SlideShare a Scribd company logo
5
Most read
7
Most read
11
Most read
Project Planning and Development
(MPA 209)
Fast Tracking a Project and Project Crashing
Josefina B. Bitonio, DPA
Professor
Fast Tracking a Project and Project Crashing.ppt
FAST TRACKING
Fast-tracking is a schedule compression
technique in which activities or phases normally
performed in a sequence are done in parallel
for at least a portion of their duration.
Fastracking
1. Details may be missed
2. Burnout among team members
What are the Risks of Fastracking
The main disadvantage of project fast tracking is the
potential for risks that may occur due to task
overlapping and dependencies. To be effective, fast
tracking requires a high level of analysis when
reorganizing activity sequences.
Project Crashing
As a compression technique, crashing concentrates on the project schedule in an effort to
accelerate the project's completion date. Plausible examples of crashing include the following:
•Over-time
•Allocating additional resources to specific activities
•Hiring additional resources
•Incentive payments for early completion
•Subsequently outsourcing portions of the project to be completed within a shorter time period
than would have been possible if the same work was to be completed by internal resources.
https://www.pmi.org/learning/library/performing-crash-analysis-alternative-cost-schedule-
6750#:~:text=Crash%20analysis%20would%20be%20used,a%20cost%20of%20%241.9%20million.
CRASHING
Crashing is a technique
used to shorten the
schedule duration for
the least incremental
cost by adding
resources.
CRASHING
https://www.pmi.org/learning/library/performing-crash-
analysis-alternative-cost-schedule-
6750#:~:text=Crash%20analysis%20would%20be%20us
ed,a%20cost%20of%20%241.9%20million.
1. Project deadline is approaching and there is still a
lot of work to be done
2. There is a delay in starting the project
Why Do We Apply Schedule Compression
on Critical Path Activities?
In summary, the
differences between fast
tracking and crashing
are:
Fast tracking involves
the performance of
activities in parallel,
whereas crashing
involves the addition of
resources to a project.
Sources
Eternity Trainings: Agile & Waterfall
Projects
https://www.youtube.com/watch?v=72T8
DqBDCMc
https://www.pmi.org/learning/library/performing-crash-analysis-alternative-cost-
schedule-
6750#:~:text=Crash%20analysis%20would%20be%20used,a%20cost%20of%2
0%241.9%20million.
Fast Tracking a Project and Project Crashing.ppt
Thank
you!

More Related Content

PPTX
project management
PDF
Topic 11 - Project Schedule Management.pdf
PPTX
PROJECT SCHEDULE
PDF
PMP Lecture 1: Introduction to Project Management
PDF
Schedule Updates
PDF
Recovery Scheduling
PDF
Introduction to Project Management
PPT
Construction scheduling & Cost control
project management
Topic 11 - Project Schedule Management.pdf
PROJECT SCHEDULE
PMP Lecture 1: Introduction to Project Management
Schedule Updates
Recovery Scheduling
Introduction to Project Management
Construction scheduling & Cost control

What's hot (20)

PDF
Resource allocation and smoothing
PPT
Project Management Tools and Techniques
PPTX
Project risk management
PPTX
Risk Management
PPT
Challenges Of Project Management
PPTX
6.5 Resource Leveling and Resource Smoothing
PDF
Time Impact Analysis
PPTX
Introduction to Project Management (workshop) - v.1
PPTX
Project management
PPTX
RESOURCE LEVELLING (MS PROJECT)
PDF
Project Risk Management - PMBOK5
PPTX
Earned Value Analysis
PDF
Project management in construction.
PPTX
Construction Delay Analysis, Simplified
PPTX
Interface Management: A Systemic Approach for Projects and Organizations
PPT
06. Project Management Process Groups
PPTX
Project management
PPT
Project management methodologies
PPTX
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Resource allocation and smoothing
Project Management Tools and Techniques
Project risk management
Risk Management
Challenges Of Project Management
6.5 Resource Leveling and Resource Smoothing
Time Impact Analysis
Introduction to Project Management (workshop) - v.1
Project management
RESOURCE LEVELLING (MS PROJECT)
Project Risk Management - PMBOK5
Earned Value Analysis
Project management in construction.
Construction Delay Analysis, Simplified
Interface Management: A Systemic Approach for Projects and Organizations
06. Project Management Process Groups
Project management
Project management methodologies
Project Management Tools and Techniques (PERT- Project Evaluation and Review ...
Ad

Similar to Fast Tracking a Project and Project Crashing.ppt (20)

PPTX
Project_Crashing_Presentation on project management .pptx
PPTX
Project Management Diagnostics for Time Management
PPTX
Estimate budget and project crashing.pptx
PPT
crashing of project
PPTX
Reducing Project Duration_Jagat Prasad Upadhyay.pptx
PPT
Resource-Allocation.ppt
PPTX
Fast Tracking a Project
PPTX
dokumen.tips_ms-project-presentation.pptx
PPTX
ms-project-presentation.pptx
PDF
Information Technology Project Management 5th Edition Marchewka Solutions Manual
PDF
Information Technology Project Management 5th Edition Marchewka Solutions Manual
PPT
ch05_crashing.ppt
PPTX
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...
PDF
Information Technology Project Management 5th Edition Marchewka Solutions Manual
PPTX
44259126 ms-project-presentation
PPTX
MS Project Presentation
PPTX
Ms project presentation
PPT
Crashing and Updating.ppt
PPT
Chapter-5-Scheduling-and-Resource-Allocation.ppt
PPTX
Jpunch 02-16-2012
Project_Crashing_Presentation on project management .pptx
Project Management Diagnostics for Time Management
Estimate budget and project crashing.pptx
crashing of project
Reducing Project Duration_Jagat Prasad Upadhyay.pptx
Resource-Allocation.ppt
Fast Tracking a Project
dokumen.tips_ms-project-presentation.pptx
ms-project-presentation.pptx
Information Technology Project Management 5th Edition Marchewka Solutions Manual
Information Technology Project Management 5th Edition Marchewka Solutions Manual
ch05_crashing.ppt
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...
Information Technology Project Management 5th Edition Marchewka Solutions Manual
44259126 ms-project-presentation
MS Project Presentation
Ms project presentation
Crashing and Updating.ppt
Chapter-5-Scheduling-and-Resource-Allocation.ppt
Jpunch 02-16-2012
Ad

More from Jo Balucanag - Bitonio (20)

DOCX
Training for Trainers DMMMSU Open University Batch 9 Comments- critiques-reco...
PPTX
Organization & Management Theories.pptx
PPT
AN INTRODUCTION TO ORGANIZATION THEORY
PPTX
MPA 210 : STRATEGIC QUALITY MANAGEMENT
PPTX
MPA 210 : POVERTY PLAN ASSESSMENT.pptx
PPTX
MPA 210 : MANAGEMENT CONCEPTS .pptx
PPTX
MPA 210 :Civil Society Organization.pptx
PPTX
ASSESSMENT PUBLIC REFORMS PHILIPPINES
PDF
ASSESSMENT OF INFRASTRUCTURE DEVELOPMENT
PDF
MPA 210 Aligned Strategy Development.pdf
PPTX
MPA 209 : Project Planning Presentation
PPTX
PROJECT DESIGN & DEVELOPMENT PHASE.pptx
PPTX
PLAN FOR MONITORING AND EVALUATING .pptx
PDF
MPA 209 : PLAN FOR IMPLEMENTATION.pdf
PDF
Issues & Concerns in Project Mgmtnt.pdf
PPTX
Government Stimulus Program for MSMEs
PPTX
MPA 213 : Philippine Rural Development
PPTX
ISSUES AND IMPLICATIONS OF URBANIZATION
PPTX
Human Beings: Consequence development
PPTX
MPA 207 : DEVT ISSUES AND CONCERNS.pptx
Training for Trainers DMMMSU Open University Batch 9 Comments- critiques-reco...
Organization & Management Theories.pptx
AN INTRODUCTION TO ORGANIZATION THEORY
MPA 210 : STRATEGIC QUALITY MANAGEMENT
MPA 210 : POVERTY PLAN ASSESSMENT.pptx
MPA 210 : MANAGEMENT CONCEPTS .pptx
MPA 210 :Civil Society Organization.pptx
ASSESSMENT PUBLIC REFORMS PHILIPPINES
ASSESSMENT OF INFRASTRUCTURE DEVELOPMENT
MPA 210 Aligned Strategy Development.pdf
MPA 209 : Project Planning Presentation
PROJECT DESIGN & DEVELOPMENT PHASE.pptx
PLAN FOR MONITORING AND EVALUATING .pptx
MPA 209 : PLAN FOR IMPLEMENTATION.pdf
Issues & Concerns in Project Mgmtnt.pdf
Government Stimulus Program for MSMEs
MPA 213 : Philippine Rural Development
ISSUES AND IMPLICATIONS OF URBANIZATION
Human Beings: Consequence development
MPA 207 : DEVT ISSUES AND CONCERNS.pptx

Recently uploaded (20)

PDF
Chapter 2 Heredity, Prenatal Development, and Birth.pdf
PPTX
Final Presentation General Medicine 03-08-2024.pptx
PPTX
Cell Structure & Organelles in detailed.
PDF
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
PDF
Weekly quiz Compilation Jan -July 25.pdf
PDF
RMMM.pdf make it easy to upload and study
PDF
grade 11-chemistry_fetena_net_5883.pdf teacher guide for all student
PPTX
school management -TNTEU- B.Ed., Semester II Unit 1.pptx
PDF
The Lost Whites of Pakistan by Jahanzaib Mughal.pdf
PPTX
GDM (1) (1).pptx small presentation for students
PDF
Trump Administration's workforce development strategy
PDF
RTP_AR_KS1_Tutor's Guide_English [FOR REPRODUCTION].pdf
PDF
O5-L3 Freight Transport Ops (International) V1.pdf
PPTX
Microbial diseases, their pathogenesis and prophylaxis
PPTX
Introduction-to-Literarature-and-Literary-Studies-week-Prelim-coverage.pptx
PDF
A systematic review of self-coping strategies used by university students to ...
PDF
Chinmaya Tiranga quiz Grand Finale.pdf
PDF
01-Introduction-to-Information-Management.pdf
PDF
Microbial disease of the cardiovascular and lymphatic systems
PDF
Abdominal Access Techniques with Prof. Dr. R K Mishra
Chapter 2 Heredity, Prenatal Development, and Birth.pdf
Final Presentation General Medicine 03-08-2024.pptx
Cell Structure & Organelles in detailed.
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
Weekly quiz Compilation Jan -July 25.pdf
RMMM.pdf make it easy to upload and study
grade 11-chemistry_fetena_net_5883.pdf teacher guide for all student
school management -TNTEU- B.Ed., Semester II Unit 1.pptx
The Lost Whites of Pakistan by Jahanzaib Mughal.pdf
GDM (1) (1).pptx small presentation for students
Trump Administration's workforce development strategy
RTP_AR_KS1_Tutor's Guide_English [FOR REPRODUCTION].pdf
O5-L3 Freight Transport Ops (International) V1.pdf
Microbial diseases, their pathogenesis and prophylaxis
Introduction-to-Literarature-and-Literary-Studies-week-Prelim-coverage.pptx
A systematic review of self-coping strategies used by university students to ...
Chinmaya Tiranga quiz Grand Finale.pdf
01-Introduction-to-Information-Management.pdf
Microbial disease of the cardiovascular and lymphatic systems
Abdominal Access Techniques with Prof. Dr. R K Mishra

Fast Tracking a Project and Project Crashing.ppt

  • 1. Project Planning and Development (MPA 209) Fast Tracking a Project and Project Crashing Josefina B. Bitonio, DPA Professor
  • 3. FAST TRACKING Fast-tracking is a schedule compression technique in which activities or phases normally performed in a sequence are done in parallel for at least a portion of their duration.
  • 5. 1. Details may be missed 2. Burnout among team members What are the Risks of Fastracking The main disadvantage of project fast tracking is the potential for risks that may occur due to task overlapping and dependencies. To be effective, fast tracking requires a high level of analysis when reorganizing activity sequences.
  • 6. Project Crashing As a compression technique, crashing concentrates on the project schedule in an effort to accelerate the project's completion date. Plausible examples of crashing include the following: •Over-time •Allocating additional resources to specific activities •Hiring additional resources •Incentive payments for early completion •Subsequently outsourcing portions of the project to be completed within a shorter time period than would have been possible if the same work was to be completed by internal resources. https://www.pmi.org/learning/library/performing-crash-analysis-alternative-cost-schedule- 6750#:~:text=Crash%20analysis%20would%20be%20used,a%20cost%20of%20%241.9%20million.
  • 7. CRASHING Crashing is a technique used to shorten the schedule duration for the least incremental cost by adding resources.
  • 10. 1. Project deadline is approaching and there is still a lot of work to be done 2. There is a delay in starting the project Why Do We Apply Schedule Compression on Critical Path Activities?
  • 11. In summary, the differences between fast tracking and crashing are: Fast tracking involves the performance of activities in parallel, whereas crashing involves the addition of resources to a project.
  • 12. Sources Eternity Trainings: Agile & Waterfall Projects https://www.youtube.com/watch?v=72T8 DqBDCMc https://www.pmi.org/learning/library/performing-crash-analysis-alternative-cost- schedule- 6750#:~:text=Crash%20analysis%20would%20be%20used,a%20cost%20of%2 0%241.9%20million.