Developing Model Procurement
  Documents for Progressive
     Design-Build Projects


              March 22, 2103
     John Awezec, P.E., LEED, AP – HDR, Inc.
    John Doller, P.E. – Carollo Engineers, Inc.
    Peter Hughes – Executive Director WDBC
Model Procurement Documents for
    Progressive Design-Build
Developing Model Procurement Documents for Progressive
                              Design-Build Projects

                           Overview
• What is progressive design-build (PDB)? How
  does it work?
• Benefits of PDB
• Key considerations in a PDB procurement
  – Understanding the model procurement documents
     • RFQ
     • RFP
     • Progressive Design Build Agreement

• Implementing the PDB procurement
Project Delivery Options
   Traditional
    Delivery                             Alternative Delivery
                       Construction        “Progressive”    Lump-Sum      Design-Build-
Design-Bid-Build    Management at Risk      Design-Build   Design-Build     Operate/
     (DBB)               (CMAR)                (GMP)           (LS)       Finance, etc.
Progressive Design-Build
         In a progressive design-build
         procurement, the design-builder
         is selected primarily based on
         qualifications before substantial
         design is completed.
         Together, the owner and the
         design-build team advance the
         design, incorporating the details
         desired by the owner and
         providing the owner with cost
         input regarding options the
         owner is considering. This open-
         book approach enables the
         owner to make well-informed
         decisions on the overall quality
         of the project.
Progressive Design-Build
Construction estimating can                          Owner               “Progressive” estimates keep
start very early in design,                                              owners informed and support-
allowing comparison of specific                                          informed scope adjustment
technical solutions                                                      decisions
             PM/OA                               Design/Builder



              Design
             Definition
                                  Design Development and Construction

                                                             100%
                                                                          Guaranteed maximum price
  First fully detailed estimate    Owners can use third-parties to        established at the right time:
  can be used to establish a
  scope baseline. Estimating       verify cost . . .                      Risk and contingency reduced,
  process is “open book”           . . . and go to the hard-bid market    schedule needs met
                                   if needed (the “off-ramp”)
Progressive Design-Build
                           Owner

PM/OA                   Design/Builder



 Design
Definition
             Design Development and Construction

                                100%
             Phase 1                     Phase 2

                         GMP
Progressive Design-Build
                                   Owner
• Investment in projects, not procurements
• Offers owners maximum flexibility/opportunity to collaborate on
   PM/OA                     Design/Builder
  permitting/ design
• Maximizes overall schedule
• Owners have an “off-ramp” in case of permitting issues or if GMP
    Design
                   Design Development and Construction
  can’t be negotiated
   Definition
• Very successful evolving model
                                       100%
Key Considerations in PDB
               Procurement
•   Existing legal authority
•   Basis for selection
•   Required contents for submission
•   Evaluation criteria and scoring methodology
•   PDB Contract
    – Agreement
    – General Conditions
Legal Authority
• Verify State and local procurement laws
  – Is PDB allowed?
  – Requirements for procurement
     • One step vs. Two-step process
     • Qualifications only vs. “best value” (quals + cost)
     • Self performance of work
• Water Design Build Council survey (July 2012)
     • Survey of relevant state legislation for select states
     • Available on WDBC website
Legal Authority
               •Does not expressly permit PDB
               •Allows evaluation of RFP based
               on criteria deemed appropriate
               for the project
               •Does not prohibit two-step
               process
               •Best value evaluation
Virginia
               •Requires price consideration in
               evaluation, but need not be the
               sole determining factor
Basis for Selection
Qualifications-Based Selection                  Best-Value Selection

• Employ evaluation criteria that are    • Allows price or costs to be
  traditionally used for any              considered with qualifications
  qualifications-based selection         • Total cost of construction is not a
• Owner able conduct process              factor
  efficiently                            • Typical cost considerations include:
• Reduces total time for                       • Fixed fees for
  procurement                                    preconstruction services
• Reduces cost of procurement                 • Raw labor hour rate sheet
• Reduces complexity                          • Design-builder fee or markup
                                                percentage of allowable
• Potentially allows for a larger pool          project costs
 of qualified firms to participate
                                              • Fixed fee for General
                                                Condition costs
Basis for Selection
Qualifications-Based Selection                         Best-Value Selection
               Basic Intent of PDB is that selection of the
• Employ evaluation criteria that are          • Allows price or costs to be
              design-builder is heavily based on qualifications
  traditionally used for any                    considered with qualifications
  qualifications-based selection
                                               • Total cost of construction is not a
          • Fees and rates account for relatively small percentage of
• Owner able conduct process                    factor
            overall project costs
  efficiently
                                               • Typical cost considerations include:
• Reduces• total time for costs should be kept to minimum for
            Weighting of                             • Fixed fees
  procurement                                          preconstruction services
        • Some state procurement laws dictate minimum
• Reduces cost of procurement
          percentages                          • Raw labor hour rate sheet
• Reduces• complexity                         • Design-builder fee
            Model procurement documents provided suggestions or markup
                                                percentage of allowable
• Potentially allows for a larger pool
            on weighting of costs               project costs
 of qualified firms to participate
                                              • Fixed fee for General
                                                Condition costs
Basis for Selection
                 Various Procurement Processes
 • Two categories for Procurement
            Single-Step                                Two - Step


 Request for          Request for      Request for             Request for
Qualifications         Proposals      Qualifications          Qualifications

                                       Request for             Request for
                     “Best Value”       Proposals               Proposals
Qualifications       Qualifications
    only                   +
                                      Qualifications            “Best Value”
                        Costs                                       Qualifications +
                                          only                           Costs
Basis for Selection
                 Various Procurement Processes
 • Single-Step – Qualifications Selection
            Single-Step    • If schedule is a critical driver
                                                        Two - Step


 Request for                • for
                      Request If maximum owner/design-builder for
                                            Request for    Request
Qualifications         Proposals
                             collaboration Qualifications
                                           is a priority  Qualifications

                                                Request for     Request for
                             • If state/local law allow qualifications- only
                      “Best Value”               Proposals       Proposals
Qualifications       Qualifications
                           + selection
 WDBC No.
    only
W-1200-2013                                  Qualifications      “Best Value”
                        Costs                                        Qualifications +
                                                 only                     Costs
Basis for Selection
                 Various Procurement Processes
 • Single-Step: Best Value
            Single-Step             • If schedule is a critical driver
                                                     Two - Step


 Request for          Request for   • If maximum owner/design-builder
                                           Request for     Request for
Qualifications         Proposals          Qualifications  Qualifications
                                     collaboration is a priority
                                           Request for        Request for
                                    • If Owner prefers
                                            Proposals    (or ifProposals
                                                                state/local
Qualifications
    only               WDBC No.
                                     law requires) inclusion of cost as a
                                         Qualifications    “Best Value”
                      W-1300-2013    selection factor
                                             only           Qualifications +
                                                                 Costs
Basis for Selection
                  Various Procurement Processes
  • Two –Step: Request for Qualifications
• If schedule can accommodate
             Single-Step                              Two - Step
 the time required for two
 procurement steps
   Request for         Request for      Request for            Request for
 Qualifications        Proposals       Qualifications         Qualifications
• Potentially greater degree of         Request for              Request for
 project data provided with RFP
                   “Best Value”          Proposals                Proposals
 Qualifications       Qualifications
     only                   +                        WDBC No.
                                       Qualifications         “Best Value”
• Short list firms   to receive RFP
                          Costs
                                           only
                                                   W-1400-2013 Qualifications +
                                                                    Costs
Basis for Selection
                  Various Procurement Processes
  • Two-Step: Request for Proposals
• Includes Single-Step
           Project Approach                          Two - Step


• Potentially greater degree of
   Request for     Request for         Request for            Request for
  Qualifications    Proposals
 project data provided with RFP       Qualifications         Qualifications

                                       Request for              Request for
• Qualifications only or best value
                   “Best Value”         Proposals                Proposals
 Qualifications     Qualifications
     only                 +
                                      Qualifications
                                       Quals                 “Best Value”
                                                                      Best
                       Costs                        WDBC No.  Qualifications +
                                          only
                                       only                          value
                                                                   Costs
                                                  W-1500-2013
Required Contents for Submission
• Model Documents – RFQ & RFP
  – Comprehensive
  – Based on historical submission requirements from
    previous PDB deliveries
  – Provide foundation for development RFQ & RFP
    that best suits an Owner’s specific needs
Required Contents for Submission
 • Statement of Qualifications - Contents
                                           •Section 1. Background
                                           • Section 2. Project Overview

                                           • Section 3. Progressive Design-Build Services

                                           • Section 4. Procurement Process

                                           • Section 5. SOQ Submission Requirements

                                           • Section 6. SOQ Evaluation and Selection

                                           • Section 7. Conditions for Respondents
WDBC Documents W-1200-2013 & W-1400-2013
Required Contents for Submission
 • Statement of Qualifications - Contents
                                                           ATTACHMENTS
                                           • A: Definition of Terms

                                           • B: Scope of Design-Builders Services

                                           • C: Draft PDB Contract

                                           • D: Project Background Documents

                                           • E: Project Technical Requirements

                                           • F: Submission Forms
WDBC Documents W-1200-2013 & W-1400-2013
Required Contents for Submission
 • Statement of Qualifications - Contents
                                                 •Section 1. Background
                                               • Section 2. Project Overview
                                      DIFFERENCES
                                                 • Section 3. Progressive Design-Build Services
                                • Procurement Schedule
                                                 • Section 4. Procurement Process
                   • Single-Step - includes Project Approach and PDB
                                                 • Section
                                     Contract Markup 5. SOQ Submission Requirements
                            • Evaluation criteria• / weighting Evaluation and Selection
                                                   Section 6. SOQ
                                                 • Section 7. Conditions for Respondents
                                       • Selection
WDBC Documents W-1200-2013 & W-1400-2013
Required Contents for Submission
 • Statement of Qualifications - Contents
                                           •Section 1. Background
                                           • Section 2. Project Overview

                                           • Section 3. Progressive Design-Build Services

                                           • Section 4. Procurement Process

                                           • Section 5. SOQ Submission Requirements

                                           • Section 6. SOQ Evaluation and Selection

                                           • Section 7. Conditions for Respondents
WDBC Documents W-1200-2013 & W-1400-2013
Required Contents for Submission
 • Statement of Qualifications – Section 5

                                           • Transmittal Letter
                                           • Part 1: Executive Summary
                                           • Part 2: Design-Builder Profile
                                           • Part 3: Project Team
                                           • Part 4: Experience

WDBC Documents W-1200-2013 & W-1400-2013
Required Contents for Submission
• Transmittal Letter
                         PURPOSE
              Identifies the design-builder and
                provides contact information

•   Page limited
•   Contact information for Respondent Contact
•   Signatory for contracts
•   Must make reference to “Forms of Compliance”
Required Contents for Submission
• Part 1: Executive Summary
                        PURPOSE
       Provides first glance overview of the SOQ contents,
                  highlighting important features

• Page limited
• Key elements of the SOQ
• No additional information not found in SOQ
Required Contents for Submission
• Part 2: Design-Builder Profile
                         PURPOSE
                Provides general, legal and financial
             information concerning the design-builder

•   General                     • Performance bonds
•   Legal Structure             • Insurance
                                • Material adverse changes in
•   Project office location       financial position
•   Financial condition         • Legal proceedings
Required Contents for Submission
• Part 2: Design-Builder Profile
                       PURPOSE
              Provides general, legal and financial
           information concerning the design-builder

• Completion of contracts
• Violation of laws
• Debarred from bidding
Required Contents for Submission
• Part 3: Project Team
                              PURPOSE
            Describes key personnel and additional firms
         * ORGANIZATION * ROLES & RESPONSIBILITIES * RESUMES

Design-builder/other firms
 * Roles and responsibilities of all firms
 * Phase 1 and Phase 2 organizational charts
Required Contents for Submission
• Part 3: Project Team
                                PURPOSE
             Describes key personnel and additional firms
         * ORGANIZATION * ROLES & RESPONSIBILITIES * RESUMES

Key Personnel
 * Roles and responsibilities
 * Level of commitment
 * Resumes
Required Contents for Submission
• Part 4: Experience
                         PURPOSE
        Provides detailed information on relevant design,
          construction, design-build projects and safety

• Reference projects – number specified by owner
• Three categories:
  – Design
  – Construction
  – Design-build
Required Contents for Submission
• Part 4: Experience
                         PURPOSE
        Provides detailed information on relevant design,
          construction, design-build projects and safety

• Information provided for each project:
   – Name of owner
   – Year started and completed
   – Owner reference and contact information
Required Contents for Submission
• Part 4: Experience
                          PURPOSE
        Provides detailed information on relevant design,
          construction, design-build projects and safety

• Information provided for each project:
   – Firms and key personnel that participated in the project
   – Description of the project
• One–page summary table to cross reference the
  projects with project team (firms and key personnel)
Required Contents for Submission
 • Request for Proposals

                                           • Two-Step RFP discussed (W-1500-2013)
                                           • Used for both
                                               - Qualifications based selection
                                               - Best Value selection
                                           • RFP for Single-Step also includes
                                             requirements outlined in Single-Step
                                             RFQ
WDBC Documents W-1300-2013 & W-1500-2013
Required Contents for Submission
 • Request for Proposals - Contents
                                           •Section 1. Background
                                           • Section 2. Project Overview

                                           • Section 3. Progressive Design-Build Services

                                           • Section 4. Procurement Process

                                           • Section 5. Proposal Submission Requirements

                                           • Section 6. Proposal Evaluation and Selection

                                           • Section 7. Conditions for Respondents


WDBC Documents W-1300-2013 & W-1500-2013
Required Contents for Submission
 • Request for Proposals - Contents
                                                              ATTACHMENTS
                                              • A: Definition of Terms
                                              • B: Scope of Design-Builders Services
                                              • C: Draft PDB Contract
                                              • D: Project Background Documents
                                              • E: Project Technical Requirements
Not used if “Qualifications Only” selection   • F: Fee and Rate Proposal Form

WDBC Documents W-1300-2013 & W-1500-2013
Required Contents for Submission
 • Request for Proposals - Contents
                                           •Section 1. Background
                                           • Section 2. Project Overview

                                           • Section 3. Progressive Design-Build Services

                                           • Section 4. Procurement Process

                                           • Section 5. Proposal Submission Requirements

                                           • Section 6. Proposal Evaluation and Selection

                                           • Section 7. Conditions for Respondents


WDBC Documents W-1300-2013 & W-1500-2013
Required Contents for Submission
 • Request for Proposals - Contents
                                              • Transmittal Letter
                                              • Part 1: Executive Summary
                                              • Part 2: Project Approach
                                              • Part 3: Draft PDB Contract Markup

Not used if “Qualifications Only” selection   • Part 4: Fee and Rate Proposal

     Not used in Single-Step Process          • Part 5: Updated Qualifications




WDBC Documents W-1300-2013 & W-1500-2013
Required Contents for Submission
• Transmittal Letter
• Part 1: Executive Summary


             Same as the RFQ
Required Contents for Submission
• Part 2: Project Approach
  – Can include discussion on:
     • How collaborative relationship with the Owner would
       be established
     • How the design and construction processes will
       interface
     • Critical work components for success
     • The process for GMP development
Required Contents for Submission
• Part 2: Project Approach
  – Also can include discussion approach to:
     •   Communications with owner and stakeholders
     •   Quality management
     •   Risk management
     •   Adherence to the GMP and schedule
Required Contents for Submission
• Part 3: Draft PDB Contract Markup
                           PURPOSE
      Provides a description and discussion of the rationale
         for proposed revisions to the draft PDB contract

• Allows proposers to revisions to the contract that would more
  efficiently allocate:
   – Risk
            Owner is not obligated to accept any of
                     the suggested revisions
   – Improve parties understanding of risk allocation
   – Improve clarity
Required Contents for Submission
• Part 4: Fee and Rate Proposal
                              PURPOSE
    Provides certain fees and rates for design-builder services during
                           Phase 1 and Phase 2

     • Fixed fee or hourly rates for:
          – Design services
          – Engineering services during construction
          – Pre-construction services
     • Design-builder fee or markup as a percentage of project
       costs
     • Fixed fee or hourly rates for components of the GCs.
Required Contents for Submission
• Part 5: Updated Qualifications
                              PURPOSE
     Confirm prior SOQ and describes any changes to projects team or
              key personnel and explains reason for change

• Any proposed changes to the SOQ
• Resumes of additional personnel proposed
• Proposed changes subject to acceptance of owner
Evaluation Criteria and Scoring
            Methodology
         EVALUATION CRITERIA
Should be designed to select a design-builder
  with the highest probability of achieving an
          Owner’s project objectives

               • Fair
               • Clear
               • Transparent
Evaluation Criteria and Scoring
             Methodology
• Minimum qualification requirements
  – SOQ and Proposal for Single-Step
  – Pass/Fail
     * Performance bond              * Net worth
     * Material adverse conditions   * Licensing and registration
     * Design experience             * Construction experience
     * Design-build experience       * Safety record
Evaluation Criteria and Scoring
                   Methodology
                                              Experience and capabilities                                Fee




                                 Best Value
              Document
                                                                            Organization,



                         Quals
Procurement                                   Design-          Key                           Project      &
                                                                            Management
 Approach                                     Builder       Personnel        and Safety     Approach     Rate
                                                                                                       Proposal
Single-Step
    RFQ       1200       X                        l              l               l             l
    RFP       1300                X               l              l               l             l          l
 Two - Step
   RFQ        1400       X                        l              l               l
    RFP       1500               X                l              l               l             l          l
    RFP       1500       X                        l              l               l             l
Evaluation Criteria and Scoring
                   Methodology
                                              Experience and capabilities                                Fee




                                 Best Value
              Document
                                                                            Organization,



                         Quals
Procurement                                   Design-          Key                           Project      &
                                                                            Management
 Approach                                     Builder       Personnel        and Safety     Approach     Rate
                                                                                                       Proposal
Single-Step
    RFQ       1200       X                      40%            30%             15%           15%
    RFP       1300                X             30%            20%             15%           15%        20%
 Two - Step
   RFQ        1400       X                      40%            40%             20%
    RFP       1500               X              30%            20%             15%           15%        20%
    RFP       1500       X                      40%            30%             15%           15%
Progressive Design Build Contract
• Agreement
• Attachments
  –   A: Scope of Work
  –   B: Compensation
  –   C: Schedule
  –   D: General Conditions
  –   E: Indemnity, Insurance & Bonding
  –   F: Owner’s Project Criteria
  –   G: Owner’s Permit List
Progressive Design Build Contract
• Agreement
Progressive Design Build Contract
• Attachment A – Scope of Work
Progressive Design Build Contract
• Attachment B - Compensation
Progressive Design Build Contract
• Attachment D – General Conditions
Progressive Design Build Contract
• Attachment E – Indemnity, Insurance &
  Bonding
Progressive Design Build Contract
• Attachment F – Owner’s Project Criteria
Progressive Design Build Contract
• Attachment G – Owner’s Permit List
Implementing the PDB Procurement




Plan Project          RFQ              RFP          Permits/Design Input       Verify DB Performance     (Verify) O&M
Define Performance Criteria        Tech Support          Verify GMP                    Inspection

                     Quals        Propose Concept    Design/Develop GMP         Construction, Startup      Warranty
                                                                               Complete Design


RFQ – defines qualifications            Select from qualified firms
criteria; short lists qualified         - selection based on qualifications;        Agree on GMP - based on
firms                                   may include “rates” or “conceptual/         collaborative scope and design;
                                        target price” in evaluation                 pricing may be verified by third
                                                                                    party
                                                                                  LC
Model Procurement Documents for
      Progressive Design-Build




www.waterdesignbuild.org
Developing Procurement Documents for Progressive Design-Build Projects
Developing Procurement Documents for Progressive Design-Build Projects
Developing Procurement Documents for Progressive Design-Build Projects
Developing Procurement Documents for Progressive Design-Build Projects
Developing Procurement Documents for Progressive Design-Build Projects
Developing Procurement Documents for Progressive Design-Build Projects
Developing Procurement Documents for Progressive Design-Build Projects
Developing Procurement Documents for Progressive Design-Build Projects

More Related Content

PDF
Design-Build Procurement Approaches
PDF
Design build risks and rewards for public owner
PDF
BIM LOD (Level of Definition)
PDF
Information Management and Model Checking
DOCX
Pp 1-report-complete
PPTX
BIM for Project Managers
Design-Build Procurement Approaches
Design build risks and rewards for public owner
BIM LOD (Level of Definition)
Information Management and Model Checking
Pp 1-report-complete
BIM for Project Managers

What's hot (20)

PPTX
BIM Execution Plan
PDF
PDF
Roads, Infrastructure and BIM
PDF
How to Create a Rock Star BIM Execution Plan (BEP) and MPDT* (Responsibility ...
PPTX
Construction Documents
PDF
The Bim Process Explained
PDF
La gestion des risques reliés aux modes de réalisation des projets miniers et...
PPTX
BIM (Building Information Modeling) for digital construction
PPTX
Bim overview
PDF
NEC Contracts - Programmes under ECC and PSC webinar
PPTX
BIM workflow for construction
PDF
NEC Framework Contract webinar
PDF
Demystifying the APMP Foundation Certification
PPTX
Effective Engineering Management in EPC Industry
PPTX
PMO 2.0 - The Strategic Focused PMO
PPTX
Building information modeling BIM
PDF
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
PPTX
PMP Exam Flashcards common definitions 7th edition original v2.0
PPTX
APMP Foundation: Proposal Outline Development
PDF
Bim codes (new egyptian code)
BIM Execution Plan
Roads, Infrastructure and BIM
How to Create a Rock Star BIM Execution Plan (BEP) and MPDT* (Responsibility ...
Construction Documents
The Bim Process Explained
La gestion des risques reliés aux modes de réalisation des projets miniers et...
BIM (Building Information Modeling) for digital construction
Bim overview
NEC Contracts - Programmes under ECC and PSC webinar
BIM workflow for construction
NEC Framework Contract webinar
Demystifying the APMP Foundation Certification
Effective Engineering Management in EPC Industry
PMO 2.0 - The Strategic Focused PMO
Building information modeling BIM
Ss 5 training fidic Dr. Moustafa Ismail 2017 _ lec 5
PMP Exam Flashcards common definitions 7th edition original v2.0
APMP Foundation: Proposal Outline Development
Bim codes (new egyptian code)
Ad

Similar to Developing Procurement Documents for Progressive Design-Build Projects (20)

PDF
Project design and management
PPTX
Team Structures and Project Performance in the Design-Build Marketplace
PDF
Flevy.com - Pricing a Consulting Project
PPTX
Ohio Construction Reform Finalized- The New Reality
PDF
20080704 innovative approach in contracts and tender procurement management
PDF
Au2010 Autodesk Deliberations11.28.10
PPTX
Lecture 1.pptx
PPTX
Андрій Просов “Fixed Price Agile Projects: Lessons Learned” Kyiv Project Man...
PDF
Brokerage Simplified
PDF
Exploration of risks and risk management in construction project delivery
KEY
Rangkuman part 2
PPTX
ACE Team 2 - WK6 - IPD Presentation
PDF
57086 10 business_case
PDF
RFPs and RFQs: Selecting the Design-Builder
PPTX
Iwsm2014 solution based estimating (eltjo poort)
PPS
Bridging Gt Apr09
PPTX
May AACE Presentation, FINAL
DOC
Estimation
PPTX
1.4 ContractAcceptance.pptx
DOC
5yr_Tendering & Estimation Engineer
Project design and management
Team Structures and Project Performance in the Design-Build Marketplace
Flevy.com - Pricing a Consulting Project
Ohio Construction Reform Finalized- The New Reality
20080704 innovative approach in contracts and tender procurement management
Au2010 Autodesk Deliberations11.28.10
Lecture 1.pptx
Андрій Просов “Fixed Price Agile Projects: Lessons Learned” Kyiv Project Man...
Brokerage Simplified
Exploration of risks and risk management in construction project delivery
Rangkuman part 2
ACE Team 2 - WK6 - IPD Presentation
57086 10 business_case
RFPs and RFQs: Selecting the Design-Builder
Iwsm2014 solution based estimating (eltjo poort)
Bridging Gt Apr09
May AACE Presentation, FINAL
Estimation
1.4 ContractAcceptance.pptx
5yr_Tendering & Estimation Engineer
Ad

Recently uploaded (20)

PDF
Solara Labs: Empowering Health through Innovative Nutraceutical Solutions
PDF
Roadmap Map-digital Banking feature MB,IB,AB
DOCX
unit 2 cost accounting- Tender and Quotation & Reconciliation Statement
PDF
Daniels 2024 Inclusive, Sustainable Development
PDF
Unit 1 Cost Accounting - Cost sheet
PDF
NISM Series V-A MFD Workbook v December 2024.khhhjtgvwevoypdnew one must use ...
PPTX
svnfcksanfskjcsnvvjknsnvsdscnsncxasxa saccacxsax
PDF
How to Get Business Funding for Small Business Fast
PDF
Laughter Yoga Basic Learning Workshop Manual
PPTX
Dragon_Fruit_Cultivation_in Nepal ppt.pptx
PDF
COST SHEET- Tender and Quotation unit 2.pdf
PDF
pdfcoffee.com-opt-b1plus-sb-answers.pdfvi
PPT
340036916-American-Literature-Literary-Period-Overview.ppt
PPTX
Board-Reporting-Package-by-Umbrex-5-23-23.pptx
PPT
Lecture 3344;;,,(,(((((((((((((((((((((((
PPTX
job Avenue by vinith.pptxvnbvnvnvbnvbnbmnbmbh
PDF
Elevate Cleaning Efficiency Using Tallfly Hair Remover Roller Factory Expertise
PPTX
Probability Distribution, binomial distribution, poisson distribution
PPTX
2025 Product Deck V1.0.pptxCATALOGTCLCIA
PDF
Chapter 5_Foreign Exchange Market in .pdf
Solara Labs: Empowering Health through Innovative Nutraceutical Solutions
Roadmap Map-digital Banking feature MB,IB,AB
unit 2 cost accounting- Tender and Quotation & Reconciliation Statement
Daniels 2024 Inclusive, Sustainable Development
Unit 1 Cost Accounting - Cost sheet
NISM Series V-A MFD Workbook v December 2024.khhhjtgvwevoypdnew one must use ...
svnfcksanfskjcsnvvjknsnvsdscnsncxasxa saccacxsax
How to Get Business Funding for Small Business Fast
Laughter Yoga Basic Learning Workshop Manual
Dragon_Fruit_Cultivation_in Nepal ppt.pptx
COST SHEET- Tender and Quotation unit 2.pdf
pdfcoffee.com-opt-b1plus-sb-answers.pdfvi
340036916-American-Literature-Literary-Period-Overview.ppt
Board-Reporting-Package-by-Umbrex-5-23-23.pptx
Lecture 3344;;,,(,(((((((((((((((((((((((
job Avenue by vinith.pptxvnbvnvnvbnvbnbmnbmbh
Elevate Cleaning Efficiency Using Tallfly Hair Remover Roller Factory Expertise
Probability Distribution, binomial distribution, poisson distribution
2025 Product Deck V1.0.pptxCATALOGTCLCIA
Chapter 5_Foreign Exchange Market in .pdf

Developing Procurement Documents for Progressive Design-Build Projects

  • 1. Developing Model Procurement Documents for Progressive Design-Build Projects March 22, 2103 John Awezec, P.E., LEED, AP – HDR, Inc. John Doller, P.E. – Carollo Engineers, Inc. Peter Hughes – Executive Director WDBC
  • 2. Model Procurement Documents for Progressive Design-Build
  • 3. Developing Model Procurement Documents for Progressive Design-Build Projects Overview • What is progressive design-build (PDB)? How does it work? • Benefits of PDB • Key considerations in a PDB procurement – Understanding the model procurement documents • RFQ • RFP • Progressive Design Build Agreement • Implementing the PDB procurement
  • 4. Project Delivery Options Traditional Delivery Alternative Delivery Construction “Progressive” Lump-Sum Design-Build- Design-Bid-Build Management at Risk Design-Build Design-Build Operate/ (DBB) (CMAR) (GMP) (LS) Finance, etc.
  • 5. Progressive Design-Build In a progressive design-build procurement, the design-builder is selected primarily based on qualifications before substantial design is completed. Together, the owner and the design-build team advance the design, incorporating the details desired by the owner and providing the owner with cost input regarding options the owner is considering. This open- book approach enables the owner to make well-informed decisions on the overall quality of the project.
  • 6. Progressive Design-Build Construction estimating can Owner “Progressive” estimates keep start very early in design, owners informed and support- allowing comparison of specific informed scope adjustment technical solutions decisions PM/OA Design/Builder Design Definition Design Development and Construction 100% Guaranteed maximum price First fully detailed estimate Owners can use third-parties to established at the right time: can be used to establish a scope baseline. Estimating verify cost . . . Risk and contingency reduced, process is “open book” . . . and go to the hard-bid market schedule needs met if needed (the “off-ramp”)
  • 7. Progressive Design-Build Owner PM/OA Design/Builder Design Definition Design Development and Construction 100% Phase 1 Phase 2 GMP
  • 8. Progressive Design-Build Owner • Investment in projects, not procurements • Offers owners maximum flexibility/opportunity to collaborate on PM/OA Design/Builder permitting/ design • Maximizes overall schedule • Owners have an “off-ramp” in case of permitting issues or if GMP Design Design Development and Construction can’t be negotiated Definition • Very successful evolving model 100%
  • 9. Key Considerations in PDB Procurement • Existing legal authority • Basis for selection • Required contents for submission • Evaluation criteria and scoring methodology • PDB Contract – Agreement – General Conditions
  • 10. Legal Authority • Verify State and local procurement laws – Is PDB allowed? – Requirements for procurement • One step vs. Two-step process • Qualifications only vs. “best value” (quals + cost) • Self performance of work • Water Design Build Council survey (July 2012) • Survey of relevant state legislation for select states • Available on WDBC website
  • 11. Legal Authority •Does not expressly permit PDB •Allows evaluation of RFP based on criteria deemed appropriate for the project •Does not prohibit two-step process •Best value evaluation Virginia •Requires price consideration in evaluation, but need not be the sole determining factor
  • 12. Basis for Selection Qualifications-Based Selection Best-Value Selection • Employ evaluation criteria that are • Allows price or costs to be traditionally used for any considered with qualifications qualifications-based selection • Total cost of construction is not a • Owner able conduct process factor efficiently • Typical cost considerations include: • Reduces total time for • Fixed fees for procurement preconstruction services • Reduces cost of procurement • Raw labor hour rate sheet • Reduces complexity • Design-builder fee or markup percentage of allowable • Potentially allows for a larger pool project costs of qualified firms to participate • Fixed fee for General Condition costs
  • 13. Basis for Selection Qualifications-Based Selection Best-Value Selection Basic Intent of PDB is that selection of the • Employ evaluation criteria that are • Allows price or costs to be design-builder is heavily based on qualifications traditionally used for any considered with qualifications qualifications-based selection • Total cost of construction is not a • Fees and rates account for relatively small percentage of • Owner able conduct process factor overall project costs efficiently • Typical cost considerations include: • Reduces• total time for costs should be kept to minimum for Weighting of • Fixed fees procurement preconstruction services • Some state procurement laws dictate minimum • Reduces cost of procurement percentages • Raw labor hour rate sheet • Reduces• complexity • Design-builder fee Model procurement documents provided suggestions or markup percentage of allowable • Potentially allows for a larger pool on weighting of costs project costs of qualified firms to participate • Fixed fee for General Condition costs
  • 14. Basis for Selection Various Procurement Processes • Two categories for Procurement Single-Step Two - Step Request for Request for Request for Request for Qualifications Proposals Qualifications Qualifications Request for Request for “Best Value” Proposals Proposals Qualifications Qualifications only + Qualifications “Best Value” Costs Qualifications + only Costs
  • 15. Basis for Selection Various Procurement Processes • Single-Step – Qualifications Selection Single-Step • If schedule is a critical driver Two - Step Request for • for Request If maximum owner/design-builder for Request for Request Qualifications Proposals collaboration Qualifications is a priority Qualifications Request for Request for • If state/local law allow qualifications- only “Best Value” Proposals Proposals Qualifications Qualifications + selection WDBC No. only W-1200-2013 Qualifications “Best Value” Costs Qualifications + only Costs
  • 16. Basis for Selection Various Procurement Processes • Single-Step: Best Value Single-Step • If schedule is a critical driver Two - Step Request for Request for • If maximum owner/design-builder Request for Request for Qualifications Proposals Qualifications Qualifications collaboration is a priority Request for Request for • If Owner prefers Proposals (or ifProposals state/local Qualifications only WDBC No. law requires) inclusion of cost as a Qualifications “Best Value” W-1300-2013 selection factor only Qualifications + Costs
  • 17. Basis for Selection Various Procurement Processes • Two –Step: Request for Qualifications • If schedule can accommodate Single-Step Two - Step the time required for two procurement steps Request for Request for Request for Request for Qualifications Proposals Qualifications Qualifications • Potentially greater degree of Request for Request for project data provided with RFP “Best Value” Proposals Proposals Qualifications Qualifications only + WDBC No. Qualifications “Best Value” • Short list firms to receive RFP Costs only W-1400-2013 Qualifications + Costs
  • 18. Basis for Selection Various Procurement Processes • Two-Step: Request for Proposals • Includes Single-Step Project Approach Two - Step • Potentially greater degree of Request for Request for Request for Request for Qualifications Proposals project data provided with RFP Qualifications Qualifications Request for Request for • Qualifications only or best value “Best Value” Proposals Proposals Qualifications Qualifications only + Qualifications Quals “Best Value” Best Costs WDBC No. Qualifications + only only value Costs W-1500-2013
  • 19. Required Contents for Submission • Model Documents – RFQ & RFP – Comprehensive – Based on historical submission requirements from previous PDB deliveries – Provide foundation for development RFQ & RFP that best suits an Owner’s specific needs
  • 20. Required Contents for Submission • Statement of Qualifications - Contents •Section 1. Background • Section 2. Project Overview • Section 3. Progressive Design-Build Services • Section 4. Procurement Process • Section 5. SOQ Submission Requirements • Section 6. SOQ Evaluation and Selection • Section 7. Conditions for Respondents WDBC Documents W-1200-2013 & W-1400-2013
  • 21. Required Contents for Submission • Statement of Qualifications - Contents ATTACHMENTS • A: Definition of Terms • B: Scope of Design-Builders Services • C: Draft PDB Contract • D: Project Background Documents • E: Project Technical Requirements • F: Submission Forms WDBC Documents W-1200-2013 & W-1400-2013
  • 22. Required Contents for Submission • Statement of Qualifications - Contents •Section 1. Background • Section 2. Project Overview DIFFERENCES • Section 3. Progressive Design-Build Services • Procurement Schedule • Section 4. Procurement Process • Single-Step - includes Project Approach and PDB • Section Contract Markup 5. SOQ Submission Requirements • Evaluation criteria• / weighting Evaluation and Selection Section 6. SOQ • Section 7. Conditions for Respondents • Selection WDBC Documents W-1200-2013 & W-1400-2013
  • 23. Required Contents for Submission • Statement of Qualifications - Contents •Section 1. Background • Section 2. Project Overview • Section 3. Progressive Design-Build Services • Section 4. Procurement Process • Section 5. SOQ Submission Requirements • Section 6. SOQ Evaluation and Selection • Section 7. Conditions for Respondents WDBC Documents W-1200-2013 & W-1400-2013
  • 24. Required Contents for Submission • Statement of Qualifications – Section 5 • Transmittal Letter • Part 1: Executive Summary • Part 2: Design-Builder Profile • Part 3: Project Team • Part 4: Experience WDBC Documents W-1200-2013 & W-1400-2013
  • 25. Required Contents for Submission • Transmittal Letter PURPOSE Identifies the design-builder and provides contact information • Page limited • Contact information for Respondent Contact • Signatory for contracts • Must make reference to “Forms of Compliance”
  • 26. Required Contents for Submission • Part 1: Executive Summary PURPOSE Provides first glance overview of the SOQ contents, highlighting important features • Page limited • Key elements of the SOQ • No additional information not found in SOQ
  • 27. Required Contents for Submission • Part 2: Design-Builder Profile PURPOSE Provides general, legal and financial information concerning the design-builder • General • Performance bonds • Legal Structure • Insurance • Material adverse changes in • Project office location financial position • Financial condition • Legal proceedings
  • 28. Required Contents for Submission • Part 2: Design-Builder Profile PURPOSE Provides general, legal and financial information concerning the design-builder • Completion of contracts • Violation of laws • Debarred from bidding
  • 29. Required Contents for Submission • Part 3: Project Team PURPOSE Describes key personnel and additional firms * ORGANIZATION * ROLES & RESPONSIBILITIES * RESUMES Design-builder/other firms * Roles and responsibilities of all firms * Phase 1 and Phase 2 organizational charts
  • 30. Required Contents for Submission • Part 3: Project Team PURPOSE Describes key personnel and additional firms * ORGANIZATION * ROLES & RESPONSIBILITIES * RESUMES Key Personnel * Roles and responsibilities * Level of commitment * Resumes
  • 31. Required Contents for Submission • Part 4: Experience PURPOSE Provides detailed information on relevant design, construction, design-build projects and safety • Reference projects – number specified by owner • Three categories: – Design – Construction – Design-build
  • 32. Required Contents for Submission • Part 4: Experience PURPOSE Provides detailed information on relevant design, construction, design-build projects and safety • Information provided for each project: – Name of owner – Year started and completed – Owner reference and contact information
  • 33. Required Contents for Submission • Part 4: Experience PURPOSE Provides detailed information on relevant design, construction, design-build projects and safety • Information provided for each project: – Firms and key personnel that participated in the project – Description of the project • One–page summary table to cross reference the projects with project team (firms and key personnel)
  • 34. Required Contents for Submission • Request for Proposals • Two-Step RFP discussed (W-1500-2013) • Used for both - Qualifications based selection - Best Value selection • RFP for Single-Step also includes requirements outlined in Single-Step RFQ WDBC Documents W-1300-2013 & W-1500-2013
  • 35. Required Contents for Submission • Request for Proposals - Contents •Section 1. Background • Section 2. Project Overview • Section 3. Progressive Design-Build Services • Section 4. Procurement Process • Section 5. Proposal Submission Requirements • Section 6. Proposal Evaluation and Selection • Section 7. Conditions for Respondents WDBC Documents W-1300-2013 & W-1500-2013
  • 36. Required Contents for Submission • Request for Proposals - Contents ATTACHMENTS • A: Definition of Terms • B: Scope of Design-Builders Services • C: Draft PDB Contract • D: Project Background Documents • E: Project Technical Requirements Not used if “Qualifications Only” selection • F: Fee and Rate Proposal Form WDBC Documents W-1300-2013 & W-1500-2013
  • 37. Required Contents for Submission • Request for Proposals - Contents •Section 1. Background • Section 2. Project Overview • Section 3. Progressive Design-Build Services • Section 4. Procurement Process • Section 5. Proposal Submission Requirements • Section 6. Proposal Evaluation and Selection • Section 7. Conditions for Respondents WDBC Documents W-1300-2013 & W-1500-2013
  • 38. Required Contents for Submission • Request for Proposals - Contents • Transmittal Letter • Part 1: Executive Summary • Part 2: Project Approach • Part 3: Draft PDB Contract Markup Not used if “Qualifications Only” selection • Part 4: Fee and Rate Proposal Not used in Single-Step Process • Part 5: Updated Qualifications WDBC Documents W-1300-2013 & W-1500-2013
  • 39. Required Contents for Submission • Transmittal Letter • Part 1: Executive Summary Same as the RFQ
  • 40. Required Contents for Submission • Part 2: Project Approach – Can include discussion on: • How collaborative relationship with the Owner would be established • How the design and construction processes will interface • Critical work components for success • The process for GMP development
  • 41. Required Contents for Submission • Part 2: Project Approach – Also can include discussion approach to: • Communications with owner and stakeholders • Quality management • Risk management • Adherence to the GMP and schedule
  • 42. Required Contents for Submission • Part 3: Draft PDB Contract Markup PURPOSE Provides a description and discussion of the rationale for proposed revisions to the draft PDB contract • Allows proposers to revisions to the contract that would more efficiently allocate: – Risk Owner is not obligated to accept any of the suggested revisions – Improve parties understanding of risk allocation – Improve clarity
  • 43. Required Contents for Submission • Part 4: Fee and Rate Proposal PURPOSE Provides certain fees and rates for design-builder services during Phase 1 and Phase 2 • Fixed fee or hourly rates for: – Design services – Engineering services during construction – Pre-construction services • Design-builder fee or markup as a percentage of project costs • Fixed fee or hourly rates for components of the GCs.
  • 44. Required Contents for Submission • Part 5: Updated Qualifications PURPOSE Confirm prior SOQ and describes any changes to projects team or key personnel and explains reason for change • Any proposed changes to the SOQ • Resumes of additional personnel proposed • Proposed changes subject to acceptance of owner
  • 45. Evaluation Criteria and Scoring Methodology EVALUATION CRITERIA Should be designed to select a design-builder with the highest probability of achieving an Owner’s project objectives • Fair • Clear • Transparent
  • 46. Evaluation Criteria and Scoring Methodology • Minimum qualification requirements – SOQ and Proposal for Single-Step – Pass/Fail * Performance bond * Net worth * Material adverse conditions * Licensing and registration * Design experience * Construction experience * Design-build experience * Safety record
  • 47. Evaluation Criteria and Scoring Methodology Experience and capabilities Fee Best Value Document Organization, Quals Procurement Design- Key Project & Management Approach Builder Personnel and Safety Approach Rate Proposal Single-Step RFQ 1200 X l l l l RFP 1300 X l l l l l Two - Step RFQ 1400 X l l l RFP 1500 X l l l l l RFP 1500 X l l l l
  • 48. Evaluation Criteria and Scoring Methodology Experience and capabilities Fee Best Value Document Organization, Quals Procurement Design- Key Project & Management Approach Builder Personnel and Safety Approach Rate Proposal Single-Step RFQ 1200 X 40% 30% 15% 15% RFP 1300 X 30% 20% 15% 15% 20% Two - Step RFQ 1400 X 40% 40% 20% RFP 1500 X 30% 20% 15% 15% 20% RFP 1500 X 40% 30% 15% 15%
  • 49. Progressive Design Build Contract • Agreement • Attachments – A: Scope of Work – B: Compensation – C: Schedule – D: General Conditions – E: Indemnity, Insurance & Bonding – F: Owner’s Project Criteria – G: Owner’s Permit List
  • 50. Progressive Design Build Contract • Agreement
  • 51. Progressive Design Build Contract • Attachment A – Scope of Work
  • 52. Progressive Design Build Contract • Attachment B - Compensation
  • 53. Progressive Design Build Contract • Attachment D – General Conditions
  • 54. Progressive Design Build Contract • Attachment E – Indemnity, Insurance & Bonding
  • 55. Progressive Design Build Contract • Attachment F – Owner’s Project Criteria
  • 56. Progressive Design Build Contract • Attachment G – Owner’s Permit List
  • 57. Implementing the PDB Procurement Plan Project RFQ RFP Permits/Design Input Verify DB Performance (Verify) O&M Define Performance Criteria Tech Support Verify GMP Inspection Quals Propose Concept Design/Develop GMP Construction, Startup Warranty Complete Design RFQ – defines qualifications Select from qualified firms criteria; short lists qualified - selection based on qualifications; Agree on GMP - based on firms may include “rates” or “conceptual/ collaborative scope and design; target price” in evaluation pricing may be verified by third party LC
  • 58. Model Procurement Documents for Progressive Design-Build www.waterdesignbuild.org