SlideShare a Scribd company logo
Earned Value Management
Drexel University, Goodwin College CT431-120 Project Management
R. Gottardi, Instructor/Author                                    May 31, 2009
Some Definitions
• Planned Value, PV (BCWS): the portion
  of the approved total cost estimate during
  a given period
• Actual Cost, AC: the total of the direct &
  indirect costs incurred in accomplishing
  work on a task or project during a given
  period
                                               2
Project Tracking without Earned Value
                                         Project Performance

                                                      BCWS      Actual Cost


              200
              180
              160
              140
              120
$000




              100
              80
              60
              40
              20
               0
                     1    2    3    4         5        6            7         8     9     10    11    12
       BCWS          10   20   25   40        62       80           98        125   137   149   160   175
       Actual Cost   30   48   52   55        60       65           70        72
                                                            Weeks


       Conclusion: It looks like we are under budget. What’s missing?
                                                                                                            3
What’s Missing
• Any measure of how much work has been
  accomplished
• Earned Value: an estimate of the value of
  the physical work actually completed
• Can be
  – currency, e.g., $
  – Quantities, e.g., tons, yds3, SF, etc.
  – Any agreed upon value for the tasks
                                             4
How Can We Measure Progress?
• % complete of the tasks’ durations
• Rate of performance (RP): % complete actual/%
  compete planned
• Physical quantities (works for some tasks but not
  others)
   –   Tons of earth moved
   –   Cubic yards of cement poured
   –   Floors completed
   –   Sq ft completed
• Let’s use RP because it is common to many tasks &
  gives us a schedule related measure
                                                      5
Establish Earning Rules
Rule         Credit at Start         Credit at End

0/100                          0%                    100%

50/50                          50%                   50%

25/75                          25%                   75%

20/80                          20%                   80%

  Credit means the budgeted cost of work
    performed is included in the earned value
    calculation to the extent of the % indicated.
                                                            6
Earned Value Vs. Planned Value
                                      Project Performance

                                      PV(BCWS)   EV(BCWP)


           200
           180
           160
           140
           120
$000




                                                                            Schedule Variance
           100
                                                                            Behind Schedule
            80
            60
            40
            20
             0
                  1    2    3    4          5       6            7    8        9        10      11    12
       PV(BCWS)   10   20   25   40        62       80           98   125     137      149      160   175
       EV(BCWP)   28   60   62   70        72       80           82   92
                                                         Weeks


                                                                                                            7
Earned Value vs. Actual Cost
                                         Project Performance

                                                    Actual Cost     EV(BCWP)


             100
              90
                                                                                    Cost Variance ($)
              80                                                                    Under Budget
              70
              60
$000




              50
              40
              30
              20
              10
               0
                     1    2    3    4         5        6            7          8    9         10        11   12
       Actual Cost   30   48   52   55        60       65           70         72
       EV(BCWP)      28   60   62   70        72       80           82         92
                                                            Weeks

                                                                                                              8
Combine All Variables
                                            Project Performance

                                            PV(BCWS)        AC(Actual Cost)        EV(BCWP)


                  200
                  180
                  160
                                                                                                          PV
                  140
                  120
$000




                  100
                                                                                               EV
                  80
                  60                                                                AC
                  40
                  20
                   0
                         1    2    3    4              5          6           7           8         9          10    11    12

       PV(BCWS)          10   20   25   40             62        80           98         125        137        149   160   175
       AC(Actual Cost)   30   48   52   55             60        65           70          72
       EV(BCWP)          28   60   62   70             72        80           82          92
                                                                      Weeks
                                                                                                                                9
Variance Computations
•   Cost Variance (CV)=EV-AC
•   Schedule Variance (SV)=EV-PV
•   Negative values are unfavorable
•   Positive values are favorable



                                      10
Performance Indices
• Cost Performance Index (CPI)=EV/AC
• Schedule Performance Index
  (SPI)=EV/PV
• <1= unfavorable
• >1=favorable


                                       11
Earned Value
• Integrates schedule & cost data
• Explains causes of variances
• Encourages objective measurement of
  progress
• Measures performance


                                        12
Problem
• Given:
  • EV = $5,000
  • PV = $10,000
  • AC = $15,000
• Solve:
  •   CV =
  •   SV =
  •   CPI =
  •   SPI =
                   13
Problem
• Given:
  • EV = $5,000 = Earned Value
  • PV = $10,000
  • AC = $15,000
• Solve:
  •   CV =
  •   SV =
  •   CPI =
  •   SPI
                                 14
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000
  • AC = $15,000
• Solve:
  •   CV =
  •   SV =
  •   CPI =
  •   SPI =
                                        15
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value
  • AC = $15,000
• Solve:
  •   CV =
  •   SV =
  •   CPI =
  •   SPI =
                                        16
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BCWS
  • AC = $15,000
• Solve:
  •   CV =
  •   SV =
  •   CPI =
  •   SPI =
                                         17
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BCWS
  • AC = $15,000 = Actual Cost
• Solve:
  •   CV =
  •   SV =
  •   CPI =
  •   SPI =
                                         18
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BSWS
  • AC = $15,000 = Actual Cost
• Solve:
  •   CV = EV-AC
  •   SV =
  •   CPI =
  •   SPI =
                                         19
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BSWS
  • AC = $15,000 = Actual Cost
• Solve:
  •   CV = EV-AC = 5,000-15,000
  •   SV =
  •   CPI =
  •   SPI =
                                         20
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BSWS
  • AC = $15,000 = Actual Cost
• Solve:
  •   CV = EV-AC = 5,000-15,000 = -10,000
  •   SV =
  •   CPI =
  •   SPI =
                                            21
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BSWS
  • AC = $15,000 = Actual Cost
• Solve:
  •   CV = EV-AC = 5,000-15,000 = -10,000
  •   SV = EV-PV
  •   CPI =
  •   SPI =
                                            22
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BSWS
  • AC = $15,000 = Actual Cost
• Solve:
  •   CV = EV-AC = 5,000-15,000 = -10,000
  •   SV = EV-PV = 5,000-10,000
  •   CPI =
  •   SPI =
                                            23
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BSWS
  • AC = $15,000 = Actual Cost
• Solve:
  •   CV = EV-AC = 5,000-15,000 = -10,000
  •   SV = EV-PV = 5,000-10,000 = -5,000
  •   CPI =
  •   SPI =
                                            24
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BSWS
  • AC = $15,000 = Actual Cost
• Solve:
  •   CV = EV-AC = 5,000-15,000 = -10,000
  •   SV = EV-PV = 5,000-10,000 = -5,000
  •   CPI = EV/AC
  •   SPI =
                                            25
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BSWS
  • AC = $15,000 = Actual Cost
• Solve:
  •   CV = EV-AC = 5,000-15,000 = -10,000
  •   SV = EV-PV = 5,000-10,000 = -5,000
  •   CPI = EV/AC = 5,000/15,000
  •   SPI =
                                            26
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BSWS
  • AC = $15,000 = Actual Cost
• Solve:
  •   CV = EV-AC = 5,000-15,000 = -10,000
  •   SV = EV-PV = 5,000-10,000 = -5,000
  •   CPI = EV/AC = 5,000/15,000 = .33
  •   SPI =
                                            27
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BSWS
  • AC = $15,000 = Actual Cost
• Solve:
  •   CV = EV-AC = 5,000-15,000 = -10,000
  •   SV = EV-PV = 5,000-10,000 = -5,000
  •   CPI = EV/AC = 5,000/15,000 = .33
  •   SPI = EV/PV
                                            28
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BSWS
  • AC = $15,000 = Actual Cost
• Solve:
  •   CV = EV-AC = 5,000-15,000 = -10,000
  •   SV = EV-PV = 5,000-10,000 = -5,000
  •   CPI = EV/AC = 5,000/15,000 = .33
  •   SPI = EV/PV = 5,000/10,000
                                            29
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BCWS
  • AC = $15,000 = Actual Cost
• Solve:
  •   CV = EV-AC = 5,000-15,000 = -10,000
  •   SV = EV-PV = 5,000-10,000 = -5,000
  •   CPI = EV/AC = 5,000/15,000 = .33
  •   SPI = EV/PV = 5,000/10,000 = .5
                                            30
Other Terms & Computations
• BAC: Budget at Completion: The
  original total budget for a project
• EAC: Estimate at Completion =
  BAC/CPI (CPI = Cost Performance Index)
• ETC: Estimate to Complete: EAC-AC
• Variance at Completion: BAC-EAC

                                       31
Earned Value
•   Title: Earned Value Management
•   Filename: Earned Value Management Lecture 2009eMY31
•   Author: Ron Gottardi
•   Author Affiliation: Drexel University, Goodwin College of
    Professional Studies
•   Course: CT431-120 Project management
•   Date: May 31, 2009
•   Copyright 2009 Ron Gottardi




                                                                32

More Related Content

PPT
Inventory management ch12
PDF
Walsall port vale
PDF
Hays cisd energy management or how do you eat an elephant
PDF
Alterra presentation DEC
PPTX
C13
PDF
Progressive loss report_0608_appendix
PPTX
Bio 2 ch1 Notes
PPT
RAKOR PERSIAPAN MUSRENBANG TAHUN 2015 - BAPPEDA GRESIK
Inventory management ch12
Walsall port vale
Hays cisd energy management or how do you eat an elephant
Alterra presentation DEC
C13
Progressive loss report_0608_appendix
Bio 2 ch1 Notes
RAKOR PERSIAPAN MUSRENBANG TAHUN 2015 - BAPPEDA GRESIK

Viewers also liked (19)

PPTX
Wxig points update
PPTX
AmyandSusan
PDF
Hugps138
PPT
Question 3 – what have you learnt from
DOCX
No tlp Polisi
PDF
SGGSWU Prospectus 2016-17
PDF
VW Santana Vista - Brochure
PDF
33559
PDF
Focusing on the Threats to the Detriment of the Vulnerabilities
TXT
Freefixer log
PDF
Create - Day 2 - 11:15 - "Six Secrets to Overcoming Social Marketing Hurdles"
DOCX
Oppa (13)
PPT
The Anatomy Of The Idea
PPT
01 introduction E-Commerce
PDF
Jft 13-desktop-optical-power-meter-jfopt
PDF
Google Ground Kiajánló
PPS
Unit 1 the universe
PDF
XING Q3 report 2012 english version
PDF
205180 cm with jde
Wxig points update
AmyandSusan
Hugps138
Question 3 – what have you learnt from
No tlp Polisi
SGGSWU Prospectus 2016-17
VW Santana Vista - Brochure
33559
Focusing on the Threats to the Detriment of the Vulnerabilities
Freefixer log
Create - Day 2 - 11:15 - "Six Secrets to Overcoming Social Marketing Hurdles"
Oppa (13)
The Anatomy Of The Idea
01 introduction E-Commerce
Jft 13-desktop-optical-power-meter-jfopt
Google Ground Kiajánló
Unit 1 the universe
XING Q3 report 2012 english version
205180 cm with jde
Ad

Similar to Earned value management lecture 2009e my31 (20)

PDF
SPICE MODEL of TPCA8004-H (Professional+BDP Model) in SPICE PARK
PDF
SPICE MODEL of TPCA8004-H (Standard+BDS Model) in SPICE PARK
PDF
SPICE MODEL of TPCM8002-H (Professional+BDP Model) in SPICE PARK
PDF
SPICE MODEL of TPCA8014 (Standard+BDS Model) in SPICE PARK
PDF
SPICE MODEL of TPC8117 (Standard+BDS Model) in SPICE PARK
PDF
SPICE MODEL of TPC8A02-H (Professional+ZDSP Model) in SPICE PARK
PDF
SPICE MODEL of TPCA8014 (Professional+BDP Model) in SPICE PARK
PDF
SPICE MODEL of TPCM8002-H (Standard+BDS Model) in SPICE PARK
PDF
SPICE MODEL of RN1417 in SPICE PARK
PDF
SPICE MODEL of RN1114FT in SPICE PARK
PDF
SPICE MODEL of TPC8032-H (Professional+BDP Model) in SPICE PARK
PDF
Free SPICE Model of S3K60 in SPICE PARK
PDF
SPICE MODEL of 2SK3906 (Standard+BDS Model) in SPICE PARK
PDF
SPICE MODEL of RN1107FS in SPICE PARK
PDF
SPICE MODEL of TPC8032-H (Standard+BDS Model) in SPICE PARK
PDF
SPICE MODEL of 2SK3435 (Professional+BDP Model) in SPICE PARK
PDF
SPICE MODEL of DTC123JM in SPICE PARK
PDF
SPICE MODEL of TPC8110 (Standard+BDS Model) in SPICE PARK
PDF
Schedule variance = 0 and we’re a year late
PDF
SPICE MODEL of TPCA8014-H (Professional+BDSP Model) in SPICE PARK
SPICE MODEL of TPCA8004-H (Professional+BDP Model) in SPICE PARK
SPICE MODEL of TPCA8004-H (Standard+BDS Model) in SPICE PARK
SPICE MODEL of TPCM8002-H (Professional+BDP Model) in SPICE PARK
SPICE MODEL of TPCA8014 (Standard+BDS Model) in SPICE PARK
SPICE MODEL of TPC8117 (Standard+BDS Model) in SPICE PARK
SPICE MODEL of TPC8A02-H (Professional+ZDSP Model) in SPICE PARK
SPICE MODEL of TPCA8014 (Professional+BDP Model) in SPICE PARK
SPICE MODEL of TPCM8002-H (Standard+BDS Model) in SPICE PARK
SPICE MODEL of RN1417 in SPICE PARK
SPICE MODEL of RN1114FT in SPICE PARK
SPICE MODEL of TPC8032-H (Professional+BDP Model) in SPICE PARK
Free SPICE Model of S3K60 in SPICE PARK
SPICE MODEL of 2SK3906 (Standard+BDS Model) in SPICE PARK
SPICE MODEL of RN1107FS in SPICE PARK
SPICE MODEL of TPC8032-H (Standard+BDS Model) in SPICE PARK
SPICE MODEL of 2SK3435 (Professional+BDP Model) in SPICE PARK
SPICE MODEL of DTC123JM in SPICE PARK
SPICE MODEL of TPC8110 (Standard+BDS Model) in SPICE PARK
Schedule variance = 0 and we’re a year late
SPICE MODEL of TPCA8014-H (Professional+BDSP Model) in SPICE PARK
Ad

Recently uploaded (20)

PDF
Tata consultancy services case study shri Sharda college, basrur
DOCX
unit 1 COST ACCOUNTING AND COST SHEET
PPTX
Lecture (1)-Introduction.pptx business communication
PPTX
job Avenue by vinith.pptxvnbvnvnvbnvbnbmnbmbh
PPTX
HR Introduction Slide (1).pptx on hr intro
PPTX
New Microsoft PowerPoint Presentation - Copy.pptx
PDF
COST SHEET- Tender and Quotation unit 2.pdf
PPTX
2025 Product Deck V1.0.pptxCATALOGTCLCIA
PDF
Types of control:Qualitative vs Quantitative
PDF
A Brief Introduction About Julia Allison
PPTX
AI-assistance in Knowledge Collection and Curation supporting Safe and Sustai...
PDF
NISM Series V-A MFD Workbook v December 2024.khhhjtgvwevoypdnew one must use ...
PDF
IFRS Notes in your pocket for study all the time
PPTX
Principles of Marketing, Industrial, Consumers,
PDF
Power and position in leadershipDOC-20250808-WA0011..pdf
PPTX
ICG2025_ICG 6th steering committee 30-8-24.pptx
PPT
Data mining for business intelligence ch04 sharda
PDF
DOC-20250806-WA0002._20250806_112011_0000.pdf
PPT
Chapter four Project-Preparation material
PDF
MSPs in 10 Words - Created by US MSP Network
Tata consultancy services case study shri Sharda college, basrur
unit 1 COST ACCOUNTING AND COST SHEET
Lecture (1)-Introduction.pptx business communication
job Avenue by vinith.pptxvnbvnvnvbnvbnbmnbmbh
HR Introduction Slide (1).pptx on hr intro
New Microsoft PowerPoint Presentation - Copy.pptx
COST SHEET- Tender and Quotation unit 2.pdf
2025 Product Deck V1.0.pptxCATALOGTCLCIA
Types of control:Qualitative vs Quantitative
A Brief Introduction About Julia Allison
AI-assistance in Knowledge Collection and Curation supporting Safe and Sustai...
NISM Series V-A MFD Workbook v December 2024.khhhjtgvwevoypdnew one must use ...
IFRS Notes in your pocket for study all the time
Principles of Marketing, Industrial, Consumers,
Power and position in leadershipDOC-20250808-WA0011..pdf
ICG2025_ICG 6th steering committee 30-8-24.pptx
Data mining for business intelligence ch04 sharda
DOC-20250806-WA0002._20250806_112011_0000.pdf
Chapter four Project-Preparation material
MSPs in 10 Words - Created by US MSP Network

Earned value management lecture 2009e my31

  • 1. Earned Value Management Drexel University, Goodwin College CT431-120 Project Management R. Gottardi, Instructor/Author May 31, 2009
  • 2. Some Definitions • Planned Value, PV (BCWS): the portion of the approved total cost estimate during a given period • Actual Cost, AC: the total of the direct & indirect costs incurred in accomplishing work on a task or project during a given period 2
  • 3. Project Tracking without Earned Value Project Performance BCWS Actual Cost 200 180 160 140 120 $000 100 80 60 40 20 0 1 2 3 4 5 6 7 8 9 10 11 12 BCWS 10 20 25 40 62 80 98 125 137 149 160 175 Actual Cost 30 48 52 55 60 65 70 72 Weeks Conclusion: It looks like we are under budget. What’s missing? 3
  • 4. What’s Missing • Any measure of how much work has been accomplished • Earned Value: an estimate of the value of the physical work actually completed • Can be – currency, e.g., $ – Quantities, e.g., tons, yds3, SF, etc. – Any agreed upon value for the tasks 4
  • 5. How Can We Measure Progress? • % complete of the tasks’ durations • Rate of performance (RP): % complete actual/% compete planned • Physical quantities (works for some tasks but not others) – Tons of earth moved – Cubic yards of cement poured – Floors completed – Sq ft completed • Let’s use RP because it is common to many tasks & gives us a schedule related measure 5
  • 6. Establish Earning Rules Rule Credit at Start Credit at End 0/100 0% 100% 50/50 50% 50% 25/75 25% 75% 20/80 20% 80% Credit means the budgeted cost of work performed is included in the earned value calculation to the extent of the % indicated. 6
  • 7. Earned Value Vs. Planned Value Project Performance PV(BCWS) EV(BCWP) 200 180 160 140 120 $000 Schedule Variance 100 Behind Schedule 80 60 40 20 0 1 2 3 4 5 6 7 8 9 10 11 12 PV(BCWS) 10 20 25 40 62 80 98 125 137 149 160 175 EV(BCWP) 28 60 62 70 72 80 82 92 Weeks 7
  • 8. Earned Value vs. Actual Cost Project Performance Actual Cost EV(BCWP) 100 90 Cost Variance ($) 80 Under Budget 70 60 $000 50 40 30 20 10 0 1 2 3 4 5 6 7 8 9 10 11 12 Actual Cost 30 48 52 55 60 65 70 72 EV(BCWP) 28 60 62 70 72 80 82 92 Weeks 8
  • 9. Combine All Variables Project Performance PV(BCWS) AC(Actual Cost) EV(BCWP) 200 180 160 PV 140 120 $000 100 EV 80 60 AC 40 20 0 1 2 3 4 5 6 7 8 9 10 11 12 PV(BCWS) 10 20 25 40 62 80 98 125 137 149 160 175 AC(Actual Cost) 30 48 52 55 60 65 70 72 EV(BCWP) 28 60 62 70 72 80 82 92 Weeks 9
  • 10. Variance Computations • Cost Variance (CV)=EV-AC • Schedule Variance (SV)=EV-PV • Negative values are unfavorable • Positive values are favorable 10
  • 11. Performance Indices • Cost Performance Index (CPI)=EV/AC • Schedule Performance Index (SPI)=EV/PV • <1= unfavorable • >1=favorable 11
  • 12. Earned Value • Integrates schedule & cost data • Explains causes of variances • Encourages objective measurement of progress • Measures performance 12
  • 13. Problem • Given: • EV = $5,000 • PV = $10,000 • AC = $15,000 • Solve: • CV = • SV = • CPI = • SPI = 13
  • 14. Problem • Given: • EV = $5,000 = Earned Value • PV = $10,000 • AC = $15,000 • Solve: • CV = • SV = • CPI = • SPI 14
  • 15. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 • AC = $15,000 • Solve: • CV = • SV = • CPI = • SPI = 15
  • 16. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value • AC = $15,000 • Solve: • CV = • SV = • CPI = • SPI = 16
  • 17. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BCWS • AC = $15,000 • Solve: • CV = • SV = • CPI = • SPI = 17
  • 18. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BCWS • AC = $15,000 = Actual Cost • Solve: • CV = • SV = • CPI = • SPI = 18
  • 19. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BSWS • AC = $15,000 = Actual Cost • Solve: • CV = EV-AC • SV = • CPI = • SPI = 19
  • 20. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BSWS • AC = $15,000 = Actual Cost • Solve: • CV = EV-AC = 5,000-15,000 • SV = • CPI = • SPI = 20
  • 21. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BSWS • AC = $15,000 = Actual Cost • Solve: • CV = EV-AC = 5,000-15,000 = -10,000 • SV = • CPI = • SPI = 21
  • 22. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BSWS • AC = $15,000 = Actual Cost • Solve: • CV = EV-AC = 5,000-15,000 = -10,000 • SV = EV-PV • CPI = • SPI = 22
  • 23. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BSWS • AC = $15,000 = Actual Cost • Solve: • CV = EV-AC = 5,000-15,000 = -10,000 • SV = EV-PV = 5,000-10,000 • CPI = • SPI = 23
  • 24. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BSWS • AC = $15,000 = Actual Cost • Solve: • CV = EV-AC = 5,000-15,000 = -10,000 • SV = EV-PV = 5,000-10,000 = -5,000 • CPI = • SPI = 24
  • 25. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BSWS • AC = $15,000 = Actual Cost • Solve: • CV = EV-AC = 5,000-15,000 = -10,000 • SV = EV-PV = 5,000-10,000 = -5,000 • CPI = EV/AC • SPI = 25
  • 26. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BSWS • AC = $15,000 = Actual Cost • Solve: • CV = EV-AC = 5,000-15,000 = -10,000 • SV = EV-PV = 5,000-10,000 = -5,000 • CPI = EV/AC = 5,000/15,000 • SPI = 26
  • 27. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BSWS • AC = $15,000 = Actual Cost • Solve: • CV = EV-AC = 5,000-15,000 = -10,000 • SV = EV-PV = 5,000-10,000 = -5,000 • CPI = EV/AC = 5,000/15,000 = .33 • SPI = 27
  • 28. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BSWS • AC = $15,000 = Actual Cost • Solve: • CV = EV-AC = 5,000-15,000 = -10,000 • SV = EV-PV = 5,000-10,000 = -5,000 • CPI = EV/AC = 5,000/15,000 = .33 • SPI = EV/PV 28
  • 29. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BSWS • AC = $15,000 = Actual Cost • Solve: • CV = EV-AC = 5,000-15,000 = -10,000 • SV = EV-PV = 5,000-10,000 = -5,000 • CPI = EV/AC = 5,000/15,000 = .33 • SPI = EV/PV = 5,000/10,000 29
  • 30. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BCWS • AC = $15,000 = Actual Cost • Solve: • CV = EV-AC = 5,000-15,000 = -10,000 • SV = EV-PV = 5,000-10,000 = -5,000 • CPI = EV/AC = 5,000/15,000 = .33 • SPI = EV/PV = 5,000/10,000 = .5 30
  • 31. Other Terms & Computations • BAC: Budget at Completion: The original total budget for a project • EAC: Estimate at Completion = BAC/CPI (CPI = Cost Performance Index) • ETC: Estimate to Complete: EAC-AC • Variance at Completion: BAC-EAC 31
  • 32. Earned Value • Title: Earned Value Management • Filename: Earned Value Management Lecture 2009eMY31 • Author: Ron Gottardi • Author Affiliation: Drexel University, Goodwin College of Professional Studies • Course: CT431-120 Project management • Date: May 31, 2009 • Copyright 2009 Ron Gottardi 32