

More from Delhi Technological University (20)

PPT
Chapter 1- Procurement management
PPT
Chapter 3- Construction Law
PPT
Chapter 1-Construction Law
PPT
Chapter 5- Lecture
PPT
Chapter 4- Lecture
PPT
Chapter 3- Lecture
PPT
Chapter 2- Lecture
PPT
Chapter 1- Lecture
PDF
Construction equipment management chapter 5
PDF
Construction equipment management chapter 4
PDF
Construction equipment management chapter 3
PDF
Construction equipment management chapter 2
PDF
Construction equipment management chapter 1pdf
PDF
Chapter 5 [compatibility mode]
PDF
Chapter 4 [compatibility mode]
PDF
Chapter 1 [compatibility mode]
PDF
Construction contract
PDF
Chapter 4 [compatibility mode]
PDF
Chapter 2 [compatibility mode]
Chapter 1- Procurement management
Chapter 3- Construction Law
Chapter 1-Construction Law
Chapter 5- Lecture
Chapter 4- Lecture
Chapter 3- Lecture
Chapter 2- Lecture
Chapter 1- Lecture
Construction equipment management chapter 5
Construction equipment management chapter 4
Construction equipment management chapter 3
Construction equipment management chapter 2
Construction equipment management chapter 1pdf
Chapter 5 [compatibility mode]
Chapter 4 [compatibility mode]
Chapter 1 [compatibility mode]
Construction contract
Chapter 4 [compatibility mode]
Chapter 2 [compatibility mode]

Recently uploaded (20)

PPTX
Internet of Things (IOT) - A guide to understanding
PPTX
UNIT 4 Total Quality Management .pptx
PPTX
UNIT-1 - COAL BASED THERMAL POWER PLANTS
PPTX
Sustainable Sites - Green Building Construction
PDF
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
PPTX
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx
PPTX
Fundamentals of safety and accident prevention -final (1).pptx
PDF
737-MAX_SRG.pdf student reference guides
DOCX
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
PPTX
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
PDF
BIO-INSPIRED HORMONAL MODULATION AND ADAPTIVE ORCHESTRATION IN S-AI-GPT
PPT
introduction to datamining and warehousing
PPTX
Current and future trends in Computer Vision.pptx
PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PDF
A SYSTEMATIC REVIEW OF APPLICATIONS IN FRAUD DETECTION
PPT
Introduction, IoT Design Methodology, Case Study on IoT System for Weather Mo...
PPTX
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
PDF
Embodied AI: Ushering in the Next Era of Intelligent Systems
PDF
PREDICTION OF DIABETES FROM ELECTRONIC HEALTH RECORDS
DOCX
573137875-Attendance-Management-System-original
Internet of Things (IOT) - A guide to understanding
UNIT 4 Total Quality Management .pptx
UNIT-1 - COAL BASED THERMAL POWER PLANTS
Sustainable Sites - Green Building Construction
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx
Fundamentals of safety and accident prevention -final (1).pptx
737-MAX_SRG.pdf student reference guides
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
BIO-INSPIRED HORMONAL MODULATION AND ADAPTIVE ORCHESTRATION IN S-AI-GPT
introduction to datamining and warehousing
Current and future trends in Computer Vision.pptx
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
A SYSTEMATIC REVIEW OF APPLICATIONS IN FRAUD DETECTION
Introduction, IoT Design Methodology, Case Study on IoT System for Weather Mo...
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
Embodied AI: Ushering in the Next Era of Intelligent Systems
PREDICTION OF DIABETES FROM ELECTRONIC HEALTH RECORDS
573137875-Attendance-Management-System-original

Chapter 3- Contract Management

  • 1. Project Delivery Methods College of Engineering Construction Technology and Management Department Mada Walabu University Procurement Management and Contract Administration CoTM 4242 Chapter Three Instructor Andualem Endris (M.Sc) andu0117@yahoo.com www.facebook.com/aendris1 www.linkedin.com/in/andualem-yadeta www.twitter.com/andualemyadeta
  • 2. Definition Project Delivery Method: Is a system used by an agency or owner for organizing and financing design, construction, operations, and maintenance services for a project. 31 July 2021 COTM 4242 2
  • 3. Construction Project Characteristics Construction projects are different than other types of projects due to the following characteristics;  Construction projects are complex undertaking.  Every construction project is unique.  Construction projects involve a lot of uncertainties, lack of information and variables.  Therefore, parties and their role shall be pre-determined. 31 July 2021 3 COTM 4242
  • 4. Traditional Vs Alternative Project Delivery Methods Traditional Approach (D-B-B): The most common delivery system is called “the traditional or standard approach” or “Design-Bid- Build (D-B-B)”, in which the employer assigns the design and construction phases to two different firms (consultant/designer and contractor). Constructing Designing Appointing Consultant Appointing Main Contractor 31 July 2021 4 COTM 4242
  • 5. Traditional Approach (D-B-B):  For many years, DBB has been the most common method of project delivery for public projects, and for many private projects as well.  Design-Bid-Build is effective on projects  where the owner needs both professional design services and construction services  where the designer does not require detailed knowledge of the means and methods of construction.  DBB provides the owner with a high degree of control. 31 July 2021 5 COTM 4242
  • 6. Traditional Approach (D-B-B) … Cont’d  The owner defines project goals and objectives, secures the financing, and specifies the standards and contract terms.  The owner may perform planning, conceptual design and full design, or may engage an outside design professional (designer) for some or all of these tasks.  During this planning and preliminary stage, owner and designer work as a team to obtain required permits and conduct necessary site investigations.  The designer prepares the construction bid documents to reflect the owner’s project goals and objectives.  Prospective contractors prepare their bids from these complete and specific bid documents.  The bidders submit their proposals to the owner, who determines the most responsive (typically the lowest) bid meeting project requirements.  In certain circumstances, owner may be justified in selecting a contractor outright and negotiating contract terms directly. 31 July 2021 6 COTM 4242
  • 7. Advantages of D-B-B Approach  Applicable to a wide range of projects.  Well established and easily understood.  Clearly defined roles for all parties.  Provides the lowest initial price that competitive bidders can offer.  Extensive litigation has resulted in well established legal precedents.  Insurance and bonding are well defined. 31 July 2021 7 COTM 4242
  • 8. Disadvantages of D-B-B Approach  Least-cost approach requires higher level of inspection.  Initial low bid might not result in ultimate lowest cost or final best value.  Designers may have limited knowledge of the true cost and scheduling implication of design decisions. 31 July 2021 8 COTM 4242
  • 9. Alternative Approach (D-B) Design-build (D-B) approach is regarded as an alternative project delivery system It involves a single contract between the project employer and a design-build contractor covering both the design and construction of a project. The design-builder performs design and construction according to design parameters and other requirements established by the employer. Constructing Designing Appointing design & construction contractor Tendering 31 July 2021 9 COTM 4242
  • 10. Design-Build Approach  The owner contracts with a single entity to provide the design and to construct the project.  The contract might be negotiated with a single design- builder or result from competitive proposals.  The selection can be based on low price or on a set of value criteria (experience, staff, bonding capacity, etc).  With the contractor playing a major role in design, costs are typically defined and maintained to a greater degree, and the coordination of fast-track management to achieve early completion is greatly simplified.  The design-builder makes many decisions that owner would make under DBB, due to delegation of greatly increased authority. 31 July 2021 10 COTM 4242
  • 11. Design-Build Approach  For many owners, delegation of responsibilities leads to satisfactory projects. However, if the parties are inexperienced and do not cooperate, the transfer of control and risk can be disappointing.  The owner may need to restructure his/her internal procedures to accommodate design-build approach.  Compared to DBB, this involves a significantly different set of requirements and expectations for process, timelines and communications.  A clear understanding and documentation of design-build processes enhances the quality of design-build projects 31 July 2021 11 COTM 4242
  • 12. Advantage of Design-Build Approach Innovation and quality improvements through: - Alternative designs and construction methods suited to the contractor’s capabilities - Flexibility in the selection of design, materials, and construction methods. • Earlier schedule and cost certainty 31 July 2021 12 COTM 4242
  • 13. Disadvantage of Design-Build Approach  Reduced opportunities for smaller, local construction firms.  Fewer competitors and increased risk may result in higher initial costs.  Elimination of traditional checks and balances. Quality may be subordinated by cost or schedule considerations.  Less Engineer control over final design.  Higher procurement costs.  Traditional funding may not support fast-tracking construction or may require accelerated cash flow.  Accelerated construction can potentially overextend the workforce. 31 July 2021 13 COTM 4242
  • 14. Others  Turnkey  Turnkey Variations  Direct Labor Approach  Construction management. 31 July 2021 14 COTM 4242
  • 15. Turnkey  Turnkey adds to the design-builder’s responsibilities the operation and/or maintenance of the completed project.  Turnkey delivery has the potential for bringing a new project on line more quickly.  Three forms of turnkey project delivery:  Design-build-operate-transfer  Design-build-operate-maintain  Design-build-own-operate-transfer 31 July 2021 15 COTM 4242
  • 16. Turnkey Variation  Variations on turnkey add financing as a key component. While financing arrangements are unique for each project, developer financed projects generally resemble one of the turnkey delivery methods:  FDBT (Finance, design, build, transfer)  FDBOT (Finance, design, build, operate, transfer)  FDBOOT (Finance, design, build ,own, operate, transfer)  In each case, the transfer of the project occurs only after the developer’s interests and financial obligations have been satisfied. 31 July 2021 16 COTM 4242