RESOURCE-SHARING ACTIVITIES
IN REPETITIVE PROJECTS
Model and schedule resource-sharing activities
for the Sequence Step Algorithm
Presented by
Chachrist Srisuwanrat
2008
(V) Resource-Sharing Activities 2
4. RESOURCE-SHARING ACTIVITIES
 Activities sharing one or more
resources, called “resource-sharing
activities”
 “Shared Resources”
 How to schedule shared resources?
 What could be the problems?
(V) Resource-Sharing Activities 3
Examples of Repetitive Projects with
Resource-Sharing Activities
(V) Resource-Sharing Activities 4
Considerations When Scheduling
Resource-Sharing Activities
 Need to collect CIT and determine CLT
• In which sequence step?
 Need to delay resources’ arrival dates to eliminate
idle time
• Can the idle time in shared resources be eliminated?
 Need to allocate shared resource to activities
• Which resource-sharing activity gets the shared
resource first?
 Imposing CLT might change:
• CIT for the shared resource itself and of other resources
• Working sequences for the shared resource?
Supplementary Presentation V
(V) Resource-Sharing Activities 5
Scheduling Resource-Sharing Activities
 When using SQS-AL to schedule repetitive projects with
resource-sharing activities, schedulers must pay
attention to:
• Increasing idle time from SQS to SQS
• Changes in work sequence for shared resources
• Slow production rates of dependents between the
resource-sharing activities
• Precedence relationships between resource-sharing
activities (e.g., direct or indirect)
• Proximity of start dates for resource-sharing activities
• Effect of assigning CLT on their dependents
(V) Resource-Sharing Activities 6
(a) Determine CLTXY in SQS2
(b) Determine CLTXY in SQS3
In Which SQS? (SQS2 or SQS3)
Activities X and Y share the
same Resource ResXY.
(V) Resource-Sharing Activities 7
Can the idle time in shared be
eliminated?
(a) Determine CLTXY in SQS2 (b) Determine CLTXY in SQS4
(V) Resource-Sharing Activities 8
(a) Using two dedicated resources (b) Introducing a work break
(c) Speeding Activity B (d) Lowering Activities X and Y
Solutions for shared resources when their idle time cannot be eliminated
(V) Resource-Sharing Activities 9
Does the working sequences
change after assigning CLT?

More Related Content

PDF
Demo of integrated synergetic preservation workflow (WP8 ForgetIT 1st year r...
PDF
Тайван улсын үндэсний газрын мэдээллийн системийн стандарт
PDF
Example of repetitive project with probabilistic activity durations and work ...
PDF
Five characteristics of repetitive activities in construction projects
PDF
Literature review of existing repetitive project scheduling techniques 2008
PDF
Literature Review in Project Scheduling Techniques
PDF
Scheduling resources and costs is a crucial aspect of project management that...
PPTX
Lecture-8-Scheduling-Resources-and-Cost.pptx
Demo of integrated synergetic preservation workflow (WP8 ForgetIT 1st year r...
Тайван улсын үндэсний газрын мэдээллийн системийн стандарт
Example of repetitive project with probabilistic activity durations and work ...
Five characteristics of repetitive activities in construction projects
Literature review of existing repetitive project scheduling techniques 2008
Literature Review in Project Scheduling Techniques
Scheduling resources and costs is a crucial aspect of project management that...
Lecture-8-Scheduling-Resources-and-Cost.pptx

Similar to Model and schedule resource-sharing activities in repetitive projects using concept of the Sequence Step Algorithm (20)

PPTX
Introduction to Software Project Management: Key Concepts, Objectives, Challe...
PPT
Chap008.ppt
PPTX
MoonDB: Restoration & Synthesis of Planetary Geochemical Data
PPTX
Allocating resources
PPT
Chapter-8-Post-Mid.ppt
PPT
project_management and its adoption_10.ppt
PPTX
Ch09 (1).pptx
PDF
789669510-SPM-Unit-2-3-Activity-Planning.pdf
PPTX
PM-Chapter8-1.pptx
PDF
B012440511
PPTX
fpbm- pg subject in Construction Managament
PPT
3- Project Time Management.ppt
PPTX
Larson2024_Ch08_PowerPoint_Accessible.pptx
PDF
Resource Allocation using Virtual Clusters
PPTX
Online3-SlideDeck.pptx
PPTX
AHM 2014: Revisting Governance Model, Preparing for Next Steps
PPTX
Container Rebalancing: Towards Proactive Linux Containers Placement in a Data...
PPTX
TIME MANAGEMENT chapter(6), PMBOK5
PPTX
The Fermilab HEPCloud Facility
PDF
Enterprise Resource Management Using MS Project Server 2007
Introduction to Software Project Management: Key Concepts, Objectives, Challe...
Chap008.ppt
MoonDB: Restoration & Synthesis of Planetary Geochemical Data
Allocating resources
Chapter-8-Post-Mid.ppt
project_management and its adoption_10.ppt
Ch09 (1).pptx
789669510-SPM-Unit-2-3-Activity-Planning.pdf
PM-Chapter8-1.pptx
B012440511
fpbm- pg subject in Construction Managament
3- Project Time Management.ppt
Larson2024_Ch08_PowerPoint_Accessible.pptx
Resource Allocation using Virtual Clusters
Online3-SlideDeck.pptx
AHM 2014: Revisting Governance Model, Preparing for Next Steps
Container Rebalancing: Towards Proactive Linux Containers Placement in a Data...
TIME MANAGEMENT chapter(6), PMBOK5
The Fermilab HEPCloud Facility
Enterprise Resource Management Using MS Project Server 2007
Ad

More from Chachrist Srisuwanrat (9)

PDF
Repetitive Scheduling Method RSM
PDF
Time-Cost Tradeoff by Examples
PDF
Project analysis and advanced data calculation and conditional formatting
PDF
Optimization in ChaStrobe Software with Genetic Algorithm
PDF
ChaStrobe Application, a simulation-based scheduling software for repetitive ...
PDF
Example of repetitive project with probabilistic activity durations
PDF
Sequence step algorithm repetitive project scheduling for project with probab...
PPTX
Microsoft Project Workshop
DOCX
Ms project 2010 workshop on july 2014
Repetitive Scheduling Method RSM
Time-Cost Tradeoff by Examples
Project analysis and advanced data calculation and conditional formatting
Optimization in ChaStrobe Software with Genetic Algorithm
ChaStrobe Application, a simulation-based scheduling software for repetitive ...
Example of repetitive project with probabilistic activity durations
Sequence step algorithm repetitive project scheduling for project with probab...
Microsoft Project Workshop
Ms project 2010 workshop on july 2014
Ad

Recently uploaded (20)

PDF
RTP_AR_KS1_Tutor's Guide_English [FOR REPRODUCTION].pdf
PDF
Hazard Identification & Risk Assessment .pdf
PDF
LDMMIA Reiki Yoga Finals Review Spring Summer
PPTX
Introduction to Building Materials
PPTX
Unit 4 Skeletal System.ppt.pptxopresentatiom
PPTX
Cell Types and Its function , kingdom of life
PDF
Complications of Minimal Access Surgery at WLH
PPTX
A powerpoint presentation on the Revised K-10 Science Shaping Paper
PPTX
Final Presentation General Medicine 03-08-2024.pptx
PDF
Supply Chain Operations Speaking Notes -ICLT Program
PDF
Empowerment Technology for Senior High School Guide
PPTX
UNIT III MENTAL HEALTH NURSING ASSESSMENT
PDF
Black Hat USA 2025 - Micro ICS Summit - ICS/OT Threat Landscape
PPTX
History, Philosophy and sociology of education (1).pptx
PDF
medical_surgical_nursing_10th_edition_ignatavicius_TEST_BANK_pdf.pdf
PDF
Weekly quiz Compilation Jan -July 25.pdf
PDF
GENETICS IN BIOLOGY IN SECONDARY LEVEL FORM 3
PPTX
Tissue processing ( HISTOPATHOLOGICAL TECHNIQUE
PDF
Chinmaya Tiranga quiz Grand Finale.pdf
PDF
RMMM.pdf make it easy to upload and study
RTP_AR_KS1_Tutor's Guide_English [FOR REPRODUCTION].pdf
Hazard Identification & Risk Assessment .pdf
LDMMIA Reiki Yoga Finals Review Spring Summer
Introduction to Building Materials
Unit 4 Skeletal System.ppt.pptxopresentatiom
Cell Types and Its function , kingdom of life
Complications of Minimal Access Surgery at WLH
A powerpoint presentation on the Revised K-10 Science Shaping Paper
Final Presentation General Medicine 03-08-2024.pptx
Supply Chain Operations Speaking Notes -ICLT Program
Empowerment Technology for Senior High School Guide
UNIT III MENTAL HEALTH NURSING ASSESSMENT
Black Hat USA 2025 - Micro ICS Summit - ICS/OT Threat Landscape
History, Philosophy and sociology of education (1).pptx
medical_surgical_nursing_10th_edition_ignatavicius_TEST_BANK_pdf.pdf
Weekly quiz Compilation Jan -July 25.pdf
GENETICS IN BIOLOGY IN SECONDARY LEVEL FORM 3
Tissue processing ( HISTOPATHOLOGICAL TECHNIQUE
Chinmaya Tiranga quiz Grand Finale.pdf
RMMM.pdf make it easy to upload and study

Model and schedule resource-sharing activities in repetitive projects using concept of the Sequence Step Algorithm

  • 1. (V) Resource-Sharing Activities 1 RESOURCE-SHARING ACTIVITIES IN REPETITIVE PROJECTS Model and schedule resource-sharing activities for the Sequence Step Algorithm Presented by Chachrist Srisuwanrat 2008
  • 2. (V) Resource-Sharing Activities 2 4. RESOURCE-SHARING ACTIVITIES  Activities sharing one or more resources, called “resource-sharing activities”  “Shared Resources”  How to schedule shared resources?  What could be the problems?
  • 3. (V) Resource-Sharing Activities 3 Examples of Repetitive Projects with Resource-Sharing Activities
  • 4. (V) Resource-Sharing Activities 4 Considerations When Scheduling Resource-Sharing Activities  Need to collect CIT and determine CLT • In which sequence step?  Need to delay resources’ arrival dates to eliminate idle time • Can the idle time in shared resources be eliminated?  Need to allocate shared resource to activities • Which resource-sharing activity gets the shared resource first?  Imposing CLT might change: • CIT for the shared resource itself and of other resources • Working sequences for the shared resource? Supplementary Presentation V
  • 5. (V) Resource-Sharing Activities 5 Scheduling Resource-Sharing Activities  When using SQS-AL to schedule repetitive projects with resource-sharing activities, schedulers must pay attention to: • Increasing idle time from SQS to SQS • Changes in work sequence for shared resources • Slow production rates of dependents between the resource-sharing activities • Precedence relationships between resource-sharing activities (e.g., direct or indirect) • Proximity of start dates for resource-sharing activities • Effect of assigning CLT on their dependents
  • 6. (V) Resource-Sharing Activities 6 (a) Determine CLTXY in SQS2 (b) Determine CLTXY in SQS3 In Which SQS? (SQS2 or SQS3) Activities X and Y share the same Resource ResXY.
  • 7. (V) Resource-Sharing Activities 7 Can the idle time in shared be eliminated? (a) Determine CLTXY in SQS2 (b) Determine CLTXY in SQS4
  • 8. (V) Resource-Sharing Activities 8 (a) Using two dedicated resources (b) Introducing a work break (c) Speeding Activity B (d) Lowering Activities X and Y Solutions for shared resources when their idle time cannot be eliminated
  • 9. (V) Resource-Sharing Activities 9 Does the working sequences change after assigning CLT?