Time-Cost Tradeoff by Examples
INTRODUCTION
1
Chachrist Srisuwanrat
ชาคริต ศรีสุวรรณรัตน์
2
YouTube
What is Time-Cost Tradeoff ?
• It is the Exchange between “Time” and “Money”
Introduction to Time-Cost Tradeoff
DirectCost
Project
Duration
76543
500k
600k
700k
800k
900k
1,000k
1,100k
1,200k
1,300k
1,400k
400k
1,500k
1,600k
Cost
(Project Duration) (Cost)
Pay Extra Money to shorten the project
3
What is Time-Cost Tradeoff ?
• It is the Exchange between “Time” and “Money”
What is its Objective?
• Find Minimum Total Cost
Introduction to Time-Cost Tradeoff
DirectCost
Total Cost
Project
Duration
76543
500k
600k
700k
800k
900k
1,000k
1,100k
1,200k
1,300k
1,400k
400k
1,500k
1,600k
Cost
(Project Duration) (Cost)
Pay Extra Money to shorten the project
4
What is Time-Cost Tradeoff ?
• It is the Exchange between “Time” and “Money”
What is its Objective?
• Find Minimum Total Cost
About Total Cost:
• Total Cost = Direct + Indirect
• Direct Cost: labor, materials, equipment, …
• Indirect Cost : managers, safety, accountants, parking, …
Introduction to Time-Cost Tradeoff
DirectCost
450
600
750
900
1,050
Project
Duration
76543
500k
600k
700k
800k
900k
1,000k
1,100k
1,200k
1,300k
1,400k
400k
1,500k
1,600k
Cost
(Project Duration) (Cost)
Total Cost
IndirectCost150k/m
Pay Extra Cost to shorten the project
5
Time-Cost Tradeoff by Examples
Shorten Project by Shorten Critical Activities
+Slope
6
How much?
• Different activities have different “Extra Cost”, extra money per shorten duration (day, week, or month)
Shorten “Project Duration” by Shorten “Critical Activity Duration”
Project
Duration
76543
500k
600k
700k
800k
900k
1,000k
1,100k
1,200k
1,300k
1,400k
400k
1,500k
1,600k
Cost
Activity
5 – 7 months
700k – 500k
= Cost
Duration
Normal Duration (ND)
Normal Cost (NC)
Crash Duration (CD)
Crash Cost (NC)
Extra cost/duration = +Slope
500 Direct Cost
7
How much?
• Different activities have different “Extra Cost”, extra money per shorten duration (day, week, or month)
Shorten “Project Duration” by Shorten “Critical Activity Duration”
Project
Duration
76543
500k
600k
700k
800k
900k
1,000k
1,100k
1,200k
1,300k
1,400k
400k
1,500k
1,600k
Cost
= Cost
Duration Normal Duration – Crash Duration
Crash Cost – Normal Cost= ND - CD
CC - NC=
Activity
5 – 7 months
700k – 500k
Normal Duration (ND)
Normal Cost (NC)
Crash Duration (CD)
Crash Cost (NC)
Extra cost/duration = +Slope
500 Direct Cost
8
How much?
• Different activities have different “Extra Cost”, extra money per shorten duration (day, week, or month)
Shorten “Project Duration” by Shorten “Critical Activity Duration”
Project
Duration
76543
500k
600k
700k
800k
900k
1,000k
1,100k
1,200k
1,300k
1,400k
400k
1,500k
1,600k
Cost
Duration Cost +Slope
Crash (CD) Normal(ND) Crash (CC) Normal(NC)
Activity 5 7 700 500 ?
ND - CD
CC - NC 700 - 500
7 - 5
+100 k/m= =+Slope =
Normal Duration – Crash Duration
Crash Cost – Normal Cost== Cost
Duration ND - CD
CC - NC=Extra cost/duration = +Slope
500 Direct Cost
Activity
5 – 7 months
700k – 500k
Normal Duration (ND)
Normal Cost (NC)
Crash Duration (CD)
Crash Cost (NC)
9
How much?
• Different activities have different “Extra Cost”, extra money per shorten duration (day, week, or month)
Shorten “Project Duration” by Shorten “Critical Activity Duration”
600
Project
Duration
76543
500k
600k
700k
800k
900k
1,000k
1,100k
1,200k
1,300k
1,400k
400k
1,500k
1,600k
Cost
Duration Cost +Slope
Crash (CD) Normal(ND) Crash (CC) Normal(NC)
Activity 5 7 700 500 +100 500 Direct Cost
Normal Duration – Crash Duration
Crash Cost – Normal Cost== Cost
Duration
Extra cost/duration = +Slope
+100k/m
ND - CD
CC - NC 700 - 500
7 - 5
+100 k/m= =+Slope =
ND - CD
CC - NC=
Activity
5 – 7 months
700k – 500k
Normal Duration (ND)
Normal Cost (NC)
Crash Duration (CD)
Crash Cost (NC)
10
+100k/m
How much?
• Different activities have different “Extra Cost”, extra money per shorten duration (day, week, or month)
Shorten “Project Duration” by Shorten “Critical Activity Duration”
Project
Duration
76543
500k
600k
700k
800k
900k
1,000k
1,100k
1,200k
1,300k
1,400k
400k
1,500k
1,600k
Cost
Duration Cost +Slope
Crash (CD) Normal(ND) Crash (CC) Normal(NC)
Activity 5 7 700 500 +100
600
700
+100
500 Direct Cost
Normal Duration – Crash Duration
Crash Cost – Normal Cost== Cost
Duration
DONE !
Extra cost/duration = +Slope
ND - CD
CC - NC 700 - 500
7 - 5
+100 k/m= =+Slope =
ND - CD
CC - NC=
Activity
5 – 7 months
700k – 500k
Normal Duration (ND)
Normal Cost (NC)
Crash Duration (CD)
Crash Cost (NC)
11
Time-Cost Tradeoff by Examples
The Process of Shortening Project
12
Process of Shortening Project
P0: Use Normal Duration to create AON
A
3 – 4 m
+100k/m
B
2 – 4 m
+50 k/m
C
3 – 5 m
+75 k/m
D
6 – 8 m
+ 150k/m
13
= shorten Critical Activities by +Slope
Process of Shortening Project
P0: Use Normal Duration to create AON
A
3 – 4 m
+100k/m
0 4
B
2 – 4 m
+50 k/m
4 8
C
3 – 5 m
+75 k/m
4 9
D
6 – 8 m
+ 150k/m
9 17
4 4
5
8
14
= shorten Critical Activities by +Slope
Process of Shortening Project
P0: Use Normal Duration to create AON
P1: Consider spend Extra Money (+Slope) on critical activities
A
3 – 4 m
+100k/m
0 4
B
2 – 4 m
+50 k/m
4 8
C
3 – 5 m
+75 k/m
4 9
D
6 – 8 m
+ 150k/m
9 17
4 4
5
8
Step 1 Choices: A+100, C+75, D+150
15
= shorten Critical Activities by +Slope
Process of Shortening Project
P0: Use Normal Duration to create AON
P1: Consider spend Extra Money (+Slope) on critical activities
P2: Choose the cheapest critical activity (minimum slope)
A
3 – 4 m
+100k/m
0 4
B
2 – 4 m
+50 k/m
4 8
C
3 – 5 m
+75 k/m
4 9
D
6 – 8 m
+ 150k/m
9 17
4 4
5
8
Step 1 Choices: A+100, C+75, D+150
Choose: C+75
16
= shorten Critical Activities by +Slope
Process of Shortening Project
P0: Use Normal Duration to create AON
P1: Consider spend Extra Money (+Slope) on critical activities
P2: Choose the cheapest critical activity (minimum slope)
P3: Update/check/confirm that the +Slope shortens the project
A
3 – 4 m
+100k/m
0 4
B
2 – 4 m
+50 k/m
4 8
C
3 – 5 m
+75 k/m
4 9
D
6 – 8 m
+ 150k/m
9 17
4 4
5
8
--- 4
--- 8
--- 8 --- 16
Step 1 Choices: A+100, C+75, D+150
Choose: C+75
17
= shorten Critical Activities by +Slope
Process of Shortening Project
P0: Use Normal Duration to create AON
P1: Consider spend Extra Money (+Slope) on critical activities
P2: Choose the cheapest critical activity (minimum slope)
P3: Update/check/confirm that the +Slope shortens the project
P4: Update AON, Critical Activities, and Critical Paths
A
3 – 4 m
+100k/m
0 4
B
2 – 4 m
+50 k/m
4 8
C
3 – 5 m
+75 k/m
4 9
D
6 – 8 m
+ 150k/m
9 17
4 4
5
8
--- 4
--- 8
--- 8 --- 16
Step 1 Choices: A+100, C+75, D+150
Choose: C+75, Project duration = 16
18
= shorten Critical Activities by +Slope
Process of Shortening Project
P0: Use Normal Duration to create AON
P1: Consider spend Extra Money (+Slope) on critical activities
P2: Choose the cheapest critical activity (minimum slope)
P3: Update/check/confirm that the +Slope shortens the project
P4: Update AON, Critical Activities, and Critical Paths
A
3 – 4 m
+100k/m
0 4
B
2 – 4 m
+50 k/m
4 8
C
3 – 5 m
+75 k/m
4 9
D
6 – 8 m
+ 150k/m
9 17
4 4
5
8
--- 4
--- 8
--- 8 --- 16
Step 1 Choices: A+100, C+75, D+150
Choose: C+75, Project duration = 16
Step 2 Choices: A+100, B+50, C+75, D+150
Choose: B+50
Anothercritical pathA-C-D still pushes the project.
Choices: A+100, B&C+125, D150
19
= shorten Critical Activities by +Slope
Process of Shortening Project
P0: Use Normal Duration to create AON
P1: Consider spend Extra Money (+Slope) on critical activities
P2: Choose the cheapest critical activity (minimum slope)
P3: Update/check/confirm that the +Slope shortens the project
P4: Update AON, Critical Activities, and Critical Paths
A
3 – 4 m
+100k/m
0 4
B
2 – 4 m
+50 k/m
4 8
C
3 – 5 m
+75 k/m
4 9
D
6 – 8 m
+ 150k/m
9 17
4 4
5
8
--- 4
--- 8
--- 8 --- 16
Step 1 Choices: A+100, C+75, D+150
Choose: C+75, Project duration = 16
Step 2 Choices: A+100, B+50, C+75, D+150
Choose: B+50
Anothercritical pathA-C-D still pushes the project.
Choices: A+100, B&C+125, D150
Choose: A+100
20
= shorten Critical Activities by +Slope
Process of Shortening Project
P0: Use Normal Duration to create AON
P1: Consider spend Extra Money (+Slope) on critical activities
P2: Choose the cheapest critical activity (minimum slope)
P3: Update/check/confirm that the +Slope shortens the project
P4: Update AON, Critical Activities, and Critical Paths
A
3 – 4 m
+100k/m
0 4
B
2 – 4 m
+50 k/m
4 8
C
3 – 5 m
+75 k/m
4 9
D
6 – 8 m
+ 150k/m
9 17
4 4
5
8
--- 4
--- 8
--- 8 --- 16
Step 1 Choices: A+100, C+75, D+150
Choose: C+75, Project duration = 16
Step 2 Choices: A+100, B+50, C+75, D+150
Choose: B+50
Anothercritical pathA-C-D still pushes the project.
Choices: A+100, B&C+125, D+150
Choose: A+100, Project duration = 15--- 3
--- 3 --- 3 --- 7
--- 3 --- 7
--- 7 --- 15
21
= shorten Critical Activities by +Slope
Process of Shortening Project
P0: Use Normal Duration to create AON
P1: Consider spend Extra Money (+Slope) on critical activities
P2: Choose the cheapest critical activity (minimum slope)
P3: Update/check/confirm that the +Slope shortens the project
P4: Update AON, Critical Activities, and Critical Paths
A
3 – 4 m
+100k/m
0 4
B
2 – 4 m
+50 k/m
4 8
C
3 – 5 m
+75 k/m
4 9
D
6 – 8 m
+ 150k/m
9 17
4 4
5
8
--- 4
--- 8
--- 8 --- 16
Step 1 Choices: A+100, C+75, D+150
Choose: C+75, Project duration = 16
Step 2 Choices: A+100, B+50, C+75, D+150
Choose: B+50
Anothercritical pathA-C-D still pushes the project.
Choices: A+100, B&C+125, D+150
Choose: A+100, Project duration = 15
Step 3 Choices: B&C+125, D+150
Choose: B&C+125
--- 3
--- 3 --- 3 --- 7
--- 3 --- 7
--- 7 --- 15
22
= shorten Critical Activities by +Slope
Process of Shortening Project
P0: Use Normal Duration to create AON
P1: Consider spend Extra Money (+Slope) on critical activities
P2: Choose the cheapest critical activity (minimum slope)
P3: Update/check/confirm that the +Slope shortens the project
P4: Update AON, Critical Activities, and Critical Paths
A
3 – 4 m
+100k/m
0 4
B
2 – 4 m
+50 k/m
4 8
C
3 – 5 m
+75 k/m
4 9
D
6 – 8 m
+ 150k/m
9 17
4 4
5
8
--- 4
--- 8
--- 8 --- 16
Step 1 Choices: A+100, C+75, D+150
Choose: C+75, Project duration = 16
Step 2 Choices: A+100, B+50, C+75, D+150
Choose: B+50
Anothercritical pathA-C-D still pushes the project.
Choices: A+100, B&C+125, D+150
Choose: A+100, Project duration = 15
Step 3 Choices: B&C+125, D+150
Choose: B&C+125, Project duration= 14
--- 3
--- 3 --- 3 --- 7
--- 3 --- 7
--- 7 --- 15
--- 3
--- 3
--- 6
--- 6 --- 14
6
---
23
= shorten Critical Activities by +Slope
Process of Shortening Project
P0: Use Normal Duration to create AON
P1: Consider spend Extra Money (+Slope) on critical activities
P2: Choose the cheapest critical activity (minimum slope)
P3: Update/check/confirm that the +Slope shortens the project
P4: Update AON, Critical Activities, and Critical Paths
A
3 – 4 m
+100k/m
0 4
B
2 – 4 m
+50 k/m
4 8
C
3 – 5 m
+75 k/m
4 9
D
6 – 8 m
+ 150k/m
9 17
4 4
5
8
--- 4
--- 8
--- 8 --- 16
Step 1 Choices: A+100, C+75, D+150
Choose: C+75, Project duration = 16
Step 2 Choices: A+100, B+50, C+75, D+150
Choose: B+50
Anothercritical pathA-C-D still pushes the project.
Choices: A+100, B&C+125, D+150
Choose: A+100, Project duration = 15
Step 3 Choices: B&C+125, D+150
Choose: B&C+125, Project duration= 14
Step 4 Choice: B+50, D+150
Choose: D+150
--- 3
--- 3 --- 3 --- 7
--- 3 --- 7
--- 7 --- 15
--- 3
--- 3
--- 6
--- 6 --- 14
6
---
24
= shorten Critical Activities by +Slope
Process of Shortening Project
P0: Use Normal Duration to create AON
P1: Consider spend Extra Money (+Slope) on critical activities
P2: Choose the cheapest critical activity (minimum slope)
P3: Update/check/confirm that the +Slope shortens the project
P4: Update AON, Critical Activities, and Critical Paths
A
3 – 4 m
+100k/m
0 4
B
2 – 4 m
+50 k/m
4 8
C
3 – 5 m
+75 k/m
4 9
D
6 – 8 m
+ 150k/m
9 17
4 4
5
8
--- 4
--- 8
--- 8 --- 16
Step 1 Choices: A+100, C+75, D+150
Choose: C+75, Project duration = 16
Step 2 Choices: A+100, B+50, C+75, D+150
Choose: B+50
Anothercritical pathA-C-D still pushes the project.
Choices: A+100, B&C+125, D+150
Choose: A+100, Project duration = 15
Step 3 Choices: B&C+125, D+150
Choose: B&C+125, Project duration= 14
Step 4 Choice: B+50, D+150
Choose: D+150, Project duration = 13
--- 3
--- 3 --- 3 --- 7
--- 3 --- 7
--- 7 --- 15
--- 3
--- 3
--- 6
--- 6 --- 14--- 13
--- 7
6
---
25
= shorten Critical Activities by +Slope
Process of Shortening Project
P0: Use Normal Duration to create AON
P1: Consider spend Extra Money (+Slope) on critical activities
P2: Choose the cheapest critical activity (minimum slope)
P3: Update/check/confirm that the +Slope shortens the project
P4: Update AON, Critical Activities, and Critical Paths
A
3 – 4 m
+100k/m
0 4
B
2 – 4 m
+50 k/m
4 8
C
3 – 5 m
+75 k/m
4 9
D
6 – 8 m
+ 150k/m
9 17
4 4
5
8
--- 4
--- 8
--- 8 --- 16
--- 3
--- 3 --- 3 --- 7
--- 3 --- 7
--- 7 --- 15
--- 3
--- 3
--- 6
--- 6 --- 14--- 13
--- 7
6
---
Step 5 Choice: B+50, D+150
Choose: D+150
Step 1 Choices: A+100, C+75, D+150
Choose: C+75, Project duration = 16
Step 2 Choices: A+100, B+50, C+75, D+150
Choose: B+50
Anothercritical pathA-C-D still pushes the project.
Choices: A+100, B&C+125, D+150
Choose: A+100, Project duration = 15
Step 3 Choices: B&C+125, D+150
Choose: B&C+125, Project duration= 14
Step 4 Choice: B+50, D+150
Choose: D+150, Project duration = 13
26
= shorten Critical Activities by +Slope
Process of Shortening Project
P0: Use Normal Duration to create AON
P1: Consider spend Extra Money (+Slope) on critical activities
P2: Choose the cheapest critical activity (minimum slope)
P3: Update/check/confirm that the +Slope shortens the project
P4: Update AON, Critical Activities, and Critical Paths
A
3 – 4 m
+100k/m
0 4
B
2 – 4 m
+50 k/m
4 8
C
3 – 5 m
+75 k/m
4 9
D
6 – 8 m
+ 150k/m
9 17
= shorten Critical Activities by +Slope
4 4
5
8
--- 4
--- 8
--- 8 --- 16
--- 3
--- 3 --- 3 --- 7
--- 3 --- 7
--- 7 --- 15
--- 3
--- 3
--- 6
--- 6 --- 14--- 13
--- 7
6
---
Step 5 Choice: B+50, D+150
Choose: D+150, Project duration= 12
12
---
--- 6
Step 1 Choices: A+100, C+75, D+150
Choose: C+75, Project duration = 16
Step 2 Choices: A+100, B+50, C+75, D+150
Choose: B+50
Anothercritical pathA-C-D still pushes the project.
Choices: A+100, B&C+125, D+150
Choose: A+100, Project duration = 15
Step 3 Choices: B&C+125, D+150
Choose: B&C+125, Project duration= 14
Step 4 Choice: B+50, D+150
Choose: D+150, Project duration = 13
27
Time-Cost Tradeoff by Examples
Minimum Total Cost
28
Total Cost = Direct Cost + Indirect Cost
A
3 – 4 m
+100k/m
B
2 – 4 m
+50 k/m
C
3 – 5 m
+75 k/m
D
6 – 8 m
+ 150k/m
400k 100k 300k
300k
Indirect cost= 125 k/m
29
Total Cost = Direct Cost + Indirect Cost
Step 1 Choices: A+100, C+75, D+150
Choose: C+75, Project duration = 16
Step 2 Choices: A+100, B+50, C+75, D+150
Choose: A+100, Project duration = 15
Step 3 Choices: B&C+125, D+150
Choose: B&C+125, Project duration= 14
Step 4 Choice: B+50, D+150
Choose: D+150, Project duration= 13
Step 5 Choice: B+50, D+150
Choose: D+150, Project duration = 12
A
3 – 4 m
+100k/m
B
2 – 4 m
+50 k/m
C
3 – 5 m
+75 k/m
D
6 – 8 m
+ 150k/m
400k 100k 300k
300k
Indirect cost= 125 k/m
30
Total Cost = Direct Cost + Indirect Cost
A
3 – 4 m
+100k/m
B
2 – 4 m
+50 k/m
C
3 – 5 m
+75 k/m
D
6 – 8 m
+ 150k/m
400k 100k 300k
300k
Indirect cost= 125 k/m
125 x Duration
Step 1 Choices: A+100, C+75, D+150
Choose: C+75, Project duration = 16
Step 2 Choices: A+100, B+50, C+75, D+150
Choose: A+100, Project duration = 15
Step 3 Choices: B&C+125, D+150
Choose: B&C+125, Project duration= 14
Step 4 Choice: B+50, D+150
Choose: D+150, Project duration= 13
Step 5 Choice: B+50, D+150
Choose: D+150, Project duration = 12
31
Total Cost = Direct Cost + Indirect Cost
A
3 – 4 m
+100k/m
B
2 – 4 m
+50 k/m
C
3 – 5 m
+75 k/m
D
6 – 8 m
+ 150k/m
400k 100k 300k
300k
Indirect cost= 125 k/m
125 x Duration
Step 1 Choices: A+100, C+75, D+150
Choose: C+75, Project duration = 16
Step 2 Choices: A+100, B+50, C+75, D+150
Choose: A+100, Project duration = 15
Step 3 Choices: B&C+125, D+150
Choose: B&C+125, Project duration= 14
Step 4 Choice: B+50, D+150
Choose: D+150, Project duration= 13
Step 5 Choice: B+50, D+150
Choose: D+150, Project duration = 12
32
Total Cost = Direct Cost + Indirect Cost
A
3 – 4 m
+100k/m
B
2 – 4 m
+50 k/m
C
3 – 5 m
+75 k/m
D
6 – 8 m
+ 150k/m
400k 100k 300k
300k
Indirect cost= 125 k/m
125 x Duration
Step 1 Choices: A+100, C+75, D+150
Choose: C+75, Project duration = 16
Step 2 Choices: A+100, B+50, C+75, D+150
Choose: A+100, Project duration = 15
Step 3 Choices: B&C+125, D+150
Choose: B&C+125, Project duration= 14
Step 4 Choice: B+50, D+150
Choose: D+150, Project duration= 13
Step 5 Choice: B+50, D+150
Choose: D+150, Project duration = 12
33
Total Cost = Direct Cost + Indirect Cost
A
3 – 4 m
+100k/m
B
2 – 4 m
+50 k/m
C
3 – 5 m
+75 k/m
D
6 – 8 m
+ 150k/m
400k 100k 300k
300k
Indirect cost= 125 k/m
125 x Duration
Step 1 Choices: A+100, C+75, D+150
Choose: C+75, Project duration = 16
Step 2 Choices: A+100, B+50, C+75, D+150
Choose: A+100, Project duration = 15
Step 3 Choices: B&C+125, D+150
Choose: B&C+125, Project duration= 14
Step 4 Choice: B+50, D+150
Choose: D+150, Project duration= 13
Step 5 Choice: B+50, D+150
Choose: D+150, Project duration = 12
34
Total Cost = Direct Cost + Indirect Cost
A
3 – 4 m
+100k/m
B
2 – 4 m
+50 k/m
C
3 – 5 m
+75 k/m
D
6 – 8 m
+ 150k/m
400k 100k 300k
300k
Indirect cost= 125 k/m
125 x Duration
Step 1 Choices: A+100, C+75, D+150
Choose: C+75, Project duration = 16
Step 2 Choices: A+100, B+50, C+75, D+150
Choose: A+100, Project duration = 15
Step 3 Choices: B&C+125, D+150
Choose: B&C+125, Project duration= 14
Step 4 Choice: B+50, D+150
Choose: D+150, Project duration= 13
Step 5 Choice: B+50, D+150
Choose: D+150, Project duration = 12
35
Total Cost = Direct Cost + Indirect Cost
A
3 – 4 m
+100k/m
B
2 – 4 m
+50 k/m
C
3 – 5 m
+75 k/m
D
6 – 8 m
+ 150k/m
400k 100k 300k
300k
Indirect cost= 125 k/m
Min Total Cost
125 x Duration
Step 1 Choices: A+100, C+75, D+150
Choose: C+75, Project duration = 16
Step 2 Choices: A+100, B+50, C+75, D+150
Choose: A+100, Project duration = 15
Step 3 Choices: B&C+125, D+150
Choose: B&C+125, Project duration= 14
Step 4 Choice: B+50, D+150
Choose: D+150, Project duration= 13
Step 5 Choice: B+50, D+150
Choose: D+150, Project duration = 12
36
Time-Cost Tradeoff by Examples
S-Curve at Min Total Cost
37
Step 1 Choices: A+100, C+75, D+150
Choose: C+75, Project duration = 16
Step 2 Choices: A+100, B+50, C+75, D+150
Choose: A+100, Project duration = 15
Step 3 Choices: B&C+125, D+150
Choose: B&C+125, Project duration= 14
Step 4 Choice: B+50, D+150
Choose: D+150, Project duration= 13
Step 5 Choice: B+50, D+150
Choose: D+150, Project duration = 12
S-Curve at Min Total Cost
A
4
3 – 4 m
+100k/m
B
4
2 – 4 m
+50 k/m
C
5
3 – 5 m
+75 k/m
D
8
6 – 8 m
+ 150k/m
400k 100k 300k
300k
Indirect cost= 125 k/m
38
A
4
3 – 4 m
+100k/m
B
4
2 – 4 m
+50 k/m
C
5
3 – 5 m
+75 k/m
D
8
6 – 8 m
+ 150k/m
400k 100k 300k
300k
Indirect cost= 125 k/m
--- 4
-------- 375
Step 1 Choices: A+100, C+75, D+150
Choose: C+75, Project duration = 16
Step 2 Choices: A+100, B+50, C+75, D+150
Choose: A+100, Project duration = 15
Step 3 Choices: B&C+125, D+150
Choose: B&C+125, Project duration= 14
39
S-Curve at Min Total Cost
A
4
3 – 4 m
+100k/m
B
4
2 – 4 m
+50 k/m
C
5
3 – 5 m
+75 k/m
D
8
6 – 8 m
+ 150k/m
400k 100k 300k
300k
Indirect cost= 125 k/m
--- 4
--- 3
-------- 500
-------- 375
Step 1 Choices: A+100, C+75, D+150
Choose: C+75, Project duration = 16
Step 2 Choices: A+100, B+50, C+75, D+150
Choose: A+100, Project duration = 15
Step 3 Choices: B&C+125, D+150
Choose: B&C+125, Project duration= 14
40
S-Curve at Min Total Cost
A
4
3 – 4 m
+100k/m
B
4
2 – 4 m
+50 k/m
C
5
3 – 5 m
+75 k/m
D
8
6 – 8 m
+ 150k/m
400k 100k 300k
300k
Indirect cost= 125 k/m
--- 4
--- 3 --- 3
--- 3
-------- 500
-------- 375-------- 450
-------- 150
Step 1 Choices: A+100, C+75, D+150
Choose: C+75, Project duration = 16
Step 2 Choices: A+100, B+50, C+75, D+150
Choose: A+100, Project duration = 15
Step 3 Choices: B&C+125, D+150
Choose: B&C+125, Project duration= 14
41
S-Curve at Min Total Cost
A
4
3 – 4 m
+100k/m
B
4
2 – 4 m
+50 k/m
C
5
3 – 5 m
+75 k/m
D
8
6 – 8 m
+ 150k/m
400k 100k 300k
300k
Indirect cost= 125 k/m
--- 4
--- 3 --- 3
--- 3
-------- 500
-------- 375-------- 450
-------- 150
Step 1 Choices: A+100, C+75, D+150
Choose: C+75, Project duration = 16
Step 2 Choices: A+100, B+50, C+75, D+150
Choose: A+100, Project duration = 15
Step 3 Choices: B&C+125, D+150
Choose: B&C+125, Project duration= 14
42
S-Curve at Min Total Cost
A
4
3 – 4 m
+100k/m
B
4
2 – 4 m
+50 k/m
C
5
3 – 5 m
+75 k/m
D
8
6 – 8 m
+ 150k/m
400k 100k 300k
300k
Indirect cost= 125 k/m
--- 4
--- 3 --- 3
--- 3
-------- 500
-------- 375-------- 450
-------- 150
Step 1 Choices: A+100, C+75, D+150
Choose: C+75, Project duration = 16
Step 2 Choices: A+100, B+50, C+75, D+150
Choose: A+100, Project duration = 15
Step 3 Choices: B&C+125, D+150
Choose: B&C+125, Project duration= 14
43
S-Curve at Min Total Cost
A
4
3 – 4 m
+100k/m
B
4
2 – 4 m
+50 k/m
C
5
3 – 5 m
+75 k/m
D
8
6 – 8 m
+ 150k/m
400k 100k 300k
300k
Indirect cost= 125 k/m
--- 4
--- 3 --- 3
--- 3
-------- 500
-------- 375-------- 450
-------- 150
Step 1 Choices: A+100, C+75, D+150
Choose: C+75, Project duration = 16
Step 2 Choices: A+100, B+50, C+75, D+150
Choose: A+100, Project duration = 15
Step 3 Choices: B&C+125, D+150
Choose: B&C+125, Project duration= 14
44
S-Curve at Min Total Cost
A
4
3 – 4 m
+100k/m
B
4
2 – 4 m
+50 k/m
C
5
3 – 5 m
+75 k/m
D
8
6 – 8 m
+ 150k/m
400k 100k 300k
300k
Indirect cost= 125 k/m
--- 4
--- 3 --- 3
--- 3
-------- 500
-------- 375-------- 450
-------- 150
Step 1 Choices: A+100, C+75, D+150
Choose: C+75, Project duration = 16
Step 2 Choices: A+100, B+50, C+75, D+150
Choose: A+100, Project duration = 15
Step 3 Choices: B&C+125, D+150
Choose: B&C+125, Project duration= 14
45
S-Curve at Min Total Cost
Time-Cost Tradeoff by Examples
Example 1-A: Direct Cost
A B C
Activity Duration Cost
Crash (CD) Normal(ND) Crash (CC) Normal(NC)
A 3 4 470 400
B 10 12 460 300
C 6 8 600 500
Indirect cost= 65 k/m46
Example 1-A
A B C
Activity Duration Cost +Slope
Crash (CD) Normal(ND) Crash (CC) Normal(NC)
A 3 4 470 400
B 10 12 460 300
C 6 8 600 500
47
Activity Duration Cost +Slope
Crash (CD) Normal(ND) Crash (CC) Normal(NC)
A 3 4 470 400
B 10 12 460 300
C 6 8 600 500
Example 1-A: Calculate +Slope
A B C
+70 k/m +80 k/m + 50 k/m
+70
+80
+50
3 – 4 m 10 – 12 m 6 – 8 m
48
Example 1-A: Start with “Normal Duration” for all activities
A B C
+70 k/m +80 k/m + 50 k/m
3 – 4 m 10 – 12 m 6 – 8 m
4 12 8
Activity Duration Cost +Slope
Crash (CD) Normal(ND) Crash (CC) Normal(NC)
A 3 4 470 400
B 10 12 460 300
C 6 8 600 500
+70
+80
+50
49
Example 1-A: Perform CPM
A B C
+70 k/m +80 k/m + 50 k/m
0 4
3 – 4 m 10 – 12 m 6 – 8 m
4 12 8
4 16 16 24
Activity Duration Cost +Slope
Crash (CD) Normal(ND) Crash (CC) Normal(NC)
A 3 4 470 400
B 10 12 460 300
C 6 8 600 500
+70
+80
+50
50
Example 1-A: Identify critical activities and critical path
A B C
+70 k/m +80 k/m + 50 k/m
0 4
3 – 4 m 10 – 12 m 6 – 8 m
4 12 8
4 16 16 24
Activity Duration Cost +Slope
Crash (CD) Normal(ND) Crash (CC) Normal(NC)
A 3 4 470 400
B 10 12 460 300
C 6 8 600 500
+70
+80
+50
51
Example 1-A: Shortening Project = Shortening critical activities
Step 1 Choices: A+70, B+80, C+50
Choose: C+50
A B C
+70 k/m +80 k/m + 50 k/m
0 4
3 – 4 m 10 – 12 m 6 – 8 m
4 12 8
4 16 16 24
Activity Duration Cost +Slope
Crash (CD) Normal(ND) Crash (CC) Normal(NC)
A 3 4 470 400
B 10 12 460 300
C 6 8 600 500
+70
+80
+50
52
Example 1-A: Shortening Project = Shortening critical activities
Step 1 Choices: A+70, B+80, C+50
Choose: C+50, Project duration= 23
A B C
+70 k/m +80 k/m + 50 k/m
--- 7
0 4
3 – 4 m 10 – 12 m 6 – 8 m
4 12 8
4 16 16 24--- 23
Activity Duration Cost +Slope
Crash (CD) Normal(ND) Crash (CC) Normal(NC)
A 3 4 470 400
B 10 12 460 300
C 6 8 600 500
+70
+80
+50
53
Example 1-A: Shortening Project = Shortening critical activities
Step 1 Choices: A+70, B+80, C+50
Choose: C+50, Project duration= 23
Step 2 Choices: A+70, B+80, C+50
Choose: C+50
A B C
+70 k/m +80 k/m + 50 k/m
--- 7
0 4
3 – 4 m 10 – 12 m 6 – 8 m
4 12 8
4 16 16 24--- 23
Activity Duration Cost +Slope
Crash (CD) Normal(ND) Crash (CC) Normal(NC)
A 3 4 470 400
B 10 12 460 300
C 6 8 600 500
+70
+80
+50
54
Example 1-A: Shortening Project = Shortening critical activities
Step 1 Choices: A+70, B+80, C+50
Choose: C+50, Project duration= 23
Step 2 Choices: A+70, B+80, C+50
Choose: C+50, Project duration= 22
A B C
+70 k/m +80 k/m + 50 k/m
--- 7
0 4
3 – 4 m 10 – 12 m 6 – 8 m
4 12 8
4 16 16 24--- 23
--- 6
--- 22
Activity Duration Cost +Slope
Crash (CD) Normal(ND) Crash (CC) Normal(NC)
A 3 4 470 400
B 10 12 460 300
C 6 8 600 500
+70
+80
+50
55
Example 1-A: Shortening Project = Shortening critical activities
Step 1 Choices: A+70, B+80, C+50
Choose: C+50, Project duration= 23
Step 2 Choices: A+70, B+80, C+50
Choose: C+50, Project duration= 22
Step 3 Choices: A+70, B+80
Choose: A+70
A B C
+70 k/m +80 k/m + 50 k/m
--- 7
0 4
3 – 4 m 10 – 12 m 6 – 8 m
4 12 8
4 16 16 24--- 23
--- 6
--- 22
Activity Duration Cost +Slope
Crash (CD) Normal(ND) Crash (CC) Normal(NC)
A 3 4 470 400
B 10 12 460 300
C 6 8 600 500
+70
+80
+50
56
Example 1-A: Shortening Project = Shortening critical activities
Step 1 Choices: A+70, B+80, C+50
Choose: C+50, Project duration= 23
Step 2 Choices: A+70, B+80, C+50
Choose: C+50, Project duration= 22
Step 3 Choices: A+70, B+80
Choose: A+70, Project duration= 21
A B C
+70 k/m +80 k/m + 50 k/m
--- 7
0 4
3 – 4 m 10 – 12 m 6 – 8 m
4 12 8
4 16 16 24--- 23
--- 6
--- 22
Activity Duration Cost +Slope
Crash (CD) Normal(ND) Crash (CC) Normal(NC)
A 3 4 470 400
B 10 12 460 300
C 6 8 600 500
+70
+80
+50
--- 3
--- 3 --- 3 --- 15 --- 15 --- 21
57
Example 1-A: Shortening Project = Shortening critical activities
Step 1 Choices: A+70, B+80, C+50
Choose: C+50, Project duration= 23
Step 2 Choices: A+70, B+80, C+50
Choose: C+50, Project duration= 22
Step 3 Choices: A+70, B+80
Choose: A+70, Project duration= 21
Step 4 Choices: B+80
Choose: B+80
A B C
+70 k/m +80 k/m + 50 k/m
--- 7
0 4
3 – 4 m 10 – 12 m 6 – 8 m
4 12 8
4 16 16 24--- 23
--- 6
--- 22
Activity Duration Cost +Slope
Crash (CD) Normal(ND) Crash (CC) Normal(NC)
A 3 4 470 400
B 10 12 460 300
C 6 8 600 500
+70
+80
+50
--- 3
--- 3 --- 3 --- 15 --- 15 --- 21
58
Example 1-A: Shortening Project = Shortening critical activities
Step 1 Choices: A+70, B+80, C+50
Choose: C+50, Project duration= 23
Step 2 Choices: A+70, B+80, C+50
Choose: C+50, Project duration= 22
Step 3 Choices: A+70, B+80
Choose: A+70, Project duration= 21
Step 4 Choices: B+80
Choose: B+80, Project duration = 20
A B C
+70 k/m +80 k/m + 50 k/m
--- 7
0 4
3 – 4 m 10 – 12 m 6 – 8 m
4 12 8
4 16 16 24--- 23
--- 6
--- 22
Activity Duration Cost +Slope
Crash (CD) Normal(ND) Crash (CC) Normal(NC)
A 3 4 470 400
B 10 12 460 300
C 6 8 600 500
+70
+80
+50
--- 3
--- 3 --- 3 --- 15 --- 15 --- 21
--- 11
--- 14
14
---
20
---
59
Example 1-A: Shortening Project = Shortening critical activities
Step 1 Choices: A+70, B+80, C+50
Choose: C+50, Project duration= 23
Step 2 Choices: A+70, B+80, C+50
Choose: C+50, Project duration= 22
Step 3 Choices: A+70, B+80
Choose: A+70, Project duration= 21
Step 4 Choices: B+80
Choose: B+80, Project duration = 20
Step 5 Choices: B+80
Choose: B+80
A B C
+70 k/m +80 k/m + 50 k/m
--- 7
0 4
3 – 4 m 10 – 12 m 6 – 8 m
4 12 8
4 16 16 24--- 23
--- 6
--- 22
Activity Duration Cost +Slope
Crash (CD) Normal(ND) Crash (CC) Normal(NC)
A 3 4 470 400
B 10 12 460 300
C 6 8 600 500
+70
+80
+50
--- 3
--- 3 --- 3 --- 15 --- 15 --- 21
--- 11
--- 14
14
---
20
---
60
Example 1-A: Shortening Project = Shortening critical activities
Step 1 Choices: A+70, B+80, C+50
Choose: C+50, Project duration= 23
Step 2 Choices: A+70, B+80, C+50
Choose: C+50, Project duration= 22
Step 3 Choices: A+70, B+80
Choose: A+70, Project duration= 21
Step 4 Choices: B+80
Choose: B+80, Project duration = 20
Step 5 Choices: B+80
Choose: B+80, Project duration = 19
A B C
+70 k/m +80 k/m + 50 k/m
--- 7
0 4
3 – 4 m 10 – 12 m 6 – 8 m
4 12 8
4 16 16 24--- 23
--- 6
--- 22
Activity Duration Cost +Slope
Crash (CD) Normal(ND) Crash (CC) Normal(NC)
A 3 4 470 400
B 10 12 460 300
C 6 8 600 500
+70
+80
+50
--- 3
--- 3 --- 3 --- 15 --- 15 --- 21
--- 11
--- 14
14
---
20
---
--- 10
--- 13
--- 13 --- 19
61
Time-Cost Tradeoff by Examples
Example 1-B: Minimum Total Cost
Indirect cost= 65 k/m62
Example 1-B: Minimum Total Cost
400k 300k 500k
A B C
+70 k/m +80 k/m + 50 k/m
3 – 4 m 10 – 12 m 6 – 8 m
Activity Duration Cost +Slope
Crash (CD) Normal(ND) Crash (CC) Normal(NC)
A 3 4 470 400
B 10 12 460 300
C 6 8 600 500
+70
+80
+50
(Indirectcost = 65 k/m)
Normal Direct Cost = 400 + 300 + 500 = 1,200 k
63
Example 1-B: Minimum Total Cost
Step 1 Choices: A+70, B+80, C+50
Choose: C+50, Project duration= 23
Step 2 Choices: A+70, B+80, C+50
Choose: C+50, Project duration= 22
Step 3 Choices: A+70, B+80
Choose: A+70, Project duration= 21
Step 4 Choices: B+80
Choose: B+80, Project duration = 20
Step 5 Choices: B+80
Choose: B+80, Project duration = 19
400k 300k 500k
A B C
+70 k/m +80 k/m + 50 k/m
3 – 4 m 10 – 12 m 6 – 8 m
Activity Duration Cost +Slope
Crash (CD) Normal(ND) Crash (CC) Normal(NC)
A 3 4 470 400
B 10 12 460 300
C 6 8 600 500
+70
+80
+50
(Indirectcost = 65 k/m)
Normal Direct Cost = 400 + 300 + 500 = 1,200 k
64
Example 1-B: Minimum Total Cost
400k 300k 500k
A B C
+70 k/m +80 k/m + 50 k/m
3 – 4 m 10 – 12 m 6 – 8 m
Activity Duration Cost +Slope
Crash (CD) Normal(ND) Crash (CC) Normal(NC)
A 3 4 470 400
B 10 12 460 300
C 6 8 600 500
+70
+80
+50
(Indirectcost = 65 k/m)
Step 1 Choices: A+70, B+80, C+50
Choose: C+50, Project duration= 23
Step 2 Choices: A+70, B+80, C+50
Choose: C+50, Project duration= 22
Step 3 Choices: A+70, B+80
Choose: A+70, Project duration= 21
Step 4 Choices: B+80
Choose: B+80, Project duration = 20
Step 5 Choices: B+80
Choose: B+80, Project duration = 19
Normal Direct Cost = 400 + 300 + 500 = 1,200 k
65
Example 1-B: Minimum Total Cost
400k 300k 500k
A B C
+70 k/m +80 k/m + 50 k/m
3 – 4 m 10 – 12 m 6 – 8 m
Activity Duration Cost +Slope
Crash (CD) Normal(ND) Crash (CC) Normal(NC)
A 3 4 470 400
B 10 12 460 300
C 6 8 600 500
+70
+80
+50
(Indirectcost = 65 k/m)
Step 1 Choices: A+70, B+80, C+50
Choose: C+50, Project duration= 23
Step 2 Choices: A+70, B+80, C+50
Choose: C+50, Project duration= 22
Step 3 Choices: A+70, B+80
Choose: A+70, Project duration= 21
Step 4 Choices: B+80
Choose: B+80, Project duration = 20
Step 5 Choices: B+80
Choose: B+80, Project duration = 19
Normal Direct Cost = 400 + 300 + 500 = 1,200 k
66
Step 1 Choices: A+70, B+80, C+50
Choose: C+50, Project duration= 23
Step 2 Choices: A+70, B+80, C+50
Choose: C+50, Project duration= 22
Step 3 Choices: A+70, B+80
Choose: A+70, Project duration= 21
Step 4 Choices: B+80
Choose: B+80, Project duration = 20
Step 5 Choices: B+80
Choose: B+80, Project duration = 19
Example 1-B: Minimum Total Cost
400k 300k 500k
A B C
+70 k/m +80 k/m + 50 k/m
3 – 4 m 10 – 12 m 6 – 8 m
Activity Duration Cost +Slope
Crash (CD) Normal(ND) Crash (CC) Normal(NC)
A 3 4 470 400
B 10 12 460 300
C 6 8 600 500
+70
+80
+50
(Indirectcost = 65 k/m)
Normal Direct Cost = 400 + 300 + 500 = 1,200 k
67
Example 1-B: Minimum Total Cost
Step 1 Choices: A+70, B+80, C+50
Choose: C+50, Project duration= 23
Step 2 Choices: A+70, B+80, C+50
Choose: C+50, Project duration= 22
400k 300k 500k
A B C
+70 k/m +80 k/m + 50 k/m
3 – 4 m 10 – 12 m 6 – 8 m
Min Total Cost
(Indirectcost = 65 k/m)
68
Time-Cost Tradeoff by Examples
Example 1-C: S-Curve at Min Total Cost
69
Example 1-C: S-Curve
Step 1 Choices: A+70, B+80, C+50
Choose: C+50, Project duration= 23
Step 2 Choices: A+70, B+80, C+50
Choose: C+50, Project duration= 22
400k 300k 500k
A
4
B
12
C
8
+70 k/m +80 k/m + 50 k/m
3 – 4 m 10 – 12 m 6 – 8 m
(Indirectcost = 65 k/m)
70
Example 1-C: S-Curve
400k 300k 500k
A
4
B
12
C
8
+70 k/m +80 k/m + 50 k/m
3 – 4 m 10 – 12 m 6 – 8 m
-------- 550
--- 7
(Indirectcost = 65 k/m)
Step 1 Choices: A+70, B+80, C+50
Choose: C+50, Project duration= 23
Step 2 Choices: A+70, B+80, C+50
Choose: C+50, Project duration= 22
71
Example 1-C: S-Curve
400k 300k 500k
A
4
B
12
C
8
+70 k/m +80 k/m + 50 k/m
3 – 4 m 10 – 12 m 6 – 8 m
-------- 550-------- 600
--- 7--- 6
(Indirectcost = 65 k/m)
Step 1 Choices: A+70, B+80, C+50
Choose: C+50, Project duration= 23
Step 2 Choices: A+70, B+80, C+50
Choose: C+50, Project duration= 22
72
Example 1-C: S-Curve
400k 300k 500k
A
4
B
12
C
8
+70 k/m +80 k/m + 50 k/m
3 – 4 m 10 – 12 m 6 – 8 m
(Indirectcost = 65 k/m)
-------- 550-------- 600
--- 7--- 6
Step 1 Choices: A+70, B+80, C+50
Choose: C+50, Project duration= 23
Step 2 Choices: A+70, B+80, C+50
Choose: C+50, Project duration= 22
73
Example 1-C: S-Curve
400k 300k 500k
A
4
B
12
C
8
+70 k/m +80 k/m + 50 k/m
3 – 4 m 10 – 12 m 6 – 8 m
(Indirectcost = 65 k/m)
-------- 550-------- 600
--- 7--- 6
Step 1 Choices: A+70, B+80, C+50
Choose: C+50, Project duration= 23
Step 2 Choices: A+70, B+80, C+50
Choose: C+50, Project duration= 22
74
Example 1-C: S-Curve
400k 300k 500k
A
4
B
12
C
8
+70 k/m +80 k/m + 50 k/m
3 – 4 m 10 – 12 m 6 – 8 m
(Indirectcost = 65 k/m)
-------- 550-------- 600
--- 7--- 6
Step 1 Choices: A+70, B+80, C+50
Choose: C+50, Project duration= 23
Step 2 Choices: A+70, B+80, C+50
Choose: C+50, Project duration= 22
75
Example 1-C: S-Curve
400k 300k 500k
A
4
B
12
C
8
+70 k/m +80 k/m + 50 k/m
3 – 4 m 10 – 12 m 6 – 8 m
(Indirectcost = 65 k/m)
-------- 550-------- 600
--- 7--- 6
Step 1 Choices: A+70, B+80, C+50
Choose: C+50, Project duration= 23
Step 2 Choices: A+70, B+80, C+50
Choose: C+50, Project duration= 22
76
Time-Cost Tradeoff by Examples
Example 2-A: Direct Cost
77
B
2
+75 k/m
A
3
+155 k/m
2 – 3 m 1 – 2 m
D
6
+50 k/m
4 – 6 m
C
3
+70 k/m
1 – 3 m
F
6
+50 k/m
2 – 6 m
E
7
+25 k/m
3 – 7 m
G
5
+60 k/m
4 – 5 m
Example 2-A
78
Example 2-A: Perform CPM
B
2
+75 k/m
A
3
+155 k/m
2 – 3 m 1 – 2 m
D
6
+50 k/m
4 – 6 m
C
3
+70 k/m
1 – 3 m
F
6
+50 k/m
2 – 6 m
E
7
+25 k/m
3 – 7 m
G
5
+60 k/m
4 – 5 m
0 3 3 5
3 6
5 11
6 13
6 12
13 18
79
Example 2-A: Identify critical path and critical activities
B
2
+75 k/m
A
3
+155 k/m
2 – 3 m 1 – 2 m
D
6
+50 k/m
4 – 6 m
C
3
+70 k/m
1 – 3 m
F
6
+50 k/m
2 – 6 m
E
7
+25 k/m
3 – 7 m
G
5
+60 k/m
4 – 5 m
0 3 3 5
3 6
5 11
6 13
6 12
13 18
80
B
2
+75 k/m
A
3
+155 k/m
2 – 3 m 1 – 2 m
D
6
+50 k/m
4 – 6 m
Step 1 Choices: A+155, C+70, E+25, G+60
Choose: E+25
C
3
+70 k/m
1 – 3 m
F
6
+50 k/m
2 – 6 m
E
7
+25 k/m
3 – 7 m
G
5
+60 k/m
4 – 5 m
0 3 3 5
3 6
5 11
6 13
6 12
13 18
81
Example 2-A: Direct Cost
Example 2-A: Direct Cost
B
2
+75 k/m
A
3
+155 k/m
2 – 3 m 1 – 2 m
D
6
+50 k/m
4 – 6 m
Step 1 Choices: A+155, C+70, E+25, G+60
Choose: E+25, Project duration = 17
C
3
+70 k/m
1 – 3 m
F
6
+50 k/m
2 – 6 m
E
7
+25 k/m
3 – 7 m
G
5
+60 k/m
4 – 5 m
0 3 3 5
3 6
5 11
6 13
6 12
--- 6
13 18
--- 12
12
---
17
---
82
Example 2-A: Direct Cost
B
2
+75 k/m
A
3
+155 k/m
2 – 3 m 1 – 2 m
D
6
+50 k/m
4 – 6 m
Step 1 Choices: A+155, C+70, E+25, G+60
Choose: E+25, Project duration = 17
C
3
+70 k/m
1 – 3 m
F
6
+50 k/m
2 – 6 m
E
7
+25 k/m
3 – 7 m
G
5
+60 k/m
4 – 5 m
0 3 3 5
3 6
5 11
6 13
6 12
--- 6
13 18
--- 12
12
---
17
---
83
Example 2-A: Direct Cost
B
2
+75 k/m
A
3
+155 k/m
2 – 3 m 1 – 2 m
D
6
+50 k/m
4 – 6 m
Step 1 Choices: A+155, C+70, E+25, G+60
Choose: E+25, Project duration = 17
Step 2 Choices: A+155, C+70, E&F+75, G+60
Choose: G+60
C
3
+70 k/m
1 – 3 m
F
6
+50 k/m
2 – 6 m
E
7
+25 k/m
3 – 7 m
G
5
+60 k/m
4 – 5 m
0 3 3 5
3 6
5 11
6 13
6 12
--- 6
13 18
--- 12
12
---
17
---
84
Example 2-A: Direct Cost
B
2
+75 k/m
A
3
+155 k/m
2 – 3 m 1 – 2 m
D
6
+50 k/m
4 – 6 m
Step 1 Choices: A+155, C+70, E+25, G+60
Choose: E+25, Project duration = 17
Step 2 Choices: A+155, C+70, E&F+75, G+60
Choose: G+60, Project duration= 16
C
3
+70 k/m
1 – 3 m
F
6
+50 k/m
2 – 6 m
E
7
+25 k/m
3 – 7 m
G
5
+60 k/m
4 – 5 m
0 3 3 5
3 6
5 11
6 13
6 12
--- 6
13 18
--- 12
12
---
17
---
--- 4
16
---
85
Example 2-A: Direct Cost
B
2
+75 k/m
A
3
+155 k/m
2 – 3 m 1 – 2 m
D
6
+50 k/m
4 – 6 m
Step 1 Choices: A+155, C+70, E+25, G+60
Choose: E+25, Project duration = 17
Step 2 Choices: A+155, C+70, E&F+75, G+60
Choose: G+60, Project duration= 16
Step 3 Choices: A+155, C+70, E&F+75
Choose: C+70
C
3
+70 k/m
1 – 3 m
F
6
+50 k/m
2 – 6 m
E
7
+25 k/m
3 – 7 m
G
5
+60 k/m
4 – 5 m
0 3 3 5
3 6
5 11
6 13
6 12
--- 6
13 18
--- 12
12
---
17
---
--- 4
16
---
86
Example 2-A: Direct Cost
B
2
+75 k/m
A
3
+155 k/m
2 – 3 m 1 – 2 m
D
6
+50 k/m
4 – 6 m
--- 2
Step 1 Choices: A+155, C+70, E+25, G+60
Choose: E+25, Project duration = 17
Step 2 Choices: A+155, C+70, E&F+75, G+60
Choose: G+60, Project duration= 16
Step 3 Choices: A+155, C+70, E&F+75
Choose: C+70, Project duration = 15
C
3
+70 k/m
1 – 3 m
F
6
+50 k/m
2 – 6 m
E
7
+25 k/m
3 – 7 m
G
5
+60 k/m
4 – 5 m
0 3 3 5
3 6
5 11
6 13
6 12
--- 6
13 18
--- 12
12
---
17
---
--- 4
16
---
--- 5
5
---
11
---
5
---
11
---
15
---
11
---
87
Example 2-A: Direct Cost
B
2
+75 k/m
A
3
+155 k/m
2 – 3 m 1 – 2 m
D
6
+50 k/m
4 – 6 m
--- 2
Step 1 Choices: A+155, C+70, E+25, G+60
Choose: E+25, Project duration = 17
Step 2 Choices: A+155, C+70, E&F+75, G+60
Choose: G+60, Project duration= 16
Step 3 Choices: A+155, C+70, E&F+75
Choose: C+70, Project duration = 15
C
3
+70 k/m
1 – 3 m
F
6
+50 k/m
2 – 6 m
E
7
+25 k/m
3 – 7 m
G
5
+60 k/m
4 – 5 m
0 3 3 5
3 6
5 11
6 13
6 12
--- 6
13 18
--- 12
12
---
17
---
--- 4
16
---
--- 5
5
---
5
---
11
---
11
---
15
---
11
---
88
Example 2-A: Direct Cost
B
2
+75 k/m
A
3
+155 k/m
2 – 3 m 1 – 2 m
D
6
+50 k/m
4 – 6 m
--- 2
Step 1 Choices: A+155, C+70, E+25, G+60
Choose: E+25, Project duration = 17
Step 2 Choices: A+155, C+70, E&F+75, G+60
Choose: G+60, Project duration= 16
Step 3 Choices: A+155, C+70, E&F+75
Choose: C+70, Project duration = 15
Step 4 Choices: A+155, B&C+145, D&C+120,
B&E&F+150, D&E&F+125
C
3
+70 k/m
1 – 3 m
F
6
+50 k/m
2 – 6 m
E
7
+25 k/m
3 – 7 m
G
5
+60 k/m
4 – 5 m
0 3 3 5
3 6
5 11
6 13
6 12
--- 6
13 18
--- 12
12
---
17
---
--- 4
16
---
--- 5
5
---
5
---
11
---
11
---
15
---
11
---
89
Example 2-A: Direct Cost
B
2
+75 k/m
A
3
+155 k/m
2 – 3 m 1 – 2 m
D
6
+50 k/m
4 – 6 m
--- 2
Step 1 Choices: A+155, C+70, E+25, G+60
Choose: E+25, Project duration = 17
Step 2 Choices: A+155, C+70, E&F+75, G+60
Choose: G+60, Project duration= 16
Step 3 Choices: A+155, C+70, E&F+75
Choose: C+70, Project duration = 15
Step 4 Choices: A+155, B&C+145, D&C+120,
B&E&F+150, D&E&F+125
C
3
+70 k/m
1 – 3 m
F
6
+50 k/m
2 – 6 m
E
7
+25 k/m
3 – 7 m
G
5
+60 k/m
4 – 5 m
0 3 3 5
3 6
5 11
6 13
6 12
--- 6
13 18
--- 12
12
---
17
---
--- 4
16
---
--- 5
5
---
5
---
11
---
11
---
15
---
11
---
90
Example 2-A: Direct Cost
B
2
+75 k/m
A
3
+155 k/m
2 – 3 m 1 – 2 m
D
6
+50 k/m
4 – 6 m
--- 2
Step 1 Choices: A+155, C+70, E+25, G+60
Choose: E+25, Project duration = 17
Step 2 Choices: A+155, C+70, E&F+75, G+60
Choose: G+60, Project duration= 16
Step 3 Choices: A+155, C+70, E&F+75
Choose: C+70, Project duration = 15
Step 4 Choices: A+155, B&C+145, D&C+120,
B&E&F+150, D&E&F+125
C
3
+70 k/m
1 – 3 m
F
6
+50 k/m
2 – 6 m
E
7
+25 k/m
3 – 7 m
G
5
+60 k/m
4 – 5 m
0 3 3 5
3 6
5 11
6 13
6 12
--- 6
13 18
--- 12
12
---
17
---
--- 4
16
---
--- 5
5
---
5
---
11
---
11
---
15
---
11
---
91
Example 2-A: Direct Cost
B
2
+75 k/m
A
3
+155 k/m
2 – 3 m 1 – 2 m
D
6
+50 k/m
4 – 6 m
--- 2
Step 1 Choices: A+155, C+70, E+25, G+60
Choose: E+25, Project duration = 17
Step 2 Choices: A+155, C+70, E&F+75, G+60
Choose: G+60, Project duration= 16
Step 3 Choices: A+155, C+70, E&F+75
Choose: C+70, Project duration = 15
Step 4 Choices: A+155, B&C+145, D&C+120,
B&E&F+150, D&E&F+125
C
3
+70 k/m
1 – 3 m
F
6
+50 k/m
2 – 6 m
E
7
+25 k/m
3 – 7 m
G
5
+60 k/m
4 – 5 m
0 3 3 5
3 6
5 11
6 13
6 12
--- 6
13 18
--- 12
12
---
17
---
--- 4
16
---
--- 5
5
---
5
---
11
---
11
---
15
---
11
---
92
Example 2-A: Direct Cost
B
2
+75 k/m
A
3
+155 k/m
2 – 3 m 1 – 2 m
D
6
+50 k/m
4 – 6 m
--- 2
Step 1 Choices: A+155, C+70, E+25, G+60
Choose: E+25, Project duration = 17
Step 2 Choices: A+155, C+70, E&F+75, G+60
Choose: G+60, Project duration= 16
Step 3 Choices: A+155, C+70, E&F+75
Choose: C+70, Project duration = 15
Step 4 Choices: A+155, B&C+145, D&C+120,
B&E&F+150, D&E&F+125
C
3
+70 k/m
1 – 3 m
F
6
+50 k/m
2 – 6 m
E
7
+25 k/m
3 – 7 m
G
5
+60 k/m
4 – 5 m
0 3 3 5
3 6
5 11
6 13
6 12
--- 6
13 18
--- 12
12
---
17
---
--- 4
16
---
--- 5
5
---
5
---
11
---
11
---
15
---
11
---
93
Example 2-A: Direct Cost
B
2
+75 k/m
A
3
+155 k/m
2 – 3 m 1 – 2 m
D
6
+50 k/m
4 – 6 m
--- 2
Step 1 Choices: A+155, C+70, E+25, G+60
Choose: E+25, Project duration = 17
Step 2 Choices: A+155, C+70, E&F+75, G+60
Choose: G+60, Project duration= 16
Step 3 Choices: A+155, C+70, E&F+75
Choose: C+70, Project duration = 15
Step 4 Choices: A+155, B&C+145, D&C+120,
B&E&F+150, D&E&F+125
Choose D&C+120C
3
+70 k/m
1 – 3 m
F
6
+50 k/m
2 – 6 m
E
7
+25 k/m
3 – 7 m
G
5
+60 k/m
4 – 5 m
0 3 3 5
3 6
5 11
6 13
6 12
--- 6
13 18
--- 12
12
---
17
---
--- 4
16
---
--- 5
5
---
5
---
11
---
11
---
15
---
11
---
94
Example 2-A: Direct Cost
B
2
+75 k/m
A
3
+155 k/m
2 – 3 m 1 – 2 m
D
6
+50 k/m
4 – 6 m
--- 2
Step 1 Choices: A+155, C+70, E+25, G+60
Choose: E+25, Project duration = 17
Step 2 Choices: A+155, C+70, E&F+75, G+60
Choose: G+60, Project duration= 16
Step 3 Choices: A+155, C+70, E&F+75
Choose: C+70, Project duration = 15
Step 4 Choices: A+155, B&C+145, D&C+120,
B&E&F+150, D&E&F+125
Choose D&C+120, Project duration = 14C
3
+70 k/m
1 – 3 m
F
6
+50 k/m
2 – 6 m
E
7
+25 k/m
3 – 7 m
G
5
+60 k/m
4 – 5 m
0 3 3 5
3 6
5 11
6 13
6 12
--- 6
13 18
--- 12
12
---
17
---
--- 4
16
---
--- 5
5
---
5
---
11
---
11
---
15
---
11
---
--- 1
--- 5
--- 10
--- 4
--- 4 --- 10
--- 4 --- 10
10
---
14
---
95
Example 2-A: Direct Cost
B
2
+75 k/m
A
3
+155 k/m
2 – 3 m 1 – 2 m
D
6
+50 k/m
4 – 6 m
--- 2
Step 1 Choices: A+155, C+70, E+25, G+60
Choose: E+25, Project duration = 17
Step 2 Choices: A+155, C+70, E&F+75, G+60
Choose: G+60, Project duration= 16
Step 3 Choices: A+155, C+70, E&F+75
Choose: C+70, Project duration = 15
Step 4 Choices: A+155, B&C+145, D&C+120,
B&E&F+150, D&E&F+125
Choose D&C+120, Project duration = 14C
3
+70 k/m
1 – 3 m
F
6
+50 k/m
2 – 6 m
E
7
+25 k/m
3 – 7 m
G
5
+60 k/m
4 – 5 m
0 3 3 5
3 4
5 10
4 10
4 10
--- 6
10 14
--- 4
--- 1
--- 5
96
Example 2-A: Direct Cost
B
2
+75 k/m
A
3
+155 k/m
2 – 3 m 1 – 2 m
D
6
+50 k/m
4 – 6 m
--- 2
Step 1 Choices: A+155, C+70, E+25, G+60
Choose: E+25, Project duration = 17
Step 2 Choices: A+155, C+70, E&F+75, G+60
Choose: G+60, Project duration= 16
Step 3 Choices: A+155, C+70, E&F+75
Choose: C+70, Project duration = 15
Step 4 Choices: A+155, B&C+145, D&C+120,
B&E&F+150, D&E&F+125
Choose D&C+120, Project duration = 14
Step 5 Choices: A+155, B&E&F+150,
D&E&F+125
Choose D&E&F+125
C
3
+70 k/m
1 – 3 m
F
6
+50 k/m
2 – 6 m
E
7
+25 k/m
3 – 7 m
G
5
+60 k/m
4 – 5 m
0 3 3 5
3 4
5 10
4 10
4 10
--- 6
10 14
--- 4
--- 1
--- 5
97
Example 2-A: Direct Cost
B
2
+75 k/m
A
3
+155 k/m
2 – 3 m 1 – 2 m
D
6
+50 k/m
4 – 6 m
--- 2
Step 1 Choices: A+155, C+70, E+25, G+60
Choose: E+25, Project duration = 17
Step 2 Choices: A+155, C+70, E&F+75, G+60
Choose: G+60, Project duration= 16
Step 3 Choices: A+155, C+70, E&F+75
Choose: C+70, Project duration = 15
Step 4 Choices: A+155, B&C+145, D&C+120,
B&E&F+150, D&E&F+125
Choose D&C+120, Project duration = 14
Step 5 Choices: A+155, B&E&F+150,
D&E&F+125
Choose D&E&F+125, Project duration = 13
C
3
+70 k/m
1 – 3 m
F
6
+50 k/m
2 – 6 m
E
7
+25 k/m
3 – 7 m
G
5
+60 k/m
4 – 5 m
0 3 3 5
3 4
5 10
4 10
4 10
--- 6
10 14
--- 4
--- 1
--- 5--- 4
--- 5
--- 5
--- 9
--- 9
--- 9
9
---
13
---
98
Example 2-A: Direct Cost
B
2
+75 k/m
A
3
+155 k/m
2 – 3 m 1 – 2 m
D
6
+50 k/m
4 – 6 m
--- 2
Step 1 Choices: A+155, C+70, E+25, G+60
Choose: E+25, Project duration = 17
Step 2 Choices: A+155, C+70, E&F+75, G+60
Choose: G+60, Project duration= 16
Step 3 Choices: A+155, C+70, E&F+75
Choose: C+70, Project duration = 15
Step 4 Choices: A+155, B&C+145, D&C+120,
B&E&F+150, D&E&F+125
Choose D&C+120, Project duration = 14
Step 5 Choices: A+155, B&E&F+150,
D&E&F+125
Choose D&E&F+125, Project duration = 14
Step 6 Choices: A+155, B&E&F+150
Choose B&E&F+150
C
3
+70 k/m
1 – 3 m
F
6
+50 k/m
2 – 6 m
E
7
+25 k/m
3 – 7 m
G
5
+60 k/m
4 – 5 m
0 3 3 5
3 4
5 10
4 10
4 10
--- 6
10 14
--- 4
--- 1
--- 5--- 4
--- 5
--- 5
--- 9
--- 9
--- 9
9
---
13
---
99
Example 2-A: Direct Cost
B
2
+75 k/m
A
3
+155 k/m
2 – 3 m 1 – 2 m
D
6
+50 k/m
4 – 6 m
--- 2
Step 1 Choices: A+155, C+70, E+25, G+60
Choose: E+25, Project duration = 17
Step 2 Choices: A+155, C+70, E&F+75, G+60
Choose: G+60, Project duration= 16
Step 3 Choices: A+155, C+70, E&F+75
Choose: C+70, Project duration = 15
Step 4 Choices: A+155, B&C+145, D&C+120,
B&E&F+150, D&E&F+125
Choose D&C+120, Project duration = 14
Step 5 Choices: A+155, B&E&F+150,
D&E&F+125
Choose D&E&F+125, Project duration = 13
Step 6 Choices: A+155, B&E&F+150,
Choose B&E&F+150, Project duration = 12
C
3
+70 k/m
1 – 3 m
F
6
+50 k/m
2 – 6 m
E
7
+25 k/m
3 – 7 m
G
5
+60 k/m
4 – 5 m
0 3 3 5
3 4
5 10
4 10
4 10
--- 6
10 14
--- 4
--- 1
--- 5--- 4
--- 5
--- 5
--- 9
--- 9
--- 9
9
---
13
------ 4 --- 8
--- 4
--- 1
--- 4
--- 4
--- 8
--- 8
8
---
12
---
100
Example 2-A: Direct Cost
B
2
+75 k/m
A
3
+155 k/m
2 – 3 m 1 – 2 m
D
6
+50 k/m
4 – 6 m
--- 2
Step 1 Choices: A+155, C+70, E+25, G+60
Choose: E+25, Project duration = 17
Step 2 Choices: A+155, C+70, E&F+75, G+60
Choose: G+60, Project duration= 16
Step 3 Choices: A+155, C+70, E&F+75
Choose: C+70, Project duration = 15
Step 4 Choices: A+155, B&C+145, D&C+120,
B&E&F+150, D&E&F+125
Choose D&C+120, Project duration = 14
Step 5 Choices: A+155, B&E&F+150,
D&E&F+125
Choose D&E&F+125, Project duration = 13
Step 6 Choices: A+155, B&E&F+150,
Choose B&E&F+150, Project duration = 12
Step 7 Choices: A+155
Choose A+155
C
3
+70 k/m
1 – 3 m
F
6
+50 k/m
2 – 6 m
E
7
+25 k/m
3 – 7 m
G
5
+60 k/m
4 – 5 m
0 3 3 5
3 4
5 10
4 10
4 10
--- 6
10 14
--- 4
--- 1
--- 5--- 4
--- 5
--- 5
--- 9
--- 9
--- 9
9
---
13
---
--- 1
--- 4 --- 4 --- 8
--- 4
--- 8
--- 4
--- 8
8
---
12
---
101
Example 2-A: Direct Cost
B
2
+75 k/m
A
3
+155 k/m
2 – 3 m 1 – 2 m
D
6
+50 k/m
4 – 6 m
--- 2
Step 1 Choices: A+155, C+70, E+25, G+60
Choose: E+25, Project duration = 17
Step 2 Choices: A+155, C+70, E&F+75, G+60
Choose: G+60, Project duration= 16
Step 3 Choices: A+155, C+70, E&F+75
Choose: C+70, Project duration = 15
Step 4 Choices: A+155, B&C+145, D&C+120,
B&E&F+150, D&E&F+125
Choose D&C+120, Project duration = 14
Step 5 Choices: A+155, B&E&F+150,
D&E&F+125
Choose D&E&F+125, Project duration = 13
Step 6 Choices: A+155, B&E&F+150,
Choose B&E&F+150, Project duration = 12
Step 7 Choices: A+155
Choose A+155, Project duration = 11
C
3
+70 k/m
1 – 3 m
F
6
+50 k/m
2 – 6 m
E
7
+25 k/m
3 – 7 m
G
5
+60 k/m
4 – 5 m
0 3 3 5
3 4
5 10
4 10
4 10
--- 6
10 14
--- 4
--- 1
--- 5--- 4
--- 5
--- 5
--- 9
--- 9
--- 9
9
---
13
---
--- 1
--- 4 --- 4 --- 8
--- 4
--- 8
--- 4
--- 8
8
---
12
---2
---
2
---
3
---
2
---
3
---
3
---
7
---
3
---
7
---
3
---
7
---
7
---
11
---
--- 2
102
Time-Cost Tradeoff by Examples
Example 2-B: Minimum Total Cost
103
Example 2-B: Minimum Total Cost (Indirectcost = 120 k/m)
B
2
+75 k/m
A
3
+155 k/m
2 – 3 m 1 – 2 m
D
6
+50 k/m
4 – 6 m
C
3
+70 k/m
1 – 3 m
F
6
+50 k/m
2 – 6 m
E
7
+25 k/m
3 – 7 m
G
5
+60 k/m
4 – 5 m
104
Example 2-B: Minimum Total Cost (Indirectcost = 120 k/m)
B
2
+75 k/m
A
3
+155 k/m
2 – 3 m 1 – 2 m
D
6
+50 k/m
4 – 6 m
C
3
+70 k/m
1 – 3 m
F
6
+50 k/m
2 – 6 m
E
7
+25 k/m
3 – 7 m
G
5
+60 k/m
4 – 5 m
245k 175k
160k
300k 340k
325k
700k
Normal Direct Cost = 245 + 175 + 160 + 300 + 325 + 700 + 340 = 2,245 k
105
Example 2-B: Minimum Total Cost (Indirectcost = 120 k/m)
B
2
+75 k/m
A
3
+155 k/m
2 – 3 m 1 – 2 m
D
6
+50 k/m
4 – 6 m
C
3
+70 k/m
1 – 3 m
F
6
+50 k/m
2 – 6 m
E
7
+25 k/m
3 – 7 m
G
5
+60 k/m
4 – 5 m
245k 175k
160k
300k 340k
325k
700k
Step 1 Choices: A+155, C+70, E+25, G+60
Choose: E+25, Project duration = 17
Step 2 Choices: A+155, C+70, E&F+75, G+60
Choose: G+60, Project duration= 16
Step 3 Choices: A+155, C+70, E&F+75
Choose: C+70, Project duration = 15
Step 4 Choices: A+155, B&C+145, D&C+120,
B&E&F+150, D&E&F+125
Choose D&C+120, Project duration = 14
Step 5 Choices: A+155, B&E&F+150,
D&E&F+125
Choose D&E&F+125, Project duration = 13
Step 6 Choices: A+155, B&E&F+150,
Choose B&E&F+150, Project duration = 12
Step 7 Choices: A+155
Choose A+155, Project duration = 11
Normal Direct Cost = 245 + 175 + 160 + 300 + 325 + 700 + 340 = 2,245 k
106
Example 2-B: Minimum Total Cost (Indirectcost = 120 k/m)
Step 1 Choices: A+155, C+70, E+25, G+60
Choose: E+25, Project duration = 17
Step 2 Choices: A+155, C+70, E&F+75, G+60
Choose: G+60, Project duration= 16
Step 3 Choices: A+155, C+70, E&F+75
Choose: C+70, Project duration = 15
Step 4 Choices: A+155, B&C+145, D&C+120,
B&E&F+150, D&E&F+125
Choose D&C+120, Project duration = 14
Step 5 Choices: A+155, B&E&F+150,
D&E&F+125
Choose D&E&F+125, Project duration = 13
Step 6 Choices: A+155, B&E&F+150,
Choose B&E&F+150, Project duration = 12
Step 7 Choices: A+155
Choose A+155, Project duration = 11107
Example 2-B: Minimum Total Cost (Indirectcost = 120 k/m)
Step 1 Choices: A+155, C+70, E+25, G+60
Choose: E+25, Project duration = 17
Step 2 Choices: A+155, C+70, E&F+75, G+60
Choose: G+60, Project duration= 16
Step 3 Choices: A+155, C+70, E&F+75
Choose: C+70, Project duration = 15
Step 4 Choices: A+155, B&C+145, D&C+120,
B&E&F+150, D&E&F+125
Choose D&C+120, Project duration = 14
Step 5 Choices: A+155, B&E&F+150,
D&E&F+125
Choose D&E&F+125, Project duration = 13
Step 6 Choices: A+155, B&E&F+150,
Choose B&E&F+150, Project duration = 12
Step 7 Choices: A+155
Choose A+155, Project duration = 11108
Example 2-B: Minimum Total Cost (Indirectcost = 120 k/m)
Step 1 Choices: A+155, C+70, E+25, G+60
Choose: E+25, Project duration = 17
Step 2 Choices: A+155, C+70, E&F+75, G+60
Choose: G+60, Project duration= 16
Step 3 Choices: A+155, C+70, E&F+75
Choose: C+70, Project duration = 15
Step 4 Choices: A+155, B&C+145, D&C+120,
B&E&F+150, D&E&F+125
Choose D&C+120, Project duration = 14
Step 5 Choices: A+155, B&E&F+150,
D&E&F+125
Choose D&E&F+125, Project duration = 13
Step 6 Choices: A+155, B&E&F+150,
Choose B&E&F+150, Project duration = 12
Step 7 Choices: A+155
Choose A+155, Project duration = 11109
Example 2-B: Minimum Total Cost (Indirectcost = 120 k/m)
Step 1 Choices: A+155, C+70, E+25, G+60
Choose: E+25, Project duration = 17
Step 2 Choices: A+155, C+70, E&F+75, G+60
Choose: G+60, Project duration= 16
Step 3 Choices: A+155, C+70, E&F+75
Choose: C+70, Project duration = 15
Step 4 Choices: A+155, B&C+145, D&C+120,
B&E&F+150, D&E&F+125
Choose D&C+120, Project duration = 14
Step 5 Choices: A+155, B&E&F+150,
D&E&F+125
Choose D&E&F+125, Project duration = 13
Step 6 Choices: A+155, B&E&F+150,
Choose B&E&F+150, Project duration = 12
Step 7 Choices: A+155
Choose A+155, Project duration = 11
Min Total Cost
110
Time-Cost Tradeoff by Examples
Example 2-C: S-Curve at Min Total Cost
111
Example 2-C: S-Curve (Indirectcost = 120 k/m)
Step 1 Choices: A+155, C+70, E+25, G+60
Choose: E+25, Project duration = 17
Step 2 Choices: A+155, C+70, E&F+75, G+60
Choose: G+60, Project duration= 16
Step 3 Choices: A+155, C+70, E&F+75
Choose: C+70, Project duration = 15
Step 4 Choices: A+155, B&C+145, D&C+120,
B&E&F+150, D&E&F+125
Choose D&C+120, Project duration = 14
Step 5 Choices: A+155, B&E&F+150,
D&E&F+125
Choose D&E&F+125, Project duration = 13
Step 6 Choices: A+155, B&E&F+150,
Choose B&E&F+150, Project duration = 12
Step 7 Choices: A+155
Choose A+155, Project duration = 11
Min Total Cost
112
B
2
+75 k/m
A
3
+155 k/m
2 – 3 m 1 – 2 m
D
6
+50 k/m
4 – 6 m
C
3
+70 k/m
1 – 3 m
F
6
+50 k/m
2 – 6 m
E
7
+25 k/m
3 – 7 m
G
5
+60 k/m
4 – 5 m
245k 175k
160k
300k 340k
325k
700k
Example 2-C: S-Curve (Indirectcost = 120 k/m)
Step 1 Choices: A+155, C+70, E+25, G+60
Choose: E+25, Project duration = 17
Step 2 Choices: A+155, C+70, E&F+75, G+60
Choose: G+60, Project duration= 16
Step 3 Choices: A+155, C+70, E&F+75
Choose: C+70, Project duration = 15
Step 4 Choices: A+155, B&C+145, D&C+120,
B&E&F+150, D&E&F+125
Choose D&C+120, Project duration = 14
Step 5 Choices: A+155, B&E&F+150,
D&E&F+125
Choose D&E&F+125, Project duration = 13
Step 6 Choices: A+155, B&E&F+150,
Choose B&E&F+150, Project duration = 12
Step 7 Choices: A+155
Choose A+155, Project duration = 11113
B
2
+75 k/m
A
3
+155 k/m
2 – 3 m 1 – 2 m
D
6
+50 k/m
4 – 6 m
C
3
+70 k/m
1 – 3 m
F
6
+50 k/m
2 – 6 m
E
7
+25 k/m
3 – 7 m
G
5
+60 k/m
4 – 5 m
245k 175k
160k
300k 340k
325k
700k
Example 2-C: S-Curve (Indirectcost = 120 k/m)
Step 1 Choices: A+155, C+70, E+25, G+60
Choose: E+25, Project duration = 17
Step 2 Choices: A+155, C+70, E&F+75, G+60
Choose: G+60, Project duration= 16
Step 3 Choices: A+155, C+70, E&F+75
Choose: C+70, Project duration = 15
Step 4 Choices: A+155, B&C+145, D&C+120,
B&E&F+150, D&E&F+125
Choose D&C+120, Project duration = 14
--- 6
--------- 350
114
B
2
+75 k/m
A
3
+155 k/m
2 – 3 m 1 – 2 m
D
6
+50 k/m
4 – 6 m
C
3
+70 k/m
1 – 3 m
F
6
+50 k/m
2 – 6 m
E
7
+25 k/m
3 – 7 m
G
5
+60 k/m
4 – 5 m
245k 175k
160k
300k 340k
325k
700k
Example 2-C: S-Curve (Indirectcost = 120 k/m)
Step 1 Choices: A+155, C+70, E+25, G+60
Choose: E+25, Project duration = 17
Step 2 Choices: A+155, C+70, E&F+75, G+60
Choose: G+60, Project duration= 16
Step 3 Choices: A+155, C+70, E&F+75
Choose: C+70, Project duration = 15
Step 4 Choices: A+155, B&C+145, D&C+120,
B&E&F+150, D&E&F+125
Choose D&C+120, Project duration = 14
--- 6
--------- 350
--- 4
--------- 400
115
B
2
+75 k/m
A
3
+155 k/m
2 – 3 m 1 – 2 m
D
6
+50 k/m
4 – 6 m
C
3
+70 k/m
1 – 3 m
F
6
+50 k/m
2 – 6 m
E
7
+25 k/m
3 – 7 m
G
5
+60 k/m
4 – 5 m
245k 175k
160k
300k 340k
325k
700k
Example 2-C: S-Curve (Indirectcost = 120 k/m)
Step 1 Choices: A+155, C+70, E+25, G+60
Choose: E+25, Project duration = 17
Step 2 Choices: A+155, C+70, E&F+75, G+60
Choose: G+60, Project duration= 16
Step 3 Choices: A+155, C+70, E&F+75
Choose: C+70, Project duration = 15
Step 4 Choices: A+155, B&C+145, D&C+120,
B&E&F+150, D&E&F+125
Choose D&C+120, Project duration = 14
--- 6
--------- 350
--- 4
--------- 400
--- 2
--------- 230
116
B
2
+75 k/m
A
3
+155 k/m
2 – 3 m 1 – 2 m
D
6
+50 k/m
4 – 6 m
C
3
+70 k/m
1 – 3 m
F
6
+50 k/m
2 – 6 m
E
7
+25 k/m
3 – 7 m
G
5
+60 k/m
4 – 5 m
245k 175k
160k
300k 340k
325k
700k
Example 2-C: S-Curve (Indirectcost = 120 k/m)
Step 1 Choices: A+155, C+70, E+25, G+60
Choose: E+25, Project duration = 17
Step 2 Choices: A+155, C+70, E&F+75, G+60
Choose: G+60, Project duration= 16
Step 3 Choices: A+155, C+70, E&F+75
Choose: C+70, Project duration = 15
Step 4 Choices: A+155, B&C+145, D&C+120,
B&E&F+150, D&E&F+125
Choose D&C+120, Project duration = 14
--- 6
--------- 350
--- 4
--------- 400
--- 2
--------- 230
--- 1
--------- 300
--- 5
--------- 350
117
B
2
+75 k/m
A
3
+155 k/m
2 – 3 m 1 – 2 m
D
6
+50 k/m
4 – 6 m
C
3
+70 k/m
1 – 3 m
F
6
+50 k/m
2 – 6 m
E
7
+25 k/m
3 – 7 m
G
5
+60 k/m
4 – 5 m
245k 175k
160k
300k 340k
325k
700k
Example 2-C: S-Curve (Indirectcost = 120 k/m)
Step 1 Choices: A+155, C+70, E+25, G+60
Choose: E+25, Project duration = 17
Step 2 Choices: A+155, C+70, E&F+75, G+60
Choose: G+60, Project duration= 16
Step 3 Choices: A+155, C+70, E&F+75
Choose: C+70, Project duration = 15
Step 4 Choices: A+155, B&C+145, D&C+120,
B&E&F+150, D&E&F+125
Choose D&C+120, Project duration = 14
--- 6
--------- 350
--- 4
--------- 400
--- 2
--------- 230
--- 1
--------- 300
--- 5
--------- 350
0 3 3 5 5 10
3 4 4 10
4 10
10 14
118
B
2
+75 k/m
A
3
+155 k/m
2 – 3 m 1 – 2 m
D
6
+50 k/m
4 – 6 m
C
3
+70 k/m
1 – 3 m
F
6
+50 k/m
2 – 6 m
E
7
+25 k/m
3 – 7 m
G
5
+60 k/m
4 – 5 m
245k 175k
160k
300k 340k
325k
700k
Example 2-C: S-Curve (Indirectcost = 120 k/m)
Step 1 Choices: A+155, C+70, E+25, G+60
Choose: E+25, Project duration = 17
Step 2 Choices: A+155, C+70, E&F+75, G+60
Choose: G+60, Project duration= 16
Step 3 Choices: A+155, C+70, E&F+75
Choose: C+70, Project duration = 15
Step 4 Choices: A+155, B&C+145, D&C+120,
B&E&F+150, D&E&F+125
Choose D&C+120, Project duration = 14
--- 6
--------- 350
--- 4
--------- 400
--- 2
--------- 230
--- 1
--------- 300
--- 5
--------- 350
0 3 3 5 5 10
3 4 4 10
4 10
10 14
119
B
2
+75 k/m
A
3
+155 k/m
2 – 3 m 1 – 2 m
D
6
+50 k/m
4 – 6 m
C
3
+70 k/m
1 – 3 m
F
6
+50 k/m
2 – 6 m
E
7
+25 k/m
3 – 7 m
G
5
+60 k/m
4 – 5 m
245k 175k
160k
300k 340k
325k
700k
Example 2-C: S-Curve (Indirectcost = 120 k/m)
Step 1 Choices: A+155, C+70, E+25, G+60
Choose: E+25, Project duration = 17
Step 2 Choices: A+155, C+70, E&F+75, G+60
Choose: G+60, Project duration= 16
Step 3 Choices: A+155, C+70, E&F+75
Choose: C+70, Project duration = 15
Step 4 Choices: A+155, B&C+145, D&C+120,
B&E&F+150, D&E&F+125
Choose D&C+120, Project duration = 14
--- 6
--------- 350
--- 4
--------- 400
--- 2
--------- 230
--- 1
--------- 300
--- 5
--------- 350
0 3 3 5 5 10
3 4 4 10
4 10
10 14
120
B
2
+75 k/m
A
3
+155 k/m
2 – 3 m 1 – 2 m
D
6
+50 k/m
4 – 6 m
C
3
+70 k/m
1 – 3 m
F
6
+50 k/m
2 – 6 m
E
7
+25 k/m
3 – 7 m
G
5
+60 k/m
4 – 5 m
245k 175k
160k
300k 340k
325k
700k
Example 2-C: S-Curve (Indirectcost = 120 k/m)
Step 1 Choices: A+155, C+70, E+25, G+60
Choose: E+25, Project duration = 17
Step 2 Choices: A+155, C+70, E&F+75, G+60
Choose: G+60, Project duration= 16
Step 3 Choices: A+155, C+70, E&F+75
Choose: C+70, Project duration = 15
Step 4 Choices: A+155, B&C+145, D&C+120,
B&E&F+150, D&E&F+125
Choose D&C+120, Project duration = 14
--- 6
--------- 350
--- 4
--------- 400
--- 2
--------- 230
--- 1
--------- 300
--- 5
--------- 350
0 3 3 5 5 10
3 4 4 10
4 10
10 14
121
Example 2-C: S-Curve
122
(Indirectcost = 120 k/m)
Time-Cost Tradeoff by Examples
Example 2-D: Excel Solver
123
Time-Cost Tradeoff by Examples
Example 2-D: Activate Excel Solver
124
Check if there is “Solver” button
If not, go to File menu
125
Select “Options”
126
127
Select “Add-ins”, and choose “Excel Add-ins”, then click “Go…”
1
2
3
128
Check “Solver Add-in” checkbox, and click “OK” button
4
5
129
Finish activating “Solver”
130
The “Solver”
131
The “Solver”
Actual Duration (AD)2. Variables
AD >= CD
AD <= ND
AD must be “Integer”.
Project Duration= …
3. Constraints
1. Objective: Minimize… Project Direct Cost
132
Time-Cost Tradeoff by Examples
Example 2-D: Let’s Start
133
Create table, add initial data, and calculate +Slope if necessary
+Slope = (Crash Cost – Normal Cost)
(Normal Duration – Crash Duration)
134
Setup Columns for Actual Duration & Actual Cost
+Slope = (Crash Cost – Normal Cost)
(Normal Duration – Crash Duration)
Actual Cost = Normal Cost +Slope x (Normal Duration – Actual Duration)
Actual Duration could be any number between “Crash” and “Normal” durations.
Variables in Solver
135
Add Formula for CPM: ESD and EFD
+Slope = (Crash Cost – Normal Cost)
(Normal Duration – Crash Duration)
Actual Cost = Normal Cost +Slope x (Normal Duration – Actual Duration)
Actual Duration could be any number between “Crash” and “Normal” durations.
Variables in Solver
136
Find the Normal and Crash Durations of the Project
Normal Duration of the Project = 18
Crash Duration of the Project = 11
Therefore, we will analyze the project
between 11 to 18 months.
137
Create a table for Total Cost = Direct + Indirect
138
Activate Solver by going to “Data” menu -> Solver
139
Set Objective, Variables, and Constraints in Excel Solver
1. Objective: Minimize Actual Direct Cost
140
Set Objective, Variables, and Constraints in Excel Solver
2. Variables
1. Objective: Minimize Actual Direct Cost
141
Set Objective, Variables, and Constraints in Excel Solver
2. Variables
1. Objective: Minimize Actual Direct Cost
3. Constraints:
Actual duration<= ND
Actual duration must be “Integer”
Actual duration >= CD
Project duration= 18
142
Set Objective, Variables, and Constraints in Excel Solver
2. Variables
1. Objective: Minimize Actual Direct Cost
3. Constraints:
Actual duration<= ND
Actual duration must be “Integer”
Actual duration >= CD
Project duration= 18
143
Set Objective, Variables, and Constraints in Excel Solver
2. Variables
1. Objective: Minimize Actual Direct Cost
3. Constraints:
Actual duration<= ND
Actual duration must be “Integer”
Actual duration >= CD
Project duration= 18
144
Set Objective, Variables, and Constraints in Excel Solver
2. Variables
4. Click “Solve” button
1. Objective: Minimize Actual Direct Cost
3. Constraints:
Actual duration<= ND
Actual duration must be “Integer”
Actual duration >= CD
Project duration= 18
145
Manually type the Cost in the table after finish solving
Click “OK” button
And type in the number.
146
Change “Constraint of Project Duration” to the next one, 17
Constraints
Actual duration<= ND
Actual duration must be “Integer”
Actual duration >= CD
Project duration= 17
1. Select the constraint
and click“Change” button
2. Click “Solve” button
147
148
Keep Solving until reaching the Crash Duration of the Project
149
Finish Solving
150
Calculate Total Cost and indicate the Minimum Total Cost
151
Calculate Total Cost and indicate the Minimum Total Cost
Minimum Total Cost
With the shortest duration
152
Use Solver to determine activities’ duration & cost at Min Total Cost
Minimum Total Cost
With the shortest duration
153
2. Click “Solve” button
1. Change
Actual Duration & Cost at Minimum Total Cost
Minimum Total Cost
With the shortest duration
154
Rate: Cost/Duration
Minimum Total Cost
With the shortest duration
155
Bar Chart with Cost/Duration
Minimum Total Cost
With the shortest duration
156
Bar Chart with Cost/Duration
157
Sum Direct, Indirect, and Total Cost
158
Calculate Cumulative Cost
159
Time-Cost Tradeoff by Examples
THANK YOU
160

More Related Content

PDF
DMC Complete UET
PDF
Lecture7_2021_v2.pdf
PPT
Critical Path Method
PPTX
construction resource optimization 1.pptx
PPT
Time cost optimisation
DOCX
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
PPTX
CPM-PERT-Examples .pptx
PDF
Time-Cost Trade Off in the construction industry
DMC Complete UET
Lecture7_2021_v2.pdf
Critical Path Method
construction resource optimization 1.pptx
Time cost optimisation
1LocationFixed CostsVariable Costs per unitA=BB=CC=DA$85,000260006.docx
CPM-PERT-Examples .pptx
Time-Cost Trade Off in the construction industry

Similar to Time-Cost Tradeoff by Examples (20)

PDF
DwC Project Management the best practice
PPTX
Drill.pptx
PPTX
Earnvalue analysis in Software engineering
PPS
Expansion of-water-treatment-plant
DOCX
Assignment 101
PDF
ملاحظات مهمة عن تعجيل المشاريع
PPTX
Lean Cell Design -Presentation project part c rohan naik & aditya kamble
PDF
Productivity improvement & waste reduction
PPT
Green Belt Project V2
PPTX
Pert analysis
PPTX
Costs_Behaviour_Curves economicas and finance slides
PDF
Chapter Five project management in operations research .pdf
PPTX
Network crashing for project management.pptx
PDF
Drilling Engineering - Drilling Economics
PPTX
Project control
PPT
Aminullah assagaf p9 mk2_manajemen keuangan 2_24 mei 2021
PPTX
Critical path method (cpm)
PPTX
THN Quotations (JKHDUIYEGHEGSDFFRWERRRRR
PPTX
PPTX
Aminullah Assagaf_P7-Ch.9_Project management-32.pptx
DwC Project Management the best practice
Drill.pptx
Earnvalue analysis in Software engineering
Expansion of-water-treatment-plant
Assignment 101
ملاحظات مهمة عن تعجيل المشاريع
Lean Cell Design -Presentation project part c rohan naik & aditya kamble
Productivity improvement & waste reduction
Green Belt Project V2
Pert analysis
Costs_Behaviour_Curves economicas and finance slides
Chapter Five project management in operations research .pdf
Network crashing for project management.pptx
Drilling Engineering - Drilling Economics
Project control
Aminullah assagaf p9 mk2_manajemen keuangan 2_24 mei 2021
Critical path method (cpm)
THN Quotations (JKHDUIYEGHEGSDFFRWERRRRR
Aminullah Assagaf_P7-Ch.9_Project management-32.pptx
Ad

More from Chachrist Srisuwanrat (12)

PDF
Repetitive Scheduling Method RSM
PDF
Project analysis and advanced data calculation and conditional formatting
PDF
Optimization in ChaStrobe Software with Genetic Algorithm
PDF
ChaStrobe Application, a simulation-based scheduling software for repetitive ...
PDF
Model and schedule resource-sharing activities in repetitive projects using c...
PDF
Example of repetitive project with probabilistic activity durations and work ...
PDF
Example of repetitive project with probabilistic activity durations
PDF
Literature review of existing repetitive project scheduling techniques 2008
PDF
Five characteristics of repetitive activities in construction projects
PDF
Sequence step algorithm repetitive project scheduling for project with probab...
PPTX
Microsoft Project Workshop
DOCX
Ms project 2010 workshop on july 2014
Repetitive Scheduling Method RSM
Project analysis and advanced data calculation and conditional formatting
Optimization in ChaStrobe Software with Genetic Algorithm
ChaStrobe Application, a simulation-based scheduling software for repetitive ...
Model and schedule resource-sharing activities in repetitive projects using c...
Example of repetitive project with probabilistic activity durations and work ...
Example of repetitive project with probabilistic activity durations
Literature review of existing repetitive project scheduling techniques 2008
Five characteristics of repetitive activities in construction projects
Sequence step algorithm repetitive project scheduling for project with probab...
Microsoft Project Workshop
Ms project 2010 workshop on july 2014
Ad

Recently uploaded (20)

PDF
1_English_Language_Set_2.pdf probationary
PPTX
Unit 4 Skeletal System.ppt.pptxopresentatiom
PDF
What if we spent less time fighting change, and more time building what’s rig...
PPTX
Digestion and Absorption of Carbohydrates, Proteina and Fats
PPTX
Tissue processing ( HISTOPATHOLOGICAL TECHNIQUE
PPTX
Final Presentation General Medicine 03-08-2024.pptx
PDF
Practical Manual AGRO-233 Principles and Practices of Natural Farming
PPTX
202450812 BayCHI UCSC-SV 20250812 v17.pptx
PDF
Classroom Observation Tools for Teachers
PDF
RTP_AR_KS1_Tutor's Guide_English [FOR REPRODUCTION].pdf
PPTX
Chinmaya Tiranga Azadi Quiz (Class 7-8 )
PDF
Indian roads congress 037 - 2012 Flexible pavement
PDF
A GUIDE TO GENETICS FOR UNDERGRADUATE MEDICAL STUDENTS
PPTX
Onco Emergencies - Spinal cord compression Superior vena cava syndrome Febr...
PPTX
Radiologic_Anatomy_of_the_Brachial_plexus [final].pptx
PDF
Black Hat USA 2025 - Micro ICS Summit - ICS/OT Threat Landscape
PPTX
Orientation - ARALprogram of Deped to the Parents.pptx
PDF
Computing-Curriculum for Schools in Ghana
PDF
GENETICS IN BIOLOGY IN SECONDARY LEVEL FORM 3
PDF
advance database management system book.pdf
1_English_Language_Set_2.pdf probationary
Unit 4 Skeletal System.ppt.pptxopresentatiom
What if we spent less time fighting change, and more time building what’s rig...
Digestion and Absorption of Carbohydrates, Proteina and Fats
Tissue processing ( HISTOPATHOLOGICAL TECHNIQUE
Final Presentation General Medicine 03-08-2024.pptx
Practical Manual AGRO-233 Principles and Practices of Natural Farming
202450812 BayCHI UCSC-SV 20250812 v17.pptx
Classroom Observation Tools for Teachers
RTP_AR_KS1_Tutor's Guide_English [FOR REPRODUCTION].pdf
Chinmaya Tiranga Azadi Quiz (Class 7-8 )
Indian roads congress 037 - 2012 Flexible pavement
A GUIDE TO GENETICS FOR UNDERGRADUATE MEDICAL STUDENTS
Onco Emergencies - Spinal cord compression Superior vena cava syndrome Febr...
Radiologic_Anatomy_of_the_Brachial_plexus [final].pptx
Black Hat USA 2025 - Micro ICS Summit - ICS/OT Threat Landscape
Orientation - ARALprogram of Deped to the Parents.pptx
Computing-Curriculum for Schools in Ghana
GENETICS IN BIOLOGY IN SECONDARY LEVEL FORM 3
advance database management system book.pdf

Time-Cost Tradeoff by Examples

  • 1. Time-Cost Tradeoff by Examples INTRODUCTION 1 Chachrist Srisuwanrat ชาคริต ศรีสุวรรณรัตน์
  • 3. What is Time-Cost Tradeoff ? • It is the Exchange between “Time” and “Money” Introduction to Time-Cost Tradeoff DirectCost Project Duration 76543 500k 600k 700k 800k 900k 1,000k 1,100k 1,200k 1,300k 1,400k 400k 1,500k 1,600k Cost (Project Duration) (Cost) Pay Extra Money to shorten the project 3
  • 4. What is Time-Cost Tradeoff ? • It is the Exchange between “Time” and “Money” What is its Objective? • Find Minimum Total Cost Introduction to Time-Cost Tradeoff DirectCost Total Cost Project Duration 76543 500k 600k 700k 800k 900k 1,000k 1,100k 1,200k 1,300k 1,400k 400k 1,500k 1,600k Cost (Project Duration) (Cost) Pay Extra Money to shorten the project 4
  • 5. What is Time-Cost Tradeoff ? • It is the Exchange between “Time” and “Money” What is its Objective? • Find Minimum Total Cost About Total Cost: • Total Cost = Direct + Indirect • Direct Cost: labor, materials, equipment, … • Indirect Cost : managers, safety, accountants, parking, … Introduction to Time-Cost Tradeoff DirectCost 450 600 750 900 1,050 Project Duration 76543 500k 600k 700k 800k 900k 1,000k 1,100k 1,200k 1,300k 1,400k 400k 1,500k 1,600k Cost (Project Duration) (Cost) Total Cost IndirectCost150k/m Pay Extra Cost to shorten the project 5
  • 6. Time-Cost Tradeoff by Examples Shorten Project by Shorten Critical Activities +Slope 6
  • 7. How much? • Different activities have different “Extra Cost”, extra money per shorten duration (day, week, or month) Shorten “Project Duration” by Shorten “Critical Activity Duration” Project Duration 76543 500k 600k 700k 800k 900k 1,000k 1,100k 1,200k 1,300k 1,400k 400k 1,500k 1,600k Cost Activity 5 – 7 months 700k – 500k = Cost Duration Normal Duration (ND) Normal Cost (NC) Crash Duration (CD) Crash Cost (NC) Extra cost/duration = +Slope 500 Direct Cost 7
  • 8. How much? • Different activities have different “Extra Cost”, extra money per shorten duration (day, week, or month) Shorten “Project Duration” by Shorten “Critical Activity Duration” Project Duration 76543 500k 600k 700k 800k 900k 1,000k 1,100k 1,200k 1,300k 1,400k 400k 1,500k 1,600k Cost = Cost Duration Normal Duration – Crash Duration Crash Cost – Normal Cost= ND - CD CC - NC= Activity 5 – 7 months 700k – 500k Normal Duration (ND) Normal Cost (NC) Crash Duration (CD) Crash Cost (NC) Extra cost/duration = +Slope 500 Direct Cost 8
  • 9. How much? • Different activities have different “Extra Cost”, extra money per shorten duration (day, week, or month) Shorten “Project Duration” by Shorten “Critical Activity Duration” Project Duration 76543 500k 600k 700k 800k 900k 1,000k 1,100k 1,200k 1,300k 1,400k 400k 1,500k 1,600k Cost Duration Cost +Slope Crash (CD) Normal(ND) Crash (CC) Normal(NC) Activity 5 7 700 500 ? ND - CD CC - NC 700 - 500 7 - 5 +100 k/m= =+Slope = Normal Duration – Crash Duration Crash Cost – Normal Cost== Cost Duration ND - CD CC - NC=Extra cost/duration = +Slope 500 Direct Cost Activity 5 – 7 months 700k – 500k Normal Duration (ND) Normal Cost (NC) Crash Duration (CD) Crash Cost (NC) 9
  • 10. How much? • Different activities have different “Extra Cost”, extra money per shorten duration (day, week, or month) Shorten “Project Duration” by Shorten “Critical Activity Duration” 600 Project Duration 76543 500k 600k 700k 800k 900k 1,000k 1,100k 1,200k 1,300k 1,400k 400k 1,500k 1,600k Cost Duration Cost +Slope Crash (CD) Normal(ND) Crash (CC) Normal(NC) Activity 5 7 700 500 +100 500 Direct Cost Normal Duration – Crash Duration Crash Cost – Normal Cost== Cost Duration Extra cost/duration = +Slope +100k/m ND - CD CC - NC 700 - 500 7 - 5 +100 k/m= =+Slope = ND - CD CC - NC= Activity 5 – 7 months 700k – 500k Normal Duration (ND) Normal Cost (NC) Crash Duration (CD) Crash Cost (NC) 10
  • 11. +100k/m How much? • Different activities have different “Extra Cost”, extra money per shorten duration (day, week, or month) Shorten “Project Duration” by Shorten “Critical Activity Duration” Project Duration 76543 500k 600k 700k 800k 900k 1,000k 1,100k 1,200k 1,300k 1,400k 400k 1,500k 1,600k Cost Duration Cost +Slope Crash (CD) Normal(ND) Crash (CC) Normal(NC) Activity 5 7 700 500 +100 600 700 +100 500 Direct Cost Normal Duration – Crash Duration Crash Cost – Normal Cost== Cost Duration DONE ! Extra cost/duration = +Slope ND - CD CC - NC 700 - 500 7 - 5 +100 k/m= =+Slope = ND - CD CC - NC= Activity 5 – 7 months 700k – 500k Normal Duration (ND) Normal Cost (NC) Crash Duration (CD) Crash Cost (NC) 11
  • 12. Time-Cost Tradeoff by Examples The Process of Shortening Project 12
  • 13. Process of Shortening Project P0: Use Normal Duration to create AON A 3 – 4 m +100k/m B 2 – 4 m +50 k/m C 3 – 5 m +75 k/m D 6 – 8 m + 150k/m 13 = shorten Critical Activities by +Slope
  • 14. Process of Shortening Project P0: Use Normal Duration to create AON A 3 – 4 m +100k/m 0 4 B 2 – 4 m +50 k/m 4 8 C 3 – 5 m +75 k/m 4 9 D 6 – 8 m + 150k/m 9 17 4 4 5 8 14 = shorten Critical Activities by +Slope
  • 15. Process of Shortening Project P0: Use Normal Duration to create AON P1: Consider spend Extra Money (+Slope) on critical activities A 3 – 4 m +100k/m 0 4 B 2 – 4 m +50 k/m 4 8 C 3 – 5 m +75 k/m 4 9 D 6 – 8 m + 150k/m 9 17 4 4 5 8 Step 1 Choices: A+100, C+75, D+150 15 = shorten Critical Activities by +Slope
  • 16. Process of Shortening Project P0: Use Normal Duration to create AON P1: Consider spend Extra Money (+Slope) on critical activities P2: Choose the cheapest critical activity (minimum slope) A 3 – 4 m +100k/m 0 4 B 2 – 4 m +50 k/m 4 8 C 3 – 5 m +75 k/m 4 9 D 6 – 8 m + 150k/m 9 17 4 4 5 8 Step 1 Choices: A+100, C+75, D+150 Choose: C+75 16 = shorten Critical Activities by +Slope
  • 17. Process of Shortening Project P0: Use Normal Duration to create AON P1: Consider spend Extra Money (+Slope) on critical activities P2: Choose the cheapest critical activity (minimum slope) P3: Update/check/confirm that the +Slope shortens the project A 3 – 4 m +100k/m 0 4 B 2 – 4 m +50 k/m 4 8 C 3 – 5 m +75 k/m 4 9 D 6 – 8 m + 150k/m 9 17 4 4 5 8 --- 4 --- 8 --- 8 --- 16 Step 1 Choices: A+100, C+75, D+150 Choose: C+75 17 = shorten Critical Activities by +Slope
  • 18. Process of Shortening Project P0: Use Normal Duration to create AON P1: Consider spend Extra Money (+Slope) on critical activities P2: Choose the cheapest critical activity (minimum slope) P3: Update/check/confirm that the +Slope shortens the project P4: Update AON, Critical Activities, and Critical Paths A 3 – 4 m +100k/m 0 4 B 2 – 4 m +50 k/m 4 8 C 3 – 5 m +75 k/m 4 9 D 6 – 8 m + 150k/m 9 17 4 4 5 8 --- 4 --- 8 --- 8 --- 16 Step 1 Choices: A+100, C+75, D+150 Choose: C+75, Project duration = 16 18 = shorten Critical Activities by +Slope
  • 19. Process of Shortening Project P0: Use Normal Duration to create AON P1: Consider spend Extra Money (+Slope) on critical activities P2: Choose the cheapest critical activity (minimum slope) P3: Update/check/confirm that the +Slope shortens the project P4: Update AON, Critical Activities, and Critical Paths A 3 – 4 m +100k/m 0 4 B 2 – 4 m +50 k/m 4 8 C 3 – 5 m +75 k/m 4 9 D 6 – 8 m + 150k/m 9 17 4 4 5 8 --- 4 --- 8 --- 8 --- 16 Step 1 Choices: A+100, C+75, D+150 Choose: C+75, Project duration = 16 Step 2 Choices: A+100, B+50, C+75, D+150 Choose: B+50 Anothercritical pathA-C-D still pushes the project. Choices: A+100, B&C+125, D150 19 = shorten Critical Activities by +Slope
  • 20. Process of Shortening Project P0: Use Normal Duration to create AON P1: Consider spend Extra Money (+Slope) on critical activities P2: Choose the cheapest critical activity (minimum slope) P3: Update/check/confirm that the +Slope shortens the project P4: Update AON, Critical Activities, and Critical Paths A 3 – 4 m +100k/m 0 4 B 2 – 4 m +50 k/m 4 8 C 3 – 5 m +75 k/m 4 9 D 6 – 8 m + 150k/m 9 17 4 4 5 8 --- 4 --- 8 --- 8 --- 16 Step 1 Choices: A+100, C+75, D+150 Choose: C+75, Project duration = 16 Step 2 Choices: A+100, B+50, C+75, D+150 Choose: B+50 Anothercritical pathA-C-D still pushes the project. Choices: A+100, B&C+125, D150 Choose: A+100 20 = shorten Critical Activities by +Slope
  • 21. Process of Shortening Project P0: Use Normal Duration to create AON P1: Consider spend Extra Money (+Slope) on critical activities P2: Choose the cheapest critical activity (minimum slope) P3: Update/check/confirm that the +Slope shortens the project P4: Update AON, Critical Activities, and Critical Paths A 3 – 4 m +100k/m 0 4 B 2 – 4 m +50 k/m 4 8 C 3 – 5 m +75 k/m 4 9 D 6 – 8 m + 150k/m 9 17 4 4 5 8 --- 4 --- 8 --- 8 --- 16 Step 1 Choices: A+100, C+75, D+150 Choose: C+75, Project duration = 16 Step 2 Choices: A+100, B+50, C+75, D+150 Choose: B+50 Anothercritical pathA-C-D still pushes the project. Choices: A+100, B&C+125, D+150 Choose: A+100, Project duration = 15--- 3 --- 3 --- 3 --- 7 --- 3 --- 7 --- 7 --- 15 21 = shorten Critical Activities by +Slope
  • 22. Process of Shortening Project P0: Use Normal Duration to create AON P1: Consider spend Extra Money (+Slope) on critical activities P2: Choose the cheapest critical activity (minimum slope) P3: Update/check/confirm that the +Slope shortens the project P4: Update AON, Critical Activities, and Critical Paths A 3 – 4 m +100k/m 0 4 B 2 – 4 m +50 k/m 4 8 C 3 – 5 m +75 k/m 4 9 D 6 – 8 m + 150k/m 9 17 4 4 5 8 --- 4 --- 8 --- 8 --- 16 Step 1 Choices: A+100, C+75, D+150 Choose: C+75, Project duration = 16 Step 2 Choices: A+100, B+50, C+75, D+150 Choose: B+50 Anothercritical pathA-C-D still pushes the project. Choices: A+100, B&C+125, D+150 Choose: A+100, Project duration = 15 Step 3 Choices: B&C+125, D+150 Choose: B&C+125 --- 3 --- 3 --- 3 --- 7 --- 3 --- 7 --- 7 --- 15 22 = shorten Critical Activities by +Slope
  • 23. Process of Shortening Project P0: Use Normal Duration to create AON P1: Consider spend Extra Money (+Slope) on critical activities P2: Choose the cheapest critical activity (minimum slope) P3: Update/check/confirm that the +Slope shortens the project P4: Update AON, Critical Activities, and Critical Paths A 3 – 4 m +100k/m 0 4 B 2 – 4 m +50 k/m 4 8 C 3 – 5 m +75 k/m 4 9 D 6 – 8 m + 150k/m 9 17 4 4 5 8 --- 4 --- 8 --- 8 --- 16 Step 1 Choices: A+100, C+75, D+150 Choose: C+75, Project duration = 16 Step 2 Choices: A+100, B+50, C+75, D+150 Choose: B+50 Anothercritical pathA-C-D still pushes the project. Choices: A+100, B&C+125, D+150 Choose: A+100, Project duration = 15 Step 3 Choices: B&C+125, D+150 Choose: B&C+125, Project duration= 14 --- 3 --- 3 --- 3 --- 7 --- 3 --- 7 --- 7 --- 15 --- 3 --- 3 --- 6 --- 6 --- 14 6 --- 23 = shorten Critical Activities by +Slope
  • 24. Process of Shortening Project P0: Use Normal Duration to create AON P1: Consider spend Extra Money (+Slope) on critical activities P2: Choose the cheapest critical activity (minimum slope) P3: Update/check/confirm that the +Slope shortens the project P4: Update AON, Critical Activities, and Critical Paths A 3 – 4 m +100k/m 0 4 B 2 – 4 m +50 k/m 4 8 C 3 – 5 m +75 k/m 4 9 D 6 – 8 m + 150k/m 9 17 4 4 5 8 --- 4 --- 8 --- 8 --- 16 Step 1 Choices: A+100, C+75, D+150 Choose: C+75, Project duration = 16 Step 2 Choices: A+100, B+50, C+75, D+150 Choose: B+50 Anothercritical pathA-C-D still pushes the project. Choices: A+100, B&C+125, D+150 Choose: A+100, Project duration = 15 Step 3 Choices: B&C+125, D+150 Choose: B&C+125, Project duration= 14 Step 4 Choice: B+50, D+150 Choose: D+150 --- 3 --- 3 --- 3 --- 7 --- 3 --- 7 --- 7 --- 15 --- 3 --- 3 --- 6 --- 6 --- 14 6 --- 24 = shorten Critical Activities by +Slope
  • 25. Process of Shortening Project P0: Use Normal Duration to create AON P1: Consider spend Extra Money (+Slope) on critical activities P2: Choose the cheapest critical activity (minimum slope) P3: Update/check/confirm that the +Slope shortens the project P4: Update AON, Critical Activities, and Critical Paths A 3 – 4 m +100k/m 0 4 B 2 – 4 m +50 k/m 4 8 C 3 – 5 m +75 k/m 4 9 D 6 – 8 m + 150k/m 9 17 4 4 5 8 --- 4 --- 8 --- 8 --- 16 Step 1 Choices: A+100, C+75, D+150 Choose: C+75, Project duration = 16 Step 2 Choices: A+100, B+50, C+75, D+150 Choose: B+50 Anothercritical pathA-C-D still pushes the project. Choices: A+100, B&C+125, D+150 Choose: A+100, Project duration = 15 Step 3 Choices: B&C+125, D+150 Choose: B&C+125, Project duration= 14 Step 4 Choice: B+50, D+150 Choose: D+150, Project duration = 13 --- 3 --- 3 --- 3 --- 7 --- 3 --- 7 --- 7 --- 15 --- 3 --- 3 --- 6 --- 6 --- 14--- 13 --- 7 6 --- 25 = shorten Critical Activities by +Slope
  • 26. Process of Shortening Project P0: Use Normal Duration to create AON P1: Consider spend Extra Money (+Slope) on critical activities P2: Choose the cheapest critical activity (minimum slope) P3: Update/check/confirm that the +Slope shortens the project P4: Update AON, Critical Activities, and Critical Paths A 3 – 4 m +100k/m 0 4 B 2 – 4 m +50 k/m 4 8 C 3 – 5 m +75 k/m 4 9 D 6 – 8 m + 150k/m 9 17 4 4 5 8 --- 4 --- 8 --- 8 --- 16 --- 3 --- 3 --- 3 --- 7 --- 3 --- 7 --- 7 --- 15 --- 3 --- 3 --- 6 --- 6 --- 14--- 13 --- 7 6 --- Step 5 Choice: B+50, D+150 Choose: D+150 Step 1 Choices: A+100, C+75, D+150 Choose: C+75, Project duration = 16 Step 2 Choices: A+100, B+50, C+75, D+150 Choose: B+50 Anothercritical pathA-C-D still pushes the project. Choices: A+100, B&C+125, D+150 Choose: A+100, Project duration = 15 Step 3 Choices: B&C+125, D+150 Choose: B&C+125, Project duration= 14 Step 4 Choice: B+50, D+150 Choose: D+150, Project duration = 13 26 = shorten Critical Activities by +Slope
  • 27. Process of Shortening Project P0: Use Normal Duration to create AON P1: Consider spend Extra Money (+Slope) on critical activities P2: Choose the cheapest critical activity (minimum slope) P3: Update/check/confirm that the +Slope shortens the project P4: Update AON, Critical Activities, and Critical Paths A 3 – 4 m +100k/m 0 4 B 2 – 4 m +50 k/m 4 8 C 3 – 5 m +75 k/m 4 9 D 6 – 8 m + 150k/m 9 17 = shorten Critical Activities by +Slope 4 4 5 8 --- 4 --- 8 --- 8 --- 16 --- 3 --- 3 --- 3 --- 7 --- 3 --- 7 --- 7 --- 15 --- 3 --- 3 --- 6 --- 6 --- 14--- 13 --- 7 6 --- Step 5 Choice: B+50, D+150 Choose: D+150, Project duration= 12 12 --- --- 6 Step 1 Choices: A+100, C+75, D+150 Choose: C+75, Project duration = 16 Step 2 Choices: A+100, B+50, C+75, D+150 Choose: B+50 Anothercritical pathA-C-D still pushes the project. Choices: A+100, B&C+125, D+150 Choose: A+100, Project duration = 15 Step 3 Choices: B&C+125, D+150 Choose: B&C+125, Project duration= 14 Step 4 Choice: B+50, D+150 Choose: D+150, Project duration = 13 27
  • 28. Time-Cost Tradeoff by Examples Minimum Total Cost 28
  • 29. Total Cost = Direct Cost + Indirect Cost A 3 – 4 m +100k/m B 2 – 4 m +50 k/m C 3 – 5 m +75 k/m D 6 – 8 m + 150k/m 400k 100k 300k 300k Indirect cost= 125 k/m 29
  • 30. Total Cost = Direct Cost + Indirect Cost Step 1 Choices: A+100, C+75, D+150 Choose: C+75, Project duration = 16 Step 2 Choices: A+100, B+50, C+75, D+150 Choose: A+100, Project duration = 15 Step 3 Choices: B&C+125, D+150 Choose: B&C+125, Project duration= 14 Step 4 Choice: B+50, D+150 Choose: D+150, Project duration= 13 Step 5 Choice: B+50, D+150 Choose: D+150, Project duration = 12 A 3 – 4 m +100k/m B 2 – 4 m +50 k/m C 3 – 5 m +75 k/m D 6 – 8 m + 150k/m 400k 100k 300k 300k Indirect cost= 125 k/m 30
  • 31. Total Cost = Direct Cost + Indirect Cost A 3 – 4 m +100k/m B 2 – 4 m +50 k/m C 3 – 5 m +75 k/m D 6 – 8 m + 150k/m 400k 100k 300k 300k Indirect cost= 125 k/m 125 x Duration Step 1 Choices: A+100, C+75, D+150 Choose: C+75, Project duration = 16 Step 2 Choices: A+100, B+50, C+75, D+150 Choose: A+100, Project duration = 15 Step 3 Choices: B&C+125, D+150 Choose: B&C+125, Project duration= 14 Step 4 Choice: B+50, D+150 Choose: D+150, Project duration= 13 Step 5 Choice: B+50, D+150 Choose: D+150, Project duration = 12 31
  • 32. Total Cost = Direct Cost + Indirect Cost A 3 – 4 m +100k/m B 2 – 4 m +50 k/m C 3 – 5 m +75 k/m D 6 – 8 m + 150k/m 400k 100k 300k 300k Indirect cost= 125 k/m 125 x Duration Step 1 Choices: A+100, C+75, D+150 Choose: C+75, Project duration = 16 Step 2 Choices: A+100, B+50, C+75, D+150 Choose: A+100, Project duration = 15 Step 3 Choices: B&C+125, D+150 Choose: B&C+125, Project duration= 14 Step 4 Choice: B+50, D+150 Choose: D+150, Project duration= 13 Step 5 Choice: B+50, D+150 Choose: D+150, Project duration = 12 32
  • 33. Total Cost = Direct Cost + Indirect Cost A 3 – 4 m +100k/m B 2 – 4 m +50 k/m C 3 – 5 m +75 k/m D 6 – 8 m + 150k/m 400k 100k 300k 300k Indirect cost= 125 k/m 125 x Duration Step 1 Choices: A+100, C+75, D+150 Choose: C+75, Project duration = 16 Step 2 Choices: A+100, B+50, C+75, D+150 Choose: A+100, Project duration = 15 Step 3 Choices: B&C+125, D+150 Choose: B&C+125, Project duration= 14 Step 4 Choice: B+50, D+150 Choose: D+150, Project duration= 13 Step 5 Choice: B+50, D+150 Choose: D+150, Project duration = 12 33
  • 34. Total Cost = Direct Cost + Indirect Cost A 3 – 4 m +100k/m B 2 – 4 m +50 k/m C 3 – 5 m +75 k/m D 6 – 8 m + 150k/m 400k 100k 300k 300k Indirect cost= 125 k/m 125 x Duration Step 1 Choices: A+100, C+75, D+150 Choose: C+75, Project duration = 16 Step 2 Choices: A+100, B+50, C+75, D+150 Choose: A+100, Project duration = 15 Step 3 Choices: B&C+125, D+150 Choose: B&C+125, Project duration= 14 Step 4 Choice: B+50, D+150 Choose: D+150, Project duration= 13 Step 5 Choice: B+50, D+150 Choose: D+150, Project duration = 12 34
  • 35. Total Cost = Direct Cost + Indirect Cost A 3 – 4 m +100k/m B 2 – 4 m +50 k/m C 3 – 5 m +75 k/m D 6 – 8 m + 150k/m 400k 100k 300k 300k Indirect cost= 125 k/m 125 x Duration Step 1 Choices: A+100, C+75, D+150 Choose: C+75, Project duration = 16 Step 2 Choices: A+100, B+50, C+75, D+150 Choose: A+100, Project duration = 15 Step 3 Choices: B&C+125, D+150 Choose: B&C+125, Project duration= 14 Step 4 Choice: B+50, D+150 Choose: D+150, Project duration= 13 Step 5 Choice: B+50, D+150 Choose: D+150, Project duration = 12 35
  • 36. Total Cost = Direct Cost + Indirect Cost A 3 – 4 m +100k/m B 2 – 4 m +50 k/m C 3 – 5 m +75 k/m D 6 – 8 m + 150k/m 400k 100k 300k 300k Indirect cost= 125 k/m Min Total Cost 125 x Duration Step 1 Choices: A+100, C+75, D+150 Choose: C+75, Project duration = 16 Step 2 Choices: A+100, B+50, C+75, D+150 Choose: A+100, Project duration = 15 Step 3 Choices: B&C+125, D+150 Choose: B&C+125, Project duration= 14 Step 4 Choice: B+50, D+150 Choose: D+150, Project duration= 13 Step 5 Choice: B+50, D+150 Choose: D+150, Project duration = 12 36
  • 37. Time-Cost Tradeoff by Examples S-Curve at Min Total Cost 37
  • 38. Step 1 Choices: A+100, C+75, D+150 Choose: C+75, Project duration = 16 Step 2 Choices: A+100, B+50, C+75, D+150 Choose: A+100, Project duration = 15 Step 3 Choices: B&C+125, D+150 Choose: B&C+125, Project duration= 14 Step 4 Choice: B+50, D+150 Choose: D+150, Project duration= 13 Step 5 Choice: B+50, D+150 Choose: D+150, Project duration = 12 S-Curve at Min Total Cost A 4 3 – 4 m +100k/m B 4 2 – 4 m +50 k/m C 5 3 – 5 m +75 k/m D 8 6 – 8 m + 150k/m 400k 100k 300k 300k Indirect cost= 125 k/m 38
  • 39. A 4 3 – 4 m +100k/m B 4 2 – 4 m +50 k/m C 5 3 – 5 m +75 k/m D 8 6 – 8 m + 150k/m 400k 100k 300k 300k Indirect cost= 125 k/m --- 4 -------- 375 Step 1 Choices: A+100, C+75, D+150 Choose: C+75, Project duration = 16 Step 2 Choices: A+100, B+50, C+75, D+150 Choose: A+100, Project duration = 15 Step 3 Choices: B&C+125, D+150 Choose: B&C+125, Project duration= 14 39 S-Curve at Min Total Cost
  • 40. A 4 3 – 4 m +100k/m B 4 2 – 4 m +50 k/m C 5 3 – 5 m +75 k/m D 8 6 – 8 m + 150k/m 400k 100k 300k 300k Indirect cost= 125 k/m --- 4 --- 3 -------- 500 -------- 375 Step 1 Choices: A+100, C+75, D+150 Choose: C+75, Project duration = 16 Step 2 Choices: A+100, B+50, C+75, D+150 Choose: A+100, Project duration = 15 Step 3 Choices: B&C+125, D+150 Choose: B&C+125, Project duration= 14 40 S-Curve at Min Total Cost
  • 41. A 4 3 – 4 m +100k/m B 4 2 – 4 m +50 k/m C 5 3 – 5 m +75 k/m D 8 6 – 8 m + 150k/m 400k 100k 300k 300k Indirect cost= 125 k/m --- 4 --- 3 --- 3 --- 3 -------- 500 -------- 375-------- 450 -------- 150 Step 1 Choices: A+100, C+75, D+150 Choose: C+75, Project duration = 16 Step 2 Choices: A+100, B+50, C+75, D+150 Choose: A+100, Project duration = 15 Step 3 Choices: B&C+125, D+150 Choose: B&C+125, Project duration= 14 41 S-Curve at Min Total Cost
  • 42. A 4 3 – 4 m +100k/m B 4 2 – 4 m +50 k/m C 5 3 – 5 m +75 k/m D 8 6 – 8 m + 150k/m 400k 100k 300k 300k Indirect cost= 125 k/m --- 4 --- 3 --- 3 --- 3 -------- 500 -------- 375-------- 450 -------- 150 Step 1 Choices: A+100, C+75, D+150 Choose: C+75, Project duration = 16 Step 2 Choices: A+100, B+50, C+75, D+150 Choose: A+100, Project duration = 15 Step 3 Choices: B&C+125, D+150 Choose: B&C+125, Project duration= 14 42 S-Curve at Min Total Cost
  • 43. A 4 3 – 4 m +100k/m B 4 2 – 4 m +50 k/m C 5 3 – 5 m +75 k/m D 8 6 – 8 m + 150k/m 400k 100k 300k 300k Indirect cost= 125 k/m --- 4 --- 3 --- 3 --- 3 -------- 500 -------- 375-------- 450 -------- 150 Step 1 Choices: A+100, C+75, D+150 Choose: C+75, Project duration = 16 Step 2 Choices: A+100, B+50, C+75, D+150 Choose: A+100, Project duration = 15 Step 3 Choices: B&C+125, D+150 Choose: B&C+125, Project duration= 14 43 S-Curve at Min Total Cost
  • 44. A 4 3 – 4 m +100k/m B 4 2 – 4 m +50 k/m C 5 3 – 5 m +75 k/m D 8 6 – 8 m + 150k/m 400k 100k 300k 300k Indirect cost= 125 k/m --- 4 --- 3 --- 3 --- 3 -------- 500 -------- 375-------- 450 -------- 150 Step 1 Choices: A+100, C+75, D+150 Choose: C+75, Project duration = 16 Step 2 Choices: A+100, B+50, C+75, D+150 Choose: A+100, Project duration = 15 Step 3 Choices: B&C+125, D+150 Choose: B&C+125, Project duration= 14 44 S-Curve at Min Total Cost
  • 45. A 4 3 – 4 m +100k/m B 4 2 – 4 m +50 k/m C 5 3 – 5 m +75 k/m D 8 6 – 8 m + 150k/m 400k 100k 300k 300k Indirect cost= 125 k/m --- 4 --- 3 --- 3 --- 3 -------- 500 -------- 375-------- 450 -------- 150 Step 1 Choices: A+100, C+75, D+150 Choose: C+75, Project duration = 16 Step 2 Choices: A+100, B+50, C+75, D+150 Choose: A+100, Project duration = 15 Step 3 Choices: B&C+125, D+150 Choose: B&C+125, Project duration= 14 45 S-Curve at Min Total Cost
  • 46. Time-Cost Tradeoff by Examples Example 1-A: Direct Cost A B C Activity Duration Cost Crash (CD) Normal(ND) Crash (CC) Normal(NC) A 3 4 470 400 B 10 12 460 300 C 6 8 600 500 Indirect cost= 65 k/m46
  • 47. Example 1-A A B C Activity Duration Cost +Slope Crash (CD) Normal(ND) Crash (CC) Normal(NC) A 3 4 470 400 B 10 12 460 300 C 6 8 600 500 47
  • 48. Activity Duration Cost +Slope Crash (CD) Normal(ND) Crash (CC) Normal(NC) A 3 4 470 400 B 10 12 460 300 C 6 8 600 500 Example 1-A: Calculate +Slope A B C +70 k/m +80 k/m + 50 k/m +70 +80 +50 3 – 4 m 10 – 12 m 6 – 8 m 48
  • 49. Example 1-A: Start with “Normal Duration” for all activities A B C +70 k/m +80 k/m + 50 k/m 3 – 4 m 10 – 12 m 6 – 8 m 4 12 8 Activity Duration Cost +Slope Crash (CD) Normal(ND) Crash (CC) Normal(NC) A 3 4 470 400 B 10 12 460 300 C 6 8 600 500 +70 +80 +50 49
  • 50. Example 1-A: Perform CPM A B C +70 k/m +80 k/m + 50 k/m 0 4 3 – 4 m 10 – 12 m 6 – 8 m 4 12 8 4 16 16 24 Activity Duration Cost +Slope Crash (CD) Normal(ND) Crash (CC) Normal(NC) A 3 4 470 400 B 10 12 460 300 C 6 8 600 500 +70 +80 +50 50
  • 51. Example 1-A: Identify critical activities and critical path A B C +70 k/m +80 k/m + 50 k/m 0 4 3 – 4 m 10 – 12 m 6 – 8 m 4 12 8 4 16 16 24 Activity Duration Cost +Slope Crash (CD) Normal(ND) Crash (CC) Normal(NC) A 3 4 470 400 B 10 12 460 300 C 6 8 600 500 +70 +80 +50 51
  • 52. Example 1-A: Shortening Project = Shortening critical activities Step 1 Choices: A+70, B+80, C+50 Choose: C+50 A B C +70 k/m +80 k/m + 50 k/m 0 4 3 – 4 m 10 – 12 m 6 – 8 m 4 12 8 4 16 16 24 Activity Duration Cost +Slope Crash (CD) Normal(ND) Crash (CC) Normal(NC) A 3 4 470 400 B 10 12 460 300 C 6 8 600 500 +70 +80 +50 52
  • 53. Example 1-A: Shortening Project = Shortening critical activities Step 1 Choices: A+70, B+80, C+50 Choose: C+50, Project duration= 23 A B C +70 k/m +80 k/m + 50 k/m --- 7 0 4 3 – 4 m 10 – 12 m 6 – 8 m 4 12 8 4 16 16 24--- 23 Activity Duration Cost +Slope Crash (CD) Normal(ND) Crash (CC) Normal(NC) A 3 4 470 400 B 10 12 460 300 C 6 8 600 500 +70 +80 +50 53
  • 54. Example 1-A: Shortening Project = Shortening critical activities Step 1 Choices: A+70, B+80, C+50 Choose: C+50, Project duration= 23 Step 2 Choices: A+70, B+80, C+50 Choose: C+50 A B C +70 k/m +80 k/m + 50 k/m --- 7 0 4 3 – 4 m 10 – 12 m 6 – 8 m 4 12 8 4 16 16 24--- 23 Activity Duration Cost +Slope Crash (CD) Normal(ND) Crash (CC) Normal(NC) A 3 4 470 400 B 10 12 460 300 C 6 8 600 500 +70 +80 +50 54
  • 55. Example 1-A: Shortening Project = Shortening critical activities Step 1 Choices: A+70, B+80, C+50 Choose: C+50, Project duration= 23 Step 2 Choices: A+70, B+80, C+50 Choose: C+50, Project duration= 22 A B C +70 k/m +80 k/m + 50 k/m --- 7 0 4 3 – 4 m 10 – 12 m 6 – 8 m 4 12 8 4 16 16 24--- 23 --- 6 --- 22 Activity Duration Cost +Slope Crash (CD) Normal(ND) Crash (CC) Normal(NC) A 3 4 470 400 B 10 12 460 300 C 6 8 600 500 +70 +80 +50 55
  • 56. Example 1-A: Shortening Project = Shortening critical activities Step 1 Choices: A+70, B+80, C+50 Choose: C+50, Project duration= 23 Step 2 Choices: A+70, B+80, C+50 Choose: C+50, Project duration= 22 Step 3 Choices: A+70, B+80 Choose: A+70 A B C +70 k/m +80 k/m + 50 k/m --- 7 0 4 3 – 4 m 10 – 12 m 6 – 8 m 4 12 8 4 16 16 24--- 23 --- 6 --- 22 Activity Duration Cost +Slope Crash (CD) Normal(ND) Crash (CC) Normal(NC) A 3 4 470 400 B 10 12 460 300 C 6 8 600 500 +70 +80 +50 56
  • 57. Example 1-A: Shortening Project = Shortening critical activities Step 1 Choices: A+70, B+80, C+50 Choose: C+50, Project duration= 23 Step 2 Choices: A+70, B+80, C+50 Choose: C+50, Project duration= 22 Step 3 Choices: A+70, B+80 Choose: A+70, Project duration= 21 A B C +70 k/m +80 k/m + 50 k/m --- 7 0 4 3 – 4 m 10 – 12 m 6 – 8 m 4 12 8 4 16 16 24--- 23 --- 6 --- 22 Activity Duration Cost +Slope Crash (CD) Normal(ND) Crash (CC) Normal(NC) A 3 4 470 400 B 10 12 460 300 C 6 8 600 500 +70 +80 +50 --- 3 --- 3 --- 3 --- 15 --- 15 --- 21 57
  • 58. Example 1-A: Shortening Project = Shortening critical activities Step 1 Choices: A+70, B+80, C+50 Choose: C+50, Project duration= 23 Step 2 Choices: A+70, B+80, C+50 Choose: C+50, Project duration= 22 Step 3 Choices: A+70, B+80 Choose: A+70, Project duration= 21 Step 4 Choices: B+80 Choose: B+80 A B C +70 k/m +80 k/m + 50 k/m --- 7 0 4 3 – 4 m 10 – 12 m 6 – 8 m 4 12 8 4 16 16 24--- 23 --- 6 --- 22 Activity Duration Cost +Slope Crash (CD) Normal(ND) Crash (CC) Normal(NC) A 3 4 470 400 B 10 12 460 300 C 6 8 600 500 +70 +80 +50 --- 3 --- 3 --- 3 --- 15 --- 15 --- 21 58
  • 59. Example 1-A: Shortening Project = Shortening critical activities Step 1 Choices: A+70, B+80, C+50 Choose: C+50, Project duration= 23 Step 2 Choices: A+70, B+80, C+50 Choose: C+50, Project duration= 22 Step 3 Choices: A+70, B+80 Choose: A+70, Project duration= 21 Step 4 Choices: B+80 Choose: B+80, Project duration = 20 A B C +70 k/m +80 k/m + 50 k/m --- 7 0 4 3 – 4 m 10 – 12 m 6 – 8 m 4 12 8 4 16 16 24--- 23 --- 6 --- 22 Activity Duration Cost +Slope Crash (CD) Normal(ND) Crash (CC) Normal(NC) A 3 4 470 400 B 10 12 460 300 C 6 8 600 500 +70 +80 +50 --- 3 --- 3 --- 3 --- 15 --- 15 --- 21 --- 11 --- 14 14 --- 20 --- 59
  • 60. Example 1-A: Shortening Project = Shortening critical activities Step 1 Choices: A+70, B+80, C+50 Choose: C+50, Project duration= 23 Step 2 Choices: A+70, B+80, C+50 Choose: C+50, Project duration= 22 Step 3 Choices: A+70, B+80 Choose: A+70, Project duration= 21 Step 4 Choices: B+80 Choose: B+80, Project duration = 20 Step 5 Choices: B+80 Choose: B+80 A B C +70 k/m +80 k/m + 50 k/m --- 7 0 4 3 – 4 m 10 – 12 m 6 – 8 m 4 12 8 4 16 16 24--- 23 --- 6 --- 22 Activity Duration Cost +Slope Crash (CD) Normal(ND) Crash (CC) Normal(NC) A 3 4 470 400 B 10 12 460 300 C 6 8 600 500 +70 +80 +50 --- 3 --- 3 --- 3 --- 15 --- 15 --- 21 --- 11 --- 14 14 --- 20 --- 60
  • 61. Example 1-A: Shortening Project = Shortening critical activities Step 1 Choices: A+70, B+80, C+50 Choose: C+50, Project duration= 23 Step 2 Choices: A+70, B+80, C+50 Choose: C+50, Project duration= 22 Step 3 Choices: A+70, B+80 Choose: A+70, Project duration= 21 Step 4 Choices: B+80 Choose: B+80, Project duration = 20 Step 5 Choices: B+80 Choose: B+80, Project duration = 19 A B C +70 k/m +80 k/m + 50 k/m --- 7 0 4 3 – 4 m 10 – 12 m 6 – 8 m 4 12 8 4 16 16 24--- 23 --- 6 --- 22 Activity Duration Cost +Slope Crash (CD) Normal(ND) Crash (CC) Normal(NC) A 3 4 470 400 B 10 12 460 300 C 6 8 600 500 +70 +80 +50 --- 3 --- 3 --- 3 --- 15 --- 15 --- 21 --- 11 --- 14 14 --- 20 --- --- 10 --- 13 --- 13 --- 19 61
  • 62. Time-Cost Tradeoff by Examples Example 1-B: Minimum Total Cost Indirect cost= 65 k/m62
  • 63. Example 1-B: Minimum Total Cost 400k 300k 500k A B C +70 k/m +80 k/m + 50 k/m 3 – 4 m 10 – 12 m 6 – 8 m Activity Duration Cost +Slope Crash (CD) Normal(ND) Crash (CC) Normal(NC) A 3 4 470 400 B 10 12 460 300 C 6 8 600 500 +70 +80 +50 (Indirectcost = 65 k/m) Normal Direct Cost = 400 + 300 + 500 = 1,200 k 63
  • 64. Example 1-B: Minimum Total Cost Step 1 Choices: A+70, B+80, C+50 Choose: C+50, Project duration= 23 Step 2 Choices: A+70, B+80, C+50 Choose: C+50, Project duration= 22 Step 3 Choices: A+70, B+80 Choose: A+70, Project duration= 21 Step 4 Choices: B+80 Choose: B+80, Project duration = 20 Step 5 Choices: B+80 Choose: B+80, Project duration = 19 400k 300k 500k A B C +70 k/m +80 k/m + 50 k/m 3 – 4 m 10 – 12 m 6 – 8 m Activity Duration Cost +Slope Crash (CD) Normal(ND) Crash (CC) Normal(NC) A 3 4 470 400 B 10 12 460 300 C 6 8 600 500 +70 +80 +50 (Indirectcost = 65 k/m) Normal Direct Cost = 400 + 300 + 500 = 1,200 k 64
  • 65. Example 1-B: Minimum Total Cost 400k 300k 500k A B C +70 k/m +80 k/m + 50 k/m 3 – 4 m 10 – 12 m 6 – 8 m Activity Duration Cost +Slope Crash (CD) Normal(ND) Crash (CC) Normal(NC) A 3 4 470 400 B 10 12 460 300 C 6 8 600 500 +70 +80 +50 (Indirectcost = 65 k/m) Step 1 Choices: A+70, B+80, C+50 Choose: C+50, Project duration= 23 Step 2 Choices: A+70, B+80, C+50 Choose: C+50, Project duration= 22 Step 3 Choices: A+70, B+80 Choose: A+70, Project duration= 21 Step 4 Choices: B+80 Choose: B+80, Project duration = 20 Step 5 Choices: B+80 Choose: B+80, Project duration = 19 Normal Direct Cost = 400 + 300 + 500 = 1,200 k 65
  • 66. Example 1-B: Minimum Total Cost 400k 300k 500k A B C +70 k/m +80 k/m + 50 k/m 3 – 4 m 10 – 12 m 6 – 8 m Activity Duration Cost +Slope Crash (CD) Normal(ND) Crash (CC) Normal(NC) A 3 4 470 400 B 10 12 460 300 C 6 8 600 500 +70 +80 +50 (Indirectcost = 65 k/m) Step 1 Choices: A+70, B+80, C+50 Choose: C+50, Project duration= 23 Step 2 Choices: A+70, B+80, C+50 Choose: C+50, Project duration= 22 Step 3 Choices: A+70, B+80 Choose: A+70, Project duration= 21 Step 4 Choices: B+80 Choose: B+80, Project duration = 20 Step 5 Choices: B+80 Choose: B+80, Project duration = 19 Normal Direct Cost = 400 + 300 + 500 = 1,200 k 66
  • 67. Step 1 Choices: A+70, B+80, C+50 Choose: C+50, Project duration= 23 Step 2 Choices: A+70, B+80, C+50 Choose: C+50, Project duration= 22 Step 3 Choices: A+70, B+80 Choose: A+70, Project duration= 21 Step 4 Choices: B+80 Choose: B+80, Project duration = 20 Step 5 Choices: B+80 Choose: B+80, Project duration = 19 Example 1-B: Minimum Total Cost 400k 300k 500k A B C +70 k/m +80 k/m + 50 k/m 3 – 4 m 10 – 12 m 6 – 8 m Activity Duration Cost +Slope Crash (CD) Normal(ND) Crash (CC) Normal(NC) A 3 4 470 400 B 10 12 460 300 C 6 8 600 500 +70 +80 +50 (Indirectcost = 65 k/m) Normal Direct Cost = 400 + 300 + 500 = 1,200 k 67
  • 68. Example 1-B: Minimum Total Cost Step 1 Choices: A+70, B+80, C+50 Choose: C+50, Project duration= 23 Step 2 Choices: A+70, B+80, C+50 Choose: C+50, Project duration= 22 400k 300k 500k A B C +70 k/m +80 k/m + 50 k/m 3 – 4 m 10 – 12 m 6 – 8 m Min Total Cost (Indirectcost = 65 k/m) 68
  • 69. Time-Cost Tradeoff by Examples Example 1-C: S-Curve at Min Total Cost 69
  • 70. Example 1-C: S-Curve Step 1 Choices: A+70, B+80, C+50 Choose: C+50, Project duration= 23 Step 2 Choices: A+70, B+80, C+50 Choose: C+50, Project duration= 22 400k 300k 500k A 4 B 12 C 8 +70 k/m +80 k/m + 50 k/m 3 – 4 m 10 – 12 m 6 – 8 m (Indirectcost = 65 k/m) 70
  • 71. Example 1-C: S-Curve 400k 300k 500k A 4 B 12 C 8 +70 k/m +80 k/m + 50 k/m 3 – 4 m 10 – 12 m 6 – 8 m -------- 550 --- 7 (Indirectcost = 65 k/m) Step 1 Choices: A+70, B+80, C+50 Choose: C+50, Project duration= 23 Step 2 Choices: A+70, B+80, C+50 Choose: C+50, Project duration= 22 71
  • 72. Example 1-C: S-Curve 400k 300k 500k A 4 B 12 C 8 +70 k/m +80 k/m + 50 k/m 3 – 4 m 10 – 12 m 6 – 8 m -------- 550-------- 600 --- 7--- 6 (Indirectcost = 65 k/m) Step 1 Choices: A+70, B+80, C+50 Choose: C+50, Project duration= 23 Step 2 Choices: A+70, B+80, C+50 Choose: C+50, Project duration= 22 72
  • 73. Example 1-C: S-Curve 400k 300k 500k A 4 B 12 C 8 +70 k/m +80 k/m + 50 k/m 3 – 4 m 10 – 12 m 6 – 8 m (Indirectcost = 65 k/m) -------- 550-------- 600 --- 7--- 6 Step 1 Choices: A+70, B+80, C+50 Choose: C+50, Project duration= 23 Step 2 Choices: A+70, B+80, C+50 Choose: C+50, Project duration= 22 73
  • 74. Example 1-C: S-Curve 400k 300k 500k A 4 B 12 C 8 +70 k/m +80 k/m + 50 k/m 3 – 4 m 10 – 12 m 6 – 8 m (Indirectcost = 65 k/m) -------- 550-------- 600 --- 7--- 6 Step 1 Choices: A+70, B+80, C+50 Choose: C+50, Project duration= 23 Step 2 Choices: A+70, B+80, C+50 Choose: C+50, Project duration= 22 74
  • 75. Example 1-C: S-Curve 400k 300k 500k A 4 B 12 C 8 +70 k/m +80 k/m + 50 k/m 3 – 4 m 10 – 12 m 6 – 8 m (Indirectcost = 65 k/m) -------- 550-------- 600 --- 7--- 6 Step 1 Choices: A+70, B+80, C+50 Choose: C+50, Project duration= 23 Step 2 Choices: A+70, B+80, C+50 Choose: C+50, Project duration= 22 75
  • 76. Example 1-C: S-Curve 400k 300k 500k A 4 B 12 C 8 +70 k/m +80 k/m + 50 k/m 3 – 4 m 10 – 12 m 6 – 8 m (Indirectcost = 65 k/m) -------- 550-------- 600 --- 7--- 6 Step 1 Choices: A+70, B+80, C+50 Choose: C+50, Project duration= 23 Step 2 Choices: A+70, B+80, C+50 Choose: C+50, Project duration= 22 76
  • 77. Time-Cost Tradeoff by Examples Example 2-A: Direct Cost 77
  • 78. B 2 +75 k/m A 3 +155 k/m 2 – 3 m 1 – 2 m D 6 +50 k/m 4 – 6 m C 3 +70 k/m 1 – 3 m F 6 +50 k/m 2 – 6 m E 7 +25 k/m 3 – 7 m G 5 +60 k/m 4 – 5 m Example 2-A 78
  • 79. Example 2-A: Perform CPM B 2 +75 k/m A 3 +155 k/m 2 – 3 m 1 – 2 m D 6 +50 k/m 4 – 6 m C 3 +70 k/m 1 – 3 m F 6 +50 k/m 2 – 6 m E 7 +25 k/m 3 – 7 m G 5 +60 k/m 4 – 5 m 0 3 3 5 3 6 5 11 6 13 6 12 13 18 79
  • 80. Example 2-A: Identify critical path and critical activities B 2 +75 k/m A 3 +155 k/m 2 – 3 m 1 – 2 m D 6 +50 k/m 4 – 6 m C 3 +70 k/m 1 – 3 m F 6 +50 k/m 2 – 6 m E 7 +25 k/m 3 – 7 m G 5 +60 k/m 4 – 5 m 0 3 3 5 3 6 5 11 6 13 6 12 13 18 80
  • 81. B 2 +75 k/m A 3 +155 k/m 2 – 3 m 1 – 2 m D 6 +50 k/m 4 – 6 m Step 1 Choices: A+155, C+70, E+25, G+60 Choose: E+25 C 3 +70 k/m 1 – 3 m F 6 +50 k/m 2 – 6 m E 7 +25 k/m 3 – 7 m G 5 +60 k/m 4 – 5 m 0 3 3 5 3 6 5 11 6 13 6 12 13 18 81 Example 2-A: Direct Cost
  • 82. Example 2-A: Direct Cost B 2 +75 k/m A 3 +155 k/m 2 – 3 m 1 – 2 m D 6 +50 k/m 4 – 6 m Step 1 Choices: A+155, C+70, E+25, G+60 Choose: E+25, Project duration = 17 C 3 +70 k/m 1 – 3 m F 6 +50 k/m 2 – 6 m E 7 +25 k/m 3 – 7 m G 5 +60 k/m 4 – 5 m 0 3 3 5 3 6 5 11 6 13 6 12 --- 6 13 18 --- 12 12 --- 17 --- 82
  • 83. Example 2-A: Direct Cost B 2 +75 k/m A 3 +155 k/m 2 – 3 m 1 – 2 m D 6 +50 k/m 4 – 6 m Step 1 Choices: A+155, C+70, E+25, G+60 Choose: E+25, Project duration = 17 C 3 +70 k/m 1 – 3 m F 6 +50 k/m 2 – 6 m E 7 +25 k/m 3 – 7 m G 5 +60 k/m 4 – 5 m 0 3 3 5 3 6 5 11 6 13 6 12 --- 6 13 18 --- 12 12 --- 17 --- 83
  • 84. Example 2-A: Direct Cost B 2 +75 k/m A 3 +155 k/m 2 – 3 m 1 – 2 m D 6 +50 k/m 4 – 6 m Step 1 Choices: A+155, C+70, E+25, G+60 Choose: E+25, Project duration = 17 Step 2 Choices: A+155, C+70, E&F+75, G+60 Choose: G+60 C 3 +70 k/m 1 – 3 m F 6 +50 k/m 2 – 6 m E 7 +25 k/m 3 – 7 m G 5 +60 k/m 4 – 5 m 0 3 3 5 3 6 5 11 6 13 6 12 --- 6 13 18 --- 12 12 --- 17 --- 84
  • 85. Example 2-A: Direct Cost B 2 +75 k/m A 3 +155 k/m 2 – 3 m 1 – 2 m D 6 +50 k/m 4 – 6 m Step 1 Choices: A+155, C+70, E+25, G+60 Choose: E+25, Project duration = 17 Step 2 Choices: A+155, C+70, E&F+75, G+60 Choose: G+60, Project duration= 16 C 3 +70 k/m 1 – 3 m F 6 +50 k/m 2 – 6 m E 7 +25 k/m 3 – 7 m G 5 +60 k/m 4 – 5 m 0 3 3 5 3 6 5 11 6 13 6 12 --- 6 13 18 --- 12 12 --- 17 --- --- 4 16 --- 85
  • 86. Example 2-A: Direct Cost B 2 +75 k/m A 3 +155 k/m 2 – 3 m 1 – 2 m D 6 +50 k/m 4 – 6 m Step 1 Choices: A+155, C+70, E+25, G+60 Choose: E+25, Project duration = 17 Step 2 Choices: A+155, C+70, E&F+75, G+60 Choose: G+60, Project duration= 16 Step 3 Choices: A+155, C+70, E&F+75 Choose: C+70 C 3 +70 k/m 1 – 3 m F 6 +50 k/m 2 – 6 m E 7 +25 k/m 3 – 7 m G 5 +60 k/m 4 – 5 m 0 3 3 5 3 6 5 11 6 13 6 12 --- 6 13 18 --- 12 12 --- 17 --- --- 4 16 --- 86
  • 87. Example 2-A: Direct Cost B 2 +75 k/m A 3 +155 k/m 2 – 3 m 1 – 2 m D 6 +50 k/m 4 – 6 m --- 2 Step 1 Choices: A+155, C+70, E+25, G+60 Choose: E+25, Project duration = 17 Step 2 Choices: A+155, C+70, E&F+75, G+60 Choose: G+60, Project duration= 16 Step 3 Choices: A+155, C+70, E&F+75 Choose: C+70, Project duration = 15 C 3 +70 k/m 1 – 3 m F 6 +50 k/m 2 – 6 m E 7 +25 k/m 3 – 7 m G 5 +60 k/m 4 – 5 m 0 3 3 5 3 6 5 11 6 13 6 12 --- 6 13 18 --- 12 12 --- 17 --- --- 4 16 --- --- 5 5 --- 11 --- 5 --- 11 --- 15 --- 11 --- 87
  • 88. Example 2-A: Direct Cost B 2 +75 k/m A 3 +155 k/m 2 – 3 m 1 – 2 m D 6 +50 k/m 4 – 6 m --- 2 Step 1 Choices: A+155, C+70, E+25, G+60 Choose: E+25, Project duration = 17 Step 2 Choices: A+155, C+70, E&F+75, G+60 Choose: G+60, Project duration= 16 Step 3 Choices: A+155, C+70, E&F+75 Choose: C+70, Project duration = 15 C 3 +70 k/m 1 – 3 m F 6 +50 k/m 2 – 6 m E 7 +25 k/m 3 – 7 m G 5 +60 k/m 4 – 5 m 0 3 3 5 3 6 5 11 6 13 6 12 --- 6 13 18 --- 12 12 --- 17 --- --- 4 16 --- --- 5 5 --- 5 --- 11 --- 11 --- 15 --- 11 --- 88
  • 89. Example 2-A: Direct Cost B 2 +75 k/m A 3 +155 k/m 2 – 3 m 1 – 2 m D 6 +50 k/m 4 – 6 m --- 2 Step 1 Choices: A+155, C+70, E+25, G+60 Choose: E+25, Project duration = 17 Step 2 Choices: A+155, C+70, E&F+75, G+60 Choose: G+60, Project duration= 16 Step 3 Choices: A+155, C+70, E&F+75 Choose: C+70, Project duration = 15 Step 4 Choices: A+155, B&C+145, D&C+120, B&E&F+150, D&E&F+125 C 3 +70 k/m 1 – 3 m F 6 +50 k/m 2 – 6 m E 7 +25 k/m 3 – 7 m G 5 +60 k/m 4 – 5 m 0 3 3 5 3 6 5 11 6 13 6 12 --- 6 13 18 --- 12 12 --- 17 --- --- 4 16 --- --- 5 5 --- 5 --- 11 --- 11 --- 15 --- 11 --- 89
  • 90. Example 2-A: Direct Cost B 2 +75 k/m A 3 +155 k/m 2 – 3 m 1 – 2 m D 6 +50 k/m 4 – 6 m --- 2 Step 1 Choices: A+155, C+70, E+25, G+60 Choose: E+25, Project duration = 17 Step 2 Choices: A+155, C+70, E&F+75, G+60 Choose: G+60, Project duration= 16 Step 3 Choices: A+155, C+70, E&F+75 Choose: C+70, Project duration = 15 Step 4 Choices: A+155, B&C+145, D&C+120, B&E&F+150, D&E&F+125 C 3 +70 k/m 1 – 3 m F 6 +50 k/m 2 – 6 m E 7 +25 k/m 3 – 7 m G 5 +60 k/m 4 – 5 m 0 3 3 5 3 6 5 11 6 13 6 12 --- 6 13 18 --- 12 12 --- 17 --- --- 4 16 --- --- 5 5 --- 5 --- 11 --- 11 --- 15 --- 11 --- 90
  • 91. Example 2-A: Direct Cost B 2 +75 k/m A 3 +155 k/m 2 – 3 m 1 – 2 m D 6 +50 k/m 4 – 6 m --- 2 Step 1 Choices: A+155, C+70, E+25, G+60 Choose: E+25, Project duration = 17 Step 2 Choices: A+155, C+70, E&F+75, G+60 Choose: G+60, Project duration= 16 Step 3 Choices: A+155, C+70, E&F+75 Choose: C+70, Project duration = 15 Step 4 Choices: A+155, B&C+145, D&C+120, B&E&F+150, D&E&F+125 C 3 +70 k/m 1 – 3 m F 6 +50 k/m 2 – 6 m E 7 +25 k/m 3 – 7 m G 5 +60 k/m 4 – 5 m 0 3 3 5 3 6 5 11 6 13 6 12 --- 6 13 18 --- 12 12 --- 17 --- --- 4 16 --- --- 5 5 --- 5 --- 11 --- 11 --- 15 --- 11 --- 91
  • 92. Example 2-A: Direct Cost B 2 +75 k/m A 3 +155 k/m 2 – 3 m 1 – 2 m D 6 +50 k/m 4 – 6 m --- 2 Step 1 Choices: A+155, C+70, E+25, G+60 Choose: E+25, Project duration = 17 Step 2 Choices: A+155, C+70, E&F+75, G+60 Choose: G+60, Project duration= 16 Step 3 Choices: A+155, C+70, E&F+75 Choose: C+70, Project duration = 15 Step 4 Choices: A+155, B&C+145, D&C+120, B&E&F+150, D&E&F+125 C 3 +70 k/m 1 – 3 m F 6 +50 k/m 2 – 6 m E 7 +25 k/m 3 – 7 m G 5 +60 k/m 4 – 5 m 0 3 3 5 3 6 5 11 6 13 6 12 --- 6 13 18 --- 12 12 --- 17 --- --- 4 16 --- --- 5 5 --- 5 --- 11 --- 11 --- 15 --- 11 --- 92
  • 93. Example 2-A: Direct Cost B 2 +75 k/m A 3 +155 k/m 2 – 3 m 1 – 2 m D 6 +50 k/m 4 – 6 m --- 2 Step 1 Choices: A+155, C+70, E+25, G+60 Choose: E+25, Project duration = 17 Step 2 Choices: A+155, C+70, E&F+75, G+60 Choose: G+60, Project duration= 16 Step 3 Choices: A+155, C+70, E&F+75 Choose: C+70, Project duration = 15 Step 4 Choices: A+155, B&C+145, D&C+120, B&E&F+150, D&E&F+125 C 3 +70 k/m 1 – 3 m F 6 +50 k/m 2 – 6 m E 7 +25 k/m 3 – 7 m G 5 +60 k/m 4 – 5 m 0 3 3 5 3 6 5 11 6 13 6 12 --- 6 13 18 --- 12 12 --- 17 --- --- 4 16 --- --- 5 5 --- 5 --- 11 --- 11 --- 15 --- 11 --- 93
  • 94. Example 2-A: Direct Cost B 2 +75 k/m A 3 +155 k/m 2 – 3 m 1 – 2 m D 6 +50 k/m 4 – 6 m --- 2 Step 1 Choices: A+155, C+70, E+25, G+60 Choose: E+25, Project duration = 17 Step 2 Choices: A+155, C+70, E&F+75, G+60 Choose: G+60, Project duration= 16 Step 3 Choices: A+155, C+70, E&F+75 Choose: C+70, Project duration = 15 Step 4 Choices: A+155, B&C+145, D&C+120, B&E&F+150, D&E&F+125 Choose D&C+120C 3 +70 k/m 1 – 3 m F 6 +50 k/m 2 – 6 m E 7 +25 k/m 3 – 7 m G 5 +60 k/m 4 – 5 m 0 3 3 5 3 6 5 11 6 13 6 12 --- 6 13 18 --- 12 12 --- 17 --- --- 4 16 --- --- 5 5 --- 5 --- 11 --- 11 --- 15 --- 11 --- 94
  • 95. Example 2-A: Direct Cost B 2 +75 k/m A 3 +155 k/m 2 – 3 m 1 – 2 m D 6 +50 k/m 4 – 6 m --- 2 Step 1 Choices: A+155, C+70, E+25, G+60 Choose: E+25, Project duration = 17 Step 2 Choices: A+155, C+70, E&F+75, G+60 Choose: G+60, Project duration= 16 Step 3 Choices: A+155, C+70, E&F+75 Choose: C+70, Project duration = 15 Step 4 Choices: A+155, B&C+145, D&C+120, B&E&F+150, D&E&F+125 Choose D&C+120, Project duration = 14C 3 +70 k/m 1 – 3 m F 6 +50 k/m 2 – 6 m E 7 +25 k/m 3 – 7 m G 5 +60 k/m 4 – 5 m 0 3 3 5 3 6 5 11 6 13 6 12 --- 6 13 18 --- 12 12 --- 17 --- --- 4 16 --- --- 5 5 --- 5 --- 11 --- 11 --- 15 --- 11 --- --- 1 --- 5 --- 10 --- 4 --- 4 --- 10 --- 4 --- 10 10 --- 14 --- 95
  • 96. Example 2-A: Direct Cost B 2 +75 k/m A 3 +155 k/m 2 – 3 m 1 – 2 m D 6 +50 k/m 4 – 6 m --- 2 Step 1 Choices: A+155, C+70, E+25, G+60 Choose: E+25, Project duration = 17 Step 2 Choices: A+155, C+70, E&F+75, G+60 Choose: G+60, Project duration= 16 Step 3 Choices: A+155, C+70, E&F+75 Choose: C+70, Project duration = 15 Step 4 Choices: A+155, B&C+145, D&C+120, B&E&F+150, D&E&F+125 Choose D&C+120, Project duration = 14C 3 +70 k/m 1 – 3 m F 6 +50 k/m 2 – 6 m E 7 +25 k/m 3 – 7 m G 5 +60 k/m 4 – 5 m 0 3 3 5 3 4 5 10 4 10 4 10 --- 6 10 14 --- 4 --- 1 --- 5 96
  • 97. Example 2-A: Direct Cost B 2 +75 k/m A 3 +155 k/m 2 – 3 m 1 – 2 m D 6 +50 k/m 4 – 6 m --- 2 Step 1 Choices: A+155, C+70, E+25, G+60 Choose: E+25, Project duration = 17 Step 2 Choices: A+155, C+70, E&F+75, G+60 Choose: G+60, Project duration= 16 Step 3 Choices: A+155, C+70, E&F+75 Choose: C+70, Project duration = 15 Step 4 Choices: A+155, B&C+145, D&C+120, B&E&F+150, D&E&F+125 Choose D&C+120, Project duration = 14 Step 5 Choices: A+155, B&E&F+150, D&E&F+125 Choose D&E&F+125 C 3 +70 k/m 1 – 3 m F 6 +50 k/m 2 – 6 m E 7 +25 k/m 3 – 7 m G 5 +60 k/m 4 – 5 m 0 3 3 5 3 4 5 10 4 10 4 10 --- 6 10 14 --- 4 --- 1 --- 5 97
  • 98. Example 2-A: Direct Cost B 2 +75 k/m A 3 +155 k/m 2 – 3 m 1 – 2 m D 6 +50 k/m 4 – 6 m --- 2 Step 1 Choices: A+155, C+70, E+25, G+60 Choose: E+25, Project duration = 17 Step 2 Choices: A+155, C+70, E&F+75, G+60 Choose: G+60, Project duration= 16 Step 3 Choices: A+155, C+70, E&F+75 Choose: C+70, Project duration = 15 Step 4 Choices: A+155, B&C+145, D&C+120, B&E&F+150, D&E&F+125 Choose D&C+120, Project duration = 14 Step 5 Choices: A+155, B&E&F+150, D&E&F+125 Choose D&E&F+125, Project duration = 13 C 3 +70 k/m 1 – 3 m F 6 +50 k/m 2 – 6 m E 7 +25 k/m 3 – 7 m G 5 +60 k/m 4 – 5 m 0 3 3 5 3 4 5 10 4 10 4 10 --- 6 10 14 --- 4 --- 1 --- 5--- 4 --- 5 --- 5 --- 9 --- 9 --- 9 9 --- 13 --- 98
  • 99. Example 2-A: Direct Cost B 2 +75 k/m A 3 +155 k/m 2 – 3 m 1 – 2 m D 6 +50 k/m 4 – 6 m --- 2 Step 1 Choices: A+155, C+70, E+25, G+60 Choose: E+25, Project duration = 17 Step 2 Choices: A+155, C+70, E&F+75, G+60 Choose: G+60, Project duration= 16 Step 3 Choices: A+155, C+70, E&F+75 Choose: C+70, Project duration = 15 Step 4 Choices: A+155, B&C+145, D&C+120, B&E&F+150, D&E&F+125 Choose D&C+120, Project duration = 14 Step 5 Choices: A+155, B&E&F+150, D&E&F+125 Choose D&E&F+125, Project duration = 14 Step 6 Choices: A+155, B&E&F+150 Choose B&E&F+150 C 3 +70 k/m 1 – 3 m F 6 +50 k/m 2 – 6 m E 7 +25 k/m 3 – 7 m G 5 +60 k/m 4 – 5 m 0 3 3 5 3 4 5 10 4 10 4 10 --- 6 10 14 --- 4 --- 1 --- 5--- 4 --- 5 --- 5 --- 9 --- 9 --- 9 9 --- 13 --- 99
  • 100. Example 2-A: Direct Cost B 2 +75 k/m A 3 +155 k/m 2 – 3 m 1 – 2 m D 6 +50 k/m 4 – 6 m --- 2 Step 1 Choices: A+155, C+70, E+25, G+60 Choose: E+25, Project duration = 17 Step 2 Choices: A+155, C+70, E&F+75, G+60 Choose: G+60, Project duration= 16 Step 3 Choices: A+155, C+70, E&F+75 Choose: C+70, Project duration = 15 Step 4 Choices: A+155, B&C+145, D&C+120, B&E&F+150, D&E&F+125 Choose D&C+120, Project duration = 14 Step 5 Choices: A+155, B&E&F+150, D&E&F+125 Choose D&E&F+125, Project duration = 13 Step 6 Choices: A+155, B&E&F+150, Choose B&E&F+150, Project duration = 12 C 3 +70 k/m 1 – 3 m F 6 +50 k/m 2 – 6 m E 7 +25 k/m 3 – 7 m G 5 +60 k/m 4 – 5 m 0 3 3 5 3 4 5 10 4 10 4 10 --- 6 10 14 --- 4 --- 1 --- 5--- 4 --- 5 --- 5 --- 9 --- 9 --- 9 9 --- 13 ------ 4 --- 8 --- 4 --- 1 --- 4 --- 4 --- 8 --- 8 8 --- 12 --- 100
  • 101. Example 2-A: Direct Cost B 2 +75 k/m A 3 +155 k/m 2 – 3 m 1 – 2 m D 6 +50 k/m 4 – 6 m --- 2 Step 1 Choices: A+155, C+70, E+25, G+60 Choose: E+25, Project duration = 17 Step 2 Choices: A+155, C+70, E&F+75, G+60 Choose: G+60, Project duration= 16 Step 3 Choices: A+155, C+70, E&F+75 Choose: C+70, Project duration = 15 Step 4 Choices: A+155, B&C+145, D&C+120, B&E&F+150, D&E&F+125 Choose D&C+120, Project duration = 14 Step 5 Choices: A+155, B&E&F+150, D&E&F+125 Choose D&E&F+125, Project duration = 13 Step 6 Choices: A+155, B&E&F+150, Choose B&E&F+150, Project duration = 12 Step 7 Choices: A+155 Choose A+155 C 3 +70 k/m 1 – 3 m F 6 +50 k/m 2 – 6 m E 7 +25 k/m 3 – 7 m G 5 +60 k/m 4 – 5 m 0 3 3 5 3 4 5 10 4 10 4 10 --- 6 10 14 --- 4 --- 1 --- 5--- 4 --- 5 --- 5 --- 9 --- 9 --- 9 9 --- 13 --- --- 1 --- 4 --- 4 --- 8 --- 4 --- 8 --- 4 --- 8 8 --- 12 --- 101
  • 102. Example 2-A: Direct Cost B 2 +75 k/m A 3 +155 k/m 2 – 3 m 1 – 2 m D 6 +50 k/m 4 – 6 m --- 2 Step 1 Choices: A+155, C+70, E+25, G+60 Choose: E+25, Project duration = 17 Step 2 Choices: A+155, C+70, E&F+75, G+60 Choose: G+60, Project duration= 16 Step 3 Choices: A+155, C+70, E&F+75 Choose: C+70, Project duration = 15 Step 4 Choices: A+155, B&C+145, D&C+120, B&E&F+150, D&E&F+125 Choose D&C+120, Project duration = 14 Step 5 Choices: A+155, B&E&F+150, D&E&F+125 Choose D&E&F+125, Project duration = 13 Step 6 Choices: A+155, B&E&F+150, Choose B&E&F+150, Project duration = 12 Step 7 Choices: A+155 Choose A+155, Project duration = 11 C 3 +70 k/m 1 – 3 m F 6 +50 k/m 2 – 6 m E 7 +25 k/m 3 – 7 m G 5 +60 k/m 4 – 5 m 0 3 3 5 3 4 5 10 4 10 4 10 --- 6 10 14 --- 4 --- 1 --- 5--- 4 --- 5 --- 5 --- 9 --- 9 --- 9 9 --- 13 --- --- 1 --- 4 --- 4 --- 8 --- 4 --- 8 --- 4 --- 8 8 --- 12 ---2 --- 2 --- 3 --- 2 --- 3 --- 3 --- 7 --- 3 --- 7 --- 3 --- 7 --- 7 --- 11 --- --- 2 102
  • 103. Time-Cost Tradeoff by Examples Example 2-B: Minimum Total Cost 103
  • 104. Example 2-B: Minimum Total Cost (Indirectcost = 120 k/m) B 2 +75 k/m A 3 +155 k/m 2 – 3 m 1 – 2 m D 6 +50 k/m 4 – 6 m C 3 +70 k/m 1 – 3 m F 6 +50 k/m 2 – 6 m E 7 +25 k/m 3 – 7 m G 5 +60 k/m 4 – 5 m 104
  • 105. Example 2-B: Minimum Total Cost (Indirectcost = 120 k/m) B 2 +75 k/m A 3 +155 k/m 2 – 3 m 1 – 2 m D 6 +50 k/m 4 – 6 m C 3 +70 k/m 1 – 3 m F 6 +50 k/m 2 – 6 m E 7 +25 k/m 3 – 7 m G 5 +60 k/m 4 – 5 m 245k 175k 160k 300k 340k 325k 700k Normal Direct Cost = 245 + 175 + 160 + 300 + 325 + 700 + 340 = 2,245 k 105
  • 106. Example 2-B: Minimum Total Cost (Indirectcost = 120 k/m) B 2 +75 k/m A 3 +155 k/m 2 – 3 m 1 – 2 m D 6 +50 k/m 4 – 6 m C 3 +70 k/m 1 – 3 m F 6 +50 k/m 2 – 6 m E 7 +25 k/m 3 – 7 m G 5 +60 k/m 4 – 5 m 245k 175k 160k 300k 340k 325k 700k Step 1 Choices: A+155, C+70, E+25, G+60 Choose: E+25, Project duration = 17 Step 2 Choices: A+155, C+70, E&F+75, G+60 Choose: G+60, Project duration= 16 Step 3 Choices: A+155, C+70, E&F+75 Choose: C+70, Project duration = 15 Step 4 Choices: A+155, B&C+145, D&C+120, B&E&F+150, D&E&F+125 Choose D&C+120, Project duration = 14 Step 5 Choices: A+155, B&E&F+150, D&E&F+125 Choose D&E&F+125, Project duration = 13 Step 6 Choices: A+155, B&E&F+150, Choose B&E&F+150, Project duration = 12 Step 7 Choices: A+155 Choose A+155, Project duration = 11 Normal Direct Cost = 245 + 175 + 160 + 300 + 325 + 700 + 340 = 2,245 k 106
  • 107. Example 2-B: Minimum Total Cost (Indirectcost = 120 k/m) Step 1 Choices: A+155, C+70, E+25, G+60 Choose: E+25, Project duration = 17 Step 2 Choices: A+155, C+70, E&F+75, G+60 Choose: G+60, Project duration= 16 Step 3 Choices: A+155, C+70, E&F+75 Choose: C+70, Project duration = 15 Step 4 Choices: A+155, B&C+145, D&C+120, B&E&F+150, D&E&F+125 Choose D&C+120, Project duration = 14 Step 5 Choices: A+155, B&E&F+150, D&E&F+125 Choose D&E&F+125, Project duration = 13 Step 6 Choices: A+155, B&E&F+150, Choose B&E&F+150, Project duration = 12 Step 7 Choices: A+155 Choose A+155, Project duration = 11107
  • 108. Example 2-B: Minimum Total Cost (Indirectcost = 120 k/m) Step 1 Choices: A+155, C+70, E+25, G+60 Choose: E+25, Project duration = 17 Step 2 Choices: A+155, C+70, E&F+75, G+60 Choose: G+60, Project duration= 16 Step 3 Choices: A+155, C+70, E&F+75 Choose: C+70, Project duration = 15 Step 4 Choices: A+155, B&C+145, D&C+120, B&E&F+150, D&E&F+125 Choose D&C+120, Project duration = 14 Step 5 Choices: A+155, B&E&F+150, D&E&F+125 Choose D&E&F+125, Project duration = 13 Step 6 Choices: A+155, B&E&F+150, Choose B&E&F+150, Project duration = 12 Step 7 Choices: A+155 Choose A+155, Project duration = 11108
  • 109. Example 2-B: Minimum Total Cost (Indirectcost = 120 k/m) Step 1 Choices: A+155, C+70, E+25, G+60 Choose: E+25, Project duration = 17 Step 2 Choices: A+155, C+70, E&F+75, G+60 Choose: G+60, Project duration= 16 Step 3 Choices: A+155, C+70, E&F+75 Choose: C+70, Project duration = 15 Step 4 Choices: A+155, B&C+145, D&C+120, B&E&F+150, D&E&F+125 Choose D&C+120, Project duration = 14 Step 5 Choices: A+155, B&E&F+150, D&E&F+125 Choose D&E&F+125, Project duration = 13 Step 6 Choices: A+155, B&E&F+150, Choose B&E&F+150, Project duration = 12 Step 7 Choices: A+155 Choose A+155, Project duration = 11109
  • 110. Example 2-B: Minimum Total Cost (Indirectcost = 120 k/m) Step 1 Choices: A+155, C+70, E+25, G+60 Choose: E+25, Project duration = 17 Step 2 Choices: A+155, C+70, E&F+75, G+60 Choose: G+60, Project duration= 16 Step 3 Choices: A+155, C+70, E&F+75 Choose: C+70, Project duration = 15 Step 4 Choices: A+155, B&C+145, D&C+120, B&E&F+150, D&E&F+125 Choose D&C+120, Project duration = 14 Step 5 Choices: A+155, B&E&F+150, D&E&F+125 Choose D&E&F+125, Project duration = 13 Step 6 Choices: A+155, B&E&F+150, Choose B&E&F+150, Project duration = 12 Step 7 Choices: A+155 Choose A+155, Project duration = 11 Min Total Cost 110
  • 111. Time-Cost Tradeoff by Examples Example 2-C: S-Curve at Min Total Cost 111
  • 112. Example 2-C: S-Curve (Indirectcost = 120 k/m) Step 1 Choices: A+155, C+70, E+25, G+60 Choose: E+25, Project duration = 17 Step 2 Choices: A+155, C+70, E&F+75, G+60 Choose: G+60, Project duration= 16 Step 3 Choices: A+155, C+70, E&F+75 Choose: C+70, Project duration = 15 Step 4 Choices: A+155, B&C+145, D&C+120, B&E&F+150, D&E&F+125 Choose D&C+120, Project duration = 14 Step 5 Choices: A+155, B&E&F+150, D&E&F+125 Choose D&E&F+125, Project duration = 13 Step 6 Choices: A+155, B&E&F+150, Choose B&E&F+150, Project duration = 12 Step 7 Choices: A+155 Choose A+155, Project duration = 11 Min Total Cost 112
  • 113. B 2 +75 k/m A 3 +155 k/m 2 – 3 m 1 – 2 m D 6 +50 k/m 4 – 6 m C 3 +70 k/m 1 – 3 m F 6 +50 k/m 2 – 6 m E 7 +25 k/m 3 – 7 m G 5 +60 k/m 4 – 5 m 245k 175k 160k 300k 340k 325k 700k Example 2-C: S-Curve (Indirectcost = 120 k/m) Step 1 Choices: A+155, C+70, E+25, G+60 Choose: E+25, Project duration = 17 Step 2 Choices: A+155, C+70, E&F+75, G+60 Choose: G+60, Project duration= 16 Step 3 Choices: A+155, C+70, E&F+75 Choose: C+70, Project duration = 15 Step 4 Choices: A+155, B&C+145, D&C+120, B&E&F+150, D&E&F+125 Choose D&C+120, Project duration = 14 Step 5 Choices: A+155, B&E&F+150, D&E&F+125 Choose D&E&F+125, Project duration = 13 Step 6 Choices: A+155, B&E&F+150, Choose B&E&F+150, Project duration = 12 Step 7 Choices: A+155 Choose A+155, Project duration = 11113
  • 114. B 2 +75 k/m A 3 +155 k/m 2 – 3 m 1 – 2 m D 6 +50 k/m 4 – 6 m C 3 +70 k/m 1 – 3 m F 6 +50 k/m 2 – 6 m E 7 +25 k/m 3 – 7 m G 5 +60 k/m 4 – 5 m 245k 175k 160k 300k 340k 325k 700k Example 2-C: S-Curve (Indirectcost = 120 k/m) Step 1 Choices: A+155, C+70, E+25, G+60 Choose: E+25, Project duration = 17 Step 2 Choices: A+155, C+70, E&F+75, G+60 Choose: G+60, Project duration= 16 Step 3 Choices: A+155, C+70, E&F+75 Choose: C+70, Project duration = 15 Step 4 Choices: A+155, B&C+145, D&C+120, B&E&F+150, D&E&F+125 Choose D&C+120, Project duration = 14 --- 6 --------- 350 114
  • 115. B 2 +75 k/m A 3 +155 k/m 2 – 3 m 1 – 2 m D 6 +50 k/m 4 – 6 m C 3 +70 k/m 1 – 3 m F 6 +50 k/m 2 – 6 m E 7 +25 k/m 3 – 7 m G 5 +60 k/m 4 – 5 m 245k 175k 160k 300k 340k 325k 700k Example 2-C: S-Curve (Indirectcost = 120 k/m) Step 1 Choices: A+155, C+70, E+25, G+60 Choose: E+25, Project duration = 17 Step 2 Choices: A+155, C+70, E&F+75, G+60 Choose: G+60, Project duration= 16 Step 3 Choices: A+155, C+70, E&F+75 Choose: C+70, Project duration = 15 Step 4 Choices: A+155, B&C+145, D&C+120, B&E&F+150, D&E&F+125 Choose D&C+120, Project duration = 14 --- 6 --------- 350 --- 4 --------- 400 115
  • 116. B 2 +75 k/m A 3 +155 k/m 2 – 3 m 1 – 2 m D 6 +50 k/m 4 – 6 m C 3 +70 k/m 1 – 3 m F 6 +50 k/m 2 – 6 m E 7 +25 k/m 3 – 7 m G 5 +60 k/m 4 – 5 m 245k 175k 160k 300k 340k 325k 700k Example 2-C: S-Curve (Indirectcost = 120 k/m) Step 1 Choices: A+155, C+70, E+25, G+60 Choose: E+25, Project duration = 17 Step 2 Choices: A+155, C+70, E&F+75, G+60 Choose: G+60, Project duration= 16 Step 3 Choices: A+155, C+70, E&F+75 Choose: C+70, Project duration = 15 Step 4 Choices: A+155, B&C+145, D&C+120, B&E&F+150, D&E&F+125 Choose D&C+120, Project duration = 14 --- 6 --------- 350 --- 4 --------- 400 --- 2 --------- 230 116
  • 117. B 2 +75 k/m A 3 +155 k/m 2 – 3 m 1 – 2 m D 6 +50 k/m 4 – 6 m C 3 +70 k/m 1 – 3 m F 6 +50 k/m 2 – 6 m E 7 +25 k/m 3 – 7 m G 5 +60 k/m 4 – 5 m 245k 175k 160k 300k 340k 325k 700k Example 2-C: S-Curve (Indirectcost = 120 k/m) Step 1 Choices: A+155, C+70, E+25, G+60 Choose: E+25, Project duration = 17 Step 2 Choices: A+155, C+70, E&F+75, G+60 Choose: G+60, Project duration= 16 Step 3 Choices: A+155, C+70, E&F+75 Choose: C+70, Project duration = 15 Step 4 Choices: A+155, B&C+145, D&C+120, B&E&F+150, D&E&F+125 Choose D&C+120, Project duration = 14 --- 6 --------- 350 --- 4 --------- 400 --- 2 --------- 230 --- 1 --------- 300 --- 5 --------- 350 117
  • 118. B 2 +75 k/m A 3 +155 k/m 2 – 3 m 1 – 2 m D 6 +50 k/m 4 – 6 m C 3 +70 k/m 1 – 3 m F 6 +50 k/m 2 – 6 m E 7 +25 k/m 3 – 7 m G 5 +60 k/m 4 – 5 m 245k 175k 160k 300k 340k 325k 700k Example 2-C: S-Curve (Indirectcost = 120 k/m) Step 1 Choices: A+155, C+70, E+25, G+60 Choose: E+25, Project duration = 17 Step 2 Choices: A+155, C+70, E&F+75, G+60 Choose: G+60, Project duration= 16 Step 3 Choices: A+155, C+70, E&F+75 Choose: C+70, Project duration = 15 Step 4 Choices: A+155, B&C+145, D&C+120, B&E&F+150, D&E&F+125 Choose D&C+120, Project duration = 14 --- 6 --------- 350 --- 4 --------- 400 --- 2 --------- 230 --- 1 --------- 300 --- 5 --------- 350 0 3 3 5 5 10 3 4 4 10 4 10 10 14 118
  • 119. B 2 +75 k/m A 3 +155 k/m 2 – 3 m 1 – 2 m D 6 +50 k/m 4 – 6 m C 3 +70 k/m 1 – 3 m F 6 +50 k/m 2 – 6 m E 7 +25 k/m 3 – 7 m G 5 +60 k/m 4 – 5 m 245k 175k 160k 300k 340k 325k 700k Example 2-C: S-Curve (Indirectcost = 120 k/m) Step 1 Choices: A+155, C+70, E+25, G+60 Choose: E+25, Project duration = 17 Step 2 Choices: A+155, C+70, E&F+75, G+60 Choose: G+60, Project duration= 16 Step 3 Choices: A+155, C+70, E&F+75 Choose: C+70, Project duration = 15 Step 4 Choices: A+155, B&C+145, D&C+120, B&E&F+150, D&E&F+125 Choose D&C+120, Project duration = 14 --- 6 --------- 350 --- 4 --------- 400 --- 2 --------- 230 --- 1 --------- 300 --- 5 --------- 350 0 3 3 5 5 10 3 4 4 10 4 10 10 14 119
  • 120. B 2 +75 k/m A 3 +155 k/m 2 – 3 m 1 – 2 m D 6 +50 k/m 4 – 6 m C 3 +70 k/m 1 – 3 m F 6 +50 k/m 2 – 6 m E 7 +25 k/m 3 – 7 m G 5 +60 k/m 4 – 5 m 245k 175k 160k 300k 340k 325k 700k Example 2-C: S-Curve (Indirectcost = 120 k/m) Step 1 Choices: A+155, C+70, E+25, G+60 Choose: E+25, Project duration = 17 Step 2 Choices: A+155, C+70, E&F+75, G+60 Choose: G+60, Project duration= 16 Step 3 Choices: A+155, C+70, E&F+75 Choose: C+70, Project duration = 15 Step 4 Choices: A+155, B&C+145, D&C+120, B&E&F+150, D&E&F+125 Choose D&C+120, Project duration = 14 --- 6 --------- 350 --- 4 --------- 400 --- 2 --------- 230 --- 1 --------- 300 --- 5 --------- 350 0 3 3 5 5 10 3 4 4 10 4 10 10 14 120
  • 121. B 2 +75 k/m A 3 +155 k/m 2 – 3 m 1 – 2 m D 6 +50 k/m 4 – 6 m C 3 +70 k/m 1 – 3 m F 6 +50 k/m 2 – 6 m E 7 +25 k/m 3 – 7 m G 5 +60 k/m 4 – 5 m 245k 175k 160k 300k 340k 325k 700k Example 2-C: S-Curve (Indirectcost = 120 k/m) Step 1 Choices: A+155, C+70, E+25, G+60 Choose: E+25, Project duration = 17 Step 2 Choices: A+155, C+70, E&F+75, G+60 Choose: G+60, Project duration= 16 Step 3 Choices: A+155, C+70, E&F+75 Choose: C+70, Project duration = 15 Step 4 Choices: A+155, B&C+145, D&C+120, B&E&F+150, D&E&F+125 Choose D&C+120, Project duration = 14 --- 6 --------- 350 --- 4 --------- 400 --- 2 --------- 230 --- 1 --------- 300 --- 5 --------- 350 0 3 3 5 5 10 3 4 4 10 4 10 10 14 121
  • 123. Time-Cost Tradeoff by Examples Example 2-D: Excel Solver 123
  • 124. Time-Cost Tradeoff by Examples Example 2-D: Activate Excel Solver 124
  • 125. Check if there is “Solver” button If not, go to File menu 125
  • 127. 127
  • 128. Select “Add-ins”, and choose “Excel Add-ins”, then click “Go…” 1 2 3 128
  • 129. Check “Solver Add-in” checkbox, and click “OK” button 4 5 129
  • 132. The “Solver” Actual Duration (AD)2. Variables AD >= CD AD <= ND AD must be “Integer”. Project Duration= … 3. Constraints 1. Objective: Minimize… Project Direct Cost 132
  • 133. Time-Cost Tradeoff by Examples Example 2-D: Let’s Start 133
  • 134. Create table, add initial data, and calculate +Slope if necessary +Slope = (Crash Cost – Normal Cost) (Normal Duration – Crash Duration) 134
  • 135. Setup Columns for Actual Duration & Actual Cost +Slope = (Crash Cost – Normal Cost) (Normal Duration – Crash Duration) Actual Cost = Normal Cost +Slope x (Normal Duration – Actual Duration) Actual Duration could be any number between “Crash” and “Normal” durations. Variables in Solver 135
  • 136. Add Formula for CPM: ESD and EFD +Slope = (Crash Cost – Normal Cost) (Normal Duration – Crash Duration) Actual Cost = Normal Cost +Slope x (Normal Duration – Actual Duration) Actual Duration could be any number between “Crash” and “Normal” durations. Variables in Solver 136
  • 137. Find the Normal and Crash Durations of the Project Normal Duration of the Project = 18 Crash Duration of the Project = 11 Therefore, we will analyze the project between 11 to 18 months. 137
  • 138. Create a table for Total Cost = Direct + Indirect 138
  • 139. Activate Solver by going to “Data” menu -> Solver 139
  • 140. Set Objective, Variables, and Constraints in Excel Solver 1. Objective: Minimize Actual Direct Cost 140
  • 141. Set Objective, Variables, and Constraints in Excel Solver 2. Variables 1. Objective: Minimize Actual Direct Cost 141
  • 142. Set Objective, Variables, and Constraints in Excel Solver 2. Variables 1. Objective: Minimize Actual Direct Cost 3. Constraints: Actual duration<= ND Actual duration must be “Integer” Actual duration >= CD Project duration= 18 142
  • 143. Set Objective, Variables, and Constraints in Excel Solver 2. Variables 1. Objective: Minimize Actual Direct Cost 3. Constraints: Actual duration<= ND Actual duration must be “Integer” Actual duration >= CD Project duration= 18 143
  • 144. Set Objective, Variables, and Constraints in Excel Solver 2. Variables 1. Objective: Minimize Actual Direct Cost 3. Constraints: Actual duration<= ND Actual duration must be “Integer” Actual duration >= CD Project duration= 18 144
  • 145. Set Objective, Variables, and Constraints in Excel Solver 2. Variables 4. Click “Solve” button 1. Objective: Minimize Actual Direct Cost 3. Constraints: Actual duration<= ND Actual duration must be “Integer” Actual duration >= CD Project duration= 18 145
  • 146. Manually type the Cost in the table after finish solving Click “OK” button And type in the number. 146
  • 147. Change “Constraint of Project Duration” to the next one, 17 Constraints Actual duration<= ND Actual duration must be “Integer” Actual duration >= CD Project duration= 17 1. Select the constraint and click“Change” button 2. Click “Solve” button 147
  • 148. 148
  • 149. Keep Solving until reaching the Crash Duration of the Project 149
  • 151. Calculate Total Cost and indicate the Minimum Total Cost 151
  • 152. Calculate Total Cost and indicate the Minimum Total Cost Minimum Total Cost With the shortest duration 152
  • 153. Use Solver to determine activities’ duration & cost at Min Total Cost Minimum Total Cost With the shortest duration 153 2. Click “Solve” button 1. Change
  • 154. Actual Duration & Cost at Minimum Total Cost Minimum Total Cost With the shortest duration 154
  • 155. Rate: Cost/Duration Minimum Total Cost With the shortest duration 155
  • 156. Bar Chart with Cost/Duration Minimum Total Cost With the shortest duration 156
  • 157. Bar Chart with Cost/Duration 157
  • 158. Sum Direct, Indirect, and Total Cost 158
  • 160. Time-Cost Tradeoff by Examples THANK YOU 160