SlideShare a Scribd company logo
https://www.linkedin.com/in/kailashchander, +91 9950461810
Rate Analysis
Quantity Surveying, Estimation & Valuation
KC associates
https://www.linkedin.com/in/kailashchander, +91 9950461810
Rate Analysis
Content
• Purpose of Rate Analysis
• Items of Rate Analysis
• Table for Rate Analysis
• Quantity of Coarse, Fine and Cement
• Estimation of Labour
• Task or out-turn work
• Labour output in 8 working hours
• Rate of Material and Labour
https://www.linkedin.com/in/kailashchander, +91 9950461810
What is Rate Analysis
• The basis of arriving at correct or reasonable rate
per unit work, for a particular item following its
specification and detailed survey of materials,
labour, equipment etc. i.e. To reach Rate of
Concrete Per CUM, individual cost of followings
are considered:
a) Materials(cement, sand, agg, steel, admixture)
used for per cum concrete
b) Labour (mason, labor, carpenter) per cum concrete
c) Equipment (vibrator, pump, transit mixer, batching
plant cost) per cum concrete
https://www.linkedin.com/in/kailashchander, +91 9950461810
Purpose of Rate Analysis
• To determine the current rate per unit of an item at
the locality
• To examine the viability of rates offered by
contractors.
• To calculate labor strength & equipment required for
Project Planning.
• To fix up labor contract rates.
Purpose
Current
Rate
Offered
Rate
Quantities
Contract
Rates
https://www.linkedin.com/in/kailashchander, +91 9950461810
How to fix up rate per Unit of an item?
• Following subheads are estimated and based on
their summation, rate per unit of an item is
arrived:-
Rate Analysis Considerations
Quantity of
Materials and
Cost
Labour Cost
Equipment, Tools
& Plant Cost
Overhead or
Establishment
Charges
Profit
https://www.linkedin.com/in/kailashchander, +91 9950461810
Rate Analysis
How to fix up rate per Unit of an item?
• Quantity of Materials and Cost:-
– As per detailed specification, quantity of an item is calculated.
Based on market rates, per unit rate is arrived.
– Following cost too is considered:-
• Freight & transportation, including loading & unloading
• Taxes & insurance
• Profit on Cement, steel stone chips and bitumen not included if
supplied departmentally.
• Labour Cost
– Number and wages of different categories of laborers, (skilled
& unskilled) namely mason or carpenter, mazdoor for per unit
of item to execute at site.
– These numbers are multiplied by market rate and labour cost
is arrived per UNIT of item.
https://www.linkedin.com/in/kailashchander, +91 9950461810
How to fix up rate per Unit of an item?
• Equipment, Tools and Plant Cost
– Equipment for General use as per item
– Example concrete mixer as per unit of concrete
– Certain tools and plants are difficult to allocate as per the
specific item hence their cost are considered in
establishment charges
– For special equipment extra 1% to 1.5% (purchasing) of
estimated cost is provided.
• Overhead & Establishment Charges
– Office Rent, Depreciation on equipments
– Salaries of office staff, postage, lighting, travelling,
telephone account
– This is actually 2.5% up to 5%
– Overhead charges increases with delay in project.
https://www.linkedin.com/in/kailashchander, +91 9950461810
How to fix up rate per Unit of an item?
• Overheads and Establishment Charges
– There are 2 types of Overheads
General Overheads (Recurring known
expenditures)
• Office Rent
• Salaries of office staff
• Stationary items, printing, postages,
repairs
• Telephone and electric Bills
• Travelling
Job Overheads (incur in construction)
• Salaries of technical or non-technical staff
• Temporary Sheds
• Go-Down rent
• Small tools, planks, ladders, ropes, hand tools for workmen
• Repairs & depreciation for tools and plant
• Lighting at site
• Mobilization of establishment
• Public Relations
• Labor Welfare & safety
• Workmen compensation, insurance
• Interest on investment
• Theft or loss
https://www.linkedin.com/in/kailashchander, +91 9950461810
Profit
• Generally 10% profit is considered for ordinary
contracts, after allocating all charges of
equipments, establishments.
• For small jobs, profit is 15%
• For large projects Profit is 8%
https://www.linkedin.com/in/kailashchander, +91 9950461810
Factoring Affecting the rate analysis
• Specification of the item
– Quality of Materials
– Proportion of materials
– Method of construction
– Protection of Work
• Rate of materials for item of work up to worksite
• Daily wages of labourer
– With different categories
– With localities
– As per outputs
• The range of lead and lift require for deposition of materials
• Percentage charge for overheads
• Possibility of theft of losses
• Range of profit
• Availability of water connection
https://www.linkedin.com/in/kailashchander, +91 9950461810
Quantity of Coarse Aggregate, Sand and Cement
for various proportion
• Quantities shall be calculated for 10 cum of
concrete.
• Exact quantities of ingredients cannot be calculated
for 10 cum of concrete so there is a thumb rule
• To calculate dry ingredients for 10 cum of concrete.
Each proportional quantity for 10 cum of concrete is
multiplied with 15.4 up to 15.7
• This 15.4 factor is due to existence of voids.
• Example: Findout qty of cement, sand and stone
chips in 1:2:4
– Cement : 1/(1+2+4) x 15.4 = 2.2cum = 3168 kg = 64 bags
– Sand : 2/(1+2+4) x 15.4 = 4.4 cum = 7.25 tons
– Stone Chips : 8.8 cum = 18 tons
https://www.linkedin.com/in/kailashchander, +91 9950461810
• Calculate quantities of Cement, sand and stone chips
for 10 cum concrete (variation of 5% is allowed)
Volumetric
Proportion
Cement Dry sand
Stone chips (20 -
6 mm)
cum bags cum cum
1:1:2 3.88 112.3 3.88 7.8
1:1.5:3 2.80 81.2 4.20 8.4
1:2:4 2.20 63.8 4.40 8.8
1:2.5:5 1.81 52.5 4.53 9.1
1:3:6 1.57 45.5 4.71 9.4
1:4:8 1.20 34.8 4.80 9.6
1:5:10 0.98 28.3 4.88 9.8
0.00
2.00
4.00
6.00
8.00
10.00
12.00
1:1:2 1:1.5:3 1:2:4 1:2.5:5 1:3:6 1:4:8 1:5:10
Quantities as per ratio
Cement Dry sand Stone chips (20 -6 mm)
Quantity of Coarse Aggregate, Sand and Cement
for various proportion
https://www.linkedin.com/in/kailashchander, +91 9950461810
Material Estimation:
Continue….
Quantity of Materials required for different items of works
Name of work Per Unit Materials Quantity
Brickwork 10 cum 19x9x9 5000nos
Dry cement mortar 3.5cum
Half brick 100 sqm 19x9x9 5000nos
Random rubble masonry 10 cum stone 12.5cum
Dry cement mortar 4.2cum
Ashlar masonry 10 cum stone 12.5cum
Brick soling 10 sqm 19x9x9 425nos
Brick on edge floor 10 sqm 19x9x9 500nos
dry cement mortar 3.5cum
20 mm DPC 100 sqm cement 27bags
sand 1.8cum
water proof 27kg
Reinforced Brick work 10 cum Bricks 4500nos
Dry cement mortar 4.8cum
Precast terrazo tiles 100 sqm Tiles 110sqm
Cement 13bags
Pigment 46kgs
Lime Terracing on roof 100 sqm Lime 2.1cum
2:2:7 and 7.5 cm thick Surkhi 2.1cum
Brick ballast 7.5cum
Rani ganj tile roofing 10sqm Tiles 124nos
cement mortar 0.15cum
https://www.linkedin.com/in/kailashchander, +91 9950461810
Material Estimation:Quantity of Materials required for different items of works
Name of work Per Unit Materials Quantity
CGI sheet roofing 10 sqm GI sheet 12.8sqm
AC sheet 10 sqm AC sheet 11.5sqm
Neat cement slurry or punning 100 sqm cement 5.5bags
1.5mm thick
12 mm thick plaster 100 sqm dry mix 1.92cum
Flush pointing plaster 100 sqm dry mix 0.7cum
White wash (single coat) 100 sqm stone lime 10kg
White wash (Double coat) 100 sqm stone lime 30kg
Distempering two coats 100 sqm Dry distemper
1st coat 12kg
2nd Coat 7.5kg
Primer coat on steel 100 sqm Primer 5.5litres
Primer coat on wood 100 sqm Primer 7.5litres
Painting (2 coats) 100 sqm Paint 12.5litres
Cement Paint with water proof 10 sqm Mixed cement paint 2litres
Spray painting 100 sqm Primer 8.1litres
Paint 11litres
Wax polishing on new wood 100 sqm Ready made wax polish 5kg
Floating coat of cement 1 Sqm Cement 2.2kg
https://www.linkedin.com/in/kailashchander, +91 9950461810
Labour Estimation:
• Wages vary as per different classes of labour
• Length of time required to finish depends on:-
– Type of work
– Amount of work
– Types of skill required
– Mental development of work man
– Surrounding area
– Weather
– Labour availability (lack/excess)
– Local customs
– Local laws
https://www.linkedin.com/in/kailashchander, +91 9950461810
Labour Estimation:
• Task or out-turn work
– Out-Turn work means the work which can not be
finished by using only designated skilled or unskilled
labour alone.
– Both or more types of labour shall be involved to
finish the tasks
– Example : A mason can complete 1.5 cum brick work
in 8 hrs (per day) provided he is helped by 2
mazdoors to carry and mix ingredients of mortar and
also to carry and place materials.
https://www.linkedin.com/in/kailashchander, +91 9950461810
Labour Estimation:
Labour Output
Continue…
Sr. No Item Volume Strength of Gang
1 Cement Concrete in foundation 10 cum 1/4 head masons + 2 mason + 20 mazdoors
2 Concrete in foundation (machine mixed) 10 cum
1/4 head masons + 2 1/2 mason + 12 mazdoors + 2
Bhisti
3 Concrete in RCC work 10 cum 1/2 head masons + 3 mason + 18 mazdoors + 4 Bhisti
4 Brickwork in foundation + Plinth 10 cum 1/2 head masons + 8 masons + 14 mazdoors + 2 Bhisti
5 Brickwork in Ground floor 10 cum 1/2 head masons + 8 masons + 15 mazdoors + 2 Bhisti
6 Brickwork in First Floor 10 cum 1/2 head masons + 9 masons + 18 mazdoors + 2 Bhisti
8
Random Rubble Masonry in foundation +
Plinth 10 cum 1/2 head masons + 10 masons + 15 mazdoors
9 Coursed Rubble Masonry in Ground Floor 10 cum 1/2 head masons + 15 masons + 24 Mazdoors
11 12 mm plaster 100 sqm 1/2 head masons + 10 masons + 10 mazdoors
12 75 mm floor concrete 100 sqm 1/2 head masons + 10 masons + 20 mazdoors
https://www.linkedin.com/in/kailashchander, +91 9950461810
Labour Estimation:
Labour Output
Sr.
No Items Volume Labour
13 Excavation (1.5m, 30m) in Ordinary Soil 10 cum Mazdoor (3+1/4)
14 Excavation (1.5m, 30m) in Hard rock 10 cum Mazdoor (7+3/4)
Note : For additional lead of 30 m, add 1/2 mazdoor
15 Filling in trenches, plinth, sides of foundation in layers no exceeding 200 mm in
depth 10 cum Mazdoor (2+1/3)
16 Supplying, fitting, fixing and removing shuttering and staging 10 sqm 3 Carpenter + 4 Mazdoor
Note : For shoring add 25% of total labour charge
17 Steel work 100 kg 1 Blacksmith + 1 Mazdoor
18 25 mm DPC concrete 100 sqm 1/2 Head Mason + 8 Mason +
8 Mazdoor + 1 Bhisti
https://www.linkedin.com/in/kailashchander, +91 9950461810
Analysis of Rates for Earthwork:
1 Earthwork in excvation in trenches for foundations and for pipes, cables (not exceeding 1.5 m width)
(lift 1.5m, lead 30 m, ordinary soil)
For 10 cum
Particulars Qty Rate Amount
Mazdoor 3.25 450 1462.5
Water 1% 14.625
Profit and Over head 10% 147.71
Total 1624.83
Per cum 162.48
2 Earthwork in excvation in trenches for foundations and for pipes, cables (not exceeding 1.5 m width)
(lift 1.5m, lead 30 m, dense soil)
For 10 cum
Particulars Qty Rate Amount
Mazdoor 5 450 2250
Water 1% 22.5
Profit and Over head 10% 227.25
Total 2499.75
Per cum 249.97
https://www.linkedin.com/in/kailashchander, +91 9950461810
Analysis of Rates for Earthwork:
3 Earthwork in excvation in trenches for foundations and for pipes, cables (not exceeding 1.5 m width)
(lift 1.5m, lead 30 m, dense soil) With Shoring
For 10 cum
Particulars Qty Rate Amount
Mazdoor 5 450 2250
Shoring labour 25% 562.5
Water 1% 28.125
Profit and Over head 10% 284.0625
3124.688
Per cum Total 312.4688
4
Filling available excavated earth in trenches, plinth sides of foundations in layers ( 200 mm) consolidating layer
by layer and watering
(lift 1.5m, lead 50 m, dense soil)
For 10 cum
Particulars Qty Rate Amount
Mazdoor 2.33 450 1050
Water 1% 10.5
Profit and Over head 10% 106.05
Total 1166.55
Per cum 116.65
https://www.linkedin.com/in/kailashchander, +91 9950461810
Analysis of Rates for Earthwork:
5 Filling in plinth with local sand under floors including, ramming, consolidating and dressing complete
For 10 cum
Particulars Qty Rate Amount
Head mason 0.083333 600 50
Mazdoor 2.5 450 1125
Fine sand 10 400 4000
Water 1% 51.75
Profit and Over head 10% 522.675
Total 5749.42
Per cum 574.94
6 One brick layer flat soling joints filled with local sand
For 10 sqm
Particulars Qty Rate Amount
Mason 0.8 600 480
Mazdoor 1.6 450 720
Bricks 1500 6.4 9600
Sand 0.373 400 149.2
Contigencies (lump sum) 0.50% 54.746
Water 1% 110.0395
Profit and Over head 10% 1111.399
Total 12225.38
Per sqm 1222.53
https://www.linkedin.com/in/kailashchander, +91 9950461810
Analysis of Rates for Concrete work (No
steel inside)
7 Cement Concrete 1:4:8 with graded stone ballast 40 mm down in foundation
For 10 cum
Particulars Qty Rate Amount
Head mason 0.25 800 200
Mason 2 600 1200
Mazdoor 20 450 9000
Stone Ballast 9.6 1200 11520
Sand 4.8 400 1920
Cement 35 350 12250
Contigencies (lump sum) 0.50% 180.45
Water 1% 360.7045
Profit and Over head 10% 3663.115
Total 40294.27
Per cum 4029.427
https://www.linkedin.com/in/kailashchander, +91 9950461810
Analysis of Rates for Concrete work (No
steel inside)
8
Cement Concrete 1:2:4 with graded stone chips from 20 mm down to mm for RCC works excluding shuttering
and Reinforcement
For 10 cum
Particulars Qty Rate Amount
Head mason 0.25 800 200
Mason 2 600 1200
Mazdoor 20 450 9000
Stone Ballast 8.8 1200 10560
Sand 4.4 400 1760
Cement 64 350 22400
Contigencies (lump sum) 0.50% 225.6
Water 1% 451.456
Profit and Over head 10% 4579.706
Total 50376.76
Per cum 5037.676
https://www.linkedin.com/in/kailashchander, +91 9950461810
Supplying, fitting, fixing and removing
shuttering and staging
• Timber (wood) shuttering (form work) can be used max 12
times.
• Steel form work can be used 40 times.
• At the end of the life, scrap value is 8% to 12%
• Calculate cost of shuttering materials new purchased, deduct
scrap value and divide balance into 12 months period or 40
months period
Continue…
https://www.linkedin.com/in/kailashchander, +91 9950461810
Supplying, fitting, fixing and removing
shuttering and staging
8 Consider a room = 5 x 4 with an intermediate T beam 250 x 200 wide web. Height of room is 3.5 m.
Area of shuttering (a) For beam = (0.25x2+0.2)x4 = 2.8 sqm (b) For Slab = 5 x 4 - (0.2 x 4) =19.2 sqm
Total Area = 22 sqm
Particulars Quantity Rate Amount
Shuttering 1.139 55000 62645
96.6 433 41827.8
Scrap Value -10% -10447.3
For 12 times 94025.52
For one time 7835.46
Head Carpenter 1.5 800 1200
Carpenter 3 600 1800
Mazdoor 6 450 2700
Carriage within a town 2.278 120 273.36
Nails 0.50% 39.1773
Contingencies 0.50% 69.23999
Over and Profit 10% 1391.724
One time use cost for 22 SQM 15308.96
So for 10 sqm is 6958.619
So for 1 sqm is 695.8619
https://www.linkedin.com/in/kailashchander, +91 9950461810
Supplying, fitting, fixing and removing
shuttering and staging
9 Shuttering (2.5x2.5x1) for footing using wooden form work
Particulars Quantity Rate Amount
Materials
Side Planks 0.25 54000 13500
Side Cleats 0.0384 54000 2073.6
Horizontal Cleats 0.096 54000 5184
Inclined battons 0.0384 54000 2073.6
Purchasing cost of Steel Formwork 22831.2
Value after Scrap value deduction 20548.08
Formwork is used 12 time, so one time cost 1712.34
Nails (1%) 5% 85.617
Carrige labor 0.4228 150 63.42
Labour
Carpenter 1 600 600
Mazdoor 2 450 900
Contingencies 0.50% 16.81
water charges 1% 33.78
Profit and Over head 10% 341.20
Total cost for 10 SQM 3753.16
Per square Meter 375.32
https://www.linkedin.com/in/kailashchander, +91 9950461810
Analysis of Rate for RCC work
RCC work analysis
11 RCC work 1:1.5:3 for Beam with 2.0% steel
Consider 10 cum concrete. Steel = 10*2/100 = 0.2 cum = 1570 kg. Binding Wire = 1% of 1570 = 15.7 kg
Particulars Quantity Rate Amount
a Material
Stone chips 20 mm down 8.4 850 7140
Sand 4.2 1050 4410
Cement 81 350 28242.07
Steel 1570 57 89490
Binding Wire (1 kg per 100 kg) 15.7 67 1051.9
Shuttering Material on hire 5% 6516.699
b Labour
For concrete :-
Head Mason 0.5 800 400
Mason 3 600 1800
Mazdoor 23 450 10350
For Steel:-
Black Smith 16 450 7200
Mazdoor helper 16 450 7200
For Shuttering:-
Carpenter 10 600 6000
Mazdoor 10 450 4500
(a+b) 174300.7
c Contingencies (0.5% of (a+b)) 0.50% 871.5034
d water charges (1% of (a+b+c)) 1% 1751.722
Profit and Overhead (10% of (a+b+c+d)) 10% 17692.39
Total cost per 10 cum 329124.9
Total Cost per cum 32912.4
https://www.linkedin.com/in/kailashchander, +91 9950461810
Analysis of Rate for RCC work
RCC work analysis
12 RCC work 1:2:4 for lintel with 0.9% steel. Consider 10 cum concrete
Steel = 10*0.9/100 = 0.09 cum = 707 kg. Binding Wire = 1% of 707 = 7 kg
Particulars Quantity Rate Amount
a Material
Stone chips 20 mm down 8.8 850 7480
Sand 4.4 1050 4620
Cement 63 350 22190.2
Steel 707 57 40299
Binding Wire (1 kg per 100 kg) 7.07 67 473.69
Shuttering Material on hire 5% 3753.145
b Labour
For concrete :-
Head Mason 0.5 800 400
Mason 3 600 1800
Mazdoor 23 450 10350
For Steel:-
Black Smith 7 450 3150
Mazdoor helper 7 450 3150
For Shuttering:-
Carpenter 7 600 4200
Mazdoor 7 450 3150
(a+b) 105016
c Contingencies (0.5% of (a+b)) 0.50% 525.0802
d water charges (1% of (a+b+c)) 1% 1055.411
Profit and Overhead (10% of (a+b+c+d)) 10% 10659.65
Total cost per 10 cum 187982
Total cost per cum 18798.2
https://www.linkedin.com/in/kailashchander, +91 9950461810
Analysis of Rate for reinforcement work
9 Providing TOR steel for RCC work including binding, placing in position up to two floor level
Particulars Quantity Rate Amount
Material
TOR Steel 100 46 4600
wastage 5% 5% 230
Binding Wire 1 45 45
Labour
Black Smith 1 450 450
Mazdoor helper 1 450 450
Contingencies 0.50% 28.875
water charges 1% 58.03875
Profit and Overhead 10% 586.1914
Total 6448.105
Per 1 kg – 64.048/-
https://www.linkedin.com/in/kailashchander, +91 9950461810
Rate Analysis
Analysis of Rate for Steel work in RCC work
10 Cold twisted reinforcement in RCC work for a slab of 10 x 10
10 mm dia steel at 10 cm centre to centre and mm at 20 cm centre to centre in roof slab
Consider 25% and 5% extra steel due to extension in second continuous slab and hooks or bends respectively
Total Length for 10 mm dia = (1000/10 x10) x (1+0.25+0.05) = 1300m
Wt of 10 mm dia = 802kg
Total Length for 6 mm dia = (1000/20 x10) x (1+0.05) = 525m
Wt of 6 mm dia = 116.6667kg
Total weight of reinforcement = 919kg
Particulars Quantity Rate Amount
Material
TOR Steel 919 46 42280.25
wastage 5% 5% 2114.012
Binding Wire (0.8 kg per 100 kg) 7.352 45 330.84
Labour
Black Smith 9 450 4050
Mazdoor helper 9 450 4050
Contingencies 0.50% 264.1255
water charges 1% 530.8922
Profit and Overhead 10% 5362.012
Total 58982.13
Steel in Slab per SQM = 0.96 kg
https://www.linkedin.com/in/kailashchander, +91 9950461810
Analysis of Rate for Brick work
13 First Class Brickwork Masonry (1:4) in superstructure, Ground Floor
Consider 10 cum
Particulars Quantitity Rate Amount
a Materials
Bricks (19x9x9) 5000 6.4 32000
Sand 2.86 1050 3003
Cement 21 350 7350
Scaffolding 0.50% 211.765
b Labour
Head Mason 0.5 800 400
Mason 2 600 1200
Mazdoor 17 450 7650
c Contingencies 0.50% 259.0738
d Water Charge 1% 520.7384
e Overhead and Profit 10% 5259.458
f Total per 10 cum 57854.03
Toal per cum 5785.403
Note: Wet mortar quantity shall be added 15% extra due to frog filling. To calculate dry
mortar 1/3 on overall shall be added. Then we can proceed for quantity of sand and
cement
https://www.linkedin.com/in/kailashchander, +91 9950461810
Analysis of Rate for Brick work
Note: Wet mortar quantity shall be added 15% extra due to frog filling. To calculate dry
mortar 1/3 on overall shall be added. Then we can proceed for quantity of sand and
cement
14 First Class Brickwork Masonry (1:6) in superstructure, First Floor
Consider 10 cum
Particulars Quantitity Rate Amount
a Materials
Bricks (19x9x9) 5000 6.4 32000
Sand 3 1050 3150
Cement 15 350 5250
Scaffolding 0.50% 202
b Labour
Head Mason 0.5 800 400
Mason 9 600 5400
Mazdoor 20 450 9000
c Contingencies 0.50% 277.01
d Water Charge 1% 556.7901
e Overhead and Profit 10% 5623.58
f Total per 10 cum 61859.38
Toal per cum 6185.938
https://www.linkedin.com/in/kailashchander, +91 9950461810
Analysis of Rate for Brick work
Note: Wet mortar quantity shall be added 15% extra due to frog filling. To calculate dry
mortar 1/3 on overall shall be added. Then we can proceed for quantity of sand and
cement
15 Second Class Brickwork Masonry (1:6) in Foundation and Plinth
Consider 10 cum
Particulars Quantitity Rate Amount
a Materials
Bricks (19x9x9) 5000 6.4 32000
Sand 3 1050 3150
Cement 15 350 5250
Scaffolding 0.50% 202
b Labour
Head Mason 0.5 800 400
Mason 8 600 4800
Mazdoor 16 450 7200
c Contingencies 0.50% 265.01
d Water Charge 1% 532.6701
e Overhead and Profit 10% 5379.968
f Total per 10 cum 59179.65
Toal per cum 5917.965
https://www.linkedin.com/in/kailashchander, +91 9950461810
Analysis of Rate for Stone Masonry work
Prepare Rubble masonry analysis for 1:3, 1:4, 1:5 and 1:6
16 Random Rubble Masonry (1:6) in foundation and Plinth
Consider 10 cum. Mortar Volume is 4.2 cum. Cement = 17 bags, Sand = 3.6 cum
Particulars Quantitity Rate Amount
a Materials
Stone (undressed) 12.5 636 7950
Sand 3.6 1050 3780
Cement 17 350 5950
b Labour
Head Mason 0.5 800 400
Mason 10 600 6000
Mazdoor 19 450 8550
c Contingencies 0.50% 163.15
d Water Charge 1% 327.9315
e Overhead and Profit 10% 3312.108
f Total per 10 cum 36433.19
Toal per cum 3643.319
https://www.linkedin.com/in/kailashchander, +91 9950461810
Analysis of Rate for Stone Masonry work
Prepare Rubble masonry analysis for 1:3, 1:4, 1:5 and 1:6
17 Random Rubble Masonry (1:6) in superstructure
Consider 10 cum. Mortar Volume is 4.2 cum. Cement = 17 bags, Sand = 3.6 cum
Particulars Quantitity Rate Amount
a Materials
Stone (undressed) 12.5 636 7950
Sand 3.6 1050 3780
Cement 17 350 5950
Scaffolding 1.00% 336.80
b Labour
Head Mason 0.5 800 400
Mason 11 600 6600
Mazdoor 20 450 9000
c Contingencies 0.50% 170.084
d Water Charge 1% 341.8688
e Overhead and Profit 10% 3452.875
f Total per 10 cum 37981.63
Toal per cum 3798.163
https://www.linkedin.com/in/kailashchander, +91 9950461810
Analysis of Rate for Stone Masonry work
Prepare Rubble masonry analysis for 1:3, 1:4, 1:5 and 1:6
18 Coursed Rubble Masonry (1:6) in foundation and Plinth
Consider 10 cum. Dry Mortar Volume is 4.0 cum. Cement = 17 bags, Sand = 3.4 cum
Particulars Quantity Rate Amount
a Materials
Stone 11.7 865 10120.5
Sand 3.42 1050 3591
Cement 17 350 5950
b Labour
Head Mason 0.5 800 400
Mason 15 600 9000
Mazdoor 24 450 10800
c Contingencies 0.50% 199.3075
d Water Charge 1% 400.6081
e Overhead and Profit 10% 4046.142
f Total per 10 cum 44507.56
Toal per cum 4450.756
https://www.linkedin.com/in/kailashchander, +91 9950461810
Analysis of Rate for Stone Masonry work
Prepare Rubble masonry analysis for 1:3, 1:4, 1:5 and 1:6
19 Coursed Rubble Masonry (1:6) in superstructure
Consider 10 cum. Mortar Volume is 4 cum. Cement = 17 bags, Sand = 3.4 cum
Particulars Quantitity Rate Amount
a Materials
Stone 11.7 865 10120.5
Sand 3.42 1050 3591
Cement 17 350 5950
Scaffolding 1.00% 196.62
b Labour
Head Mason 0.5 800 400
Mason 17 600 10200
Mazdoor 28 450 12600
c Contingencies 0.50% 215.2906
d Water Charge 1% 432.7341
e Overhead and Profit 10% 4370.614
f Total per 10 cum 48076.75
Toal per cum 4807.675
https://www.linkedin.com/in/kailashchander, +91 9950461810
Analysis of Rate Damp Proof Course
20 20 mm thick cement mortar 1:2 damp proof course
For 100 sqm
Particulars Quantity Rate Amount
a Materials
Cement 27 350 9450
Sand 1.8 1050 1890
Water Proofing compound (2% by cement wt) 27 190 5130
Form work 1% 164.7
b Labour
Head Mason 0.5 800 400
Mason 5 600 3000
Mazdoor 6 450 2700
Contingencies 0.50% 113.67
Water Charges 1% 228.48
Profit and Overhead 10% 2307.69
Total cost per 100 sqm 25384.54
Total cost per 1 sqm 253.84
https://www.linkedin.com/in/kailashchander, +91 9950461810
Analysis of Rate Damp Proof Course
21 2.5 cm thick cement concrete 1:2:4 damp proof course
For 100 sqm
Particulars Quantity Rate Amount
a Materials
Cement 16 350 5600
Sand 1.1 1050 1155
Stone Chips 2.2 850 1870
Water Proofing compound (3% by cement wt) 24 190 4560
b Labour
Head Mason 0.5 800 400
Masons 8 600 4800
Mazdoors 9 450 4050
Contingencies 0.50% 112.175
Water charges 1.00% 225.4718
Profit and Overhead 10.00% 2277.265
Total cost per 100 sqm 25049.91
Total cost per sqm 250.5
https://www.linkedin.com/in/kailashchander, +91 9950461810
Analysis of Rate PlasteringNote:
• Increase wet volume by 20% due to extra filling of depression, joints, wastage on wall surface.
• Then increase this volume by 1/3rd to get dry volume of mortar generally for 1:4 to 1:6.
• But in case on 1:2 and 1:3 the dry mortar volume shall be reduced by 3% as compared to above calculated
because the voids in sand is lesser.
• Calculate for 1:3, 1:4, 1:5 for 12 mm thick plaster
• Calculate for 1:2, 1:3, 1:4 for 20 mm thick plaster
22 Cement Plaster 12 mm thick 1:6 on new brickwork
Consider 100 sqm
Particulars Quantity Rate Amount
a Materials
Cement 8 350 2800
Sand 1.64 1050 1722
Scaffolding 1% 176.72
b Labour
Head Mason 0.5 800 400
Mason 10 600 6000
Mazdoor 15 450 6750
Contingencies 0.50% 89.2436
Water charges 1% 179.3796
Over head and profit 10% 1811.734
Total cost per 100 sqm 19929.08
Total cost per sqm 199.29
https://www.linkedin.com/in/kailashchander, +91 9950461810
Analysis of Rate Plastering
23 Cement Plastering of 6 mm thickness 1:3 on ceiling. Consider 100 sqm area
Particulars Quantity Rate Amount
a Materials
Cement 7 350 2450
Sand 0.7182 1050 754.11
Scaffolding 1% 150.0411
b Labour
Head Mason 0.5 800 400
Mason 10 600 6000
Mazdoor 12 450 5400
Contingencies 0.50% 75.77
Water Charges 1% 152.30
Overhead and Profit 10% 1538.22
Total cost per 100 sqm 16920.44
Total cost per Sqm 169.20
https://www.linkedin.com/in/kailashchander, +91 9950461810
Analysis of Rate for Road Works
24 Earthwork in excavation from borrow pits
Particulars Quantity Rate Amount
a Labour
Mazdoor for cutting and placing 1.5 350 525
Mazdoor for loading and unloading 2 350 700
Mazdoor for rough dressing 0.2 350 70
Contingency 0.50% 6.48
Water 1% 13.01
Overhead and Profit 10% 131.45
Total cost per 10 cum 1445.94
Total cost per 1 cum 144.59
24 Earthwork in excavation from borrow pits by using JCB machine (NOT in COURSE)
Particulars Quantity Rate Amount
a Equipment
JCB 0.083333 2000 166.67
JCB operators 0.083333 500 41.67
Fuel 4.166667 70 291.67
Helper 0.083333 350 29.17
Contingencies charges 0.50% 2.65
Water Charges 1% 5.32
Over head and Profit 10% 53.71
Total Cost per 10 cum 590.84
Total cost per 1 cum 59.08
https://www.linkedin.com/in/kailashchander, +91 9950461810
Analysis of Rate for Flooring, Wood, road
etc
Not complete yet,
Will discuss some more after valuation
chapter

More Related Content

PPTX
THUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITY
DOCX
Analysis of rates for labour and material
PPTX
Analysis of rates
PPT
Rates Analysis For Calculating Material and Labour for building works
PPTX
Rate analysis
PPTX
Heavy Construction Equipment Productivity
PPT
Estimation (power point)
PPTX
Presentation On Auto Cad
THUMB RULE FOR CIVIL WORKS LABOUR PRODUCTIVITY
Analysis of rates for labour and material
Analysis of rates
Rates Analysis For Calculating Material and Labour for building works
Rate analysis
Heavy Construction Equipment Productivity
Estimation (power point)
Presentation On Auto Cad

What's hot (20)

PPTX
estimation,its types and methods
PPTX
Schedule of Rates
PPTX
Approximate estimate
PDF
Estimating and-costing
PPTX
Types of Contract in Construction Management
PPT
Estimation
PPTX
Approximate estimate
PPTX
Estimating & Costing - I
PDF
Estimating and-costing book
PPT
Stages in Construction
PPTX
Estimating, administrative approval, technical sanction, budget provision
PPT
Ready mix concrete
PPTX
ESTIMATING AND COSTING
PPTX
Estimating and costing
PPTX
Contract and Arbitration
PDF
estimation and quantity surveying
PPTX
Fundamentals of Estimating and Costing
PPTX
Types of estimates
PPTX
Rate analysis road work in Estimation & Rate Analyisis
PPTX
Rate analysis and costing - Estimation, Costing and Valuation Engineering
estimation,its types and methods
Schedule of Rates
Approximate estimate
Estimating and-costing
Types of Contract in Construction Management
Estimation
Approximate estimate
Estimating & Costing - I
Estimating and-costing book
Stages in Construction
Estimating, administrative approval, technical sanction, budget provision
Ready mix concrete
ESTIMATING AND COSTING
Estimating and costing
Contract and Arbitration
estimation and quantity surveying
Fundamentals of Estimating and Costing
Types of estimates
Rate analysis road work in Estimation & Rate Analyisis
Rate analysis and costing - Estimation, Costing and Valuation Engineering
Ad

Similar to Rate analysis in civil engineering (20)

PPTX
sunil mishra pptmmmmmmmmmmmmmmmmmmmmmmmmm
PPTX
rate analysis for structural buildingsppt 1.pptx
PDF
EQS - RATE ANALYSIS.pdf
PPTX
rateanalysis.pptxbbbbbbbb njjjj jjjjj jjjjj
PPTX
JAjjajajns jajjajaj ajkakajjajajjakwkabbbn
PPTX
Getting the construction right
PPT
Eqs unit 3 final
PDF
Environment friendly building_material_technologies_for_low_cost_housing (1)
PPTX
Construction of 1000 Sq.ft Individual house
PDF
Hot sale calcite grinding mill with ce approved
PDF
Higher capacity calcite grinding machine with ceiso
PDF
Energy saving fine grinding mill with ce approved
PDF
50,000 m3 AAC Line Technical Introduction of Zhengzhou DEYI
PDF
The latest r & d mica grinding machine with ceiso
PDF
tile making machine
PDF
specification dsfghresdfgkrzdxfcrztxfhuyttd
PPTX
Rate analysis vansheika
PDF
Cbecl clay brick project with tunnel kiln-200000 pcs per day
PPTX
FLY ASH BRICK PRODUCTION
PDF
The latest r & d micro powder grinding machine, powder making machine
sunil mishra pptmmmmmmmmmmmmmmmmmmmmmmmmm
rate analysis for structural buildingsppt 1.pptx
EQS - RATE ANALYSIS.pdf
rateanalysis.pptxbbbbbbbb njjjj jjjjj jjjjj
JAjjajajns jajjajaj ajkakajjajajjakwkabbbn
Getting the construction right
Eqs unit 3 final
Environment friendly building_material_technologies_for_low_cost_housing (1)
Construction of 1000 Sq.ft Individual house
Hot sale calcite grinding mill with ce approved
Higher capacity calcite grinding machine with ceiso
Energy saving fine grinding mill with ce approved
50,000 m3 AAC Line Technical Introduction of Zhengzhou DEYI
The latest r & d mica grinding machine with ceiso
tile making machine
specification dsfghresdfgkrzdxfcrztxfhuyttd
Rate analysis vansheika
Cbecl clay brick project with tunnel kiln-200000 pcs per day
FLY ASH BRICK PRODUCTION
The latest r & d micro powder grinding machine, powder making machine
Ad

Recently uploaded (20)

PPTX
UNIT 4 Total Quality Management .pptx
PPT
Mechanical Engineering MATERIALS Selection
PPTX
Welding lecture in detail for understanding
PDF
July 2025 - Top 10 Read Articles in International Journal of Software Enginee...
PPTX
Internet of Things (IOT) - A guide to understanding
PDF
Embodied AI: Ushering in the Next Era of Intelligent Systems
PPTX
bas. eng. economics group 4 presentation 1.pptx
DOCX
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
PPTX
KTU 2019 -S7-MCN 401 MODULE 2-VINAY.pptx
PDF
Well-logging-methods_new................
PPTX
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
PPTX
Construction Project Organization Group 2.pptx
PPTX
web development for engineering and engineering
PPTX
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
PPTX
CH1 Production IntroductoryConcepts.pptx
PPTX
Geodesy 1.pptx...............................................
PPTX
MCN 401 KTU-2019-PPE KITS-MODULE 2.pptx
PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PPTX
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
PPTX
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
UNIT 4 Total Quality Management .pptx
Mechanical Engineering MATERIALS Selection
Welding lecture in detail for understanding
July 2025 - Top 10 Read Articles in International Journal of Software Enginee...
Internet of Things (IOT) - A guide to understanding
Embodied AI: Ushering in the Next Era of Intelligent Systems
bas. eng. economics group 4 presentation 1.pptx
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
KTU 2019 -S7-MCN 401 MODULE 2-VINAY.pptx
Well-logging-methods_new................
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
Construction Project Organization Group 2.pptx
web development for engineering and engineering
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
CH1 Production IntroductoryConcepts.pptx
Geodesy 1.pptx...............................................
MCN 401 KTU-2019-PPE KITS-MODULE 2.pptx
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx

Rate analysis in civil engineering

  • 1. https://www.linkedin.com/in/kailashchander, +91 9950461810 Rate Analysis Quantity Surveying, Estimation & Valuation KC associates
  • 2. https://www.linkedin.com/in/kailashchander, +91 9950461810 Rate Analysis Content • Purpose of Rate Analysis • Items of Rate Analysis • Table for Rate Analysis • Quantity of Coarse, Fine and Cement • Estimation of Labour • Task or out-turn work • Labour output in 8 working hours • Rate of Material and Labour
  • 3. https://www.linkedin.com/in/kailashchander, +91 9950461810 What is Rate Analysis • The basis of arriving at correct or reasonable rate per unit work, for a particular item following its specification and detailed survey of materials, labour, equipment etc. i.e. To reach Rate of Concrete Per CUM, individual cost of followings are considered: a) Materials(cement, sand, agg, steel, admixture) used for per cum concrete b) Labour (mason, labor, carpenter) per cum concrete c) Equipment (vibrator, pump, transit mixer, batching plant cost) per cum concrete
  • 4. https://www.linkedin.com/in/kailashchander, +91 9950461810 Purpose of Rate Analysis • To determine the current rate per unit of an item at the locality • To examine the viability of rates offered by contractors. • To calculate labor strength & equipment required for Project Planning. • To fix up labor contract rates. Purpose Current Rate Offered Rate Quantities Contract Rates
  • 5. https://www.linkedin.com/in/kailashchander, +91 9950461810 How to fix up rate per Unit of an item? • Following subheads are estimated and based on their summation, rate per unit of an item is arrived:- Rate Analysis Considerations Quantity of Materials and Cost Labour Cost Equipment, Tools & Plant Cost Overhead or Establishment Charges Profit
  • 6. https://www.linkedin.com/in/kailashchander, +91 9950461810 Rate Analysis How to fix up rate per Unit of an item? • Quantity of Materials and Cost:- – As per detailed specification, quantity of an item is calculated. Based on market rates, per unit rate is arrived. – Following cost too is considered:- • Freight & transportation, including loading & unloading • Taxes & insurance • Profit on Cement, steel stone chips and bitumen not included if supplied departmentally. • Labour Cost – Number and wages of different categories of laborers, (skilled & unskilled) namely mason or carpenter, mazdoor for per unit of item to execute at site. – These numbers are multiplied by market rate and labour cost is arrived per UNIT of item.
  • 7. https://www.linkedin.com/in/kailashchander, +91 9950461810 How to fix up rate per Unit of an item? • Equipment, Tools and Plant Cost – Equipment for General use as per item – Example concrete mixer as per unit of concrete – Certain tools and plants are difficult to allocate as per the specific item hence their cost are considered in establishment charges – For special equipment extra 1% to 1.5% (purchasing) of estimated cost is provided. • Overhead & Establishment Charges – Office Rent, Depreciation on equipments – Salaries of office staff, postage, lighting, travelling, telephone account – This is actually 2.5% up to 5% – Overhead charges increases with delay in project.
  • 8. https://www.linkedin.com/in/kailashchander, +91 9950461810 How to fix up rate per Unit of an item? • Overheads and Establishment Charges – There are 2 types of Overheads General Overheads (Recurring known expenditures) • Office Rent • Salaries of office staff • Stationary items, printing, postages, repairs • Telephone and electric Bills • Travelling Job Overheads (incur in construction) • Salaries of technical or non-technical staff • Temporary Sheds • Go-Down rent • Small tools, planks, ladders, ropes, hand tools for workmen • Repairs & depreciation for tools and plant • Lighting at site • Mobilization of establishment • Public Relations • Labor Welfare & safety • Workmen compensation, insurance • Interest on investment • Theft or loss
  • 9. https://www.linkedin.com/in/kailashchander, +91 9950461810 Profit • Generally 10% profit is considered for ordinary contracts, after allocating all charges of equipments, establishments. • For small jobs, profit is 15% • For large projects Profit is 8%
  • 10. https://www.linkedin.com/in/kailashchander, +91 9950461810 Factoring Affecting the rate analysis • Specification of the item – Quality of Materials – Proportion of materials – Method of construction – Protection of Work • Rate of materials for item of work up to worksite • Daily wages of labourer – With different categories – With localities – As per outputs • The range of lead and lift require for deposition of materials • Percentage charge for overheads • Possibility of theft of losses • Range of profit • Availability of water connection
  • 11. https://www.linkedin.com/in/kailashchander, +91 9950461810 Quantity of Coarse Aggregate, Sand and Cement for various proportion • Quantities shall be calculated for 10 cum of concrete. • Exact quantities of ingredients cannot be calculated for 10 cum of concrete so there is a thumb rule • To calculate dry ingredients for 10 cum of concrete. Each proportional quantity for 10 cum of concrete is multiplied with 15.4 up to 15.7 • This 15.4 factor is due to existence of voids. • Example: Findout qty of cement, sand and stone chips in 1:2:4 – Cement : 1/(1+2+4) x 15.4 = 2.2cum = 3168 kg = 64 bags – Sand : 2/(1+2+4) x 15.4 = 4.4 cum = 7.25 tons – Stone Chips : 8.8 cum = 18 tons
  • 12. https://www.linkedin.com/in/kailashchander, +91 9950461810 • Calculate quantities of Cement, sand and stone chips for 10 cum concrete (variation of 5% is allowed) Volumetric Proportion Cement Dry sand Stone chips (20 - 6 mm) cum bags cum cum 1:1:2 3.88 112.3 3.88 7.8 1:1.5:3 2.80 81.2 4.20 8.4 1:2:4 2.20 63.8 4.40 8.8 1:2.5:5 1.81 52.5 4.53 9.1 1:3:6 1.57 45.5 4.71 9.4 1:4:8 1.20 34.8 4.80 9.6 1:5:10 0.98 28.3 4.88 9.8 0.00 2.00 4.00 6.00 8.00 10.00 12.00 1:1:2 1:1.5:3 1:2:4 1:2.5:5 1:3:6 1:4:8 1:5:10 Quantities as per ratio Cement Dry sand Stone chips (20 -6 mm) Quantity of Coarse Aggregate, Sand and Cement for various proportion
  • 13. https://www.linkedin.com/in/kailashchander, +91 9950461810 Material Estimation: Continue…. Quantity of Materials required for different items of works Name of work Per Unit Materials Quantity Brickwork 10 cum 19x9x9 5000nos Dry cement mortar 3.5cum Half brick 100 sqm 19x9x9 5000nos Random rubble masonry 10 cum stone 12.5cum Dry cement mortar 4.2cum Ashlar masonry 10 cum stone 12.5cum Brick soling 10 sqm 19x9x9 425nos Brick on edge floor 10 sqm 19x9x9 500nos dry cement mortar 3.5cum 20 mm DPC 100 sqm cement 27bags sand 1.8cum water proof 27kg Reinforced Brick work 10 cum Bricks 4500nos Dry cement mortar 4.8cum Precast terrazo tiles 100 sqm Tiles 110sqm Cement 13bags Pigment 46kgs Lime Terracing on roof 100 sqm Lime 2.1cum 2:2:7 and 7.5 cm thick Surkhi 2.1cum Brick ballast 7.5cum Rani ganj tile roofing 10sqm Tiles 124nos cement mortar 0.15cum
  • 14. https://www.linkedin.com/in/kailashchander, +91 9950461810 Material Estimation:Quantity of Materials required for different items of works Name of work Per Unit Materials Quantity CGI sheet roofing 10 sqm GI sheet 12.8sqm AC sheet 10 sqm AC sheet 11.5sqm Neat cement slurry or punning 100 sqm cement 5.5bags 1.5mm thick 12 mm thick plaster 100 sqm dry mix 1.92cum Flush pointing plaster 100 sqm dry mix 0.7cum White wash (single coat) 100 sqm stone lime 10kg White wash (Double coat) 100 sqm stone lime 30kg Distempering two coats 100 sqm Dry distemper 1st coat 12kg 2nd Coat 7.5kg Primer coat on steel 100 sqm Primer 5.5litres Primer coat on wood 100 sqm Primer 7.5litres Painting (2 coats) 100 sqm Paint 12.5litres Cement Paint with water proof 10 sqm Mixed cement paint 2litres Spray painting 100 sqm Primer 8.1litres Paint 11litres Wax polishing on new wood 100 sqm Ready made wax polish 5kg Floating coat of cement 1 Sqm Cement 2.2kg
  • 15. https://www.linkedin.com/in/kailashchander, +91 9950461810 Labour Estimation: • Wages vary as per different classes of labour • Length of time required to finish depends on:- – Type of work – Amount of work – Types of skill required – Mental development of work man – Surrounding area – Weather – Labour availability (lack/excess) – Local customs – Local laws
  • 16. https://www.linkedin.com/in/kailashchander, +91 9950461810 Labour Estimation: • Task or out-turn work – Out-Turn work means the work which can not be finished by using only designated skilled or unskilled labour alone. – Both or more types of labour shall be involved to finish the tasks – Example : A mason can complete 1.5 cum brick work in 8 hrs (per day) provided he is helped by 2 mazdoors to carry and mix ingredients of mortar and also to carry and place materials.
  • 17. https://www.linkedin.com/in/kailashchander, +91 9950461810 Labour Estimation: Labour Output Continue… Sr. No Item Volume Strength of Gang 1 Cement Concrete in foundation 10 cum 1/4 head masons + 2 mason + 20 mazdoors 2 Concrete in foundation (machine mixed) 10 cum 1/4 head masons + 2 1/2 mason + 12 mazdoors + 2 Bhisti 3 Concrete in RCC work 10 cum 1/2 head masons + 3 mason + 18 mazdoors + 4 Bhisti 4 Brickwork in foundation + Plinth 10 cum 1/2 head masons + 8 masons + 14 mazdoors + 2 Bhisti 5 Brickwork in Ground floor 10 cum 1/2 head masons + 8 masons + 15 mazdoors + 2 Bhisti 6 Brickwork in First Floor 10 cum 1/2 head masons + 9 masons + 18 mazdoors + 2 Bhisti 8 Random Rubble Masonry in foundation + Plinth 10 cum 1/2 head masons + 10 masons + 15 mazdoors 9 Coursed Rubble Masonry in Ground Floor 10 cum 1/2 head masons + 15 masons + 24 Mazdoors 11 12 mm plaster 100 sqm 1/2 head masons + 10 masons + 10 mazdoors 12 75 mm floor concrete 100 sqm 1/2 head masons + 10 masons + 20 mazdoors
  • 18. https://www.linkedin.com/in/kailashchander, +91 9950461810 Labour Estimation: Labour Output Sr. No Items Volume Labour 13 Excavation (1.5m, 30m) in Ordinary Soil 10 cum Mazdoor (3+1/4) 14 Excavation (1.5m, 30m) in Hard rock 10 cum Mazdoor (7+3/4) Note : For additional lead of 30 m, add 1/2 mazdoor 15 Filling in trenches, plinth, sides of foundation in layers no exceeding 200 mm in depth 10 cum Mazdoor (2+1/3) 16 Supplying, fitting, fixing and removing shuttering and staging 10 sqm 3 Carpenter + 4 Mazdoor Note : For shoring add 25% of total labour charge 17 Steel work 100 kg 1 Blacksmith + 1 Mazdoor 18 25 mm DPC concrete 100 sqm 1/2 Head Mason + 8 Mason + 8 Mazdoor + 1 Bhisti
  • 19. https://www.linkedin.com/in/kailashchander, +91 9950461810 Analysis of Rates for Earthwork: 1 Earthwork in excvation in trenches for foundations and for pipes, cables (not exceeding 1.5 m width) (lift 1.5m, lead 30 m, ordinary soil) For 10 cum Particulars Qty Rate Amount Mazdoor 3.25 450 1462.5 Water 1% 14.625 Profit and Over head 10% 147.71 Total 1624.83 Per cum 162.48 2 Earthwork in excvation in trenches for foundations and for pipes, cables (not exceeding 1.5 m width) (lift 1.5m, lead 30 m, dense soil) For 10 cum Particulars Qty Rate Amount Mazdoor 5 450 2250 Water 1% 22.5 Profit and Over head 10% 227.25 Total 2499.75 Per cum 249.97
  • 20. https://www.linkedin.com/in/kailashchander, +91 9950461810 Analysis of Rates for Earthwork: 3 Earthwork in excvation in trenches for foundations and for pipes, cables (not exceeding 1.5 m width) (lift 1.5m, lead 30 m, dense soil) With Shoring For 10 cum Particulars Qty Rate Amount Mazdoor 5 450 2250 Shoring labour 25% 562.5 Water 1% 28.125 Profit and Over head 10% 284.0625 3124.688 Per cum Total 312.4688 4 Filling available excavated earth in trenches, plinth sides of foundations in layers ( 200 mm) consolidating layer by layer and watering (lift 1.5m, lead 50 m, dense soil) For 10 cum Particulars Qty Rate Amount Mazdoor 2.33 450 1050 Water 1% 10.5 Profit and Over head 10% 106.05 Total 1166.55 Per cum 116.65
  • 21. https://www.linkedin.com/in/kailashchander, +91 9950461810 Analysis of Rates for Earthwork: 5 Filling in plinth with local sand under floors including, ramming, consolidating and dressing complete For 10 cum Particulars Qty Rate Amount Head mason 0.083333 600 50 Mazdoor 2.5 450 1125 Fine sand 10 400 4000 Water 1% 51.75 Profit and Over head 10% 522.675 Total 5749.42 Per cum 574.94 6 One brick layer flat soling joints filled with local sand For 10 sqm Particulars Qty Rate Amount Mason 0.8 600 480 Mazdoor 1.6 450 720 Bricks 1500 6.4 9600 Sand 0.373 400 149.2 Contigencies (lump sum) 0.50% 54.746 Water 1% 110.0395 Profit and Over head 10% 1111.399 Total 12225.38 Per sqm 1222.53
  • 22. https://www.linkedin.com/in/kailashchander, +91 9950461810 Analysis of Rates for Concrete work (No steel inside) 7 Cement Concrete 1:4:8 with graded stone ballast 40 mm down in foundation For 10 cum Particulars Qty Rate Amount Head mason 0.25 800 200 Mason 2 600 1200 Mazdoor 20 450 9000 Stone Ballast 9.6 1200 11520 Sand 4.8 400 1920 Cement 35 350 12250 Contigencies (lump sum) 0.50% 180.45 Water 1% 360.7045 Profit and Over head 10% 3663.115 Total 40294.27 Per cum 4029.427
  • 23. https://www.linkedin.com/in/kailashchander, +91 9950461810 Analysis of Rates for Concrete work (No steel inside) 8 Cement Concrete 1:2:4 with graded stone chips from 20 mm down to mm for RCC works excluding shuttering and Reinforcement For 10 cum Particulars Qty Rate Amount Head mason 0.25 800 200 Mason 2 600 1200 Mazdoor 20 450 9000 Stone Ballast 8.8 1200 10560 Sand 4.4 400 1760 Cement 64 350 22400 Contigencies (lump sum) 0.50% 225.6 Water 1% 451.456 Profit and Over head 10% 4579.706 Total 50376.76 Per cum 5037.676
  • 24. https://www.linkedin.com/in/kailashchander, +91 9950461810 Supplying, fitting, fixing and removing shuttering and staging • Timber (wood) shuttering (form work) can be used max 12 times. • Steel form work can be used 40 times. • At the end of the life, scrap value is 8% to 12% • Calculate cost of shuttering materials new purchased, deduct scrap value and divide balance into 12 months period or 40 months period Continue…
  • 25. https://www.linkedin.com/in/kailashchander, +91 9950461810 Supplying, fitting, fixing and removing shuttering and staging 8 Consider a room = 5 x 4 with an intermediate T beam 250 x 200 wide web. Height of room is 3.5 m. Area of shuttering (a) For beam = (0.25x2+0.2)x4 = 2.8 sqm (b) For Slab = 5 x 4 - (0.2 x 4) =19.2 sqm Total Area = 22 sqm Particulars Quantity Rate Amount Shuttering 1.139 55000 62645 96.6 433 41827.8 Scrap Value -10% -10447.3 For 12 times 94025.52 For one time 7835.46 Head Carpenter 1.5 800 1200 Carpenter 3 600 1800 Mazdoor 6 450 2700 Carriage within a town 2.278 120 273.36 Nails 0.50% 39.1773 Contingencies 0.50% 69.23999 Over and Profit 10% 1391.724 One time use cost for 22 SQM 15308.96 So for 10 sqm is 6958.619 So for 1 sqm is 695.8619
  • 26. https://www.linkedin.com/in/kailashchander, +91 9950461810 Supplying, fitting, fixing and removing shuttering and staging 9 Shuttering (2.5x2.5x1) for footing using wooden form work Particulars Quantity Rate Amount Materials Side Planks 0.25 54000 13500 Side Cleats 0.0384 54000 2073.6 Horizontal Cleats 0.096 54000 5184 Inclined battons 0.0384 54000 2073.6 Purchasing cost of Steel Formwork 22831.2 Value after Scrap value deduction 20548.08 Formwork is used 12 time, so one time cost 1712.34 Nails (1%) 5% 85.617 Carrige labor 0.4228 150 63.42 Labour Carpenter 1 600 600 Mazdoor 2 450 900 Contingencies 0.50% 16.81 water charges 1% 33.78 Profit and Over head 10% 341.20 Total cost for 10 SQM 3753.16 Per square Meter 375.32
  • 27. https://www.linkedin.com/in/kailashchander, +91 9950461810 Analysis of Rate for RCC work RCC work analysis 11 RCC work 1:1.5:3 for Beam with 2.0% steel Consider 10 cum concrete. Steel = 10*2/100 = 0.2 cum = 1570 kg. Binding Wire = 1% of 1570 = 15.7 kg Particulars Quantity Rate Amount a Material Stone chips 20 mm down 8.4 850 7140 Sand 4.2 1050 4410 Cement 81 350 28242.07 Steel 1570 57 89490 Binding Wire (1 kg per 100 kg) 15.7 67 1051.9 Shuttering Material on hire 5% 6516.699 b Labour For concrete :- Head Mason 0.5 800 400 Mason 3 600 1800 Mazdoor 23 450 10350 For Steel:- Black Smith 16 450 7200 Mazdoor helper 16 450 7200 For Shuttering:- Carpenter 10 600 6000 Mazdoor 10 450 4500 (a+b) 174300.7 c Contingencies (0.5% of (a+b)) 0.50% 871.5034 d water charges (1% of (a+b+c)) 1% 1751.722 Profit and Overhead (10% of (a+b+c+d)) 10% 17692.39 Total cost per 10 cum 329124.9 Total Cost per cum 32912.4
  • 28. https://www.linkedin.com/in/kailashchander, +91 9950461810 Analysis of Rate for RCC work RCC work analysis 12 RCC work 1:2:4 for lintel with 0.9% steel. Consider 10 cum concrete Steel = 10*0.9/100 = 0.09 cum = 707 kg. Binding Wire = 1% of 707 = 7 kg Particulars Quantity Rate Amount a Material Stone chips 20 mm down 8.8 850 7480 Sand 4.4 1050 4620 Cement 63 350 22190.2 Steel 707 57 40299 Binding Wire (1 kg per 100 kg) 7.07 67 473.69 Shuttering Material on hire 5% 3753.145 b Labour For concrete :- Head Mason 0.5 800 400 Mason 3 600 1800 Mazdoor 23 450 10350 For Steel:- Black Smith 7 450 3150 Mazdoor helper 7 450 3150 For Shuttering:- Carpenter 7 600 4200 Mazdoor 7 450 3150 (a+b) 105016 c Contingencies (0.5% of (a+b)) 0.50% 525.0802 d water charges (1% of (a+b+c)) 1% 1055.411 Profit and Overhead (10% of (a+b+c+d)) 10% 10659.65 Total cost per 10 cum 187982 Total cost per cum 18798.2
  • 29. https://www.linkedin.com/in/kailashchander, +91 9950461810 Analysis of Rate for reinforcement work 9 Providing TOR steel for RCC work including binding, placing in position up to two floor level Particulars Quantity Rate Amount Material TOR Steel 100 46 4600 wastage 5% 5% 230 Binding Wire 1 45 45 Labour Black Smith 1 450 450 Mazdoor helper 1 450 450 Contingencies 0.50% 28.875 water charges 1% 58.03875 Profit and Overhead 10% 586.1914 Total 6448.105 Per 1 kg – 64.048/-
  • 30. https://www.linkedin.com/in/kailashchander, +91 9950461810 Rate Analysis Analysis of Rate for Steel work in RCC work 10 Cold twisted reinforcement in RCC work for a slab of 10 x 10 10 mm dia steel at 10 cm centre to centre and mm at 20 cm centre to centre in roof slab Consider 25% and 5% extra steel due to extension in second continuous slab and hooks or bends respectively Total Length for 10 mm dia = (1000/10 x10) x (1+0.25+0.05) = 1300m Wt of 10 mm dia = 802kg Total Length for 6 mm dia = (1000/20 x10) x (1+0.05) = 525m Wt of 6 mm dia = 116.6667kg Total weight of reinforcement = 919kg Particulars Quantity Rate Amount Material TOR Steel 919 46 42280.25 wastage 5% 5% 2114.012 Binding Wire (0.8 kg per 100 kg) 7.352 45 330.84 Labour Black Smith 9 450 4050 Mazdoor helper 9 450 4050 Contingencies 0.50% 264.1255 water charges 1% 530.8922 Profit and Overhead 10% 5362.012 Total 58982.13 Steel in Slab per SQM = 0.96 kg
  • 31. https://www.linkedin.com/in/kailashchander, +91 9950461810 Analysis of Rate for Brick work 13 First Class Brickwork Masonry (1:4) in superstructure, Ground Floor Consider 10 cum Particulars Quantitity Rate Amount a Materials Bricks (19x9x9) 5000 6.4 32000 Sand 2.86 1050 3003 Cement 21 350 7350 Scaffolding 0.50% 211.765 b Labour Head Mason 0.5 800 400 Mason 2 600 1200 Mazdoor 17 450 7650 c Contingencies 0.50% 259.0738 d Water Charge 1% 520.7384 e Overhead and Profit 10% 5259.458 f Total per 10 cum 57854.03 Toal per cum 5785.403 Note: Wet mortar quantity shall be added 15% extra due to frog filling. To calculate dry mortar 1/3 on overall shall be added. Then we can proceed for quantity of sand and cement
  • 32. https://www.linkedin.com/in/kailashchander, +91 9950461810 Analysis of Rate for Brick work Note: Wet mortar quantity shall be added 15% extra due to frog filling. To calculate dry mortar 1/3 on overall shall be added. Then we can proceed for quantity of sand and cement 14 First Class Brickwork Masonry (1:6) in superstructure, First Floor Consider 10 cum Particulars Quantitity Rate Amount a Materials Bricks (19x9x9) 5000 6.4 32000 Sand 3 1050 3150 Cement 15 350 5250 Scaffolding 0.50% 202 b Labour Head Mason 0.5 800 400 Mason 9 600 5400 Mazdoor 20 450 9000 c Contingencies 0.50% 277.01 d Water Charge 1% 556.7901 e Overhead and Profit 10% 5623.58 f Total per 10 cum 61859.38 Toal per cum 6185.938
  • 33. https://www.linkedin.com/in/kailashchander, +91 9950461810 Analysis of Rate for Brick work Note: Wet mortar quantity shall be added 15% extra due to frog filling. To calculate dry mortar 1/3 on overall shall be added. Then we can proceed for quantity of sand and cement 15 Second Class Brickwork Masonry (1:6) in Foundation and Plinth Consider 10 cum Particulars Quantitity Rate Amount a Materials Bricks (19x9x9) 5000 6.4 32000 Sand 3 1050 3150 Cement 15 350 5250 Scaffolding 0.50% 202 b Labour Head Mason 0.5 800 400 Mason 8 600 4800 Mazdoor 16 450 7200 c Contingencies 0.50% 265.01 d Water Charge 1% 532.6701 e Overhead and Profit 10% 5379.968 f Total per 10 cum 59179.65 Toal per cum 5917.965
  • 34. https://www.linkedin.com/in/kailashchander, +91 9950461810 Analysis of Rate for Stone Masonry work Prepare Rubble masonry analysis for 1:3, 1:4, 1:5 and 1:6 16 Random Rubble Masonry (1:6) in foundation and Plinth Consider 10 cum. Mortar Volume is 4.2 cum. Cement = 17 bags, Sand = 3.6 cum Particulars Quantitity Rate Amount a Materials Stone (undressed) 12.5 636 7950 Sand 3.6 1050 3780 Cement 17 350 5950 b Labour Head Mason 0.5 800 400 Mason 10 600 6000 Mazdoor 19 450 8550 c Contingencies 0.50% 163.15 d Water Charge 1% 327.9315 e Overhead and Profit 10% 3312.108 f Total per 10 cum 36433.19 Toal per cum 3643.319
  • 35. https://www.linkedin.com/in/kailashchander, +91 9950461810 Analysis of Rate for Stone Masonry work Prepare Rubble masonry analysis for 1:3, 1:4, 1:5 and 1:6 17 Random Rubble Masonry (1:6) in superstructure Consider 10 cum. Mortar Volume is 4.2 cum. Cement = 17 bags, Sand = 3.6 cum Particulars Quantitity Rate Amount a Materials Stone (undressed) 12.5 636 7950 Sand 3.6 1050 3780 Cement 17 350 5950 Scaffolding 1.00% 336.80 b Labour Head Mason 0.5 800 400 Mason 11 600 6600 Mazdoor 20 450 9000 c Contingencies 0.50% 170.084 d Water Charge 1% 341.8688 e Overhead and Profit 10% 3452.875 f Total per 10 cum 37981.63 Toal per cum 3798.163
  • 36. https://www.linkedin.com/in/kailashchander, +91 9950461810 Analysis of Rate for Stone Masonry work Prepare Rubble masonry analysis for 1:3, 1:4, 1:5 and 1:6 18 Coursed Rubble Masonry (1:6) in foundation and Plinth Consider 10 cum. Dry Mortar Volume is 4.0 cum. Cement = 17 bags, Sand = 3.4 cum Particulars Quantity Rate Amount a Materials Stone 11.7 865 10120.5 Sand 3.42 1050 3591 Cement 17 350 5950 b Labour Head Mason 0.5 800 400 Mason 15 600 9000 Mazdoor 24 450 10800 c Contingencies 0.50% 199.3075 d Water Charge 1% 400.6081 e Overhead and Profit 10% 4046.142 f Total per 10 cum 44507.56 Toal per cum 4450.756
  • 37. https://www.linkedin.com/in/kailashchander, +91 9950461810 Analysis of Rate for Stone Masonry work Prepare Rubble masonry analysis for 1:3, 1:4, 1:5 and 1:6 19 Coursed Rubble Masonry (1:6) in superstructure Consider 10 cum. Mortar Volume is 4 cum. Cement = 17 bags, Sand = 3.4 cum Particulars Quantitity Rate Amount a Materials Stone 11.7 865 10120.5 Sand 3.42 1050 3591 Cement 17 350 5950 Scaffolding 1.00% 196.62 b Labour Head Mason 0.5 800 400 Mason 17 600 10200 Mazdoor 28 450 12600 c Contingencies 0.50% 215.2906 d Water Charge 1% 432.7341 e Overhead and Profit 10% 4370.614 f Total per 10 cum 48076.75 Toal per cum 4807.675
  • 38. https://www.linkedin.com/in/kailashchander, +91 9950461810 Analysis of Rate Damp Proof Course 20 20 mm thick cement mortar 1:2 damp proof course For 100 sqm Particulars Quantity Rate Amount a Materials Cement 27 350 9450 Sand 1.8 1050 1890 Water Proofing compound (2% by cement wt) 27 190 5130 Form work 1% 164.7 b Labour Head Mason 0.5 800 400 Mason 5 600 3000 Mazdoor 6 450 2700 Contingencies 0.50% 113.67 Water Charges 1% 228.48 Profit and Overhead 10% 2307.69 Total cost per 100 sqm 25384.54 Total cost per 1 sqm 253.84
  • 39. https://www.linkedin.com/in/kailashchander, +91 9950461810 Analysis of Rate Damp Proof Course 21 2.5 cm thick cement concrete 1:2:4 damp proof course For 100 sqm Particulars Quantity Rate Amount a Materials Cement 16 350 5600 Sand 1.1 1050 1155 Stone Chips 2.2 850 1870 Water Proofing compound (3% by cement wt) 24 190 4560 b Labour Head Mason 0.5 800 400 Masons 8 600 4800 Mazdoors 9 450 4050 Contingencies 0.50% 112.175 Water charges 1.00% 225.4718 Profit and Overhead 10.00% 2277.265 Total cost per 100 sqm 25049.91 Total cost per sqm 250.5
  • 40. https://www.linkedin.com/in/kailashchander, +91 9950461810 Analysis of Rate PlasteringNote: • Increase wet volume by 20% due to extra filling of depression, joints, wastage on wall surface. • Then increase this volume by 1/3rd to get dry volume of mortar generally for 1:4 to 1:6. • But in case on 1:2 and 1:3 the dry mortar volume shall be reduced by 3% as compared to above calculated because the voids in sand is lesser. • Calculate for 1:3, 1:4, 1:5 for 12 mm thick plaster • Calculate for 1:2, 1:3, 1:4 for 20 mm thick plaster 22 Cement Plaster 12 mm thick 1:6 on new brickwork Consider 100 sqm Particulars Quantity Rate Amount a Materials Cement 8 350 2800 Sand 1.64 1050 1722 Scaffolding 1% 176.72 b Labour Head Mason 0.5 800 400 Mason 10 600 6000 Mazdoor 15 450 6750 Contingencies 0.50% 89.2436 Water charges 1% 179.3796 Over head and profit 10% 1811.734 Total cost per 100 sqm 19929.08 Total cost per sqm 199.29
  • 41. https://www.linkedin.com/in/kailashchander, +91 9950461810 Analysis of Rate Plastering 23 Cement Plastering of 6 mm thickness 1:3 on ceiling. Consider 100 sqm area Particulars Quantity Rate Amount a Materials Cement 7 350 2450 Sand 0.7182 1050 754.11 Scaffolding 1% 150.0411 b Labour Head Mason 0.5 800 400 Mason 10 600 6000 Mazdoor 12 450 5400 Contingencies 0.50% 75.77 Water Charges 1% 152.30 Overhead and Profit 10% 1538.22 Total cost per 100 sqm 16920.44 Total cost per Sqm 169.20
  • 42. https://www.linkedin.com/in/kailashchander, +91 9950461810 Analysis of Rate for Road Works 24 Earthwork in excavation from borrow pits Particulars Quantity Rate Amount a Labour Mazdoor for cutting and placing 1.5 350 525 Mazdoor for loading and unloading 2 350 700 Mazdoor for rough dressing 0.2 350 70 Contingency 0.50% 6.48 Water 1% 13.01 Overhead and Profit 10% 131.45 Total cost per 10 cum 1445.94 Total cost per 1 cum 144.59 24 Earthwork in excavation from borrow pits by using JCB machine (NOT in COURSE) Particulars Quantity Rate Amount a Equipment JCB 0.083333 2000 166.67 JCB operators 0.083333 500 41.67 Fuel 4.166667 70 291.67 Helper 0.083333 350 29.17 Contingencies charges 0.50% 2.65 Water Charges 1% 5.32 Over head and Profit 10% 53.71 Total Cost per 10 cum 590.84 Total cost per 1 cum 59.08
  • 43. https://www.linkedin.com/in/kailashchander, +91 9950461810 Analysis of Rate for Flooring, Wood, road etc Not complete yet, Will discuss some more after valuation chapter