Presented by: Aditi
Manoj
Charul
 The CPM, time is related to cost and the objective
is to develop an optimum time –cost relationship.
Sometimes it becomes necessary to complete the
project earlier than the normal time, in such
situations the cost of expediting the operations has
to be considered.
CPM makes the use of cost estimate alongwith
time estimate and provides a schedule for
completing the activities at the minimum total
cost.
LIMIT STATE
METHOD
This procedure improves planning, scheduling
and controlling of the project and also assesses the
possibility to arrive at a feasible and desirable time
cost relationship.
The project duration can be reduced by reducing
the duration of only the critical activities in the
project network.
Reduction in the time duration can be done by:
1) Deploying more resources for early completion.
2)Relaxing the technical specifications
LIMIT STATE
METHOD
OPTIMUM DURATION:
the duration which gives the most economic cost
for completing the project.
TIME-COST ESTIMATES:
1) NORMAL ESTIMATE:
emphasis is on cost with time being associated
with minimum cost.
2) CRASH ESTIMATE:
emphasis is on time . It involves the absolute
minimum time required for the job and the cost
necessary to achieve it. LIMIT STATE
METHOD
LIMIT STATE
METHOD
5
COST
TIME
Minimum cost
Optimum duration
Cost rises if project is
prolonged
Cost rises if project is crashed
LIMIT STATE
METHOD
LIMIT STATE
METHOD
INDIRECTCOST
TIME
Total indirect cost curve
Over heads
Outage loss
 These are those expenditures which cannot clearly
allocated to the individual activities of a project,
but are assessed as whole.
It includes expenditure related to administrative
and establishment charges, supervision,
expenditures on central store organisation, loss of
revenue, lost profit, penalty etc.
Indirect cost rises with increased duration.
OUTAGE LOSS : loss in profits due to inability to
meet demand or penalty due to delay. LIMIT STATE
METHOD
 Those expenditures which are directly chargeable
to and can be identified specifically with the
activities of the project.
These include labour cost, material cost,
equipment cost etc.
LIMIT STATE
METHOD
LIMIT STATE
METHOD
COST
TIME
Cc
tn
Normal Duration
tc
Crash duration
Cn
 NORMAL TIME(tn):
Standard time that an estimator whould usually
allow for an activity.
CRASH TIME(tc):
minimum possible time in which an activity can be
completed, by employing extra resources.
NORMAL COST(Cn):
Direct cost required to complete the acticity in
normal time.
CRASH COST(Cc):
Direct cost corresponding to completion of activity
within crash time. LIMIT STATE
METHOD
 COST SLOPE:
It is the slope of the direct cost curve, approximated
as a straight line in order to have a single cross
slope.
Cost Slope = crash cost-normal cost
Normal time-crash time
CS = Cc-Cn = ∆C
tn-tc ∆t
LIMIT STATE
METHOD
 It is the sum of direct and indirect costs.
LIMIT STATE
METHOD
COST
TIME
Indirect cost curve
direct cost curve
total cost curve
tc crash tn
normal
to
optimum
Minimum cost
Time cost optimisation
To examine « what will be the cost structure of the
project if some or all of the activities is crashed ? »
we should have following data with us :-
- Normal direct cost data for each activity if it is to
be completed in normal time duration .
- crashed direct cost data if that activity is crashed.
After this cost slope for each activity can be
determined.
- The indirect cost rate should also be known so that
total cost can be determined.
LIMIT STATE
METHOD
 Normal time of project- sum of the normal durations of
each activity along the critical path.
 Minimum time of project – sum of the crashed time
duration of each activity along the critical path.
 Non-critical activity need not to be speed up as their
crashing is not going to decrease the project duration
further. Moreover the cost will be high without any
additional advantage.
 Some non-critical activities become critical in the process
of crashing the critical activities.
 It is always better to start with crashing first that critical
activity that has the lowest cost slope.Then we take
another critical activity which is having next higher slope.
 While crashing an activity fully by time “t” ,it should be
examined whether its affecting the non –critical
activity or not.
1 2 3 4
9(2)
c
A
5(4)
B
6(2)
D
5(3)
STEPS IN TIME COST OPTIMISATION
1. Establish:- Direct cost time relationship for various
activities of the project.
2. Determine:- Cost slope for various activities and
arrange them in the ascending order of cost slope.
3. Compute:- Direct cost for the network with normal
duration of activities.
4. Crash:- The activities in the critical path as per
ranking i.e starting with the the activity having the
lowest slope.
5. Continue:-Crashing the critical activities in the
ascending order of the slope.
6. Crash:- Parallel non-critical activities which have
become critical by the reduction of critical path duration
due to crashing in steps 4 and 5.
7. Continue :- Crashing process through steps 4 to 6 , till a
stage is reached beyond which no further crashing is
possible.
8. Find:- Find total cost of the project at every stage by
adding indirect costs to the direct costs determined
above.
9. Plot:- Total cost–duration curve.
10. Pick Up:-The optimum duration corresponding to
which least total project cost is obtained.
.
LIMIT STATE
METHOD
.
ACTIVITY NORMAL
DURATION
(WEEKS)
NORMAL
COST
(RUPEES)
CRASH
DURATION
(WEEKS)
CRASH COST
(RUPEES)
1-2 4 4000 2 12000
2-3 5 3000 2 7500
2-4 7 3600 5 6000
3-4 4 5000 2 10000
 .
1 2
3
4
4(2)
5(2) 4(2)
7(5)
STEP 1. TIME SCALED VERSION OF NETWORK
1 32 4
7(5)
4(2) 4(2)
5(2)
ACTIVITY Δ C
(RUPEES)
Δ t
(WEEKS)
COST
SLOPE
RS./WEEK
1-2 8000 2 4000
2-3 4500 3 1500
2-4 2400 2 1200
3-4 5000 2 2500
The normal; duration of the project is the sum of the
normal durations of each activity on the critical path.
(It is not the sum of normal durations of all the
activities).
Therefore, Normal duration of the project
= 4+5+4 = 13 weeks.
Direct cost = 4000+3000+3600+5000
= 15600
While crashing the activities, we shall first select that critical activity
which has minimum cost slope.
Let say Activity 2-4 has minimum cost slope of 1500 per week.
Crash period is 2 weeks i.e. Δt = 5-2 = 3 weeks.
However, crashing it by 3 weeks will affect non-critical activity 2-4 which
has float of only 2 weeks. Hence restrict the crashing of 2-3 by 2 weeks
only, in the first stage.
New duration of the project= 13-2 = 11 weeks.
Extra cost of crashing activity 2-3 by 2 weeks
= 2*1500 = 3000
Direct cost of the project of 11 weeks duration
= 15600 + 3000 = 18600
The time-scaled version of the network, after first stage crashing, for the
project of 11 weeks duration is shown in the figure.
41 2 34(2) 3(2) 4(2)
7(5)
From the figure above it is clear that activity 2-4 lying on the parallel path
has also become critical, though activity 2-3 has still 1 week crashing left.
However, Activity 2-3 cannot be crashed unless 2-4 is also crashed. So
crash 2-3 &2-4 for 1 week simultaneously.
Further crashing can be done with three alternatives:
 crashing activities 2-3 & 2-4 simultaneously, having a combined cost
slope of 1500 + 1200 = 2700 per week.
 Crashing activities 3-4 & 2-4 simultaneously, having a combined cost
slope of 2500 + 1200 = 3700 per week
 Crashing activity 1-2 alone, having a cost slope of rupees 4500 per week
out of these, the first alternative has the minimum cost slope.
Thus, the extra cost of crashing 2-3 & 2-4 by 1 week
= 2700
therefore, Direct cost of Project for 10 weeks duration
= 18600 + 2700 = 21300
In this step, activity 2-3 has been crashed to its fullest extent.
1 2 3 4
4(2) 2(2) 4(2)
6(5)
The remaining activities to be crashed are 1-2 , 2-4, 3-4.
out of these, activities 2-4 & 3-4 are to be crashed
jointly, with a combined cost slope of 2500 + 1200 =
3700.
The cost slope of activity 1-2 is 4000 which is higher .
Hence period of 6-5 = 1 week left.
Hence only 1 week crashing will be done in this step,
leading to a project duration of 9 weeks.
cost of crashing 2-4 & 3-4 by 1 week.
= 3700 * 1 = 3700
Therefore, cost of project for 9 weeks duration
= 21300 + 3700 = 25000.
The Time scaled version of the network for 9 weeks
duration is shown in fig. we crashed activity 2-4 also
to its fullest extent.
Time- scaled network for 9 weeks Duration.
1 2 3 4
6(5)
4(2) 2(2) 3(2)
Out of remaining critical activities ( i.e. 1-2&3-4)
Activity 3-4 cannot be further crashed to its fullest crash
period of 2 weeks, since it will affect activity 2-4 which has
already been fully crashed.
Hence activity 1-2 is the only remaining activity to be
crashed. The period by which it can be crashed is = 4-2 = 2
weeks, reducing the project duration to 9-2 = 7 weeks.
Extra cost of crashing 1-2 by 2 weeks = 2*4000 = 8000
Therefore, Direct cost of Project of 7 weeks duration
= 25000 + 8000 = 33000.
1 2 3
5(2)
4
2(2) 2(2) 3(2)
PROJECT
DURATIO
N
13
(NORMAL
)
11 10 9 7
DIRECT
COST (RS.)
15600 18600 21200 25000 31000
INDIRECT
COST (RS.)
26000 22000 20000 18000 14000
TOTAL
COST (RS.)
41600 40600 41300 43000 47000

More Related Content

PPT
Cost plan
PPTX
Line of balance in civil engineering
PDF
Introduction to cost management & control in construction projects
PDF
time cost trade off
PDF
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
PPT
8. (lecture 6) Project Cost Control.ppt
PPT
Construction scheduling & Cost control
Cost plan
Line of balance in civil engineering
Introduction to cost management & control in construction projects
time cost trade off
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
8. (lecture 6) Project Cost Control.ppt
Construction scheduling & Cost control

What's hot (20)

PPTX
Valuation(1)
PDF
CPM-Updating
PPTX
Types of estimate
PPTX
rate analysis
PPTX
Construction equipments
PPT
Depreciation & obsolescence
PPTX
1. classification of urban roads 28 jun
PPTX
Construction Equipment Management
PPTX
Approximate estimate
PPTX
Valuation - Estimation, Costing and Valuation Engineering
PPTX
Valuation
PPTX
Tenders contract -arti
PPTX
civil engineering-Contracts
PDF
Project management in construction.
PPTX
estimation,its types and methods
PPTX
Purpose of Valuation
PDF
Construction Planing & Schedule
PDF
Estimating part 2
PPTX
Specifications of buildings
Valuation(1)
CPM-Updating
Types of estimate
rate analysis
Construction equipments
Depreciation & obsolescence
1. classification of urban roads 28 jun
Construction Equipment Management
Approximate estimate
Valuation - Estimation, Costing and Valuation Engineering
Valuation
Tenders contract -arti
civil engineering-Contracts
Project management in construction.
estimation,its types and methods
Purpose of Valuation
Construction Planing & Schedule
Estimating part 2
Specifications of buildings
Ad

Viewers also liked (20)

PPT
Cost Optimization
DOCX
Resume - C A - Dillip Kumar Sahoo having post qualification experience 17 ye...
PDF
Failure prediction of propeller shaft prototype using finite element analysis
PDF
PPTX
Cost optimisation
PPTX
Maintenance and Management Best Practices from Support
PPT
Best Practices - Software Engineering
PPTX
Software maintenance Unit5
PPTX
Utsav Mahendra : Customer Feedback and Service Recovery
PPT
Software Maintenance
PPTX
Software development best practices & coding guidelines
PPT
Project crashing and job sequencing
PPTX
Multinational corporation
PPTX
Crashing and cost plan-cpm
PPTX
Crashing in Project Management
PPTX
Software maintenance
PPT
The Art of Negotiating
PDF
PMP Chap 6 - Project Time management - Part1
PPT
Program Evaluation and Review Technique
Cost Optimization
Resume - C A - Dillip Kumar Sahoo having post qualification experience 17 ye...
Failure prediction of propeller shaft prototype using finite element analysis
Cost optimisation
Maintenance and Management Best Practices from Support
Best Practices - Software Engineering
Software maintenance Unit5
Utsav Mahendra : Customer Feedback and Service Recovery
Software Maintenance
Software development best practices & coding guidelines
Project crashing and job sequencing
Multinational corporation
Crashing and cost plan-cpm
Crashing in Project Management
Software maintenance
The Art of Negotiating
PMP Chap 6 - Project Time management - Part1
Program Evaluation and Review Technique
Ad

Similar to Time cost optimisation (20)

PPT
PPTX
construction resource optimization 1.pptx
PPTX
Project crashing and project management - 01
PPT
Critical Path Method
PDF
MODULE 8 NOTES CEM (1).pdf
PDF
Unit 3-Analysis.pdf DOOBY DADA DOLI MAYAA
PPTX
4 b. Project management - network analysis
PDF
Lecture7_2021_v2.pdf
PDF
Crash management
PDF
Time-Cost Trade Off in the construction industry
PPT
Comparative characteristics of pert and cpm
PPTX
crashing.pptxbbbbbbbbbbbbbbbbbbbbbbbbbbbbbb
PPT
49091291-PERT and CPM topic of industrial .ppt
PPTX
Per tand project crashing
PPT
CPM solution.ppt, Finance Department, Rajshahi University
PPSX
Critical path method & pert
PDF
Time-Cost Tradeoff by Examples
PDF
ملاحظات مهمة عن تعجيل المشاريع
PPSX
DOC
Operation Research
construction resource optimization 1.pptx
Project crashing and project management - 01
Critical Path Method
MODULE 8 NOTES CEM (1).pdf
Unit 3-Analysis.pdf DOOBY DADA DOLI MAYAA
4 b. Project management - network analysis
Lecture7_2021_v2.pdf
Crash management
Time-Cost Trade Off in the construction industry
Comparative characteristics of pert and cpm
crashing.pptxbbbbbbbbbbbbbbbbbbbbbbbbbbbbbb
49091291-PERT and CPM topic of industrial .ppt
Per tand project crashing
CPM solution.ppt, Finance Department, Rajshahi University
Critical path method & pert
Time-Cost Tradeoff by Examples
ملاحظات مهمة عن تعجيل المشاريع
Operation Research

Recently uploaded (20)

PPTX
Welding lecture in detail for understanding
PPTX
bas. eng. economics group 4 presentation 1.pptx
PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PDF
Digital Logic Computer Design lecture notes
PDF
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
PPTX
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
PPT
Project quality management in manufacturing
PDF
Automation-in-Manufacturing-Chapter-Introduction.pdf
PPTX
web development for engineering and engineering
PPTX
Recipes for Real Time Voice AI WebRTC, SLMs and Open Source Software.pptx
PDF
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
PPTX
additive manufacturing of ss316l using mig welding
PPTX
Geodesy 1.pptx...............................................
PPTX
Lecture Notes Electrical Wiring System Components
PPTX
UNIT-1 - COAL BASED THERMAL POWER PLANTS
PPTX
UNIT 4 Total Quality Management .pptx
PPTX
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
DOCX
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
PDF
R24 SURVEYING LAB MANUAL for civil enggi
PPTX
MCN 401 KTU-2019-PPE KITS-MODULE 2.pptx
Welding lecture in detail for understanding
bas. eng. economics group 4 presentation 1.pptx
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
Digital Logic Computer Design lecture notes
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
Project quality management in manufacturing
Automation-in-Manufacturing-Chapter-Introduction.pdf
web development for engineering and engineering
Recipes for Real Time Voice AI WebRTC, SLMs and Open Source Software.pptx
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
additive manufacturing of ss316l using mig welding
Geodesy 1.pptx...............................................
Lecture Notes Electrical Wiring System Components
UNIT-1 - COAL BASED THERMAL POWER PLANTS
UNIT 4 Total Quality Management .pptx
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
R24 SURVEYING LAB MANUAL for civil enggi
MCN 401 KTU-2019-PPE KITS-MODULE 2.pptx

Time cost optimisation

  • 2.  The CPM, time is related to cost and the objective is to develop an optimum time –cost relationship. Sometimes it becomes necessary to complete the project earlier than the normal time, in such situations the cost of expediting the operations has to be considered. CPM makes the use of cost estimate alongwith time estimate and provides a schedule for completing the activities at the minimum total cost. LIMIT STATE METHOD
  • 3. This procedure improves planning, scheduling and controlling of the project and also assesses the possibility to arrive at a feasible and desirable time cost relationship. The project duration can be reduced by reducing the duration of only the critical activities in the project network. Reduction in the time duration can be done by: 1) Deploying more resources for early completion. 2)Relaxing the technical specifications LIMIT STATE METHOD
  • 4. OPTIMUM DURATION: the duration which gives the most economic cost for completing the project. TIME-COST ESTIMATES: 1) NORMAL ESTIMATE: emphasis is on cost with time being associated with minimum cost. 2) CRASH ESTIMATE: emphasis is on time . It involves the absolute minimum time required for the job and the cost necessary to achieve it. LIMIT STATE METHOD
  • 5. LIMIT STATE METHOD 5 COST TIME Minimum cost Optimum duration Cost rises if project is prolonged Cost rises if project is crashed
  • 7. LIMIT STATE METHOD INDIRECTCOST TIME Total indirect cost curve Over heads Outage loss
  • 8.  These are those expenditures which cannot clearly allocated to the individual activities of a project, but are assessed as whole. It includes expenditure related to administrative and establishment charges, supervision, expenditures on central store organisation, loss of revenue, lost profit, penalty etc. Indirect cost rises with increased duration. OUTAGE LOSS : loss in profits due to inability to meet demand or penalty due to delay. LIMIT STATE METHOD
  • 9.  Those expenditures which are directly chargeable to and can be identified specifically with the activities of the project. These include labour cost, material cost, equipment cost etc. LIMIT STATE METHOD
  • 11.  NORMAL TIME(tn): Standard time that an estimator whould usually allow for an activity. CRASH TIME(tc): minimum possible time in which an activity can be completed, by employing extra resources. NORMAL COST(Cn): Direct cost required to complete the acticity in normal time. CRASH COST(Cc): Direct cost corresponding to completion of activity within crash time. LIMIT STATE METHOD
  • 12.  COST SLOPE: It is the slope of the direct cost curve, approximated as a straight line in order to have a single cross slope. Cost Slope = crash cost-normal cost Normal time-crash time CS = Cc-Cn = ∆C tn-tc ∆t LIMIT STATE METHOD
  • 13.  It is the sum of direct and indirect costs. LIMIT STATE METHOD COST TIME Indirect cost curve direct cost curve total cost curve tc crash tn normal to optimum Minimum cost
  • 15. To examine « what will be the cost structure of the project if some or all of the activities is crashed ? » we should have following data with us :- - Normal direct cost data for each activity if it is to be completed in normal time duration . - crashed direct cost data if that activity is crashed. After this cost slope for each activity can be determined. - The indirect cost rate should also be known so that total cost can be determined. LIMIT STATE METHOD
  • 16.  Normal time of project- sum of the normal durations of each activity along the critical path.  Minimum time of project – sum of the crashed time duration of each activity along the critical path.  Non-critical activity need not to be speed up as their crashing is not going to decrease the project duration further. Moreover the cost will be high without any additional advantage.  Some non-critical activities become critical in the process of crashing the critical activities.  It is always better to start with crashing first that critical activity that has the lowest cost slope.Then we take another critical activity which is having next higher slope.
  • 17.  While crashing an activity fully by time “t” ,it should be examined whether its affecting the non –critical activity or not. 1 2 3 4 9(2) c A 5(4) B 6(2) D 5(3)
  • 18. STEPS IN TIME COST OPTIMISATION 1. Establish:- Direct cost time relationship for various activities of the project. 2. Determine:- Cost slope for various activities and arrange them in the ascending order of cost slope. 3. Compute:- Direct cost for the network with normal duration of activities. 4. Crash:- The activities in the critical path as per ranking i.e starting with the the activity having the lowest slope. 5. Continue:-Crashing the critical activities in the ascending order of the slope.
  • 19. 6. Crash:- Parallel non-critical activities which have become critical by the reduction of critical path duration due to crashing in steps 4 and 5. 7. Continue :- Crashing process through steps 4 to 6 , till a stage is reached beyond which no further crashing is possible. 8. Find:- Find total cost of the project at every stage by adding indirect costs to the direct costs determined above. 9. Plot:- Total cost–duration curve. 10. Pick Up:-The optimum duration corresponding to which least total project cost is obtained.
  • 20. . LIMIT STATE METHOD . ACTIVITY NORMAL DURATION (WEEKS) NORMAL COST (RUPEES) CRASH DURATION (WEEKS) CRASH COST (RUPEES) 1-2 4 4000 2 12000 2-3 5 3000 2 7500 2-4 7 3600 5 6000 3-4 4 5000 2 10000
  • 22. STEP 1. TIME SCALED VERSION OF NETWORK 1 32 4 7(5) 4(2) 4(2) 5(2)
  • 23. ACTIVITY Δ C (RUPEES) Δ t (WEEKS) COST SLOPE RS./WEEK 1-2 8000 2 4000 2-3 4500 3 1500 2-4 2400 2 1200 3-4 5000 2 2500
  • 24. The normal; duration of the project is the sum of the normal durations of each activity on the critical path. (It is not the sum of normal durations of all the activities). Therefore, Normal duration of the project = 4+5+4 = 13 weeks. Direct cost = 4000+3000+3600+5000 = 15600
  • 25. While crashing the activities, we shall first select that critical activity which has minimum cost slope. Let say Activity 2-4 has minimum cost slope of 1500 per week. Crash period is 2 weeks i.e. Δt = 5-2 = 3 weeks. However, crashing it by 3 weeks will affect non-critical activity 2-4 which has float of only 2 weeks. Hence restrict the crashing of 2-3 by 2 weeks only, in the first stage. New duration of the project= 13-2 = 11 weeks. Extra cost of crashing activity 2-3 by 2 weeks = 2*1500 = 3000 Direct cost of the project of 11 weeks duration = 15600 + 3000 = 18600 The time-scaled version of the network, after first stage crashing, for the project of 11 weeks duration is shown in the figure.
  • 26. 41 2 34(2) 3(2) 4(2) 7(5)
  • 27. From the figure above it is clear that activity 2-4 lying on the parallel path has also become critical, though activity 2-3 has still 1 week crashing left. However, Activity 2-3 cannot be crashed unless 2-4 is also crashed. So crash 2-3 &2-4 for 1 week simultaneously. Further crashing can be done with three alternatives:  crashing activities 2-3 & 2-4 simultaneously, having a combined cost slope of 1500 + 1200 = 2700 per week.  Crashing activities 3-4 & 2-4 simultaneously, having a combined cost slope of 2500 + 1200 = 3700 per week  Crashing activity 1-2 alone, having a cost slope of rupees 4500 per week out of these, the first alternative has the minimum cost slope. Thus, the extra cost of crashing 2-3 & 2-4 by 1 week = 2700 therefore, Direct cost of Project for 10 weeks duration = 18600 + 2700 = 21300 In this step, activity 2-3 has been crashed to its fullest extent.
  • 28. 1 2 3 4 4(2) 2(2) 4(2) 6(5)
  • 29. The remaining activities to be crashed are 1-2 , 2-4, 3-4. out of these, activities 2-4 & 3-4 are to be crashed jointly, with a combined cost slope of 2500 + 1200 = 3700. The cost slope of activity 1-2 is 4000 which is higher . Hence period of 6-5 = 1 week left. Hence only 1 week crashing will be done in this step, leading to a project duration of 9 weeks.
  • 30. cost of crashing 2-4 & 3-4 by 1 week. = 3700 * 1 = 3700 Therefore, cost of project for 9 weeks duration = 21300 + 3700 = 25000. The Time scaled version of the network for 9 weeks duration is shown in fig. we crashed activity 2-4 also to its fullest extent.
  • 31. Time- scaled network for 9 weeks Duration. 1 2 3 4 6(5) 4(2) 2(2) 3(2)
  • 32. Out of remaining critical activities ( i.e. 1-2&3-4) Activity 3-4 cannot be further crashed to its fullest crash period of 2 weeks, since it will affect activity 2-4 which has already been fully crashed. Hence activity 1-2 is the only remaining activity to be crashed. The period by which it can be crashed is = 4-2 = 2 weeks, reducing the project duration to 9-2 = 7 weeks. Extra cost of crashing 1-2 by 2 weeks = 2*4000 = 8000 Therefore, Direct cost of Project of 7 weeks duration = 25000 + 8000 = 33000.
  • 33. 1 2 3 5(2) 4 2(2) 2(2) 3(2)
  • 34. PROJECT DURATIO N 13 (NORMAL ) 11 10 9 7 DIRECT COST (RS.) 15600 18600 21200 25000 31000 INDIRECT COST (RS.) 26000 22000 20000 18000 14000 TOTAL COST (RS.) 41600 40600 41300 43000 47000