Digital initiative Status RRTS L2.ppt with prject life cycle x
1. Sensitivity: LNT Construction Internal Use 1
1
HCIC Digital Initiatives Status
Concrete
Management
system
Workmen Monitoring
EP Tracking
Aggregate Management
Segment Tracking
System
Pour Planning &
CMPC-Enabling Structure
2. Sensitivity: LNT Construction Internal Use 2
Project : RRTS L2
Prestart(No. of forms)- 508
Near miss (No. of near miss)-14
EHS observation(No. of forms)-147
VR(No. of workmen trained)-25
CON PRO(Oct’21):
Actual Ordered concrete- 11311cum
Con Pro Approved concrete- 10737cum
Adoption (%) - 95%
EHS: IB4U:
No. of inspection- 122
PROCUBE:
Pro cube DPR submission- 8
P&M:
Asset identified- 76
Asset tagged- 24
Asset reporting- 9
Training:
Pro Cube – 15 July
Rebar Pro – 22 July
Attendees- 34
Rebar Pro:
BBS uploading in Progress