TYPES OF ESTIMATES
Prepared by:-
Simarpreet Singh
A.P, Civil Engg.
ACET, Amritsar
 Contingencies – Indicates incidental expenses of
miscellaneous character which cannot be classified under any
distinct item. (3% to 5% of the estimated cost is provided to
allow for contingencies)
 Work-charged Establishment – Work-charged employees are
temporary staff whose services are terminated at the expiry
of sanctioned period but usually one month notice is given.
(1.5% to 2% of the estimated cost is added)
 Tools and Plants – Normally contractor has to arrange tools
and plants. (1% to 1.5% of estimated cost is provided)
 Centage charges or Departmental charges – Also known as
Supervision charges for works. To meet the expenses of
establishment, designing, planning, supervision etc. (10% to
15% of the estimated cost). When engineering department
takes up work of other department.
TERMINOLOGY
 Report gives brief information of whole project. It should consist of the
following :
 Brief history (with proposal)
 Necessity and feasibility of project
 Selection of site
 Survey
 Brief description of works
 Nature of soil, topography of land etc.
 Basis of design calculations
 Arrangement for water supply, sanitation and electrical installations etc.
 Roads and drains
 Temporary accommodations for staff, labour etc included in misc.
 Manner of execution
 Total cost and how to be financed
 Return or revenue income
 Rent statement
 Time of execution
TERMINOLOGY
 Sub-Head items of work – Works like earthwork, concrete
work, brick work etc. Under each sub head there are different
items of work.
 Sub-Work – Large project may consist of small buildings.
Detailed estimate of each sub-work is prepared separately.
 Schedule of Rates – It is a list of rate of various items of
works maintained by engineering department under the name
“Schedule of Rates Book”. “Road Metal Rate Book” is also
maintained by PWD.
 Administrative Sanction/ Approval – It is the formal
acceptance by the department concerned of the proposal.
After the approval, design, estimates etc. are prepared and
thereafter execution of work.
TERMINOLOGY
 Expenditure Sanction – It represents allotment of money to
meet the expenditure. It is usually accorded by Finance
Department.
 Technical Sanction – It is the sanction of the detailed
estimate, design calculation, quantities of work etc. Technical
sanction is accorded by engineering department and
execution of work is carried out thereafter.
 Quantity Survey – It means estimating of quantities of
different items of works.
 Plinth Area – It is the built up covered area of a building
measured at floor level of any storey by taking external
dimensions of the building at the floor level.
TERMINOLOGY
 Floor Area – It is obtained after deducting area of walls from the
plinth area of building. It should include:
 Door and other openings
 Intermediate pillars and supports
 Circulation Area – It is the floor area of verandahs, passages,
corridors, balconies, staircases, lift etc. which are used for
movements of persons using the building. It is further classified
into Horizontal and Vertical.
 Carpet Area – It is the useful area of the building. It is
determined after deducting :
 Circulation Area
 Sanitary Accommodations
 Kitchen, Pantry, Stores
 For office building approximate 60% to 75% of plinth area
 For residential buildings approximate 50% to 65% of plinth area
TERMINOLOGY
 Site Plan – Plan showing orientation of building, boundaries of
land, position of roads, drains, sewer line, water pipelines and
adjoining plots of lands. North direction is also shown on one
corner of site plan)
 Layout Plan –
 Plan showing proposed buildings, structures etc. showing their locations,
size and orientations.
 Roads, drains, pipe lines , electric lines, parks etc are shown.
 The boundary, main approach roads and adjoining areas are also
indicated.
 Index Plan –
 Plan is usually drawn for Roads, Irrigation, Water supply etc.
 It shows alignment with position of culverts, main outline of whole work
to give idea of the project
 For big project it is drawn with much small scale and is known as key
plan
TERMINOLOGY
 Preliminary/Appx./Abstract/Rough Cost Estimate
 Plinth Area Estimate
 Cube Rate or Cubical Content Estimate
 Appx. Quantity Method Estimate
 Detailed Estimate or Item Rate Estimate
 Revised Estimate
 Supplementary Estimate
 Supplementary and Revised Estimate
 Annual Repair or Maintenance Estimate (A.R or A.M
Estimate)
DIFFERENT TYPES OF ESTIMATES
Preliminary Estimate is prepared by various ways for different
structures as mentioned below :
 Buildings
 Per Unit Basis – Per student for schools and hostels, per class room
for schools, per bed for hospitals, per seat for cinema and theatre
halls, per tenement for residential buildings.
 Plinth area basis
 Cubic content basis
 Appx. Quantity method
 Roads and Highways – Per km basis depending upon nature of
road, width and thickness of metalling.
 Irrigation Channels
 Per km basis
 Per hectare basis (Area of land commanded)
PRELIMINARY ESTIMATE
 Bridges and Culverts – Per running meter of span depending
upon type of structure, type and depth of foundation.
 Sewerage and Water Supply Project
 Per head of population served
 Per hectare basis (Area covered)
 Over Head water Tank – Per liter or per gallon of tank
depending upon type of structure and height of tank.
PRELIMINARY ESTIMATE (Ctd.)
 P.A. is approximate estimate
 Plinth area should be calculated for covered area by taking
external dimensions of the building at the floor level
 Courtyard and other open area should not be included
 For multi storeyed building Plinth Area for each storey is
determined separately.
 Approximate total plinth area may be calculated by adding 30
to 40% of the already calculated area for walls, circulation
and waste etc.
 Plinth area rate is known from cost of similar building in the
locality.
PLINTH AREA ESTIMATE (P.A. ESTIMATE)
 Cube rate estimate is again approximate estimate
 Cubical content of the building is determined by multiplying
length, breadth and height of the building.
 External length and breadth at the floor level are calculated
for the purpose
 Height should be taken from the floor level to the top of roof.
 For multi storeyed building height is taken from floor level of
one storey to top of next higher floor.
 Cube rate estimate is more accurate as compared to the
plinth area estimate.
CUBE RATE ESTIMATE
 Structure divided into two parts – (i) Foundation including
plinth (ii) Superstructure
 Total length of walls is found out.
 To find running meter rate of foundation, appx. quantities of
various items are calculated per running meter
 Similarly for superstructure appx. Quantities of brickwork,
roof, flooring etc is calculated per running meter.
APPROXIMATE QUANTITY METHOD
ESTIMATE
 It is the accurate estimate prepared by working out quantities of
each items of work.
 It is prepared in two stages –
 Details of measurements and calculation of quantities.
 Abstract of estimated cost – 3% to 5% of estimated cost is added to
cover miscellaneous expenditure
 Detailed estimate is prepared work-wise.
 Detailed estimate consists of –
 Report
 General Specifications
 Detailed specifications
 Drawings
 Calculation and designs
 Analysis of rates
 Detailed estimate is prepared for technical sanction, for
arranging contract and for execution of project.
DETAILED ESTIMATE
 Revised estimate is prepared when original sanctioned
estimate is likely to exceed more than 5%.
 When expenditure on work is likely to exceed amount of
administrative sanction by more than 10%
 When there are material deviation from original proposal even
though cost may be met from sanctioned cost.
 It is accompanied by comparative statement showing
variations in each item of works and reason for the same.
REVISED ESTIMATE
 It is the fresh detailed estimate of the additional works in
addition to the original estimate.
 It is required when further development is required during the
progress of work.
 Abstract should show the amount of original estimate and
total amount including supplementary amount.
SUPPLEMENTARY ESTIMATE
 When a work is partially abandoned and estimated cost of
remaining work is less than 95% of original sanctioned
estimate.
 When there are material deviations and changes in the design
 If at any time before or during the execution of work, it is
found that original estimate is excessive then divisional
officer may sanction a revised estimate of reduced amount.
SUPPLEMENTARY AND REVISED
ESTIMATE
 It is prepared to maintain structure or work in proper order
and safe condition
 For buildings like white washing, painting, minor repairs etc.
 For road works A.R. estimate provides for patch repairing,
repairs of bridges and culverts etc.
ANNUAL REPAIR OR MAINTENANCE
ESTIMATE (A.R / A.M ESTIMATE)
Any Questions?
THANK YOU

More Related Content

PPTX
Estimating and costing
PPTX
Estimating & Costing - I
PPTX
Estimation and Costing
PPT
Estimation
PDF
Estimating part 2
PPTX
estimation,its types and methods
PPTX
ESTIMATING AND COSTING
PPT
Estimation (power point)
Estimating and costing
Estimating & Costing - I
Estimation and Costing
Estimation
Estimating part 2
estimation,its types and methods
ESTIMATING AND COSTING
Estimation (power point)

What's hot (20)

PPTX
Approximate estimate
PPTX
Rate analysis
PPTX
Estimation and Costing - Contracts
PPTX
Estimating, administrative approval, technical sanction, budget provision
PPTX
Rate analysis in civil engineering
PPTX
Approximate estimate
PPTX
Fundamentals of Estimating and Costing
PPSX
Design of steel structures Introduction
PPTX
Analysis of rates
PDF
SPECIFICATION AND ESTIMATION
PDF
Estimating and-costing
PPTX
Building by laws
PPT
Roof truss
PPTX
Introduction to estimation
PPTX
rate analysis
PPTX
Types of estimate
PPTX
Industrial building
PDF
estimation and quantity surveying
PPTX
IMPORTANCE & PURPOSES OF SPECIFICATION
PPTX
Types of formwork
Approximate estimate
Rate analysis
Estimation and Costing - Contracts
Estimating, administrative approval, technical sanction, budget provision
Rate analysis in civil engineering
Approximate estimate
Fundamentals of Estimating and Costing
Design of steel structures Introduction
Analysis of rates
SPECIFICATION AND ESTIMATION
Estimating and-costing
Building by laws
Roof truss
Introduction to estimation
rate analysis
Types of estimate
Industrial building
estimation and quantity surveying
IMPORTANCE & PURPOSES OF SPECIFICATION
Types of formwork
Ad

Viewers also liked (19)

PPTX
Building estimation methods
PPTX
Point Estimation
PPTX
Point and Interval Estimation
PDF
Estimating and-costing book
PPTX
Theory of estimation
PPTX
Preliminary estimate
PDF
Enlistment rules2014 07
PPT
WORKS MANAGEMENT IN CPWD PART-I
PDF
Nrega Technical Aspects Of Execution Of Works By S.Anwar Hussain
PPTX
Introduction to Civil Engineering (Harsh Gupta)
PPTX
Estimation of a residential building
PPT
Probability Distributions
DOCX
Analysis of rates for labour and material
PPTX
Estimation and quantity surveying
PPTX
QUANTITY SURVEYING
PPT
Estimation and costing
PPT
Rates Analysis For Calculating Material and Labour for building works
PPT
Probability concept and Probability distribution
PPTX
RESEARCH METHOD - SAMPLING
Building estimation methods
Point Estimation
Point and Interval Estimation
Estimating and-costing book
Theory of estimation
Preliminary estimate
Enlistment rules2014 07
WORKS MANAGEMENT IN CPWD PART-I
Nrega Technical Aspects Of Execution Of Works By S.Anwar Hussain
Introduction to Civil Engineering (Harsh Gupta)
Estimation of a residential building
Probability Distributions
Analysis of rates for labour and material
Estimation and quantity surveying
QUANTITY SURVEYING
Estimation and costing
Rates Analysis For Calculating Material and Labour for building works
Probability concept and Probability distribution
RESEARCH METHOD - SAMPLING
Ad

Similar to Types of estimates (20)

PPTX
Estimation and Costing
PDF
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
PDF
ECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdf
PPTX
specification estimation and valuation of a building
PPTX
2# types of estimate
PPTX
Quantity Survey and Estimation basic terms
PPTX
Estimating and costing I Chapter 2.pptx
PPTX
ECV All Chapters
PDF
ESTIMATION_AND_COSTING assignmentt-1.pdf
PPTX
Types of estimate - Estimation, Costing and Valuation Engineering
PDF
Estimation and Costing course lecture 1.pdf
PPT
lecture ppt for contract administration and governing
 
PPTX
ESTIMATION AND COSTING AND SPECIFICATION.pptx
PPTX
IV -I - EQS - .pptx
DOC
Aiet e&c lecture_notes
DOC
type of cost Estimation
PPTX
Estimation Costing and Valuation Unit 1 to Unit 6
PDF
Unit 1.pdf.engineering civil work of technology
DOCX
Unit 1 - General Items used for building
Estimation and Costing
0111CE702-ESTIMATION AND QUANTITY SURVEYING VII SEMESTER E-LEARNING MATERIAL
ECONOMICS%20FOR%20ENGINEERS%20%5BHM-EE601%5D_removed.pdf
specification estimation and valuation of a building
2# types of estimate
Quantity Survey and Estimation basic terms
Estimating and costing I Chapter 2.pptx
ECV All Chapters
ESTIMATION_AND_COSTING assignmentt-1.pdf
Types of estimate - Estimation, Costing and Valuation Engineering
Estimation and Costing course lecture 1.pdf
lecture ppt for contract administration and governing
 
ESTIMATION AND COSTING AND SPECIFICATION.pptx
IV -I - EQS - .pptx
Aiet e&c lecture_notes
type of cost Estimation
Estimation Costing and Valuation Unit 1 to Unit 6
Unit 1.pdf.engineering civil work of technology
Unit 1 - General Items used for building

Recently uploaded (20)

PDF
Chapter 2 Heredity, Prenatal Development, and Birth.pdf
PDF
01-Introduction-to-Information-Management.pdf
PDF
Pre independence Education in Inndia.pdf
PDF
BÀI TẬP BỔ TRỢ 4 KỸ NĂNG TIẾNG ANH 9 GLOBAL SUCCESS - CẢ NĂM - BÁM SÁT FORM Đ...
PDF
Anesthesia in Laparoscopic Surgery in India
PPTX
PPH.pptx obstetrics and gynecology in nursing
PDF
VCE English Exam - Section C Student Revision Booklet
PPTX
Cell Structure & Organelles in detailed.
PDF
ANTIBIOTICS.pptx.pdf………………… xxxxxxxxxxxxx
PPTX
Renaissance Architecture: A Journey from Faith to Humanism
PDF
STATICS OF THE RIGID BODIES Hibbelers.pdf
PDF
Mark Klimek Lecture Notes_240423 revision books _173037.pdf
PDF
Supply Chain Operations Speaking Notes -ICLT Program
PDF
O5-L3 Freight Transport Ops (International) V1.pdf
PDF
2.FourierTransform-ShortQuestionswithAnswers.pdf
PDF
Basic Mud Logging Guide for educational purpose
PPTX
BOWEL ELIMINATION FACTORS AFFECTING AND TYPES
PPTX
PPT- ENG7_QUARTER1_LESSON1_WEEK1. IMAGERY -DESCRIPTIONS pptx.pptx
PDF
Module 4: Burden of Disease Tutorial Slides S2 2025
PPTX
Microbial diseases, their pathogenesis and prophylaxis
Chapter 2 Heredity, Prenatal Development, and Birth.pdf
01-Introduction-to-Information-Management.pdf
Pre independence Education in Inndia.pdf
BÀI TẬP BỔ TRỢ 4 KỸ NĂNG TIẾNG ANH 9 GLOBAL SUCCESS - CẢ NĂM - BÁM SÁT FORM Đ...
Anesthesia in Laparoscopic Surgery in India
PPH.pptx obstetrics and gynecology in nursing
VCE English Exam - Section C Student Revision Booklet
Cell Structure & Organelles in detailed.
ANTIBIOTICS.pptx.pdf………………… xxxxxxxxxxxxx
Renaissance Architecture: A Journey from Faith to Humanism
STATICS OF THE RIGID BODIES Hibbelers.pdf
Mark Klimek Lecture Notes_240423 revision books _173037.pdf
Supply Chain Operations Speaking Notes -ICLT Program
O5-L3 Freight Transport Ops (International) V1.pdf
2.FourierTransform-ShortQuestionswithAnswers.pdf
Basic Mud Logging Guide for educational purpose
BOWEL ELIMINATION FACTORS AFFECTING AND TYPES
PPT- ENG7_QUARTER1_LESSON1_WEEK1. IMAGERY -DESCRIPTIONS pptx.pptx
Module 4: Burden of Disease Tutorial Slides S2 2025
Microbial diseases, their pathogenesis and prophylaxis

Types of estimates

  • 1. TYPES OF ESTIMATES Prepared by:- Simarpreet Singh A.P, Civil Engg. ACET, Amritsar
  • 2.  Contingencies – Indicates incidental expenses of miscellaneous character which cannot be classified under any distinct item. (3% to 5% of the estimated cost is provided to allow for contingencies)  Work-charged Establishment – Work-charged employees are temporary staff whose services are terminated at the expiry of sanctioned period but usually one month notice is given. (1.5% to 2% of the estimated cost is added)  Tools and Plants – Normally contractor has to arrange tools and plants. (1% to 1.5% of estimated cost is provided)  Centage charges or Departmental charges – Also known as Supervision charges for works. To meet the expenses of establishment, designing, planning, supervision etc. (10% to 15% of the estimated cost). When engineering department takes up work of other department. TERMINOLOGY
  • 3.  Report gives brief information of whole project. It should consist of the following :  Brief history (with proposal)  Necessity and feasibility of project  Selection of site  Survey  Brief description of works  Nature of soil, topography of land etc.  Basis of design calculations  Arrangement for water supply, sanitation and electrical installations etc.  Roads and drains  Temporary accommodations for staff, labour etc included in misc.  Manner of execution  Total cost and how to be financed  Return or revenue income  Rent statement  Time of execution TERMINOLOGY
  • 4.  Sub-Head items of work – Works like earthwork, concrete work, brick work etc. Under each sub head there are different items of work.  Sub-Work – Large project may consist of small buildings. Detailed estimate of each sub-work is prepared separately.  Schedule of Rates – It is a list of rate of various items of works maintained by engineering department under the name “Schedule of Rates Book”. “Road Metal Rate Book” is also maintained by PWD.  Administrative Sanction/ Approval – It is the formal acceptance by the department concerned of the proposal. After the approval, design, estimates etc. are prepared and thereafter execution of work. TERMINOLOGY
  • 5.  Expenditure Sanction – It represents allotment of money to meet the expenditure. It is usually accorded by Finance Department.  Technical Sanction – It is the sanction of the detailed estimate, design calculation, quantities of work etc. Technical sanction is accorded by engineering department and execution of work is carried out thereafter.  Quantity Survey – It means estimating of quantities of different items of works.  Plinth Area – It is the built up covered area of a building measured at floor level of any storey by taking external dimensions of the building at the floor level. TERMINOLOGY
  • 6.  Floor Area – It is obtained after deducting area of walls from the plinth area of building. It should include:  Door and other openings  Intermediate pillars and supports  Circulation Area – It is the floor area of verandahs, passages, corridors, balconies, staircases, lift etc. which are used for movements of persons using the building. It is further classified into Horizontal and Vertical.  Carpet Area – It is the useful area of the building. It is determined after deducting :  Circulation Area  Sanitary Accommodations  Kitchen, Pantry, Stores  For office building approximate 60% to 75% of plinth area  For residential buildings approximate 50% to 65% of plinth area TERMINOLOGY
  • 7.  Site Plan – Plan showing orientation of building, boundaries of land, position of roads, drains, sewer line, water pipelines and adjoining plots of lands. North direction is also shown on one corner of site plan)  Layout Plan –  Plan showing proposed buildings, structures etc. showing their locations, size and orientations.  Roads, drains, pipe lines , electric lines, parks etc are shown.  The boundary, main approach roads and adjoining areas are also indicated.  Index Plan –  Plan is usually drawn for Roads, Irrigation, Water supply etc.  It shows alignment with position of culverts, main outline of whole work to give idea of the project  For big project it is drawn with much small scale and is known as key plan TERMINOLOGY
  • 8.  Preliminary/Appx./Abstract/Rough Cost Estimate  Plinth Area Estimate  Cube Rate or Cubical Content Estimate  Appx. Quantity Method Estimate  Detailed Estimate or Item Rate Estimate  Revised Estimate  Supplementary Estimate  Supplementary and Revised Estimate  Annual Repair or Maintenance Estimate (A.R or A.M Estimate) DIFFERENT TYPES OF ESTIMATES
  • 9. Preliminary Estimate is prepared by various ways for different structures as mentioned below :  Buildings  Per Unit Basis – Per student for schools and hostels, per class room for schools, per bed for hospitals, per seat for cinema and theatre halls, per tenement for residential buildings.  Plinth area basis  Cubic content basis  Appx. Quantity method  Roads and Highways – Per km basis depending upon nature of road, width and thickness of metalling.  Irrigation Channels  Per km basis  Per hectare basis (Area of land commanded) PRELIMINARY ESTIMATE
  • 10.  Bridges and Culverts – Per running meter of span depending upon type of structure, type and depth of foundation.  Sewerage and Water Supply Project  Per head of population served  Per hectare basis (Area covered)  Over Head water Tank – Per liter or per gallon of tank depending upon type of structure and height of tank. PRELIMINARY ESTIMATE (Ctd.)
  • 11.  P.A. is approximate estimate  Plinth area should be calculated for covered area by taking external dimensions of the building at the floor level  Courtyard and other open area should not be included  For multi storeyed building Plinth Area for each storey is determined separately.  Approximate total plinth area may be calculated by adding 30 to 40% of the already calculated area for walls, circulation and waste etc.  Plinth area rate is known from cost of similar building in the locality. PLINTH AREA ESTIMATE (P.A. ESTIMATE)
  • 12.  Cube rate estimate is again approximate estimate  Cubical content of the building is determined by multiplying length, breadth and height of the building.  External length and breadth at the floor level are calculated for the purpose  Height should be taken from the floor level to the top of roof.  For multi storeyed building height is taken from floor level of one storey to top of next higher floor.  Cube rate estimate is more accurate as compared to the plinth area estimate. CUBE RATE ESTIMATE
  • 13.  Structure divided into two parts – (i) Foundation including plinth (ii) Superstructure  Total length of walls is found out.  To find running meter rate of foundation, appx. quantities of various items are calculated per running meter  Similarly for superstructure appx. Quantities of brickwork, roof, flooring etc is calculated per running meter. APPROXIMATE QUANTITY METHOD ESTIMATE
  • 14.  It is the accurate estimate prepared by working out quantities of each items of work.  It is prepared in two stages –  Details of measurements and calculation of quantities.  Abstract of estimated cost – 3% to 5% of estimated cost is added to cover miscellaneous expenditure  Detailed estimate is prepared work-wise.  Detailed estimate consists of –  Report  General Specifications  Detailed specifications  Drawings  Calculation and designs  Analysis of rates  Detailed estimate is prepared for technical sanction, for arranging contract and for execution of project. DETAILED ESTIMATE
  • 15.  Revised estimate is prepared when original sanctioned estimate is likely to exceed more than 5%.  When expenditure on work is likely to exceed amount of administrative sanction by more than 10%  When there are material deviation from original proposal even though cost may be met from sanctioned cost.  It is accompanied by comparative statement showing variations in each item of works and reason for the same. REVISED ESTIMATE
  • 16.  It is the fresh detailed estimate of the additional works in addition to the original estimate.  It is required when further development is required during the progress of work.  Abstract should show the amount of original estimate and total amount including supplementary amount. SUPPLEMENTARY ESTIMATE
  • 17.  When a work is partially abandoned and estimated cost of remaining work is less than 95% of original sanctioned estimate.  When there are material deviations and changes in the design  If at any time before or during the execution of work, it is found that original estimate is excessive then divisional officer may sanction a revised estimate of reduced amount. SUPPLEMENTARY AND REVISED ESTIMATE
  • 18.  It is prepared to maintain structure or work in proper order and safe condition  For buildings like white washing, painting, minor repairs etc.  For road works A.R. estimate provides for patch repairing, repairs of bridges and culverts etc. ANNUAL REPAIR OR MAINTENANCE ESTIMATE (A.R / A.M ESTIMATE)