Project Management Approach
 to Source Evaluation Boards
   Presented to: NASA Project Management Challenge

                February 26-27, 2008

           K. Lee Pagel and Vanessa Beene




                                                     1
Purpose and Objectives
• Discuss initiative at Johnson Space Center to align SEB
  processes to project management principles:
   – Sources of Feedback
   – Results of Feedback
   – The Project Cycle
   – Project Management Elements
      • Common Vocabulary
      • Teamwork
      • The Project Cycle
      • Requirements
      • Project Planning & Control
• Discuss other source selection initiatives currently underway at
  JSC                                                              2
Acknowledgement



•   The model for project management used in
    this presentation is taken from Visualizing
    Project Management, by Forsberg, Moog,
    and Cotterman.




                                                  3
Sources of Feedback
•   Receiving extensive feedback on Acquisition process:
     – Routine feedback sought from Industry at public events (Industry Day, Pre-proposal
       conferences)
     – Benchmarking activities with industry over the last year
     – Routine lessons learned gleaned from exiting SEB Chairs
     – Internal assessment from JSC Office of Analysis and Assessment (OAA) on Source
       Selection process and procurement processes
     – Included assessment by Booz Allen Hamilton, comparing JSC to other procuring
       organizations
     – Anonymous survey data from procurement employees
•   Still digesting this enormous volume of information. Some highlights:
     – Early requirements definition critical
     – Schedule management needs work
     – Review process needs examination
•   Knowledge capture initiative
     – Assign exiting COs after completion of source board to APAT for short period of time
          • Update templates, work instructions with latest experience
          • Assist in counseling incoming Chairs, COs on how-to info
     – Establishing lessons learned database
     – Considering ways to solicit lessons learned info real-time from Chairs and COs during
       SEB                                                                                     4
Results of Feedback – Some Themes

• SEB Chairs are schedule-focused, and process-
  frustrated
   – Process is unknown
   – Attempts to understand the process highlight the variations
   – Responsible for schedule, yet lacking control of stages of the
     process (like reviews)
• They expressed a strong desire for
   –   Consistency
   –   Templates of standard products
   –   Some semblance of control over external activities
   –   Understanding of the full cycle
                                                                 5
“What is to be done?”
• Caveat – A lot of excellent work has already been done
• Since most SEB Chairs come from Project
  Management:
   – Visualized the SEB Cycle as a project
   – Considered our team, Acquisition Planning Advisory Team,
     as managers of a group of project managers
   – Modeled our role as:
      •   Facilitators of the “Project” (SEB) Cycle
      •   Owners of certain scarce resources
      •   Owners of certain mandatory processes (FAR, Center Procedures)
      •   Provider of tools, training, logistics, and experience
• Repackaged procedures and initiatives
• Designing new activities where gaps are perceived
                                                                           6
Common Vocabulary

• Establish generic WBS for SEBs
  – Utilize in preparing generic master schedule template
  – Build a WBS dictionary over time, providing common
    definition for SEB-related terms
• Provide starting point for common documents
  – Templates for PSM, Comp Range, Source Selection
  – Do not provide “cold” to SEBs, provide with advice
  – Emphasize that a template is a starting point, not the end
• Build vocabulary through exposure
  – Common training, both basic SEB class and just-in-time
    training modules
                                                                 7
Teamwork

• In order to include reviewers (procurement and legal) in the
  “team,” need to consider imbedded reviewers
   – Dependent on reviewer resources
   – For JSC Acquisition Planning and Advisory Team (APAT), we are
     attempting to establish one person that is assigned to an SEB, but not
     imbedded

• Well defined responsibilities enhances the growth of mutual
  respect
   – Activity underway to define the roles and responsibilities of reviewers
     in the JSC procurement process
   – Carefully define the standards for SEB products: Findings, Reports,
     Presentations
       • Good initial product reduces review time, increases respect on both sides
         of the review process
       • Tailor training packages and templates to emphasize product standards
                                                                                     8
The Project Cycle

• Make Chairs aware of the SEB cycle – A
  Series of Gates
  – Accomplished through the master schedule
    template and WBS, which are major milestone-
    based
  – APAT counseling emphasizes both upcoming
    major milestone and how it fits into overall cycle
• JSC has established new joint HQ/JSC
  concurrent review board for major SEB
  documents (Senior Advisory Review)
                                                         9
Requirements
•   For most source selections, the three most important things to remember
    are requirements, Requirements, REQUIREMENTS!
•   Requirement definition needs to begin earlier and demand more attention
•   Historically, the majority of schedule slips in SEBs occur at the beginning
    of the process, during requirements definition
•   Greater understanding of your need leads to
     –   Better understanding of the contractor you want
     –   Better definition of discriminators, that leads to better Section M
     –   That leads to a focused, compact Section L and resulting proposals
     –   Providing faster evaluation, review and selection.
•   To increase focus on this at JSC, we are establishing Requirements
    Development Teams (RDT) to address this critical issue earlier.
•   Using new Roadmap from SOMD/ESMD to assist in managing early
    stages of requirements planning
•   Considering training of procurement personnel in Systems Engineering
    basics to allow us to “sling the lingo” with our customers in this area

                                                                               10
Multiplier Effect of Good Requirements
                        Process Evaluation
                        Results for that Requirement

                     Proposal Evaluation
                     Process for that Requirement

                 Proposal Writing Process
                 for that Requirement

             Section L Proposal
             Instruction for that Requirement

          Section M Selection
          Criteria for that Requirement


        Original Requirement
                                                       11
Project Planning and Control

• Use master schedule template as starting point for
  new SEBs
   – APAT assists in customizing schedule for individual boards
   – Point out common bottlenecks on schedule
• Common WBS provides resource planning for scarce
  resources (reviewers)
• Routine reviews with Chairs maintain focus on
  current schedule performance and awareness of
  upcoming bottlenecks
• This consistent approach to schedule will also yield
  detailed performance data for future analysis of the
  SEB process, permitting next wave of initiatives
                                                              12
Other SEB-related Initiatives at JSC

•   Blatantly “leveraging” from NASA best practices:
     – Utilizing Acquisition Evaluation Software (AES) developed at Goddard for
       evaluation tool (to replace FedSelect)
     – Utilizing Acquisition Planning Tool (APT) developed at Marshall to provide
       greater information earlier to industry planners
•   Increased staffing to APAT, emphasizing counseling and guidance role as a
    resource to SEB Chairs and COs
•   Established team web site to keep APAT activities consistent across SEBs
•   APAT calendar to assist reviewers in planning scarce resources
•   Strategic planning for logistics to SEB facilities
     – IT (printers, projectors, MS Project)
     – Upgrades to facilities (currently have 5 SEB buildings)
     – Applying consistent approach to logistics across all facilities
•   Integrate existing RBAM activities more closely to the project’s Risk
    management activities


                                                                                    13

More Related Content

PPTX
Amer.tahani
PDF
Gary.humphreys
PDF
Bryan.moser
PDF
Healy edward
PPTX
C armstrong tbyers
PPT
Gonzales.matthew
PDF
Louis.cioletti
PDF
Kelly.elliott
Amer.tahani
Gary.humphreys
Bryan.moser
Healy edward
C armstrong tbyers
Gonzales.matthew
Louis.cioletti
Kelly.elliott

What's hot (20)

PPTX
Val.lunz
PPTX
Sally godfreyheatherrarick
PDF
Richard.laws
PDF
Murphy.dar jean.jean
PDF
Eggert.joe
PDF
Vonnie simonsen
PPTX
Bauer.frank
PDF
Law.richard
PPTX
Borchardt.heidemarie
PDF
Jim.cassidy
PDF
Terry.conroy
PDF
Snow lee
PPTX
Solomon.paul
PPTX
Backup darren elliott
PDF
Carol.mullenax
PDF
Daniel.dvorak
PDF
Osterkamp jeff
PDF
Ingoldsby.k.lee.y
PPTX
Horn thomas
PDF
Romeo.mitchell
Val.lunz
Sally godfreyheatherrarick
Richard.laws
Murphy.dar jean.jean
Eggert.joe
Vonnie simonsen
Bauer.frank
Law.richard
Borchardt.heidemarie
Jim.cassidy
Terry.conroy
Snow lee
Solomon.paul
Backup darren elliott
Carol.mullenax
Daniel.dvorak
Osterkamp jeff
Ingoldsby.k.lee.y
Horn thomas
Romeo.mitchell
Ad

Viewers also liked (20)

PPT
Serrato.be be
PDF
Dillon.r.tinsley.c.rogers.e
PPTX
Grubbs teams and digital collaboration pmc2012
PPTX
Coonce.tom
PDF
John.olson
PDF
Barth simpkins
PDF
Stacy.cusack
PDF
Hulett
PPTX
Rippe.carpio
PDF
Diffoot fayful
PPTX
Wienkoop.glenn
PDF
Harrison.g.poole.k
PDF
John.emond
PPTX
C null 01-17-2011
PPTX
Battista barlowpmc conference 2012 rev. 2
PDF
Brockhurst.lane
PPTX
B ackroyd
PDF
Debbie.dusterwald
PDF
Michael.aucoin
PPT
Mc nally
Serrato.be be
Dillon.r.tinsley.c.rogers.e
Grubbs teams and digital collaboration pmc2012
Coonce.tom
John.olson
Barth simpkins
Stacy.cusack
Hulett
Rippe.carpio
Diffoot fayful
Wienkoop.glenn
Harrison.g.poole.k
John.emond
C null 01-17-2011
Battista barlowpmc conference 2012 rev. 2
Brockhurst.lane
B ackroyd
Debbie.dusterwald
Michael.aucoin
Mc nally
Ad

Similar to K.pagel.beene (20)

PPTX
4. PMP Training - Scope management
PDF
Intergrated baseline reviews as a tool in assurance
PDF
Flevy.com - Pricing a Consulting Project
PDF
Fleming.jon
PPTX
IIBA Basel Event March 2016 - Case Study Agile Waterfall.pptx
PPTX
System Project initiation and planning.pptx
PPTX
Projects2016_Franks_Top10ReasonsProjectsFail
PPTX
Project Initiation Document
PPTX
Stoyan Atanasov “How crucial is the BA role in an IT Project"
PPTX
04 projectintegrationmanagement
PPT
Training on ASAP Methodology_11.10.2020.ppt
PPT
B2 bluffers-guide-v1 2
PPTX
01 introductiontoframework
PPTX
Applying both of waterfall and iterative development
PPT
Training on ASAP Methodology.ppt
PPTX
Project Management Foundations Series Course 102 - Project Management Processes
PDF
Ortiz.james
PPT
1. introduction
PPTX
Going & seeing in construction
PPTX
Ipao great houseetc-programmatic analysis ll
4. PMP Training - Scope management
Intergrated baseline reviews as a tool in assurance
Flevy.com - Pricing a Consulting Project
Fleming.jon
IIBA Basel Event March 2016 - Case Study Agile Waterfall.pptx
System Project initiation and planning.pptx
Projects2016_Franks_Top10ReasonsProjectsFail
Project Initiation Document
Stoyan Atanasov “How crucial is the BA role in an IT Project"
04 projectintegrationmanagement
Training on ASAP Methodology_11.10.2020.ppt
B2 bluffers-guide-v1 2
01 introductiontoframework
Applying both of waterfall and iterative development
Training on ASAP Methodology.ppt
Project Management Foundations Series Course 102 - Project Management Processes
Ortiz.james
1. introduction
Going & seeing in construction
Ipao great houseetc-programmatic analysis ll

More from NASAPMC (20)

PDF
Bejmuk bo
PDF
Baniszewski john
PDF
Yew manson
PDF
Wood frank
PDF
Wood frank
PDF
Wessen randi (cd)
PDF
Vellinga joe
PDF
Trahan stuart
PDF
Stock gahm
PDF
Smalley sandra
PDF
Seftas krage
PDF
Sampietro marco
PDF
Rudolphi mike
PDF
Roberts karlene
PDF
Rackley mike
PDF
Paradis william
PDF
O'keefe william
PDF
Muller ralf
PDF
Mulenburg jerry
PDF
Mitskevich amanda
Bejmuk bo
Baniszewski john
Yew manson
Wood frank
Wood frank
Wessen randi (cd)
Vellinga joe
Trahan stuart
Stock gahm
Smalley sandra
Seftas krage
Sampietro marco
Rudolphi mike
Roberts karlene
Rackley mike
Paradis william
O'keefe william
Muller ralf
Mulenburg jerry
Mitskevich amanda

Recently uploaded (20)

PDF
Training And Development of Employee .pdf
PPTX
Belch_12e_PPT_Ch18_Accessible_university.pptx
PPTX
CkgxkgxydkydyldylydlydyldlyddolydyoyyU2.pptx
PDF
Types of control:Qualitative vs Quantitative
PDF
SIMNET Inc – 2023’s Most Trusted IT Services & Solution Provider
PDF
A Brief Introduction About Julia Allison
PPTX
The Marketing Journey - Tracey Phillips - Marketing Matters 7-2025.pptx
PDF
Reconciliation AND MEMORANDUM RECONCILATION
PPTX
5 Stages of group development guide.pptx
PDF
20250805_A. Stotz All Weather Strategy - Performance review July 2025.pdf
PPTX
HR Introduction Slide (1).pptx on hr intro
PPTX
Amazon (Business Studies) management studies
DOCX
Business Management - unit 1 and 2
PDF
Business model innovation report 2022.pdf
PDF
MSPs in 10 Words - Created by US MSP Network
PDF
IFRS Notes in your pocket for study all the time
PPTX
Dragon_Fruit_Cultivation_in Nepal ppt.pptx
PDF
kom-180-proposal-for-a-directive-amending-directive-2014-45-eu-and-directive-...
DOCX
Euro SEO Services 1st 3 General Updates.docx
PPT
Chapter four Project-Preparation material
Training And Development of Employee .pdf
Belch_12e_PPT_Ch18_Accessible_university.pptx
CkgxkgxydkydyldylydlydyldlyddolydyoyyU2.pptx
Types of control:Qualitative vs Quantitative
SIMNET Inc – 2023’s Most Trusted IT Services & Solution Provider
A Brief Introduction About Julia Allison
The Marketing Journey - Tracey Phillips - Marketing Matters 7-2025.pptx
Reconciliation AND MEMORANDUM RECONCILATION
5 Stages of group development guide.pptx
20250805_A. Stotz All Weather Strategy - Performance review July 2025.pdf
HR Introduction Slide (1).pptx on hr intro
Amazon (Business Studies) management studies
Business Management - unit 1 and 2
Business model innovation report 2022.pdf
MSPs in 10 Words - Created by US MSP Network
IFRS Notes in your pocket for study all the time
Dragon_Fruit_Cultivation_in Nepal ppt.pptx
kom-180-proposal-for-a-directive-amending-directive-2014-45-eu-and-directive-...
Euro SEO Services 1st 3 General Updates.docx
Chapter four Project-Preparation material

K.pagel.beene

  • 1. Project Management Approach to Source Evaluation Boards Presented to: NASA Project Management Challenge February 26-27, 2008 K. Lee Pagel and Vanessa Beene 1
  • 2. Purpose and Objectives • Discuss initiative at Johnson Space Center to align SEB processes to project management principles: – Sources of Feedback – Results of Feedback – The Project Cycle – Project Management Elements • Common Vocabulary • Teamwork • The Project Cycle • Requirements • Project Planning & Control • Discuss other source selection initiatives currently underway at JSC 2
  • 3. Acknowledgement • The model for project management used in this presentation is taken from Visualizing Project Management, by Forsberg, Moog, and Cotterman. 3
  • 4. Sources of Feedback • Receiving extensive feedback on Acquisition process: – Routine feedback sought from Industry at public events (Industry Day, Pre-proposal conferences) – Benchmarking activities with industry over the last year – Routine lessons learned gleaned from exiting SEB Chairs – Internal assessment from JSC Office of Analysis and Assessment (OAA) on Source Selection process and procurement processes – Included assessment by Booz Allen Hamilton, comparing JSC to other procuring organizations – Anonymous survey data from procurement employees • Still digesting this enormous volume of information. Some highlights: – Early requirements definition critical – Schedule management needs work – Review process needs examination • Knowledge capture initiative – Assign exiting COs after completion of source board to APAT for short period of time • Update templates, work instructions with latest experience • Assist in counseling incoming Chairs, COs on how-to info – Establishing lessons learned database – Considering ways to solicit lessons learned info real-time from Chairs and COs during SEB 4
  • 5. Results of Feedback – Some Themes • SEB Chairs are schedule-focused, and process- frustrated – Process is unknown – Attempts to understand the process highlight the variations – Responsible for schedule, yet lacking control of stages of the process (like reviews) • They expressed a strong desire for – Consistency – Templates of standard products – Some semblance of control over external activities – Understanding of the full cycle 5
  • 6. “What is to be done?” • Caveat – A lot of excellent work has already been done • Since most SEB Chairs come from Project Management: – Visualized the SEB Cycle as a project – Considered our team, Acquisition Planning Advisory Team, as managers of a group of project managers – Modeled our role as: • Facilitators of the “Project” (SEB) Cycle • Owners of certain scarce resources • Owners of certain mandatory processes (FAR, Center Procedures) • Provider of tools, training, logistics, and experience • Repackaged procedures and initiatives • Designing new activities where gaps are perceived 6
  • 7. Common Vocabulary • Establish generic WBS for SEBs – Utilize in preparing generic master schedule template – Build a WBS dictionary over time, providing common definition for SEB-related terms • Provide starting point for common documents – Templates for PSM, Comp Range, Source Selection – Do not provide “cold” to SEBs, provide with advice – Emphasize that a template is a starting point, not the end • Build vocabulary through exposure – Common training, both basic SEB class and just-in-time training modules 7
  • 8. Teamwork • In order to include reviewers (procurement and legal) in the “team,” need to consider imbedded reviewers – Dependent on reviewer resources – For JSC Acquisition Planning and Advisory Team (APAT), we are attempting to establish one person that is assigned to an SEB, but not imbedded • Well defined responsibilities enhances the growth of mutual respect – Activity underway to define the roles and responsibilities of reviewers in the JSC procurement process – Carefully define the standards for SEB products: Findings, Reports, Presentations • Good initial product reduces review time, increases respect on both sides of the review process • Tailor training packages and templates to emphasize product standards 8
  • 9. The Project Cycle • Make Chairs aware of the SEB cycle – A Series of Gates – Accomplished through the master schedule template and WBS, which are major milestone- based – APAT counseling emphasizes both upcoming major milestone and how it fits into overall cycle • JSC has established new joint HQ/JSC concurrent review board for major SEB documents (Senior Advisory Review) 9
  • 10. Requirements • For most source selections, the three most important things to remember are requirements, Requirements, REQUIREMENTS! • Requirement definition needs to begin earlier and demand more attention • Historically, the majority of schedule slips in SEBs occur at the beginning of the process, during requirements definition • Greater understanding of your need leads to – Better understanding of the contractor you want – Better definition of discriminators, that leads to better Section M – That leads to a focused, compact Section L and resulting proposals – Providing faster evaluation, review and selection. • To increase focus on this at JSC, we are establishing Requirements Development Teams (RDT) to address this critical issue earlier. • Using new Roadmap from SOMD/ESMD to assist in managing early stages of requirements planning • Considering training of procurement personnel in Systems Engineering basics to allow us to “sling the lingo” with our customers in this area 10
  • 11. Multiplier Effect of Good Requirements Process Evaluation Results for that Requirement Proposal Evaluation Process for that Requirement Proposal Writing Process for that Requirement Section L Proposal Instruction for that Requirement Section M Selection Criteria for that Requirement Original Requirement 11
  • 12. Project Planning and Control • Use master schedule template as starting point for new SEBs – APAT assists in customizing schedule for individual boards – Point out common bottlenecks on schedule • Common WBS provides resource planning for scarce resources (reviewers) • Routine reviews with Chairs maintain focus on current schedule performance and awareness of upcoming bottlenecks • This consistent approach to schedule will also yield detailed performance data for future analysis of the SEB process, permitting next wave of initiatives 12
  • 13. Other SEB-related Initiatives at JSC • Blatantly “leveraging” from NASA best practices: – Utilizing Acquisition Evaluation Software (AES) developed at Goddard for evaluation tool (to replace FedSelect) – Utilizing Acquisition Planning Tool (APT) developed at Marshall to provide greater information earlier to industry planners • Increased staffing to APAT, emphasizing counseling and guidance role as a resource to SEB Chairs and COs • Established team web site to keep APAT activities consistent across SEBs • APAT calendar to assist reviewers in planning scarce resources • Strategic planning for logistics to SEB facilities – IT (printers, projectors, MS Project) – Upgrades to facilities (currently have 5 SEB buildings) – Applying consistent approach to logistics across all facilities • Integrate existing RBAM activities more closely to the project’s Risk management activities 13