SlideShare a Scribd company logo
State Grid Corporation of China!
Otc.2013!
EV infrastructure and standardization in
China!
1 Overview of EV infrastructure construction
2 Standardization of EV infrastructure in China
Comparison of EV infrastructure Standards
3
EV infrastructure!
Charging ! Battery swap!
On-board
charging!
Off-board
charging!
Commercial
vehicle!
Passenger car
l  AC Charging spot! l  DC charger! l  Side-swapping!
l  Rear-swapping!
l  Bottom-swapping!
Overview-types of infrastructure
Private car
Private car
Public bus
Public bus
Sanitation vehicle
Private car
Taxi
【AC Charging Spot】
Item Spec.
Coupler GB
UI
LCD / LED / VFD
Keyboard
	
Billing RFID / IC card
Power
AC 220V (380V)
50Hz ± 1Hz
Output-U single-phase ,220V ± 10%
Output-I ≤ 32A
IP
	
 IP55
Communication
interface
RS485 / 2G / 3G
Installation Pillar/Wallbox
Overview-AC charging spot
Item Spec.
Coupler GB
UI
LCD / LED / VFD
Keyboard
	
Billing RFID / IC card
Power AC 380V ± 10%,50Hz -60Hz
Output
DC 200-500V, 0-100A
DC 300-700V, 0-250(600)A
Efficiency (50%-100%
load)	
≥92% 	
IP
	
 IP55
【DC Charger】
Overview-DC charger
【Battery swap
station】
Side-swapping: applicable to
commercial electric vehicles such as
buses and sanitation trucks which have
battery packs installed in both sides of
the vehicle body.
Rear-swapping:
applicable to
electric passenger
vehicles such as
private cars and
taxis, with battery packs installed in
the trunk of the vehicle body.
Bottom-swapping:
applicable to electric
passenger vehicles
such as private cars
and taxis, with battery packs installed in
the chasiss of the vehicle body.
Overview-battery swap station
Up to Jun.2013, SGCC has built 383 charging
stations/battery swap stations and 15,333 AC charging
spots.!
Overview-main supplier
Up to the end of 2012, CSG has built 18 charging
stations/battery swap stations and 3,229 AC charging
spots.!
Overview-main supplier
Up to the end of 2012, Potevio has built 74
charging stations.!
Overview-main supplier
27,400	
  
39,800	
  
49,700	
  
60,000	
  
2012.12	
   2013.03	
   2013.07	
  
pilot	
  city	
  
na6onwide	
  
Application of new energy vehicles in China!
Overview-summary of NEV
ISO/IEC China
Safety
Interface
Interoperability
Basic Component
System
Design Acceptance
Comparison of the standard structure between ISO/IEC and China
Standardization
ISO/IEC China
Corresponding of the standard
IEC 61851 GB/T 18487-2001
GB/T 27930-2011
IEC 62196
ISO 15118
GB/T 20234-2011
GB/T	
  27930-­‐2011
Q/GDW	
  397-­‐2009	
  
Q/GDW	
  398-­‐2009	
  
Q/GDW	
  399-­‐2009	
  
IEC 62840
GB/T 29317
Q/GDW	
  486-­‐2010	
  
Q/GDW	
  487-­‐2010	
  
Q/GDW	
  488-­‐2010	
  
Q/GDW	
  685-­‐2011	
  
Q/GDW	
  686-­‐2011	
  
System
Interface
Communication
Battery swap
Standardization
Na6onal	
  Standards	
  
No Publish	
  No Name
1 GB/T	
  20234.1-­‐2011
Connec&on	
  set	
  of	
  conduc&ve	
  charging	
  for	
  electric	
  vehicles-­‐
Part	
  1:General	
  requirements
2 GB/T	
  20234.2-­‐2011
Connec&on	
  set	
  of	
  conduc&ve	
  charging	
  for	
  electric	
  vehicles-­‐
Part2:AC	
  Charging	
  coupler
3 GB/T	
  20234.3-­‐2011
Connec&on	
  set	
  of	
  conduc&ve	
  charging	
  for	
  electric	
  vehicles-­‐
Part3:DC	
  charging	
  coupler
4 GB/T	
  27930-­‐2011
Communica&on	
  protocols	
  between	
  off-­‐board	
  conduc&ve	
  charger	
  and	
  
baCery	
  management	
  system	
  for	
  electric	
  vehicle
5 GB/T	
  28569-­‐2012 Electric	
  energy	
  metering	
  for	
  electric	
  vehicle	
  AC	
  charging	
  spot
6 GB/T	
  29317-­‐2012 Terminology	
  of	
  electric	
  vehicle	
  charging/baCery	
  swap	
  infrastructure	
  
7 GB/T	
  29318-­‐2012 Electric	
  energy	
  metering	
  for	
  electric	
  vehicle	
  off-­‐board	
  charger	
  
	
  Maintenance	
  of	
  GB18487.1	
  Electric	
  vehicle	
  conduc&ve	
  charging	
  
system	
  Part1:	
  General	
  requirement	
  (kick-­‐off	
  mee&ng	
  2013.09.02)	
  
Milestone:	
  2013.12	
  1st	
  	
  WD,	
  	
  	
  2014.03	
  2nd	
  WD,	
  	
  	
  2014.05	
  CD,	
  	
  	
  2014.09	
  FDIS
Standardization
(18	
  Industry	
  Standards	
  	
  and	
  37	
  Enterprise	
  Standards	
  are	
  published	
  or	
  being	
  prepared.)
China: Mode 2 and Mode 3 connection with single-phase(32A) power
supply are recommended, three-phase is under consideration.
Mode 2
Mode 1 Mode 3
Ø Mode 1 connection: normal socket-outlet charging
Ø Mode 2 connection : normal socket-outlet with in cable control box
Ø Mode 3 connection : dedicated AC charging spot
AC charging coupler
IEC 62196-2:2010 GB
20234.2-2011
Type1-U.S Type 2-Germany Type 3-Italy China
Phase
Current
Voltage
Single phase
32A(80A U.S)
250V
Single/Three phase
70A/63A
480V
Single phase
16A,32A/32A
250V,250V/500V
Single phase
(Three phase reserved)
16A,32A
250V/400V
Pin &
interlock
5-pin,
mechanical lock
7-pin,
electronic lock
4-pin, 5-pin 7-pin,
mechanical lock
(optional electronic lock)
Control pilot pin Two short pins One short pin, one long pin Two short pins
Male & female
pin
Plug: male
Vehicle connector: female
Plug: male
Vehicle connector: male
Dimensions
Comparison-AC charging coupler
Japan proposal CHAdeMO
China proposal GB/T 20234 Connection set for
conductive charging of electric vehicles
Germany proposal AC & DC Combo coupler
China
Japan Europe/US
Comparison-DC charging coupler
Ø Communication Protocol
International: China:
Physical layer PLC CAN BUS
Link/Network layer IP Based CAN
Ø PWM pilot control
International: China:
EVSE side Voltage detection Current detection
Comparison-Communication interconnection
Thank you for your attention!

More Related Content

PPTX
PPTX
Bharat electronics ltd.
PDF
Continuous and-discrete-signals-and-systems-2nd-edition-by-soliman-samir-s-sr...
PDF
Patent Watch report on EV, Self Driving Car, V2X
PDF
3M Electrical Catalogue - Low & High Voltage Cable Accessories (Scotchcast & ...
PDF
20220601_2022全球風能市場報告簡介
PDF
Wi-Fi Controlled Car
PDF
【Junior新趨勢_精準醫療】
Bharat electronics ltd.
Continuous and-discrete-signals-and-systems-2nd-edition-by-soliman-samir-s-sr...
Patent Watch report on EV, Self Driving Car, V2X
3M Electrical Catalogue - Low & High Voltage Cable Accessories (Scotchcast & ...
20220601_2022全球風能市場報告簡介
Wi-Fi Controlled Car
【Junior新趨勢_精準醫療】

What's hot (8)

PDF
Ic foundry
PDF
車用連結器
PDF
System-in-Package Technology and Market Trends 2021 - Sample
PDF
Junior新趨勢: 邊緣運算
PPTX
FPGA based mini Project.pptx
PPTX
Benefits and advantages of led lights ppt
PPTX
HEALTH MONITORING SYSTEM using mbed NXP LPC11U24
PDF
الأدب الإنجليزي
Ic foundry
車用連結器
System-in-Package Technology and Market Trends 2021 - Sample
Junior新趨勢: 邊緣運算
FPGA based mini Project.pptx
Benefits and advantages of led lights ppt
HEALTH MONITORING SYSTEM using mbed NXP LPC11U24
الأدب الإنجليزي
Ad

Similar to EVE-07-14e.pdf (20)

PPTX
Table-1,2,3.pptx
PDF
SOLAR POWERED WIRELESS CHARGING STATION FOR ELECTRIC CYCLE
PDF
vss102_lewis_2015_o
PDF
EV infrastructure - AC charger ABB
PPTX
Patent Landscape Report on “Electric vehicles – Vehicle to Grid Technology” b...
PDF
Ricardo DC-DC Converter Presentation for NMI
PDF
7 dani heredero v2_g_06_dani h
PDF
IRJET - Semi-Automated Electric Automobile Charger Testing Platform
PDF
Electric Vehicle Alternating Current Charging
PDF
Electric Motorbike
PPTX
EV Charging Infrastructure: Littelfuse Solutions to Enhance Safety, Efficienc...
PDF
Topological Advancement in DVR; A review
PDF
Circontrol Circarlife Catalogue 2013 2014 - EV Charging Stations
PDF
Beama ev guide
PDF
8 inch TFT-LCD Datesheet, AUO, 800*1280, MIPI Interface
PDF
IRJET - Single Phase Inverter using MOSFET
PDF
TechShanghai2016 - Reliable automotive-grade Isolators for new energy vehicles
PDF
IRJET- Smart Battery Management
PDF
IRJET- Speed Control of BLDC Motor using PID Tuned Fuzzy Controller
PDF
Speed control of single phase induction motor by android bluetooth
Table-1,2,3.pptx
SOLAR POWERED WIRELESS CHARGING STATION FOR ELECTRIC CYCLE
vss102_lewis_2015_o
EV infrastructure - AC charger ABB
Patent Landscape Report on “Electric vehicles – Vehicle to Grid Technology” b...
Ricardo DC-DC Converter Presentation for NMI
7 dani heredero v2_g_06_dani h
IRJET - Semi-Automated Electric Automobile Charger Testing Platform
Electric Vehicle Alternating Current Charging
Electric Motorbike
EV Charging Infrastructure: Littelfuse Solutions to Enhance Safety, Efficienc...
Topological Advancement in DVR; A review
Circontrol Circarlife Catalogue 2013 2014 - EV Charging Stations
Beama ev guide
8 inch TFT-LCD Datesheet, AUO, 800*1280, MIPI Interface
IRJET - Single Phase Inverter using MOSFET
TechShanghai2016 - Reliable automotive-grade Isolators for new energy vehicles
IRJET- Smart Battery Management
IRJET- Speed Control of BLDC Motor using PID Tuned Fuzzy Controller
Speed control of single phase induction motor by android bluetooth
Ad

More from Zulhamidi Zulhamidi (20)

PDF
Menentukan Beban Angin Rencana Sesuai SNI 1727-2019.pdf
PPTX
Tata cara peremajaan data di Myasn(1).pptx
PPTX
UNDERSTANDING SaMD, MDSW AND SiMD .pptx
PDF
Heri Subagyo_Pupuk Kaltim_Manfaat Implementasi Sistem Manajemen Energi SNI IS...
PDF
Dewi Komalasari_BSN_SME-Persyaratan dengan pedoman penggunaan.pdf
PDF
Kristianto W_BSN_Dukungan SNI Dalam Meningkatkan Efisiensi Energi.pdf
PDF
EVS-06-33e.pdf
PDF
Battery Management System For Electric Vehicle Applications.pdf
PDF
EVS-08-19e.pdf
PDF
ANSI_EVSP_Roadmap_May_2013.pdf
PDF
Final Product information and specification_20170802 to BSN.pdf
PDF
EVS-04-12e.pdf
PDF
EVS-1-08 (1).pdf
PDF
EVS-1-08.pdf
PDF
SNI UNTUK DAYA SAING PRODUK DAN JASA.pdf
DOCX
Tesis tentang Training Kompetensi
PDF
Motivation at work Deck_HR Business Talks 18 January 2022.pdf
PDF
materi SNI dan CPPOB.pdf
PDF
Smart City sesuai Standar ISO
PDF
Success story umkm_program_pembinaan_penerapan_sni-bsn_(2018)
Menentukan Beban Angin Rencana Sesuai SNI 1727-2019.pdf
Tata cara peremajaan data di Myasn(1).pptx
UNDERSTANDING SaMD, MDSW AND SiMD .pptx
Heri Subagyo_Pupuk Kaltim_Manfaat Implementasi Sistem Manajemen Energi SNI IS...
Dewi Komalasari_BSN_SME-Persyaratan dengan pedoman penggunaan.pdf
Kristianto W_BSN_Dukungan SNI Dalam Meningkatkan Efisiensi Energi.pdf
EVS-06-33e.pdf
Battery Management System For Electric Vehicle Applications.pdf
EVS-08-19e.pdf
ANSI_EVSP_Roadmap_May_2013.pdf
Final Product information and specification_20170802 to BSN.pdf
EVS-04-12e.pdf
EVS-1-08 (1).pdf
EVS-1-08.pdf
SNI UNTUK DAYA SAING PRODUK DAN JASA.pdf
Tesis tentang Training Kompetensi
Motivation at work Deck_HR Business Talks 18 January 2022.pdf
materi SNI dan CPPOB.pdf
Smart City sesuai Standar ISO
Success story umkm_program_pembinaan_penerapan_sni-bsn_(2018)

Recently uploaded (20)

PDF
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
PDF
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
DOCX
573137875-Attendance-Management-System-original
PPTX
UNIT 4 Total Quality Management .pptx
PPTX
OOP with Java - Java Introduction (Basics)
PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PDF
composite construction of structures.pdf
PPTX
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
PDF
July 2025 - Top 10 Read Articles in International Journal of Software Enginee...
PDF
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
PDF
Structs to JSON How Go Powers REST APIs.pdf
PPTX
web development for engineering and engineering
PDF
Well-logging-methods_new................
DOCX
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
PPT
Project quality management in manufacturing
PPTX
Sustainable Sites - Green Building Construction
PDF
PRIZ Academy - 9 Windows Thinking Where to Invest Today to Win Tomorrow.pdf
PPTX
CH1 Production IntroductoryConcepts.pptx
PPTX
Geodesy 1.pptx...............................................
PPTX
Lecture Notes Electrical Wiring System Components
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
573137875-Attendance-Management-System-original
UNIT 4 Total Quality Management .pptx
OOP with Java - Java Introduction (Basics)
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
composite construction of structures.pdf
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
July 2025 - Top 10 Read Articles in International Journal of Software Enginee...
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
Structs to JSON How Go Powers REST APIs.pdf
web development for engineering and engineering
Well-logging-methods_new................
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
Project quality management in manufacturing
Sustainable Sites - Green Building Construction
PRIZ Academy - 9 Windows Thinking Where to Invest Today to Win Tomorrow.pdf
CH1 Production IntroductoryConcepts.pptx
Geodesy 1.pptx...............................................
Lecture Notes Electrical Wiring System Components

EVE-07-14e.pdf

  • 1. State Grid Corporation of China! Otc.2013! EV infrastructure and standardization in China!
  • 2. 1 Overview of EV infrastructure construction 2 Standardization of EV infrastructure in China Comparison of EV infrastructure Standards 3
  • 3. EV infrastructure! Charging ! Battery swap! On-board charging! Off-board charging! Commercial vehicle! Passenger car l  AC Charging spot! l  DC charger! l  Side-swapping! l  Rear-swapping! l  Bottom-swapping! Overview-types of infrastructure Private car Private car Public bus Public bus Sanitation vehicle Private car Taxi
  • 4. 【AC Charging Spot】 Item Spec. Coupler GB UI LCD / LED / VFD Keyboard Billing RFID / IC card Power AC 220V (380V) 50Hz ± 1Hz Output-U single-phase ,220V ± 10% Output-I ≤ 32A IP IP55 Communication interface RS485 / 2G / 3G Installation Pillar/Wallbox Overview-AC charging spot
  • 5. Item Spec. Coupler GB UI LCD / LED / VFD Keyboard Billing RFID / IC card Power AC 380V ± 10%,50Hz -60Hz Output DC 200-500V, 0-100A DC 300-700V, 0-250(600)A Efficiency (50%-100% load) ≥92% IP IP55 【DC Charger】 Overview-DC charger
  • 6. 【Battery swap station】 Side-swapping: applicable to commercial electric vehicles such as buses and sanitation trucks which have battery packs installed in both sides of the vehicle body. Rear-swapping: applicable to electric passenger vehicles such as private cars and taxis, with battery packs installed in the trunk of the vehicle body. Bottom-swapping: applicable to electric passenger vehicles such as private cars and taxis, with battery packs installed in the chasiss of the vehicle body. Overview-battery swap station
  • 7. Up to Jun.2013, SGCC has built 383 charging stations/battery swap stations and 15,333 AC charging spots.! Overview-main supplier
  • 8. Up to the end of 2012, CSG has built 18 charging stations/battery swap stations and 3,229 AC charging spots.! Overview-main supplier
  • 9. Up to the end of 2012, Potevio has built 74 charging stations.! Overview-main supplier
  • 10. 27,400   39,800   49,700   60,000   2012.12   2013.03   2013.07   pilot  city   na6onwide   Application of new energy vehicles in China! Overview-summary of NEV
  • 11. ISO/IEC China Safety Interface Interoperability Basic Component System Design Acceptance Comparison of the standard structure between ISO/IEC and China Standardization
  • 12. ISO/IEC China Corresponding of the standard IEC 61851 GB/T 18487-2001 GB/T 27930-2011 IEC 62196 ISO 15118 GB/T 20234-2011 GB/T  27930-­‐2011 Q/GDW  397-­‐2009   Q/GDW  398-­‐2009   Q/GDW  399-­‐2009   IEC 62840 GB/T 29317 Q/GDW  486-­‐2010   Q/GDW  487-­‐2010   Q/GDW  488-­‐2010   Q/GDW  685-­‐2011   Q/GDW  686-­‐2011   System Interface Communication Battery swap Standardization
  • 13. Na6onal  Standards   No Publish  No Name 1 GB/T  20234.1-­‐2011 Connec&on  set  of  conduc&ve  charging  for  electric  vehicles-­‐ Part  1:General  requirements 2 GB/T  20234.2-­‐2011 Connec&on  set  of  conduc&ve  charging  for  electric  vehicles-­‐ Part2:AC  Charging  coupler 3 GB/T  20234.3-­‐2011 Connec&on  set  of  conduc&ve  charging  for  electric  vehicles-­‐ Part3:DC  charging  coupler 4 GB/T  27930-­‐2011 Communica&on  protocols  between  off-­‐board  conduc&ve  charger  and   baCery  management  system  for  electric  vehicle 5 GB/T  28569-­‐2012 Electric  energy  metering  for  electric  vehicle  AC  charging  spot 6 GB/T  29317-­‐2012 Terminology  of  electric  vehicle  charging/baCery  swap  infrastructure   7 GB/T  29318-­‐2012 Electric  energy  metering  for  electric  vehicle  off-­‐board  charger    Maintenance  of  GB18487.1  Electric  vehicle  conduc&ve  charging   system  Part1:  General  requirement  (kick-­‐off  mee&ng  2013.09.02)   Milestone:  2013.12  1st    WD,      2014.03  2nd  WD,      2014.05  CD,      2014.09  FDIS Standardization (18  Industry  Standards    and  37  Enterprise  Standards  are  published  or  being  prepared.)
  • 14. China: Mode 2 and Mode 3 connection with single-phase(32A) power supply are recommended, three-phase is under consideration. Mode 2 Mode 1 Mode 3 Ø Mode 1 connection: normal socket-outlet charging Ø Mode 2 connection : normal socket-outlet with in cable control box Ø Mode 3 connection : dedicated AC charging spot AC charging coupler
  • 15. IEC 62196-2:2010 GB 20234.2-2011 Type1-U.S Type 2-Germany Type 3-Italy China Phase Current Voltage Single phase 32A(80A U.S) 250V Single/Three phase 70A/63A 480V Single phase 16A,32A/32A 250V,250V/500V Single phase (Three phase reserved) 16A,32A 250V/400V Pin & interlock 5-pin, mechanical lock 7-pin, electronic lock 4-pin, 5-pin 7-pin, mechanical lock (optional electronic lock) Control pilot pin Two short pins One short pin, one long pin Two short pins Male & female pin Plug: male Vehicle connector: female Plug: male Vehicle connector: male Dimensions Comparison-AC charging coupler
  • 16. Japan proposal CHAdeMO China proposal GB/T 20234 Connection set for conductive charging of electric vehicles Germany proposal AC & DC Combo coupler China Japan Europe/US Comparison-DC charging coupler
  • 17. Ø Communication Protocol International: China: Physical layer PLC CAN BUS Link/Network layer IP Based CAN Ø PWM pilot control International: China: EVSE side Voltage detection Current detection Comparison-Communication interconnection
  • 18. Thank you for your attention!