Prof.Tatikonda G. S.
 Approximate estimate is prepared to decide
the financial aspect, administrative approval
for sending the proposal and appraisal of
various civil engineering works.
 The approximate estimate is prepared from
the practical knowledge and cost of similar
works.The estimate is accompanied by a
report duly explaining necessity and utility of
the project and with a site or layout plan.
 To give a rough idea of the probable expenditure: At the early
stages of the development of a project it is necessary to ensure
whether the project can be financed. A rough idea of the probable
expenditure has to be obtained and if this appears feasible, then
further details may be considered.
 Administrative approval: In the case of government and other
public works, proper sanction has to be obtained for allocating the
expenditure required for the detailed investigations and
preparation of plans and estimates.This sanction is given based on
approximate cost estimating method.
 Valuation and rent fixation: Sometimes it is required to estimate
the cost of an existing structure, for one or more of the following
reasons: for sale or purchase, for rent fixing, for framing tax
schedules, or for insurance requirement. In these cases the
approximate methods are adopted.
 Service unit method
 Plinth area rate method
 Cubical content method
 Typical bay method
 Approximate quantity method
Buildings are constructed to serve a specific purpose.
For example hospitals are designed to accommodate
certain number of beds. Each bed is then considered
a service unit. Hotels are designed to accommodate
certain number of guest rooms. each guest room is
considered a service unit. Same applies to offices,
residential houses, .. etc.
Whenever a building is constructed the Engineer or the
architect keeps the record of the place, actual cost,
number of service units, and the year of construction.
From this record, it is possible to work out the cost per
service unit.
Approximate Estimate can be calculated by
multiplying no. of service unit and Rate of per service unit.
In this methodThe built up area of the
proposed structure is worked out, and then
multiplied by a suitable rate.
This rate of construction per square meter
of built up area is worked out by dividing the
known cost of construction of a similar
building by the built up of that building.
App. Estimate = Built up area of proposed
structure X Rate per Sq m of built up area
This method is more accurate than the
square meter of floor area method. because
the depth of foundations and the height of
the structure above the ground level are the
additional dimensions taken into
consideration.
App. Estimate = volume of buildings x
rate/ unit volume.
The calculation of Sub structure and super
structure is done separately
 This bay method is applicable in garages,
factory, and railway platform where identical
structures are visible.
 Bay in a construction term means a
compartment of a building Or Space between
two supports in building.
 The cost of one bay is calculated first and it is
multiplied by the number of bays.
 App. Estimate = No. of Bays X Rate per Bay
For estimate of a railway project main
work are foundation embankment in cutting
and banking, bridges, culverts, level, and road
crossing, fencing etc are prepared by
knowing the cost per Km of recently
constructed similar structure.
App. Estimate = length of structure in Km X
Rate per Km

More Related Content

PPTX
Introduction to estimation
PPTX
Approximate estimate
PPTX
Estimation Costing and Valuation Unit 1
PPTX
Classification of bridges
PDF
Contribution of Peter F Drucker
PPTX
ONE WAY SLAB DESIGN
PPTX
Travel ppt
PPT
Elements&Principles Of Interior Design
Introduction to estimation
Approximate estimate
Estimation Costing and Valuation Unit 1
Classification of bridges
Contribution of Peter F Drucker
ONE WAY SLAB DESIGN
Travel ppt
Elements&Principles Of Interior Design

What's hot (20)

PPTX
Analysis of rates
PPTX
Estimating, administrative approval, technical sanction, budget provision
PPTX
Rate analysis
PPTX
Rate analysis in civil engineering
PPTX
civil engineering-Contracts
PPTX
Estimating and costing
PDF
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
PPTX
Rate analysis brief
PPTX
Contracts and-tenders
PPTX
Estimating & Costing - I
PPTX
Construction Project Management
PPTX
Types of estimates
PPTX
Types of Contract in Construction Management
PPTX
Earthwork and excavation
PPTX
estimation,its types and methods
PPTX
Types of resources in civil engineering field
PPTX
Construction Management & Equipments
PDF
Valuation
PPTX
Mechanized construction
PPTX
rate analysis
Analysis of rates
Estimating, administrative approval, technical sanction, budget provision
Rate analysis
Rate analysis in civil engineering
civil engineering-Contracts
Estimating and costing
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
Rate analysis brief
Contracts and-tenders
Estimating & Costing - I
Construction Project Management
Types of estimates
Types of Contract in Construction Management
Earthwork and excavation
estimation,its types and methods
Types of resources in civil engineering field
Construction Management & Equipments
Valuation
Mechanized construction
rate analysis
Ad

Similar to Approximate estimate (20)

PPTX
Chapter 2 Approximate Estimates.pptx
DOC
type of cost Estimation
PPTX
Estimation and Costing
PDF
Project cost management
PDF
SPECIFICATION AND ESTIMATION
PPTX
Cost Estimation for civil engineering .pptx
PDF
EEEC pdf.pdf
DOCX
Construction Planning and Scheduling of Residential Building by MS Project by...
PDF
Constructiion cost estimating 2017
PPTX
Quantity Survey and Estimation basic terms
DOCX
Unit 1 - General Items used for building
PPTX
Lec05.pptx
PDF
Guideline-for-the-preparation-of-Total Cost.pdf
PDF
Estimating part 2
PPTX
CHAPTER-3 COST ESTABLISHMEN for civil engineeringT.pptx
PPTX
Types of estimate
PDF
Estimation and Costing course lecture 1.pdf
PDF
Lec.1 Introduction to Estimation
DOCX
Project selection and estimating technique spencer o’briencpmgt303
Chapter 2 Approximate Estimates.pptx
type of cost Estimation
Estimation and Costing
Project cost management
SPECIFICATION AND ESTIMATION
Cost Estimation for civil engineering .pptx
EEEC pdf.pdf
Construction Planning and Scheduling of Residential Building by MS Project by...
Constructiion cost estimating 2017
Quantity Survey and Estimation basic terms
Unit 1 - General Items used for building
Lec05.pptx
Guideline-for-the-preparation-of-Total Cost.pdf
Estimating part 2
CHAPTER-3 COST ESTABLISHMEN for civil engineeringT.pptx
Types of estimate
Estimation and Costing course lecture 1.pdf
Lec.1 Introduction to Estimation
Project selection and estimating technique spencer o’briencpmgt303
Ad

Recently uploaded (20)

PDF
Empowerment Technology for Senior High School Guide
PDF
IGGE1 Understanding the Self1234567891011
PDF
Hazard Identification & Risk Assessment .pdf
PDF
Practical Manual AGRO-233 Principles and Practices of Natural Farming
DOC
Soft-furnishing-By-Architect-A.F.M.Mohiuddin-Akhand.doc
PPTX
ELIAS-SEZIURE AND EPilepsy semmioan session.pptx
PPTX
B.Sc. DS Unit 2 Software Engineering.pptx
PDF
David L Page_DCI Research Study Journey_how Methodology can inform one's prac...
PDF
RTP_AR_KS1_Tutor's Guide_English [FOR REPRODUCTION].pdf
PDF
AI-driven educational solutions for real-life interventions in the Philippine...
PDF
Weekly quiz Compilation Jan -July 25.pdf
PDF
Trump Administration's workforce development strategy
PPTX
Introduction to Building Materials
PPTX
20th Century Theater, Methods, History.pptx
PDF
OBE - B.A.(HON'S) IN INTERIOR ARCHITECTURE -Ar.MOHIUDDIN.pdf
PDF
CISA (Certified Information Systems Auditor) Domain-Wise Summary.pdf
PDF
FOISHS ANNUAL IMPLEMENTATION PLAN 2025.pdf
PDF
A GUIDE TO GENETICS FOR UNDERGRADUATE MEDICAL STUDENTS
PDF
MBA _Common_ 2nd year Syllabus _2021-22_.pdf
PPTX
History, Philosophy and sociology of education (1).pptx
Empowerment Technology for Senior High School Guide
IGGE1 Understanding the Self1234567891011
Hazard Identification & Risk Assessment .pdf
Practical Manual AGRO-233 Principles and Practices of Natural Farming
Soft-furnishing-By-Architect-A.F.M.Mohiuddin-Akhand.doc
ELIAS-SEZIURE AND EPilepsy semmioan session.pptx
B.Sc. DS Unit 2 Software Engineering.pptx
David L Page_DCI Research Study Journey_how Methodology can inform one's prac...
RTP_AR_KS1_Tutor's Guide_English [FOR REPRODUCTION].pdf
AI-driven educational solutions for real-life interventions in the Philippine...
Weekly quiz Compilation Jan -July 25.pdf
Trump Administration's workforce development strategy
Introduction to Building Materials
20th Century Theater, Methods, History.pptx
OBE - B.A.(HON'S) IN INTERIOR ARCHITECTURE -Ar.MOHIUDDIN.pdf
CISA (Certified Information Systems Auditor) Domain-Wise Summary.pdf
FOISHS ANNUAL IMPLEMENTATION PLAN 2025.pdf
A GUIDE TO GENETICS FOR UNDERGRADUATE MEDICAL STUDENTS
MBA _Common_ 2nd year Syllabus _2021-22_.pdf
History, Philosophy and sociology of education (1).pptx

Approximate estimate

  • 2.  Approximate estimate is prepared to decide the financial aspect, administrative approval for sending the proposal and appraisal of various civil engineering works.  The approximate estimate is prepared from the practical knowledge and cost of similar works.The estimate is accompanied by a report duly explaining necessity and utility of the project and with a site or layout plan.
  • 3.  To give a rough idea of the probable expenditure: At the early stages of the development of a project it is necessary to ensure whether the project can be financed. A rough idea of the probable expenditure has to be obtained and if this appears feasible, then further details may be considered.  Administrative approval: In the case of government and other public works, proper sanction has to be obtained for allocating the expenditure required for the detailed investigations and preparation of plans and estimates.This sanction is given based on approximate cost estimating method.  Valuation and rent fixation: Sometimes it is required to estimate the cost of an existing structure, for one or more of the following reasons: for sale or purchase, for rent fixing, for framing tax schedules, or for insurance requirement. In these cases the approximate methods are adopted.
  • 4.  Service unit method  Plinth area rate method  Cubical content method  Typical bay method  Approximate quantity method
  • 5. Buildings are constructed to serve a specific purpose. For example hospitals are designed to accommodate certain number of beds. Each bed is then considered a service unit. Hotels are designed to accommodate certain number of guest rooms. each guest room is considered a service unit. Same applies to offices, residential houses, .. etc. Whenever a building is constructed the Engineer or the architect keeps the record of the place, actual cost, number of service units, and the year of construction. From this record, it is possible to work out the cost per service unit. Approximate Estimate can be calculated by multiplying no. of service unit and Rate of per service unit.
  • 6. In this methodThe built up area of the proposed structure is worked out, and then multiplied by a suitable rate. This rate of construction per square meter of built up area is worked out by dividing the known cost of construction of a similar building by the built up of that building. App. Estimate = Built up area of proposed structure X Rate per Sq m of built up area
  • 7. This method is more accurate than the square meter of floor area method. because the depth of foundations and the height of the structure above the ground level are the additional dimensions taken into consideration. App. Estimate = volume of buildings x rate/ unit volume. The calculation of Sub structure and super structure is done separately
  • 8.  This bay method is applicable in garages, factory, and railway platform where identical structures are visible.  Bay in a construction term means a compartment of a building Or Space between two supports in building.  The cost of one bay is calculated first and it is multiplied by the number of bays.  App. Estimate = No. of Bays X Rate per Bay
  • 9. For estimate of a railway project main work are foundation embankment in cutting and banking, bridges, culverts, level, and road crossing, fencing etc are prepared by knowing the cost per Km of recently constructed similar structure. App. Estimate = length of structure in Km X Rate per Km