SlideShare a Scribd company logo
How the Risk Register Drives the Schedule
              Risk Analysis

   David T. Hulett, Hulett & Associates, LLC (USA)
    Waylon T. Whitehead, ConocoPhillips (USA)


             NASA PM Challenge
               Daytona Beach, FL
              February 26-27, 2008



                 © 2007 Hulett & Associates, LLC
Agenda
• Risk Register identifies high-priority risks
• Explain “Risk Factors” approach
   – Risks have probability, impact
   – Risks are assigned to activities
• Compute Monte Carlo simulation results
• Estimate sensitivity and net effect of key risks
• Apply Risk Factors to simple space vehicle
  development schedule as an example
• Collecting risk data for the model
• How results are used to manage project risk

                      © 2007 Hulett & Associates, LLC
Limitations with the Traditional
  3-point Estimate of Activity Duration
• Typical schedule risk analysis starts with the
  activity that is impacted by risks
  – Estimates the 3-point estimate for optimistic, most
    likely and pessimistic duration
  – Creates a probability distribution for activity duration
  – Performs Monte Carlo simulation
• Which risks cause the most overall schedule
  risk? These questions are typically answered by:
  – Sensitivity to activity durations
  – Criticality of activity durations
  – NOT sensitivity to the risks themselves

                    © 2007 Hulett & Associates, LLC
Some Problems with Traditional
             Approach
• Can tell which activities are crucial, but not
  directly which risks are driving
• Makes poor use of the Risk Register that
  is usually available
• Cannot decompose the overall schedule
  risk into its components BY RISK
  – Ability to assign the risk to its specific risk
    drivers helps with communication of risk
    causes and risk mitigation

                  © 2007 Hulett & Associates, LLC
We Propose a Different Approach:
      Start with the Risks Themselves
• Drive the schedule risk by the risks already analyzed
  in the Risk Register
• For each risk, specify:
  – Probability it will occur
  – Impact on time if it does
  – Activities it will affect
• Starting with the risks themselves gives us benefits
  – Links qualitative analysis to the quantitative analysis
  – Estimates the impact of specific risks for prioritized
    mitigation purposes


                      © 2007 Hulett & Associates, LLC
Simple Example of Risk Register Risks




•   Use the Risk Factors module in Pertmaster 8
•   Collect probability and impact data on risks
•   Load the risks
•   Assign risks to schedule activities


                  © 2007 Hulett & Associates, LLC
Risk Factors Mechanics (1)
• The risk factor is assigned to one or several
  activities, affecting their durations by a
  multiplicative factor
  – E.g., the factor may be .90 for optimistic, 1.0 for most
    likely and 1.25 for pessimistic
  – These factors multiply the schedule durations of the
    activities to which they are assigned
• Risks can be assigned to one or more activities
• Activity durations can be influenced by one or
  more risks

                   © 2007 Hulett & Associates, LLC
Risk Factors Mechanics (2)
• Risk Factors are assigned a probability of
  occurring on any iteration.
   – When the risk occurs, the factor used is chosen at
     random from the 3-point estimate and operates on all
     activities to which it is assigned
   – When not occurring on an iteration the risk factor
     takes the value 1.0, a neutral value
• When an activity is influenced by more than one
  risk, their factors are multiplied together, if they
  happen, on any iteration

                   © 2007 Hulett & Associates, LLC
Risk Factor
          Applied to a 100 day Task (1)

                                        0 0 1 0 - C o n s tr u c tio n : D u r a tio n
                                                                                                       1 0 0% 11 5
                      2 50
                                                                                                       9 5 % 1 11


Here the                                                                                               9 0 % 1 09

                                                                                                       8 5 % 1 08
                                                                                                                                            For the
Ranges are            2 00
                                                                                                       8 0 % 1 06

                                                                                                       7 5 % 1 05
                                                                                                                                            examples we
based on                                                                                               7 0 % 1 04                           use an activity
                                                                                                       6 5 % 1 04
deviations +                                                                                                                                with 100 days




                                                                                                                     Cumulative Frequency
                                                                                                       6 0 % 1 03
                      1 50

and – from                                                                                             5 5 % 1 02
                                                                                                                                            in the
               Hits




                                                                                                       5 0 % 1 01

the Plan.                                                                                              4 5 % 1 01

                                                                                                       4 0 % 1 00
                                                                                                                                            schedule
                      1 00
Probability                                                                                            35% 99

                                                                                                       30% 99
is 100%                                                                                                25% 98

                       50                                                                              20% 97

                                                                                                       15% 96

                                                                                                       10% 95

                                                                                                       5 % 94

                        0                                                                              0 % 90
                             90    95             10 0                  1 05             1 10   11 5
                                             D istrib u tio n (sta rt o f in te rva l)




                                  © 2007 Hulett & Associates, LLC
Risk Factor
          Applied to a 100-day Task (2)

                                 0 0 4 0 - T e c h n o lo g y D e s ig n : D u r a tio n
                                                                                                 100% 130

                                                                                                 95% 125
                     200
                                                                                                 90% 122

                                                                                                 85% 121
                     180

Here the                                                                                         80% 119

                                                                                                 75% 118
                     160

Plan is the                                                                                      70% 117

                     140                                                                         65% 116
Optimistic




                                                                                                            Cumulative Frequency
                                                                                                 60% 115


Value.               120                                                                         55% 114
              Hits




                                                                                                 50% 113

Probability          100
                                                                                                 45% 112

                                                                                                 40% 111
is 100%               80
                                                                                                 35% 110

                                                                                                 30% 109
                      60
                                                                                                 25% 109

                                                                                                 20% 108
                      40
                                                                                                 15% 107

                      20                                                                         10% 105

                                                                                                 5% 104

                       0                                                                         0% 100
                           100            110                                120           130
                                           D istrib u tio n (sta rt o f in te rva l)




                                 © 2007 Hulett & Associates, LLC
Assigning a Probability Less than 100%

• The essence of “risk” is the uncertainty
  – Uncertainty of its occurrence, specified by a
    probability
  – Uncertainty of its impact, specified by a range of
    durations
• If the risk may or may not occur, we specify the
  probability that it will occur
  – The risk occurs and affects the activities it is assigned
    to on X% of the iterations, chosen at random
  – On (1 – X)% of the iterations, the plan value is used

                   © 2007 Hulett & Associates, LLC
Assigning a Probability Less than 100%


                                 0010 - Construction : Duration                                                                          0040 - Technology Design : Duration
                                                                                   100% 115                                                                                             100% 130

Spike                                                                              95% 107                                                                                              95% 123



contains
                                                                                   90% 103                                  1200                                                        90% 120
                                                                                                                                                                                                                          Spike
                                                                                   85% 101                                                                                              85% 118


70% of
                     2000
                                                                                   80% 100                                                                                              80% 116                           contains
the
                                                                                   75% 100

                                                                                   70% 100
                                                                                                                            1000                                                        75% 114

                                                                                                                                                                                        70% 113
                                                                                                                                                                                                                          40% of
probability
                                                                                   65% 100                                                                                              65% 111
                                                                                                                                                                                                                          the




                                                                                                                                                                                                   Cumulative Frequency
                                                                                              Cumulative Frequency
                     1500
                                                                                   60% 100                                  800                                                         60% 110

                                                                                   55% 100                                                                                              55% 109                           probability

                                                                                                                     Hits
              Hits




                                                                                   50% 100                                                                                              50% 107

                                                                                   45% 100                                  600                                                         45% 105

                     1000                                                                                                                                                               40% 100
                                                                                   40% 100

                                                                                   35% 100                                                                                              35% 100

                                                                                   30% 100                                  400                                                         30% 100

                                                                                   25% 100                                                                                              25% 100

                     500                                                           20% 100                                                                                              20% 100

                                                                                   15% 100                                  200                                                         15% 100

                                                                                   10% 99                                                                                               10% 100

                                                                                   5% 97                                                                                                5% 100

                                                                                                                              0                                                         0% 100
                       0                                                           0% 91
                                                                                                                                   100        110                         120     130
                            95        100              105             110   115
                                    Distribution (start of interval)                                                                           Distribution (start of interval)




                                                                       © 2007 Hulett & Associates, LLC
Assigning
   More than One Risk to an Activity
• If more than one risk is acting on an
  activity, the resulting ranges are the
  multiplication of the percentages
  – Risk 1 has 90%, 100% and 115%
  – Risk 2 has 100%, 110% and 130%
  – The resulting risk has ranges of
     • Optimistic: 90% (.9 x 1.0)
     • Most Likely:110% (1.0 x 1.1)
     • Pessimistic:150% (1.15 x 1.3)

                  © 2007 Hulett & Associates, LLC
Two Risks affect One Activity
               using Factors

                                 0040 - T echnology Design : Duration
                                                                                         100% 144

                                                                                         95% 130

                                                                                         90% 127
                    140
                                                                                         85% 124

                                                                                         80% 123

                    120                                                                  75% 121

                                                                                         70% 119

Range               100
                                                                                         65% 118




                                                                                                    Cumulative Frequency
                                                                                         60% 117
from 90 to                                                                               55% 116
             Hits




150 days,            80                                                                  50% 115

                                                                                         45% 114

Peak about           60
                                                                                         40% 113

                                                                                         35% 111
113 days                                                                                 30% 110

                     40                                                                  25% 109

                                                                                         20% 108

                                                                                         15% 106
                     20
                                                                                         10% 104

                                                                                         5% 102

                      0                                                                  0% 93
                           100         110              120                  130   140
                                       Distribution (sta rt of inte rva l)




                          © 2007 Hulett & Associates, LLC
Two Risks with Less than 100%
          Probability Affecting one Activity

                                          0040 - T echnology Design : Duration
                           1100                                                                   100% 144

                                                                                                  95% 123


The spike at               1000                                                                   90% 119

                                                                                                  85% 116

100 days                    900
                                                                                                  80% 113

                                                                                                  75% 111
represents (1)              800
                                                                                                  70% 110


the likelihood              700
                                                                                                  65% 108




                                                                                                             Cumulative Frequency
                                                                                                  60% 106

that neither risk           600                                                                   55% 104
                    Hits




                                                                                                  50% 102
occurs and (2)              500                                                                   45% 101


the chance that             400
                                                                                                  40% 100

                                                                                                  35% 100

100 days is                 300
                                                                                                  30% 100

                                                                                                  25% 100
picked when                 200
                                                                                                  20% 100


one or both                 100
                                                                                                  15% 100

                                                                                                  10% 99

occur                                                                                             5% 97

                              0                                                                   0% 91
                                    100          110               120                130   140
                                                Distribution (sta rt of inte rva l)




                                  © 2007 Hulett & Associates, LLC
Sensitivity to the Risk Factors


Risk #1 has
larger
percentage
extremes but
Risk #2 has
a higher
probability.




                 © 2007 Hulett & Associates, LLC
Simple 2-Stage Space Vehicle Schedule




         Software used: Pertmaster v. 8.0
                © 2007 Hulett & Associates, LLC
Simple Space Vehicle
            Development Schedule
• 87 month schedule
    – 67 months for design, fabrication, and test of FS, US
    – 16 months of integration and test
•   10 activities linked
•   Beginning 3 March 2008
•   PDR on 11 SEPT 2009
•   CDR on 3 June 2011
•   Delivery to launch site 7 Feb 2014


                    © 2007 Hulett & Associates, LLC
Two Types of Risk
• Background risk based on typical general
  risk, estimating error
  – Used Quick Risk of -5% and +10%
• Discrete risks derived from Risk Register
  – Summarized from detailed Risk Register
  – These have a probability of occurring and an
    impact on specific activities if they do
  – Parallel to their Risk Register information,
    which is used in data collection

                © 2007 Hulett & Associates, LLC
Schedule Including Background Risk



 Background risk:
Optimistic -5% and
Pessimistic +10%




                     © 2007 Hulett & Associates, LLC
Results with Background Risk Only
                              Spacecraft Program
                             Entire Plan : Finish Date
                                                                           100% 30/Dec/15
                                                                           95% 27/Oct/15
          400
                                                                           90% 15/Oct/15
                                                                           85% 07/Oct/15
                                                                           80% 30/Sep/15
                                                                                                                   Deterministic:
                                                                           75% 24/Sep/15                           12JUN15 is <1%
          300                                                              70% 18/Sep/15




                                                                                            Cumulative Frequency
                                                                           65% 14/Sep/15
                                                                           60% 09/Sep/15
                                                                                                                   P-80 is 30SEP15,
                                                                           55% 04/Sep/15                           about 3.5 months
   Hits




          200
                                                                           50% 01/Sep/15
                                                                           45% 26/Aug/15
                                                                                                                   later than planned
                                                                           40% 21/Aug/15
                                                                           35% 18/Aug/15                           Spread from P-5 to
                                                                           30% 12/Aug/15
                                                                                                                   P-95 is 5JUL15 to
                                                                           25% 07/Aug/15
          100
                                                                           20% 31/Jul/15                           27OCT15 for 3.7
                                                                           15% 24/Jul/15
                                                                           10% 17/Jul/15
                                                                                                                   months
                                                                           5% 06/Jul/15
            0                                                              0% 14/May/15
                31/May/15              08/Sep/15               17/Dec/15
                            Distribution (start of interval)




                                    © 2007 Hulett & Associates, LLC
Discovery of Risk Factors
• From exploratory interviews w/ all project
  stakeholders to arrive at their general
  ideas about what the risks are
• From the project risk register (each risk
  listed on the risk register should be
  “mapped” to one Risk Factor)
• From general knowledge about conditions
  (market, analogous data) that might affect
  the project

               © 2007 Hulett & Associates, LLC
Detailed Interviews for Information
           about Risk Factors
• Using the arrived at Risk Factors, conduct
  interviews to assess their likelihood and
  impact
• Be alert to the discussion of new risks
  during the interviews
• The use of pre-read information can assist
  with the amount of information that can be
  covered in a time limited interview

               © 2007 Hulett & Associates, LLC
Applying Risk Factors
• Where possible, cover what type of
  schedule activities the risk factor will apply
  to
• Be alert to the need for applying the same
  risk factor with more than one range for
  different types of activities
• Be alert to the need to divide schedule
  activities in order to discretely apply Risk
  Factors

                © 2007 Hulett & Associates, LLC
Risk Analysis on Space Vehicle Project
 Risk Factors are from Risk Register




• Seven risk factors have been identified and
  quantified.
• Each Risk has probability assigned
• Some have optimistic ranges possible, others
  are pure threats

                © 2007 Hulett & Associates, LLC
Risks Assigned to Activities (1)
                      Requirements     FS Preliminary   FS Final   FS            Test FS
Risk
                      Definition       Design           Design     Fabrication   Engine

Requirements Not
                           X
Complete
Alternative Designs
                                              X
Possible

Designs Not Proven                                          X

New Materials in
                                                                        X
Fabrication

Lost Know-How                                                           X

Funding Problematic                           X             X           X             X

Testing Schedule
                                                                                      X
Aggressive




                               © 2007 Hulett & Associates, LLC
Risks Assigned to Activities (2)
                      US Preliminary    US Final    US             US                   Integration
Risk                                                                      Integration
                      Design            Design      Fabrication    Test                 Testing
Requirements Not
Complete
Alternative Designs
                             X
Possible

Designs Not Proven                          X

New Materials in
                                                         X
Fabrication

Lost Know-How                                            X                     X

Funding Problematic          X              X            X          X          X             X

Testing Schedule
                                                                    X                        X
Aggressive




                                 © 2007 Hulett & Associates, LLC
Results Adding
   Risk Factors to the Background Risk
                                           Spacecraft Program
                                          Entire Plan : Finish Date
                              800                                                       100% 31/Jul/17
                                                                                        95% 02/Sep/16
Baseline 12JUN 15                                                                       90% 29/Jun/16
                                                                                        85% 06/May/16
is only 3% likely                                                                       80% 29/Mar/16
                              600                                                       75% 01/Mar/16
The 80th  percentile                                                                    70% 11/Feb/16




                                                                                                         Cumulative Frequency
                                                                                        65% 26/Jan/16
(P-80) is 29MAR16,                                                                      60% 11/Jan/16

9.5 months later                                                                        55% 29/Dec/15
                       Hits




                              400                                                       50% 18/Dec/15
                                                                                        45% 07/Dec/15
Spread P-5 to P-95                                                                      40% 27/Nov/15
is 12AUG15 to                                                                           35% 17/Nov/15
                                                                                        30% 06/Nov/15
2SEP16, for 12.5              200                                                       25% 27/Oct/15

months                                                                                  20% 14/Oct/15
                                                                                        15% 30/Sep/15
                                                                                        10% 11/Sep/15
                                                                                        5% 12/Aug/15
                               0                                                        0% 29/Jan/15
                                            17/Dec/15                       30/Apr/17
                                         Distribution (start of interval)




                              © 2007 Hulett & Associates, LLC
Activity Tornado Chart
                                  from All-In Simulation
                                   Spacecraft Program
                                      Duration Sensitivity


                                                                                         Risky Activities:
       00011 - FS Fabrication                                                      78%
                                                                                         Fabrication,
       00025 - US Fabrication                                                      77%
                                                                                         Integration, Final
            00028 - Integration                                              72%
                                                                                         Design, Preliminary
                                                                                         Design, Testing
      00009 - FS Final Design                                               70%


     00023 - US Final Design                                                70%          All except testing
                                                                                         have about the same
00007 - FS Preliminary Design                                         64%
                                                                                         influence
00021 - US Preliminary Design                                         64%


              00026 - US Test                                   55%


    00029 - Integration Testing                                 55%


      00012 - Test FS Engine                                    55%




                                                © 2007 Hulett & Associates, LLC
Risk Factor Tornado
                                                      from All-In Simulation
                                        Driving Schedule Risk Factors



  6 - Funding from Congress is problematic


                                                                                                 The main RISK,
      4 - Fabricaton requires new materials
                                                                                                 however, is funding
            3 - New designs not yet proven
                                                                                                 from Congress, which
                                                                                                 affected all activities.
      7 - Schedule for testing is aggressive                                                     This is the main risk to
                                                                                                 mitigate, if possible
 2 - Several alternative designs considered




5 - Lost know-how since last full spacecraft




  1 - Requirements have not been decided




                                               0.00     0.20      0.40         0.60   0.80
                                                                 Correlation




                                                               © 2007 Hulett & Associates, LLC
Contribution of
        Each Risk to the Contingency (1)
                       Explain the Contingency to the P-80
                                    P-80 Date              Take Risks Out:
All Risks In                          6-Jun-16 Days Saved           % of Contingency
Specific Risks Taken Out in Order
No Funding Risk                      19-Jan-16             139                  39%
No Tight Testing Schedule Risk        1-Dec-15                 49               14%
No New Design Risk                   15-Oct-15                 47               13%
No Alternative Design Risk             5-Oct-15                10                3%
No Lost Know How Risk                  2-Oct-15                3                 1%
No Requirements Risk                 30-Sep-15                 2                 1%
Background Schedule Estimating Risks
No Background Risk                   12-Jun-15             110                  31%
      Total Contingency                                    360                 100%


                             © 2007 Hulett & Associates, LLC
Contribution of
     Each Risk to the Contingency (2)
                                                                             Distribution Analyzer Report
No Background Risk - Finish Date                                                       No Design Alternative Risk - Finish Date                    No Testing Scheudle Risk - Finish Date
No Requirements Risk - Finish Date                                                     No New Design Risk - Finish Date                            No Funding Risk - Finish Date
No Lost Know How risk - Finish Date                                                    No New Materials Risk - Finish Date                         All Risks - Finish Date
                                                                                                                                                                                               100%


                                                                                                                                                                                               90%




                                                             01/Dec/15




                                                                                                  29/Mar/16
                   12/Jun/15




                                             02/Oct/15
                                             05/Oct/15
                                             30/Sep/15
                                             15/Oct/15
                                             27/Oct/15




                                                                           19/Jan/16
                                                                                                                                                                                               80%


                                                                                                                                                                                               70%




                                                                                                                                                                                                      Cumulative Probability
                                                                                                                                                                                               60%


                                                                                                                                                                                               50%


                                                                                                                                                                                               40%


                                                                                                                                                                                               30%


                                                                                                                                                                                               20%


                                                                                                                                                                                               10%


                                                                                                                                                                                               0%
   06/ Apr/ 15                 15/ Jul/ 15     23/ Oct/ 15                 31/ Jan/ 16                        10/ May/ 16   18/ Aug/ 16   26/ Nov/ 16        06/ Mar/ 17         14/ Jun/ 17




                                                                         © 2007 Hulett & Associates, LLC
Summary (1)
• The focus is on the risks, not their impact
• Risks “explain” the need for a contingency
• Management appreciates this focus on
  risks
• Risk interviews are conducted at 20,000
  foot level, where people typically think of
  risk
• Interviews go faster, stick to the substance

               © 2007 Hulett & Associates, LLC
Summary (2)
• Risk Register exists, use it for quantitative
  analysis
• Specific risks can be quantified and assigned to
  schedule activities
  – Quantification is probability and impact
  – A risk can affect several activities
  – An activity can be affected by several risks
• Risk Factors can be combined with other more
  traditional approaches such as 3-point estimates
  for background risk or probabilistic branching

                   © 2007 Hulett & Associates, LLC
Using the Risk Register in Schedule Risk
 Analysis with Monte Carlo Simulation

  David T. Hulett, Hulett & Associates, LLC (USA)
   Waylon T. Whitehead, ConocoPhillips (USA)


            NASA PM Challenge
              Daytona Beach, FL
             February 26-27, 2008



                © 2007 Hulett & Associates, LLC

More Related Content

PDF
Hulett
PDF
Inventory Record Accuracy
PDF
Bilardo vincent
PPT
Concepts and best practices for the risk register in primavera risk analysis
PPTX
Risk Technology Strategy, Selection and Implementation
PPTX
Backup norm.smith
PDF
Heard
PPTX
C null 01-17-2011
Hulett
Inventory Record Accuracy
Bilardo vincent
Concepts and best practices for the risk register in primavera risk analysis
Risk Technology Strategy, Selection and Implementation
Backup norm.smith
Heard
C null 01-17-2011

Viewers also liked (20)

PDF
Patrick.guske.update
PPTX
Grubbs teams and digital collaboration pmc2012
PPTX
Coonce.tom
PPTX
Wienkoop.glenn
PPTX
Bauer.frank
PDF
Inter pech bounds
PDF
Harrison.g.poole.k
PPT
M washington
PPT
Serrato.be be
PDF
Kirsch.mike
PDF
Patrick.guske.update
PDF
K.pagel.beene
PDF
Stacy.cusack
PDF
Brockhurst.lane
PDF
John.emond
PDF
Dillon.r.tinsley.c.rogers.e
PPTX
Rippe.carpio
PDF
Barth simpkins
PPTX
Battista barlowpmc conference 2012 rev. 2
PPT
Mc nally
Patrick.guske.update
Grubbs teams and digital collaboration pmc2012
Coonce.tom
Wienkoop.glenn
Bauer.frank
Inter pech bounds
Harrison.g.poole.k
M washington
Serrato.be be
Kirsch.mike
Patrick.guske.update
K.pagel.beene
Stacy.cusack
Brockhurst.lane
John.emond
Dillon.r.tinsley.c.rogers.e
Rippe.carpio
Barth simpkins
Battista barlowpmc conference 2012 rev. 2
Mc nally
Ad

Similar to David.hulett (10)

PDF
Patterson.dan
PDF
Hulett
PDF
Making Sense of the U.S. Economy and Housing Market (Credit Union Webinar Han...
PDF
U ti investorday2011-freightforwarding
PDF
フォームを編集 [ ブログを読んだ方、ぜひアンケートにご協力下さい ] - Google ドキュメント
PDF
Future Challenges for Big Pharma
PPT
Enter ReLEx-goodbye excimer
PPT
Investment Policy for Insurers - June 2012
PPTX
Thomson reuters cio advisory board state of legal industry by steve daitch ...
PDF
Odds of investing in indian equity market
Patterson.dan
Hulett
Making Sense of the U.S. Economy and Housing Market (Credit Union Webinar Han...
U ti investorday2011-freightforwarding
フォームを編集 [ ブログを読んだ方、ぜひアンケートにご協力下さい ] - Google ドキュメント
Future Challenges for Big Pharma
Enter ReLEx-goodbye excimer
Investment Policy for Insurers - June 2012
Thomson reuters cio advisory board state of legal industry by steve daitch ...
Odds of investing in indian equity market
Ad

More from NASAPMC (20)

PDF
Bejmuk bo
PDF
Baniszewski john
PDF
Yew manson
PDF
Wood frank
PDF
Wood frank
PDF
Wessen randi (cd)
PDF
Vellinga joe
PDF
Trahan stuart
PDF
Stock gahm
PDF
Snow lee
PDF
Smalley sandra
PDF
Seftas krage
PDF
Sampietro marco
PDF
Rudolphi mike
PDF
Roberts karlene
PDF
Rackley mike
PDF
Paradis william
PDF
Osterkamp jeff
PDF
O'keefe william
PDF
Muller ralf
Bejmuk bo
Baniszewski john
Yew manson
Wood frank
Wood frank
Wessen randi (cd)
Vellinga joe
Trahan stuart
Stock gahm
Snow lee
Smalley sandra
Seftas krage
Sampietro marco
Rudolphi mike
Roberts karlene
Rackley mike
Paradis william
Osterkamp jeff
O'keefe william
Muller ralf

Recently uploaded (20)

PPTX
OAT_ORI_Fed Independence_August 2025.pptx
PPT
KPMG FA Benefits Report_FINAL_Jan 27_2010.ppt
DOCX
Final. 150 minutes exercise agrumentative Essay
PPTX
lesson in englishhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhh
PDF
Pitch Deck.pdf .pdf all about finance in
PDF
Principal of magaement is good fundamentals in economics
PDF
2018_Simulating Hedge Fund Strategies Generalising Fund Performance Presentat...
PDF
DTC TRADIND CLUB MAKE YOUR TRADING BETTER
PPTX
Maths science sst hindi english cucumber
PPTX
Very useful ppt for your banking assignments Banking.pptx
PDF
USS pension Report and Accounts 2025.pdf
PDF
Best Accounting Outsourcing Companies in The USA
PDF
Fintech Regulatory Sandbox: Lessons Learned and Future Prospects
PPTX
Grp C.ppt presentation.pptx for Economics
PPTX
Group Presentation Development Econ and Envi..pptx
PDF
3CMT J.AFABLE Flexible-Learning ENTREPRENEURIAL MANAGEMENT.pdf
PPTX
PPT-Lesson-2-Recognize-a-Potential-Market-2-3.pptx
PDF
5-principles-of-PD-design.pdfvvvhvjvvcjcxhhcjb ggfvjhvjjhbvbbbvccxhgcxzzghjbv...
PPTX
INDIAN FINANCIAL SYSTEM (Financial institutions, Financial Markets & Services)
PPTX
Q1 PE AND HEALTH 5 WEEK 5 DAY 1 powerpoint template
OAT_ORI_Fed Independence_August 2025.pptx
KPMG FA Benefits Report_FINAL_Jan 27_2010.ppt
Final. 150 minutes exercise agrumentative Essay
lesson in englishhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhhh
Pitch Deck.pdf .pdf all about finance in
Principal of magaement is good fundamentals in economics
2018_Simulating Hedge Fund Strategies Generalising Fund Performance Presentat...
DTC TRADIND CLUB MAKE YOUR TRADING BETTER
Maths science sst hindi english cucumber
Very useful ppt for your banking assignments Banking.pptx
USS pension Report and Accounts 2025.pdf
Best Accounting Outsourcing Companies in The USA
Fintech Regulatory Sandbox: Lessons Learned and Future Prospects
Grp C.ppt presentation.pptx for Economics
Group Presentation Development Econ and Envi..pptx
3CMT J.AFABLE Flexible-Learning ENTREPRENEURIAL MANAGEMENT.pdf
PPT-Lesson-2-Recognize-a-Potential-Market-2-3.pptx
5-principles-of-PD-design.pdfvvvhvjvvcjcxhhcjb ggfvjhvjjhbvbbbvccxhgcxzzghjbv...
INDIAN FINANCIAL SYSTEM (Financial institutions, Financial Markets & Services)
Q1 PE AND HEALTH 5 WEEK 5 DAY 1 powerpoint template

David.hulett

  • 1. How the Risk Register Drives the Schedule Risk Analysis David T. Hulett, Hulett & Associates, LLC (USA) Waylon T. Whitehead, ConocoPhillips (USA) NASA PM Challenge Daytona Beach, FL February 26-27, 2008 © 2007 Hulett & Associates, LLC
  • 2. Agenda • Risk Register identifies high-priority risks • Explain “Risk Factors” approach – Risks have probability, impact – Risks are assigned to activities • Compute Monte Carlo simulation results • Estimate sensitivity and net effect of key risks • Apply Risk Factors to simple space vehicle development schedule as an example • Collecting risk data for the model • How results are used to manage project risk © 2007 Hulett & Associates, LLC
  • 3. Limitations with the Traditional 3-point Estimate of Activity Duration • Typical schedule risk analysis starts with the activity that is impacted by risks – Estimates the 3-point estimate for optimistic, most likely and pessimistic duration – Creates a probability distribution for activity duration – Performs Monte Carlo simulation • Which risks cause the most overall schedule risk? These questions are typically answered by: – Sensitivity to activity durations – Criticality of activity durations – NOT sensitivity to the risks themselves © 2007 Hulett & Associates, LLC
  • 4. Some Problems with Traditional Approach • Can tell which activities are crucial, but not directly which risks are driving • Makes poor use of the Risk Register that is usually available • Cannot decompose the overall schedule risk into its components BY RISK – Ability to assign the risk to its specific risk drivers helps with communication of risk causes and risk mitigation © 2007 Hulett & Associates, LLC
  • 5. We Propose a Different Approach: Start with the Risks Themselves • Drive the schedule risk by the risks already analyzed in the Risk Register • For each risk, specify: – Probability it will occur – Impact on time if it does – Activities it will affect • Starting with the risks themselves gives us benefits – Links qualitative analysis to the quantitative analysis – Estimates the impact of specific risks for prioritized mitigation purposes © 2007 Hulett & Associates, LLC
  • 6. Simple Example of Risk Register Risks • Use the Risk Factors module in Pertmaster 8 • Collect probability and impact data on risks • Load the risks • Assign risks to schedule activities © 2007 Hulett & Associates, LLC
  • 7. Risk Factors Mechanics (1) • The risk factor is assigned to one or several activities, affecting their durations by a multiplicative factor – E.g., the factor may be .90 for optimistic, 1.0 for most likely and 1.25 for pessimistic – These factors multiply the schedule durations of the activities to which they are assigned • Risks can be assigned to one or more activities • Activity durations can be influenced by one or more risks © 2007 Hulett & Associates, LLC
  • 8. Risk Factors Mechanics (2) • Risk Factors are assigned a probability of occurring on any iteration. – When the risk occurs, the factor used is chosen at random from the 3-point estimate and operates on all activities to which it is assigned – When not occurring on an iteration the risk factor takes the value 1.0, a neutral value • When an activity is influenced by more than one risk, their factors are multiplied together, if they happen, on any iteration © 2007 Hulett & Associates, LLC
  • 9. Risk Factor Applied to a 100 day Task (1) 0 0 1 0 - C o n s tr u c tio n : D u r a tio n 1 0 0% 11 5 2 50 9 5 % 1 11 Here the 9 0 % 1 09 8 5 % 1 08 For the Ranges are 2 00 8 0 % 1 06 7 5 % 1 05 examples we based on 7 0 % 1 04 use an activity 6 5 % 1 04 deviations + with 100 days Cumulative Frequency 6 0 % 1 03 1 50 and – from 5 5 % 1 02 in the Hits 5 0 % 1 01 the Plan. 4 5 % 1 01 4 0 % 1 00 schedule 1 00 Probability 35% 99 30% 99 is 100% 25% 98 50 20% 97 15% 96 10% 95 5 % 94 0 0 % 90 90 95 10 0 1 05 1 10 11 5 D istrib u tio n (sta rt o f in te rva l) © 2007 Hulett & Associates, LLC
  • 10. Risk Factor Applied to a 100-day Task (2) 0 0 4 0 - T e c h n o lo g y D e s ig n : D u r a tio n 100% 130 95% 125 200 90% 122 85% 121 180 Here the 80% 119 75% 118 160 Plan is the 70% 117 140 65% 116 Optimistic Cumulative Frequency 60% 115 Value. 120 55% 114 Hits 50% 113 Probability 100 45% 112 40% 111 is 100% 80 35% 110 30% 109 60 25% 109 20% 108 40 15% 107 20 10% 105 5% 104 0 0% 100 100 110 120 130 D istrib u tio n (sta rt o f in te rva l) © 2007 Hulett & Associates, LLC
  • 11. Assigning a Probability Less than 100% • The essence of “risk” is the uncertainty – Uncertainty of its occurrence, specified by a probability – Uncertainty of its impact, specified by a range of durations • If the risk may or may not occur, we specify the probability that it will occur – The risk occurs and affects the activities it is assigned to on X% of the iterations, chosen at random – On (1 – X)% of the iterations, the plan value is used © 2007 Hulett & Associates, LLC
  • 12. Assigning a Probability Less than 100% 0010 - Construction : Duration 0040 - Technology Design : Duration 100% 115 100% 130 Spike 95% 107 95% 123 contains 90% 103 1200 90% 120 Spike 85% 101 85% 118 70% of 2000 80% 100 80% 116 contains the 75% 100 70% 100 1000 75% 114 70% 113 40% of probability 65% 100 65% 111 the Cumulative Frequency Cumulative Frequency 1500 60% 100 800 60% 110 55% 100 55% 109 probability Hits Hits 50% 100 50% 107 45% 100 600 45% 105 1000 40% 100 40% 100 35% 100 35% 100 30% 100 400 30% 100 25% 100 25% 100 500 20% 100 20% 100 15% 100 200 15% 100 10% 99 10% 100 5% 97 5% 100 0 0% 100 0 0% 91 100 110 120 130 95 100 105 110 115 Distribution (start of interval) Distribution (start of interval) © 2007 Hulett & Associates, LLC
  • 13. Assigning More than One Risk to an Activity • If more than one risk is acting on an activity, the resulting ranges are the multiplication of the percentages – Risk 1 has 90%, 100% and 115% – Risk 2 has 100%, 110% and 130% – The resulting risk has ranges of • Optimistic: 90% (.9 x 1.0) • Most Likely:110% (1.0 x 1.1) • Pessimistic:150% (1.15 x 1.3) © 2007 Hulett & Associates, LLC
  • 14. Two Risks affect One Activity using Factors 0040 - T echnology Design : Duration 100% 144 95% 130 90% 127 140 85% 124 80% 123 120 75% 121 70% 119 Range 100 65% 118 Cumulative Frequency 60% 117 from 90 to 55% 116 Hits 150 days, 80 50% 115 45% 114 Peak about 60 40% 113 35% 111 113 days 30% 110 40 25% 109 20% 108 15% 106 20 10% 104 5% 102 0 0% 93 100 110 120 130 140 Distribution (sta rt of inte rva l) © 2007 Hulett & Associates, LLC
  • 15. Two Risks with Less than 100% Probability Affecting one Activity 0040 - T echnology Design : Duration 1100 100% 144 95% 123 The spike at 1000 90% 119 85% 116 100 days 900 80% 113 75% 111 represents (1) 800 70% 110 the likelihood 700 65% 108 Cumulative Frequency 60% 106 that neither risk 600 55% 104 Hits 50% 102 occurs and (2) 500 45% 101 the chance that 400 40% 100 35% 100 100 days is 300 30% 100 25% 100 picked when 200 20% 100 one or both 100 15% 100 10% 99 occur 5% 97 0 0% 91 100 110 120 130 140 Distribution (sta rt of inte rva l) © 2007 Hulett & Associates, LLC
  • 16. Sensitivity to the Risk Factors Risk #1 has larger percentage extremes but Risk #2 has a higher probability. © 2007 Hulett & Associates, LLC
  • 17. Simple 2-Stage Space Vehicle Schedule Software used: Pertmaster v. 8.0 © 2007 Hulett & Associates, LLC
  • 18. Simple Space Vehicle Development Schedule • 87 month schedule – 67 months for design, fabrication, and test of FS, US – 16 months of integration and test • 10 activities linked • Beginning 3 March 2008 • PDR on 11 SEPT 2009 • CDR on 3 June 2011 • Delivery to launch site 7 Feb 2014 © 2007 Hulett & Associates, LLC
  • 19. Two Types of Risk • Background risk based on typical general risk, estimating error – Used Quick Risk of -5% and +10% • Discrete risks derived from Risk Register – Summarized from detailed Risk Register – These have a probability of occurring and an impact on specific activities if they do – Parallel to their Risk Register information, which is used in data collection © 2007 Hulett & Associates, LLC
  • 20. Schedule Including Background Risk Background risk: Optimistic -5% and Pessimistic +10% © 2007 Hulett & Associates, LLC
  • 21. Results with Background Risk Only Spacecraft Program Entire Plan : Finish Date 100% 30/Dec/15 95% 27/Oct/15 400 90% 15/Oct/15 85% 07/Oct/15 80% 30/Sep/15 Deterministic: 75% 24/Sep/15 12JUN15 is <1% 300 70% 18/Sep/15 Cumulative Frequency 65% 14/Sep/15 60% 09/Sep/15 P-80 is 30SEP15, 55% 04/Sep/15 about 3.5 months Hits 200 50% 01/Sep/15 45% 26/Aug/15 later than planned 40% 21/Aug/15 35% 18/Aug/15 Spread from P-5 to 30% 12/Aug/15 P-95 is 5JUL15 to 25% 07/Aug/15 100 20% 31/Jul/15 27OCT15 for 3.7 15% 24/Jul/15 10% 17/Jul/15 months 5% 06/Jul/15 0 0% 14/May/15 31/May/15 08/Sep/15 17/Dec/15 Distribution (start of interval) © 2007 Hulett & Associates, LLC
  • 22. Discovery of Risk Factors • From exploratory interviews w/ all project stakeholders to arrive at their general ideas about what the risks are • From the project risk register (each risk listed on the risk register should be “mapped” to one Risk Factor) • From general knowledge about conditions (market, analogous data) that might affect the project © 2007 Hulett & Associates, LLC
  • 23. Detailed Interviews for Information about Risk Factors • Using the arrived at Risk Factors, conduct interviews to assess their likelihood and impact • Be alert to the discussion of new risks during the interviews • The use of pre-read information can assist with the amount of information that can be covered in a time limited interview © 2007 Hulett & Associates, LLC
  • 24. Applying Risk Factors • Where possible, cover what type of schedule activities the risk factor will apply to • Be alert to the need for applying the same risk factor with more than one range for different types of activities • Be alert to the need to divide schedule activities in order to discretely apply Risk Factors © 2007 Hulett & Associates, LLC
  • 25. Risk Analysis on Space Vehicle Project Risk Factors are from Risk Register • Seven risk factors have been identified and quantified. • Each Risk has probability assigned • Some have optimistic ranges possible, others are pure threats © 2007 Hulett & Associates, LLC
  • 26. Risks Assigned to Activities (1) Requirements FS Preliminary FS Final FS Test FS Risk Definition Design Design Fabrication Engine Requirements Not X Complete Alternative Designs X Possible Designs Not Proven X New Materials in X Fabrication Lost Know-How X Funding Problematic X X X X Testing Schedule X Aggressive © 2007 Hulett & Associates, LLC
  • 27. Risks Assigned to Activities (2) US Preliminary US Final US US Integration Risk Integration Design Design Fabrication Test Testing Requirements Not Complete Alternative Designs X Possible Designs Not Proven X New Materials in X Fabrication Lost Know-How X X Funding Problematic X X X X X X Testing Schedule X X Aggressive © 2007 Hulett & Associates, LLC
  • 28. Results Adding Risk Factors to the Background Risk Spacecraft Program Entire Plan : Finish Date 800 100% 31/Jul/17 95% 02/Sep/16 Baseline 12JUN 15 90% 29/Jun/16 85% 06/May/16 is only 3% likely 80% 29/Mar/16 600 75% 01/Mar/16 The 80th percentile 70% 11/Feb/16 Cumulative Frequency 65% 26/Jan/16 (P-80) is 29MAR16, 60% 11/Jan/16 9.5 months later 55% 29/Dec/15 Hits 400 50% 18/Dec/15 45% 07/Dec/15 Spread P-5 to P-95 40% 27/Nov/15 is 12AUG15 to 35% 17/Nov/15 30% 06/Nov/15 2SEP16, for 12.5 200 25% 27/Oct/15 months 20% 14/Oct/15 15% 30/Sep/15 10% 11/Sep/15 5% 12/Aug/15 0 0% 29/Jan/15 17/Dec/15 30/Apr/17 Distribution (start of interval) © 2007 Hulett & Associates, LLC
  • 29. Activity Tornado Chart from All-In Simulation Spacecraft Program Duration Sensitivity Risky Activities: 00011 - FS Fabrication 78% Fabrication, 00025 - US Fabrication 77% Integration, Final 00028 - Integration 72% Design, Preliminary Design, Testing 00009 - FS Final Design 70% 00023 - US Final Design 70% All except testing have about the same 00007 - FS Preliminary Design 64% influence 00021 - US Preliminary Design 64% 00026 - US Test 55% 00029 - Integration Testing 55% 00012 - Test FS Engine 55% © 2007 Hulett & Associates, LLC
  • 30. Risk Factor Tornado from All-In Simulation Driving Schedule Risk Factors 6 - Funding from Congress is problematic The main RISK, 4 - Fabricaton requires new materials however, is funding 3 - New designs not yet proven from Congress, which affected all activities. 7 - Schedule for testing is aggressive This is the main risk to mitigate, if possible 2 - Several alternative designs considered 5 - Lost know-how since last full spacecraft 1 - Requirements have not been decided 0.00 0.20 0.40 0.60 0.80 Correlation © 2007 Hulett & Associates, LLC
  • 31. Contribution of Each Risk to the Contingency (1) Explain the Contingency to the P-80 P-80 Date Take Risks Out: All Risks In 6-Jun-16 Days Saved % of Contingency Specific Risks Taken Out in Order No Funding Risk 19-Jan-16 139 39% No Tight Testing Schedule Risk 1-Dec-15 49 14% No New Design Risk 15-Oct-15 47 13% No Alternative Design Risk 5-Oct-15 10 3% No Lost Know How Risk 2-Oct-15 3 1% No Requirements Risk 30-Sep-15 2 1% Background Schedule Estimating Risks No Background Risk 12-Jun-15 110 31% Total Contingency 360 100% © 2007 Hulett & Associates, LLC
  • 32. Contribution of Each Risk to the Contingency (2) Distribution Analyzer Report No Background Risk - Finish Date No Design Alternative Risk - Finish Date No Testing Scheudle Risk - Finish Date No Requirements Risk - Finish Date No New Design Risk - Finish Date No Funding Risk - Finish Date No Lost Know How risk - Finish Date No New Materials Risk - Finish Date All Risks - Finish Date 100% 90% 01/Dec/15 29/Mar/16 12/Jun/15 02/Oct/15 05/Oct/15 30/Sep/15 15/Oct/15 27/Oct/15 19/Jan/16 80% 70% Cumulative Probability 60% 50% 40% 30% 20% 10% 0% 06/ Apr/ 15 15/ Jul/ 15 23/ Oct/ 15 31/ Jan/ 16 10/ May/ 16 18/ Aug/ 16 26/ Nov/ 16 06/ Mar/ 17 14/ Jun/ 17 © 2007 Hulett & Associates, LLC
  • 33. Summary (1) • The focus is on the risks, not their impact • Risks “explain” the need for a contingency • Management appreciates this focus on risks • Risk interviews are conducted at 20,000 foot level, where people typically think of risk • Interviews go faster, stick to the substance © 2007 Hulett & Associates, LLC
  • 34. Summary (2) • Risk Register exists, use it for quantitative analysis • Specific risks can be quantified and assigned to schedule activities – Quantification is probability and impact – A risk can affect several activities – An activity can be affected by several risks • Risk Factors can be combined with other more traditional approaches such as 3-point estimates for background risk or probabilistic branching © 2007 Hulett & Associates, LLC
  • 35. Using the Risk Register in Schedule Risk Analysis with Monte Carlo Simulation David T. Hulett, Hulett & Associates, LLC (USA) Waylon T. Whitehead, ConocoPhillips (USA) NASA PM Challenge Daytona Beach, FL February 26-27, 2008 © 2007 Hulett & Associates, LLC