DIAGNOSTICS FOR
TIME MANAGEMENT
TO C R A S H O R N OT TO C R A S H ?
TA K E T H E G U E S S W O R K O U T O F Y O U R D E A D L I N E .
PROJECT TIME MANAGEMENT
KNOWLEDGE AREA
• AGENDA:
– COST TIME TRADE OFFS OF CRASHING
– PROBABILITY OF COMPLETING A PROJECT BASED ON PERT ANALYSYS
• PMBOK GUIDE 6TH EDITION
• DEVELOP SCHEDULE: TOOLS AND TECHNIQUES –
– SCHEDULE COMPRESSION – CRASHING (6.5.2.6)
– DATA ANALYSIS – SIMULATION MODELS (6.5.2.4)
• PLANNING PROCESS GROUP
WHO WE ARE
• ROBERT DAVIES – LEAD ELECTRONICS ENGINEER, PRIDE MOBILITY PRODUCTS
• MS ENGINEERING OPERATIONS AND STRATEGY 2018’
• OVER A DECADE OF EXPERIENCE IN ELECTRICAL/ELECTRONIC SYSTEMS DESIGN
• 4 US PATENTS (PENDING) & 1 EU PATENT (PENDING)
• APRIL DAVIES – PROJECT COORDINATOR, TMG HEALTH / COGNIZANT
• MS PROJECT MANAGEMENT (HEALTHCARE ADMINISTRATION) 2018
• MA COMMUNICATION ARTS – MARYWOOD UNIVERSITY
• DECADE OF EXPERIECNE IN EXECUTIVE LEVEL SUPPORT AND SPECIAL PROJECTS
• CAPM JUNE 2017
PROJECT
CRASHING
PROJECT CRASHING
• The PMBOK defines project crashing as a technique used to
shorten the schedule duration for the least cost by adding
resources.
• Crashing is one method of schedule compression used to
accelerate the schedule duration to meet constraints, key
dates and other schedule objectives without reducing the
project scope.
COST TIME TRADE OFFS OF
CRASHING
• When managing a project it’s not uncommon for a project
manager to be faced with these scenarios.
–A project is falling behind schedule.
And/or
–The scheduled completion date of a project is moved
forward.
–In either scenario, we need to determine how to speed up
the activities that occur within the project’s pipeline.
DETERMINING ACTIVITIES TO CRASH
• The concern lies in the question of:
– Which activities should be shortened?
– How many activities should be shortened?
• The project manager needs to review the critical activities and
determine which would have the least impact to the cost.
• Costs need to be compared, but how?
• Assumptions:
– Manager is working to ensure that the cost of the crash is permissible.
– The shortened activity time will allow us to meet the due date.
– Total cost of crashing is as small as possible.
PROJECT COSTS
• Project direct costs to the project that consist of labor, materials,
equipment and contractor expenses.
• Direct cost are assigned to each of the project activities.
• Under a normal assumption, the direct costs represent normal delivery
of project activities.
• Changes to the normal delivery of of these activities would constitute an
increase to the project’s direct costs.
• The sum of all project costs is equivalent to the sum of all activities and
the total direct cost of the project.
• Not all costs are the same for every activity, therefore it could be
difficult to determine which activity to shorten.
COST TIME TRADE OFF
Crash Point
Cost
Activity 1
Activity 2
Crash Point
Normal
HOW TO CRASH A PROJECT
1) Compute the crash cost per time period.
2) Find the critical path of the project’s network.
3) Find the activities on the critical path that can be
crashed and have the smallest crash cost.
4) Update activity times to determine if the desired due
dates can be reached.
THE DILEMMA
T H E D E L I M M A
Julie Anne’s boss tells her
that she must complete her
project at an earlier than
anticipated due date. He is
willing to pay any price to
have the project come in
sooner then planned. Julie
Anne needs to determine
which activities to crash, by
how much, and how to meet
his 13 week deadline which
was shortened from 15
weeks. She would like to
speed up her project by 2
weeks at the least minimal
STEP 1
Compute the crash cost per time period.
Crash Cost per Period =
Crash Cost – Normal Cost
Normal Time – Crash Time
CALCULATING CRASH COST
Crash Cost =
Crash Cost – Normal Cost
Normal Time – Crash Time
Activity Normal Time Crash Time Normal Cost Crash Cost Cost per
time period
A 2 1 22,000 22,750 750
B 3 1 30,000 34,000 2,000
C 2 1 26,000 27,000 1,000
D 4 3 48,000 49,000 1,000
E 4 2 56,000 58,000 1,000
F 3 2 30,000 30,500 500
G 5 2 80,000 84,500 1,500
H 2 1 16,000 19,000 3,000
CRITICAL PATH
POP QUIZ
STEP 2
Find the Critical Path
S
0
F
3
G
5
E
4
B
3
D
4
C
2
A
2
H
2
Activity
Duration
STEP 2
Find the Critical Path
S
0
F
3
G
5
E
4
B
3
D
4
C
2
A
2
H
2
Activity
Duration
STEP 3
• Find the critical path activities with smallest crash cost.
Activity Normal
Time
Crash
Time
Normal
Cost
Crash
Cost
Cost per
time
period
Critical
Path
A 2 1 22,000 22,750 750 Yes
B 3 1 30,000 34,000 2,000 No
C 2 1 26,000 27,000 1,000 Yes
D 4 3 48,000 49,000 1,000 No
E 4 2 56,000 58,000 1,000 Yes
F 3 2 30,000 30,500 500 No
G 5 2 80,000 84,500 1,500 Yes
H 2 1 16,000 19,000 3,000 Yes
STEP 4
Update activity times to determine if the desired due dates can be
reached.
S
0
F
3
G
5
E
4
B
3
D
4
C
2
A
2
H
2
Activity
Duration
15 weeks
Act T $
A 1 750
C 1 1,000
E 2 1,000
G 2 1,500
H 1 3,000
STEP 4
Update activity times to determine if the desired due dates can be
reached.
S
0
F
3
G
5
E
4
B
3
D
4
C
2
A
2
H
2
Activity
Duration
15 weeks
Act T $
A 1 750
C 1 1,000
E 2 1,000
G 2 1,500
H 1 3,000
STEP 4
Update activity times to determine if the desired due dates can be
reached.
S
0
F
3
G
5
E
4
B
3
D
4
C
2
A
1
H
2
Activity
Duration
14 weeks
Total: $750
Act T $
A 1 750
C 1 1,000
E 2 1,000
G 2 1,500
H 1 3,000
STEP 4
Update activity times to determine if the desired due dates can be
reached.
S
0
F
3
G
5
E
4
B
3
D
4
C
2
A
1
H
2
Activity
Duration
13 weeks
Act T $
A 1 750
C 1 1,000
E 2 1,000
G 2 1,500
H 1 3,000
Total: $2,750
STEP 4
Update activity times to determine if the desired due dates can be
reached.
S
0
F
3
G
5
E
4
B
3
D
4
C
2
A
2
H
2
Activity
Duration
15 weeks
Act T $
A 1 750
C 1 1,000
E 2 1,000
G 2 1,500
H 1 3,000
Total: $1,500
STEP 4
Update activity times to determine if the desired due dates can be
reached.
S
0
F
3
G
2
E
4
B
3
D
4
C
2
A
2
H
2
Activity
Duration
12 weeks
Act T $
A 1 750
C 1 1,000
E 2 1,000
G 2 1,500
H 1 3,000
SUCCESSFUL CRASH REMINDERS
• Ensure that the cost to crash is as small as possible.
• Update your project with new activity times and budget with
new cost considerations. Crashing only works for critical path
activities.
• Crashing can increase risk. Reevaluate risk as needed.
• Ensure your resources are available to complete the crash.
• Receive the proper prior authorization to make the change (CR)
• Remember to be considerate of money. Consider the approach
of take only what is needed.
• Remember Responsible Crashing: Always Weigh Impact to
Quality
– 4 Hour House – What is the cost of quality.
– https://www.youtube.com/watch?v=oDB1O5cadQw
PERT ANALYSIS
WHAT IS PERT?
• The program (or project) evaluation and review
technique, commonly abbreviated PERT, is a
statistical tool, used in project management…
PERT
HISTORY?
• Initially PERT stood for
Program Evaluation
Research Task
• Started by the US NAVY
1950’s – as part of a
(CPM) analysis Critical
Path Method.
• Design to simplify and
plan complex projects i.e.
building of a nuclear
submarines.
WHAT DOES PERT DO?
• PERT - in its simplest form is a tool for estimating
the probability of completing a task (program or
project) in a given time constraint.
• “What is the confidence level of completing phase
2 by Oct 15th ?” said the VP
EXAMPLE OF PERT
PERT STEP 1.
• Identify Critical Path Tasks
• The longest possible continuous pathway taken from the
initial event to the terminal event. It determines the total
calendar time required for the project; and, therefore, any
time delays along the critical path will delay the reaching
of the terminal event by at least the same amount.
PERT STEP 2.
• Optimistic : The
minimum possible
time required to
accomplish a task,
assuming
everything
proceeds better
than is normally
expected.
PERT STEP 3.
• Likely : The best
estimate of the time
required to
accomplish a task,
assuming everything
proceeds as normal.
PERT STEP 4.
• Pessimistic : The
maximum possible
time required to
accomplish a task,
assuming
everything goes
wrong (but
excluding major
catastrophes).
PERT STEP 5.
• Calculate Expected Duration using given inputs
PERT STEP 6.
• Calculate Standard Deviation / Variance
PERT STEP 6.2.0
• Calculate Standard Deviation / Variance
PERT STEP 7.
• Given a due date we can calculate the
probability of meeting a particular due date
PERT STEP 8.
• Now we look up
Z in the Normal
Distribution
Table
PERT STEP 9.
• That’s it! Report the probability of completion in
percentage i.e. 0.99 equates to 99% probability.
QUESTIONS AND
CONCLUSION

More Related Content

PPT
PROJECT SCHEDULING
PPTX
Project management technique PERT & CPM
PPT
crashing of project
PPT
Pert & Cpm
PPT
Pert
PPTX
Project Management Techniques ( CPM & PERT Techniques )
PPTX
Delay analysis of raw water reservoir and pumping Station
PROJECT SCHEDULING
Project management technique PERT & CPM
crashing of project
Pert & Cpm
Pert
Project Management Techniques ( CPM & PERT Techniques )
Delay analysis of raw water reservoir and pumping Station

What's hot (19)

PPT
Chapter 6 project management
PPTX
Project management techniques
PPTX
00 Introduction of project scheduling
PDF
construction project planing
PPT
Software project-scheduling
PDF
Meeting Project Schedule Compliance Standards
PPTX
Project scheduling
PPTX
Pb602 operation management chapter 7
PDF
CPM-Updating
ODP
Critical path method
PPTX
PERT-CPM : PROJECT MANAGEMENT TOOLS
PPT
Program Evaluation and Review Technique
PDF
Critical Path Method
PDF
Complex Project Crashing Algorithm
DOCX
Project scheduling
PPTX
Program Evaluation and Review Technique (PERT)
PPTX
PROJECT SCHEDULE
PDF
Critical Path Analysis
PPT
Time cost optimisation
Chapter 6 project management
Project management techniques
00 Introduction of project scheduling
construction project planing
Software project-scheduling
Meeting Project Schedule Compliance Standards
Project scheduling
Pb602 operation management chapter 7
CPM-Updating
Critical path method
PERT-CPM : PROJECT MANAGEMENT TOOLS
Program Evaluation and Review Technique
Critical Path Method
Complex Project Crashing Algorithm
Project scheduling
Program Evaluation and Review Technique (PERT)
PROJECT SCHEDULE
Critical Path Analysis
Time cost optimisation
Ad

Similar to Project Management Diagnostics for Time Management (20)

PPTX
MARKS IN YOUR POCKET PMP for PMP Preparation
PPT
Project planning-and-control
PDF
PERT AND CPM PROJECT MANAGEMENT
PPTX
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptx
PPTX
PERT-AND-CPM JNIBJJJJJJJJJJJJJJJJJJ.pptx
PPTX
Materi 08 ( Project Management for Manufacturing ).pptx
PPTX
Project Managment overview and definition
PDF
Cpm n pert
PPTX
Critical Path Method
PPT
project management -04.ppt
PPTX
Unit 3 PERT.pptx in related to supply chain
PPT
Chapter 12(cpm pert)
PPTX
cpmpertmy (1)
PDF
MandC.pdf
PPT
7. (lecture 5) Project scheduling..ppt
PPTX
Pert and CPM
PPTX
Ch 06 - CPM PERT (1).pptx
PPT
Comparative characteristics of pert and cpm
PPTX
Unit IV-Project Management
PPTX
Primavera presentation
MARKS IN YOUR POCKET PMP for PMP Preparation
Project planning-and-control
PERT AND CPM PROJECT MANAGEMENT
CCM821S _ Contract Management _ 8. Monitoring Project Performance.pptx
PERT-AND-CPM JNIBJJJJJJJJJJJJJJJJJJ.pptx
Materi 08 ( Project Management for Manufacturing ).pptx
Project Managment overview and definition
Cpm n pert
Critical Path Method
project management -04.ppt
Unit 3 PERT.pptx in related to supply chain
Chapter 12(cpm pert)
cpmpertmy (1)
MandC.pdf
7. (lecture 5) Project scheduling..ppt
Pert and CPM
Ch 06 - CPM PERT (1).pptx
Comparative characteristics of pert and cpm
Unit IV-Project Management
Primavera presentation
Ad

Recently uploaded (20)

PPTX
INTRODUCTION TO EVS | Concept of sustainability
PDF
. Radiology Case Scenariosssssssssssssss
PPTX
BIOMOLECULES PPT........................
DOCX
Q1_LE_Mathematics 8_Lesson 5_Week 5.docx
PPTX
ANEMIA WITH LEUKOPENIA MDS 07_25.pptx htggtftgt fredrctvg
PDF
The scientific heritage No 166 (166) (2025)
PDF
Formation of Supersonic Turbulence in the Primordial Star-forming Cloud
PPTX
neck nodes and dissection types and lymph nodes levels
PDF
An interstellar mission to test astrophysical black holes
PDF
ELS_Q1_Module-11_Formation-of-Rock-Layers_v2.pdf
PPTX
famous lake in india and its disturibution and importance
PDF
Unveiling a 36 billion solar mass black hole at the centre of the Cosmic Hors...
PPTX
The KM-GBF monitoring framework – status & key messages.pptx
PDF
Placing the Near-Earth Object Impact Probability in Context
PPTX
G5Q1W8 PPT SCIENCE.pptx 2025-2026 GRADE 5
PPTX
EPIDURAL ANESTHESIA ANATOMY AND PHYSIOLOGY.pptx
PPTX
DRUG THERAPY FOR SHOCK gjjjgfhhhhh.pptx.
PDF
HPLC-PPT.docx high performance liquid chromatography
PPTX
TOTAL hIP ARTHROPLASTY Presentation.pptx
PDF
IFIT3 RNA-binding activity primores influenza A viruz infection and translati...
INTRODUCTION TO EVS | Concept of sustainability
. Radiology Case Scenariosssssssssssssss
BIOMOLECULES PPT........................
Q1_LE_Mathematics 8_Lesson 5_Week 5.docx
ANEMIA WITH LEUKOPENIA MDS 07_25.pptx htggtftgt fredrctvg
The scientific heritage No 166 (166) (2025)
Formation of Supersonic Turbulence in the Primordial Star-forming Cloud
neck nodes and dissection types and lymph nodes levels
An interstellar mission to test astrophysical black holes
ELS_Q1_Module-11_Formation-of-Rock-Layers_v2.pdf
famous lake in india and its disturibution and importance
Unveiling a 36 billion solar mass black hole at the centre of the Cosmic Hors...
The KM-GBF monitoring framework – status & key messages.pptx
Placing the Near-Earth Object Impact Probability in Context
G5Q1W8 PPT SCIENCE.pptx 2025-2026 GRADE 5
EPIDURAL ANESTHESIA ANATOMY AND PHYSIOLOGY.pptx
DRUG THERAPY FOR SHOCK gjjjgfhhhhh.pptx.
HPLC-PPT.docx high performance liquid chromatography
TOTAL hIP ARTHROPLASTY Presentation.pptx
IFIT3 RNA-binding activity primores influenza A viruz infection and translati...

Project Management Diagnostics for Time Management

  • 1. DIAGNOSTICS FOR TIME MANAGEMENT TO C R A S H O R N OT TO C R A S H ? TA K E T H E G U E S S W O R K O U T O F Y O U R D E A D L I N E .
  • 2. PROJECT TIME MANAGEMENT KNOWLEDGE AREA • AGENDA: – COST TIME TRADE OFFS OF CRASHING – PROBABILITY OF COMPLETING A PROJECT BASED ON PERT ANALYSYS • PMBOK GUIDE 6TH EDITION • DEVELOP SCHEDULE: TOOLS AND TECHNIQUES – – SCHEDULE COMPRESSION – CRASHING (6.5.2.6) – DATA ANALYSIS – SIMULATION MODELS (6.5.2.4) • PLANNING PROCESS GROUP
  • 3. WHO WE ARE • ROBERT DAVIES – LEAD ELECTRONICS ENGINEER, PRIDE MOBILITY PRODUCTS • MS ENGINEERING OPERATIONS AND STRATEGY 2018’ • OVER A DECADE OF EXPERIENCE IN ELECTRICAL/ELECTRONIC SYSTEMS DESIGN • 4 US PATENTS (PENDING) & 1 EU PATENT (PENDING) • APRIL DAVIES – PROJECT COORDINATOR, TMG HEALTH / COGNIZANT • MS PROJECT MANAGEMENT (HEALTHCARE ADMINISTRATION) 2018 • MA COMMUNICATION ARTS – MARYWOOD UNIVERSITY • DECADE OF EXPERIECNE IN EXECUTIVE LEVEL SUPPORT AND SPECIAL PROJECTS • CAPM JUNE 2017
  • 5. PROJECT CRASHING • The PMBOK defines project crashing as a technique used to shorten the schedule duration for the least cost by adding resources. • Crashing is one method of schedule compression used to accelerate the schedule duration to meet constraints, key dates and other schedule objectives without reducing the project scope.
  • 6. COST TIME TRADE OFFS OF CRASHING • When managing a project it’s not uncommon for a project manager to be faced with these scenarios. –A project is falling behind schedule. And/or –The scheduled completion date of a project is moved forward. –In either scenario, we need to determine how to speed up the activities that occur within the project’s pipeline.
  • 7. DETERMINING ACTIVITIES TO CRASH • The concern lies in the question of: – Which activities should be shortened? – How many activities should be shortened? • The project manager needs to review the critical activities and determine which would have the least impact to the cost. • Costs need to be compared, but how? • Assumptions: – Manager is working to ensure that the cost of the crash is permissible. – The shortened activity time will allow us to meet the due date. – Total cost of crashing is as small as possible.
  • 8. PROJECT COSTS • Project direct costs to the project that consist of labor, materials, equipment and contractor expenses. • Direct cost are assigned to each of the project activities. • Under a normal assumption, the direct costs represent normal delivery of project activities. • Changes to the normal delivery of of these activities would constitute an increase to the project’s direct costs. • The sum of all project costs is equivalent to the sum of all activities and the total direct cost of the project. • Not all costs are the same for every activity, therefore it could be difficult to determine which activity to shorten.
  • 9. COST TIME TRADE OFF Crash Point Cost Activity 1 Activity 2 Crash Point Normal
  • 10. HOW TO CRASH A PROJECT 1) Compute the crash cost per time period. 2) Find the critical path of the project’s network. 3) Find the activities on the critical path that can be crashed and have the smallest crash cost. 4) Update activity times to determine if the desired due dates can be reached.
  • 12. T H E D E L I M M A Julie Anne’s boss tells her that she must complete her project at an earlier than anticipated due date. He is willing to pay any price to have the project come in sooner then planned. Julie Anne needs to determine which activities to crash, by how much, and how to meet his 13 week deadline which was shortened from 15 weeks. She would like to speed up her project by 2 weeks at the least minimal
  • 13. STEP 1 Compute the crash cost per time period. Crash Cost per Period = Crash Cost – Normal Cost Normal Time – Crash Time
  • 14. CALCULATING CRASH COST Crash Cost = Crash Cost – Normal Cost Normal Time – Crash Time Activity Normal Time Crash Time Normal Cost Crash Cost Cost per time period A 2 1 22,000 22,750 750 B 3 1 30,000 34,000 2,000 C 2 1 26,000 27,000 1,000 D 4 3 48,000 49,000 1,000 E 4 2 56,000 58,000 1,000 F 3 2 30,000 30,500 500 G 5 2 80,000 84,500 1,500 H 2 1 16,000 19,000 3,000
  • 16. STEP 2 Find the Critical Path S 0 F 3 G 5 E 4 B 3 D 4 C 2 A 2 H 2 Activity Duration
  • 17. STEP 2 Find the Critical Path S 0 F 3 G 5 E 4 B 3 D 4 C 2 A 2 H 2 Activity Duration
  • 18. STEP 3 • Find the critical path activities with smallest crash cost. Activity Normal Time Crash Time Normal Cost Crash Cost Cost per time period Critical Path A 2 1 22,000 22,750 750 Yes B 3 1 30,000 34,000 2,000 No C 2 1 26,000 27,000 1,000 Yes D 4 3 48,000 49,000 1,000 No E 4 2 56,000 58,000 1,000 Yes F 3 2 30,000 30,500 500 No G 5 2 80,000 84,500 1,500 Yes H 2 1 16,000 19,000 3,000 Yes
  • 19. STEP 4 Update activity times to determine if the desired due dates can be reached. S 0 F 3 G 5 E 4 B 3 D 4 C 2 A 2 H 2 Activity Duration 15 weeks Act T $ A 1 750 C 1 1,000 E 2 1,000 G 2 1,500 H 1 3,000
  • 20. STEP 4 Update activity times to determine if the desired due dates can be reached. S 0 F 3 G 5 E 4 B 3 D 4 C 2 A 2 H 2 Activity Duration 15 weeks Act T $ A 1 750 C 1 1,000 E 2 1,000 G 2 1,500 H 1 3,000
  • 21. STEP 4 Update activity times to determine if the desired due dates can be reached. S 0 F 3 G 5 E 4 B 3 D 4 C 2 A 1 H 2 Activity Duration 14 weeks Total: $750 Act T $ A 1 750 C 1 1,000 E 2 1,000 G 2 1,500 H 1 3,000
  • 22. STEP 4 Update activity times to determine if the desired due dates can be reached. S 0 F 3 G 5 E 4 B 3 D 4 C 2 A 1 H 2 Activity Duration 13 weeks Act T $ A 1 750 C 1 1,000 E 2 1,000 G 2 1,500 H 1 3,000 Total: $2,750
  • 23. STEP 4 Update activity times to determine if the desired due dates can be reached. S 0 F 3 G 5 E 4 B 3 D 4 C 2 A 2 H 2 Activity Duration 15 weeks Act T $ A 1 750 C 1 1,000 E 2 1,000 G 2 1,500 H 1 3,000 Total: $1,500
  • 24. STEP 4 Update activity times to determine if the desired due dates can be reached. S 0 F 3 G 2 E 4 B 3 D 4 C 2 A 2 H 2 Activity Duration 12 weeks Act T $ A 1 750 C 1 1,000 E 2 1,000 G 2 1,500 H 1 3,000
  • 25. SUCCESSFUL CRASH REMINDERS • Ensure that the cost to crash is as small as possible. • Update your project with new activity times and budget with new cost considerations. Crashing only works for critical path activities. • Crashing can increase risk. Reevaluate risk as needed. • Ensure your resources are available to complete the crash. • Receive the proper prior authorization to make the change (CR) • Remember to be considerate of money. Consider the approach of take only what is needed. • Remember Responsible Crashing: Always Weigh Impact to Quality – 4 Hour House – What is the cost of quality. – https://www.youtube.com/watch?v=oDB1O5cadQw
  • 27. WHAT IS PERT? • The program (or project) evaluation and review technique, commonly abbreviated PERT, is a statistical tool, used in project management…
  • 28. PERT HISTORY? • Initially PERT stood for Program Evaluation Research Task • Started by the US NAVY 1950’s – as part of a (CPM) analysis Critical Path Method. • Design to simplify and plan complex projects i.e. building of a nuclear submarines.
  • 29. WHAT DOES PERT DO? • PERT - in its simplest form is a tool for estimating the probability of completing a task (program or project) in a given time constraint. • “What is the confidence level of completing phase 2 by Oct 15th ?” said the VP
  • 31. PERT STEP 1. • Identify Critical Path Tasks • The longest possible continuous pathway taken from the initial event to the terminal event. It determines the total calendar time required for the project; and, therefore, any time delays along the critical path will delay the reaching of the terminal event by at least the same amount.
  • 32. PERT STEP 2. • Optimistic : The minimum possible time required to accomplish a task, assuming everything proceeds better than is normally expected.
  • 33. PERT STEP 3. • Likely : The best estimate of the time required to accomplish a task, assuming everything proceeds as normal.
  • 34. PERT STEP 4. • Pessimistic : The maximum possible time required to accomplish a task, assuming everything goes wrong (but excluding major catastrophes).
  • 35. PERT STEP 5. • Calculate Expected Duration using given inputs
  • 36. PERT STEP 6. • Calculate Standard Deviation / Variance
  • 37. PERT STEP 6.2.0 • Calculate Standard Deviation / Variance
  • 38. PERT STEP 7. • Given a due date we can calculate the probability of meeting a particular due date
  • 39. PERT STEP 8. • Now we look up Z in the Normal Distribution Table
  • 40. PERT STEP 9. • That’s it! Report the probability of completion in percentage i.e. 0.99 equates to 99% probability.

Editor's Notes

  • #2: Northeast Branch: September 2017 Meeting When: September 28, 2017 Where: Marzoni's Brick Oven & Brewing - 26 Montage Mountain Rd, Moosic, PA 18507 Speaker:  Robert & April Davies Topic: Diagnostic Techniques for Project Time Management Brief Description: To crash or not to crash? Take the guesswork out of your deadline.     Find out how to calculate the probability of hitting target dates at September's PMI Keystone Chapter’s Meeting. Robert and April Davies will be presenting on diagnostic techniques for project time management. In their presentation, they will review PERT analysis, probability of completion, and cost time trade-offs.  Talent Triangle Category(s): Technical Project Management (1 PDU)
  • #3: References: Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc. Gray, C. & Larson, E. (2011). Project Management: The Managerial Process. New York, NY: McGraw-Hill Irwin. Project Management Institute (2013). A Guide to the Project Management Body of Knowledge (PMBOK guide).  Newtown Square, PA: Project Management Institute.  ISBN-13: 9781935589679 In this presentation will be touching on to diagnostic techniques for project time management. We will review probability of completion using PERT, and cost time trade-offs.
  • #7: Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc. Gray, C. & Larson, E. (2011). Project Management: The Managerial Process. New York, NY: McGraw-Hill Irwin. Project Management Institute (2013). A Guide to the Project Management Body of Knowledge (PMBOK guide).  Newtown Square, PA: Project Management Institute.  ISBN-13: 9781935589679
  • #8: The shortest possible time that a project activity can be completed which is called crash time. Crash time must be realistic. The cost to crash is called the crash cost. Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc. Gray, C. & Larson, E. (2011). Project Management: The Managerial Process. New York, NY: McGraw-Hill Irwin. Project Management Institute (2013). A Guide to the Project Management Body of Knowledge (PMBOK guide).  Newtown Square, PA: Project Management Institute.  ISBN-13: 9781935589679
  • #9: Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc. Gray, C. & Larson, E. (2011). Project Management: The Managerial Process. New York, NY: McGraw-Hill Irwin. Project Management Institute (2013). A Guide to the Project Management Body of Knowledge (PMBOK guide).  Newtown Square, PA: Project Management Institute.  ISBN-13: 9781935589679
  • #10: We are making the assumptions are that the cost time relationship is linear. Normal cost assumes the must efficient methods to complete the activity. Crash Time represents the least amount of time needed to complete an activity - which is the greatest time reduction possible under realistic conditions Slope assumes the cost per unit of time. Less steep slopes means that it costs less to shorten the duration of that activity. All accelerations must occur within normal and crash times. It’s also normal to assume that crash cost will be higher than normal. In some cases we find that adding more resources will help shorten the time it takes to complete an activity but at a higher cost. Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc. Gray, C. & Larson, E. (2011). Project Management: The Managerial Process. New York, NY: McGraw-Hill Irwin. Project Management Institute (2013). A Guide to the Project Management Body of Knowledge (PMBOK guide).  Newtown Square, PA: Project Management Institute.  ISBN-13: 9781935589679
  • #11: Compute the crash cost per time period. EX: Grocery Store: Pound of bananas. We need to consider the cost of each banana, not the complete bunch. We will look at calculating the cost of the activity per time segment. Find the critical path of the project’s network. Using the same approach as defined in the PMBOK. We will look at the critical path to determine which activities can have an impact on our schedule Find the activities on the critical path that have the smallest crash cost. Determine which activities are the best candidates for crashing. Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc. Gray, C. & Larson, E. (2011). Project Management: The Managerial Process. New York, NY: McGraw-Hill Irwin. Project Management Institute (2013). A Guide to the Project Management Body of Knowledge (PMBOK guide).  Newtown Square, PA: Project Management Institute.  ISBN-13: 9781935589679
  • #13: Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc.
  • #14: Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc.
  • #15: Julie Anne needs to crash at the least minimal cost. Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc.
  • #16: Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc.
  • #17: Find the critical path of the activities S – A – C – E – G – H Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc.
  • #18: Option would be to use MS Project to determine the activities. 0 slack activities Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc.
  • #19: Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc.
  • #20: Option would be to use MS Project to determine the activities. 0 slack activities Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc.
  • #21: Option would be to use MS Project to determine the activities. 0 slack activities Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc.
  • #22: Option would be to use MS Project to determine the activities. 0 slack activities Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc.
  • #23: Option would be to use MS Project to determine the activities. 0 slack activities D not originally on critical path but changed. Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc.
  • #24: Option would be to use MS Project to determine the activities. 0 slack activities Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc.
  • #25: Option would be to use MS Project to determine the activities. 0 slack activities Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc.
  • #26: Compute the crash cost per time period. EX: Grocery Store: Pound of bananas. We need to consider the cost of each banana, not the complete bunch. We will look at calculating the cost of the activity per time segment. Find the critical path of the project’s network. Using the same approach as defined in the PMBOK. We will look at the critical path to determine which activities can have an impact on our schedule Find the activities on the critical path that have the smallest crash cost. Determine which activities are the best candidates for crashing. Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc.
  • #31: Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc. Gray, C. & Larson, E. (2011). Project Management: The Managerial Process. New York, NY: McGraw-Hill Irwin. Project Management Institute (2013). A Guide to the Project Management Body of Knowledge (PMBOK guide).  Newtown Square, PA: Project Management Institute.  ISBN-13: 9781935589679
  • #32: Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc. Gray, C. & Larson, E. (2011). Project Management: The Managerial Process. New York, NY: McGraw-Hill Irwin. Project Management Institute (2013). A Guide to the Project Management Body of Knowledge (PMBOK guide).  Newtown Square, PA: Project Management Institute.  ISBN-13: 9781935589679
  • #33: Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc. Gray, C. & Larson, E. (2011). Project Management: The Managerial Process. New York, NY: McGraw-Hill Irwin. Project Management Institute (2013). A Guide to the Project Management Body of Knowledge (PMBOK guide).  Newtown Square, PA: Project Management Institute.  ISBN-13: 9781935589679
  • #34: Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc. Gray, C. & Larson, E. (2011). Project Management: The Managerial Process. New York, NY: McGraw-Hill Irwin. Project Management Institute (2013). A Guide to the Project Management Body of Knowledge (PMBOK guide).  Newtown Square, PA: Project Management Institute.  ISBN-13: 9781935589679
  • #35: Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc. Gray, C. & Larson, E. (2011). Project Management: The Managerial Process. New York, NY: McGraw-Hill Irwin. Project Management Institute (2013). A Guide to the Project Management Body of Knowledge (PMBOK guide).  Newtown Square, PA: Project Management Institute.  ISBN-13: 9781935589679
  • #36: Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc. Gray, C. & Larson, E. (2011). Project Management: The Managerial Process. New York, NY: McGraw-Hill Irwin. Project Management Institute (2013). A Guide to the Project Management Body of Knowledge (PMBOK guide).  Newtown Square, PA: Project Management Institute.  ISBN-13: 9781935589679
  • #37: Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc. Gray, C. & Larson, E. (2011). Project Management: The Managerial Process. New York, NY: McGraw-Hill Irwin. Project Management Institute (2013). A Guide to the Project Management Body of Knowledge (PMBOK guide).  Newtown Square, PA: Project Management Institute.  ISBN-13: 9781935589679
  • #38: Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc. Gray, C. & Larson, E. (2011). Project Management: The Managerial Process. New York, NY: McGraw-Hill Irwin. Project Management Institute (2013). A Guide to the Project Management Body of Knowledge (PMBOK guide).  Newtown Square, PA: Project Management Institute.  ISBN-13: 9781935589679
  • #39: Heizer, J., & Render, B. (2014). Operations Management:  Sustainability and supply chain management (11th ed.). Upper Saddle River, NJ: Pearson Education, Inc. Gray, C. & Larson, E. (2011). Project Management: The Managerial Process. New York, NY: McGraw-Hill Irwin. Project Management Institute (2013). A Guide to the Project Management Body of Knowledge (PMBOK guide).  Newtown Square, PA: Project Management Institute.  ISBN-13: 9781935589679
  • #42: I hope you enjoyed our presentation on cost time trade offs and the probability of completion.