ESTIMATING & COSTING
ARUN RAVI.K.R
Instructor, Draughtsman (Civil)
Part -2
Different Types of Sanctions01
LEARNING OBJECTIVES
Different Types of Estimates02
Estimate Sanction
Before the execution Three Sanctions are Required
Administrative Sanction
Financial Sanction (Expenditure sanction)
Technical sanction
Administrative Sanction (A.S)
For any project an approval or sanction of the competent authority
of the department is necessary at the first instance with respect of the cost
and work. (Sanction from Govt.)
Administrative approval denotes to formal acceptance of the
proposal. After A.S, the engineering department take up the work and
prepares detailed design, plans and estimates and then executes the work.
Financial Sanction (Expenditure sanction)
Financial sanction means allotment of fund or money for
a project from the finance department of Government
Technical Sanction (T.S)
The sanction of the detailed estimates,
design calculation, quantities of works,
rates and cost of the work by the
competent authority of the engineering
department is known as Technical
Sanction.
TYPES OF ESTIMATE
Preliminary or approximate or abstract estimate
This type of estimate is required for preliminary studies of
a project, to decide the financial position and policy for
administrative sanction by the competent administrative
authority.
The approximate estimate is prepared
with the practical knowledge and cost of the
similar works. This is also accompanied with
a site plan or layout plan. A percentage of
about 5% to 10% is added as contingencies.
Plinth area estimate (P.A. estimate)
This is prepared on the basis of plinth area of building, the
rate being deducted from the cost of similar building having
similar specification, heights and construction, in the locality.
Plinth area estimate is calculated
by finding the plinth area of the building
and multiplying by the plinth area rate.
Cubic rate estimate
This is prepared on the basis of the cubical contents of
the building. The cube rate being deducted from the cost of the
similar building having similar specifications and construction,
in the locality.
This is calculated by finding the
cubical content of the building (length
x breadth x height) and multiplied it by
the cube rate.
Cube rate estimate is most accurate
than to the plinth area estimate
Approximate quantity method
In this method approximate total length of work is found
in running metre and this total length multiplied by the rate per
running metre of wall gives a fairly accurate cost.
For this method the plan or line plan
of the structure should be available.
Detailed estimate
Detailed estimate is an accurate estimate consists of the
quantities of each item of works, and working the cost.
The dimensions, (length, breadth and height) of each item
are taken out correctly from drawing and quantities of each item
are calculated.
The detailed estimate is prepared in two stages.
1) Details of measurement and calculation of quantities
2) Abstract of estimate cost
1) Details of measurement and calculation of quantities
The details of measurement of each item of work are
taken out correctly from plan and drawings and quantities
under each item are computed or calculated in a tabular form
named as Details of Measurement Form (Table 1).
2) Abstract of estimate cost
The cost of each item of work is calculated in a tabular
form from the quantities already computed and total cost is
worked out in abstract of estimate form (Table 2). The rates of
different items of work are taken as per schedule of rates
Detailed Estimate Abstract estimate
Revised estimate
Revised Estimate is detailed estimate and is prepared
under any one of the following circumstances.
I. When the original sanctioned estimate is exceeds more than
5%.
II. When the expenditure on a work exceeds of administrative
sanction by more than 10%
III. When there are material deviation from the original proposal,
even though the cost may be met from the sanctioned
amount.
The revised estimate should be accompanied by a
comparative statement showing the variations of each
item of works
Supplementary estimate
Supplementary estimate is a detailed estimate and is
prepared when additional works are required to supplement the
original works, or when further developments is required during
the progress of work.
This is a fresh detailed estimate of the additional works in
addition to the original estimate.
Supplementary and revised estimate
 When a work is partially abandoned and the remaining
work is less than 95% of the original sanctioned estimate.
Or
 when there are material deviations and changes in the design
which may cause excess or saving in the estimate,
A supplementary and Revised Estimate is then prepared
and fresh technical sanction of the competent authority is
obtained.
Annual repair or annual maintenance estimate (A.R. or A.M. Estimate):
This estimate is a detailed estimate and is prepared to
maintain the structure or work in proper order and safe
condition.
For building: Includes white
washing, colour washing,
painting, minor repairs etc.
For road works: Tarring patch repairing,
renewals, repairs of bridges and culvert, etc.
Extension and improvement estimate
When some changes and
extensions are required to be made in
the old work, the cost of which cannot
be met by the annual
repair/maintenance estimate, a detailed
estimate is prepared for such work
which is called as extension and
improvement estimate.
ARUN RAVI.K.R
Instructor, Draughtsman (Civil)
arunravikr@gmail.com
9447622946

More Related Content

PPT
Rates Analysis For Calculating Material and Labour for building works
PPT
EstimationandCosting.ppt
PPTX
Kinematics in Engineering Mechanics
PPTX
Estimation and Costing
PPTX
Estimating and costing
PPTX
Contracts - Estimation, Costing and Valuation Engineering
PPTX
Building by laws
PPTX
Topic1_Castiglianos Theorem.pptx
Rates Analysis For Calculating Material and Labour for building works
EstimationandCosting.ppt
Kinematics in Engineering Mechanics
Estimation and Costing
Estimating and costing
Contracts - Estimation, Costing and Valuation Engineering
Building by laws
Topic1_Castiglianos Theorem.pptx

What's hot (20)

PPTX
Underpinning
PDF
Estimating and-costing
PPTX
prefabricated Structures
PPTX
Pile foundation
PPTX
Foundation types
PPTX
Terminology used in estimating and costing
PPTX
Approximate estimate
PPTX
estimation,its types and methods
PDF
MODULE-II BUILDING PLANNING AND DESIGN [BTCVC606]
PPTX
Grouting, guniting, jacketing
PPTX
Estimation and Costing - Contracts
PDF
Long wall and short wall method 1
PPTX
Types of estimates
PPTX
Rate analysis
PPT
TALL BUILDINGS
PPTX
Retaining walls
PPTX
PRESTRESSED CONCRETE STRUCTURES
PDF
Precast concrete construction
PPT
1.1 box jacking
PPTX
Construction Project Management
Underpinning
Estimating and-costing
prefabricated Structures
Pile foundation
Foundation types
Terminology used in estimating and costing
Approximate estimate
estimation,its types and methods
MODULE-II BUILDING PLANNING AND DESIGN [BTCVC606]
Grouting, guniting, jacketing
Estimation and Costing - Contracts
Long wall and short wall method 1
Types of estimates
Rate analysis
TALL BUILDINGS
Retaining walls
PRESTRESSED CONCRETE STRUCTURES
Precast concrete construction
1.1 box jacking
Construction Project Management
Ad

Similar to Estimating part 2 (20)

PPTX
Estimation and Costing
DOCX
Unit 1 - General Items used for building
PDF
EEEC pdf.pdf
PPTX
IV -I - EQS - .pptx
PDF
Estimation and Costing course lecture 1.pdf
PPTX
Lec05.pptx
PPTX
Types of estimate
DOC
Aiet e&c lecture_notes
PPTX
Estimation Costing and Valuation Unit 2
PDF
approximateestimate-200713090343.pdf
PDF
Estimating part 1
PPTX
ESTIMATION AND COSTING OF A COMMERCIAL BUILDING
DOCX
Construction Planning and Scheduling of Residential Building by MS Project by...
PDF
chapter3-210122050220.pdf
PPTX
Estimating and Costing
PPTX
Fundamentals of estimating_and_costing
PPTX
Introduction to estimation
DOC
type of cost Estimation
PPTX
Estimation and costing of a commercial building
Estimation and Costing
Unit 1 - General Items used for building
EEEC pdf.pdf
IV -I - EQS - .pptx
Estimation and Costing course lecture 1.pdf
Lec05.pptx
Types of estimate
Aiet e&c lecture_notes
Estimation Costing and Valuation Unit 2
approximateestimate-200713090343.pdf
Estimating part 1
ESTIMATION AND COSTING OF A COMMERCIAL BUILDING
Construction Planning and Scheduling of Residential Building by MS Project by...
chapter3-210122050220.pdf
Estimating and Costing
Fundamentals of estimating_and_costing
Introduction to estimation
type of cost Estimation
Estimation and costing of a commercial building
Ad

Recently uploaded (20)

PDF
SMART SIGNAL TIMING FOR URBAN INTERSECTIONS USING REAL-TIME VEHICLE DETECTI...
PDF
Soil Improvement Techniques Note - Rabbi
PDF
PREDICTION OF DIABETES FROM ELECTRONIC HEALTH RECORDS
PPTX
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
PDF
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
PPTX
6ME3A-Unit-II-Sensors and Actuators_Handouts.pptx
PDF
Artificial Superintelligence (ASI) Alliance Vision Paper.pdf
PPTX
CURRICULAM DESIGN engineering FOR CSE 2025.pptx
PDF
A SYSTEMATIC REVIEW OF APPLICATIONS IN FRAUD DETECTION
PPT
A5_DistSysCh1.ppt_INTRODUCTION TO DISTRIBUTED SYSTEMS
PDF
Integrating Fractal Dimension and Time Series Analysis for Optimized Hyperspe...
PDF
86236642-Electric-Loco-Shed.pdf jfkduklg
PDF
Abrasive, erosive and cavitation wear.pdf
PDF
BIO-INSPIRED ARCHITECTURE FOR PARSIMONIOUS CONVERSATIONAL INTELLIGENCE : THE ...
PPT
introduction to datamining and warehousing
PDF
Categorization of Factors Affecting Classification Algorithms Selection
PDF
UNIT no 1 INTRODUCTION TO DBMS NOTES.pdf
PPTX
introduction to high performance computing
PDF
EXPLORING LEARNING ENGAGEMENT FACTORS INFLUENCING BEHAVIORAL, COGNITIVE, AND ...
PPTX
Fundamentals of safety and accident prevention -final (1).pptx
SMART SIGNAL TIMING FOR URBAN INTERSECTIONS USING REAL-TIME VEHICLE DETECTI...
Soil Improvement Techniques Note - Rabbi
PREDICTION OF DIABETES FROM ELECTRONIC HEALTH RECORDS
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
6ME3A-Unit-II-Sensors and Actuators_Handouts.pptx
Artificial Superintelligence (ASI) Alliance Vision Paper.pdf
CURRICULAM DESIGN engineering FOR CSE 2025.pptx
A SYSTEMATIC REVIEW OF APPLICATIONS IN FRAUD DETECTION
A5_DistSysCh1.ppt_INTRODUCTION TO DISTRIBUTED SYSTEMS
Integrating Fractal Dimension and Time Series Analysis for Optimized Hyperspe...
86236642-Electric-Loco-Shed.pdf jfkduklg
Abrasive, erosive and cavitation wear.pdf
BIO-INSPIRED ARCHITECTURE FOR PARSIMONIOUS CONVERSATIONAL INTELLIGENCE : THE ...
introduction to datamining and warehousing
Categorization of Factors Affecting Classification Algorithms Selection
UNIT no 1 INTRODUCTION TO DBMS NOTES.pdf
introduction to high performance computing
EXPLORING LEARNING ENGAGEMENT FACTORS INFLUENCING BEHAVIORAL, COGNITIVE, AND ...
Fundamentals of safety and accident prevention -final (1).pptx

Estimating part 2

  • 1. ESTIMATING & COSTING ARUN RAVI.K.R Instructor, Draughtsman (Civil) Part -2
  • 2. Different Types of Sanctions01 LEARNING OBJECTIVES Different Types of Estimates02
  • 3. Estimate Sanction Before the execution Three Sanctions are Required Administrative Sanction Financial Sanction (Expenditure sanction) Technical sanction
  • 4. Administrative Sanction (A.S) For any project an approval or sanction of the competent authority of the department is necessary at the first instance with respect of the cost and work. (Sanction from Govt.) Administrative approval denotes to formal acceptance of the proposal. After A.S, the engineering department take up the work and prepares detailed design, plans and estimates and then executes the work.
  • 5. Financial Sanction (Expenditure sanction) Financial sanction means allotment of fund or money for a project from the finance department of Government
  • 6. Technical Sanction (T.S) The sanction of the detailed estimates, design calculation, quantities of works, rates and cost of the work by the competent authority of the engineering department is known as Technical Sanction.
  • 8. Preliminary or approximate or abstract estimate This type of estimate is required for preliminary studies of a project, to decide the financial position and policy for administrative sanction by the competent administrative authority. The approximate estimate is prepared with the practical knowledge and cost of the similar works. This is also accompanied with a site plan or layout plan. A percentage of about 5% to 10% is added as contingencies.
  • 9. Plinth area estimate (P.A. estimate) This is prepared on the basis of plinth area of building, the rate being deducted from the cost of similar building having similar specification, heights and construction, in the locality. Plinth area estimate is calculated by finding the plinth area of the building and multiplying by the plinth area rate.
  • 10. Cubic rate estimate This is prepared on the basis of the cubical contents of the building. The cube rate being deducted from the cost of the similar building having similar specifications and construction, in the locality. This is calculated by finding the cubical content of the building (length x breadth x height) and multiplied it by the cube rate. Cube rate estimate is most accurate than to the plinth area estimate
  • 11. Approximate quantity method In this method approximate total length of work is found in running metre and this total length multiplied by the rate per running metre of wall gives a fairly accurate cost. For this method the plan or line plan of the structure should be available.
  • 12. Detailed estimate Detailed estimate is an accurate estimate consists of the quantities of each item of works, and working the cost. The dimensions, (length, breadth and height) of each item are taken out correctly from drawing and quantities of each item are calculated. The detailed estimate is prepared in two stages. 1) Details of measurement and calculation of quantities 2) Abstract of estimate cost
  • 13. 1) Details of measurement and calculation of quantities The details of measurement of each item of work are taken out correctly from plan and drawings and quantities under each item are computed or calculated in a tabular form named as Details of Measurement Form (Table 1).
  • 14. 2) Abstract of estimate cost The cost of each item of work is calculated in a tabular form from the quantities already computed and total cost is worked out in abstract of estimate form (Table 2). The rates of different items of work are taken as per schedule of rates
  • 16. Revised estimate Revised Estimate is detailed estimate and is prepared under any one of the following circumstances. I. When the original sanctioned estimate is exceeds more than 5%. II. When the expenditure on a work exceeds of administrative sanction by more than 10% III. When there are material deviation from the original proposal, even though the cost may be met from the sanctioned amount. The revised estimate should be accompanied by a comparative statement showing the variations of each item of works
  • 17. Supplementary estimate Supplementary estimate is a detailed estimate and is prepared when additional works are required to supplement the original works, or when further developments is required during the progress of work. This is a fresh detailed estimate of the additional works in addition to the original estimate.
  • 18. Supplementary and revised estimate  When a work is partially abandoned and the remaining work is less than 95% of the original sanctioned estimate. Or  when there are material deviations and changes in the design which may cause excess or saving in the estimate, A supplementary and Revised Estimate is then prepared and fresh technical sanction of the competent authority is obtained.
  • 19. Annual repair or annual maintenance estimate (A.R. or A.M. Estimate): This estimate is a detailed estimate and is prepared to maintain the structure or work in proper order and safe condition. For building: Includes white washing, colour washing, painting, minor repairs etc. For road works: Tarring patch repairing, renewals, repairs of bridges and culvert, etc.
  • 20. Extension and improvement estimate When some changes and extensions are required to be made in the old work, the cost of which cannot be met by the annual repair/maintenance estimate, a detailed estimate is prepared for such work which is called as extension and improvement estimate.
  • 21. ARUN RAVI.K.R Instructor, Draughtsman (Civil) arunravikr@gmail.com 9447622946