SlideShare a Scribd company logo
PROJECT SIMULATION AND
ADVANCED DATA CALCULATION
IN EXCEL
Dr. Chachrist Srisuwanrat
สาขาวิชาการบริหารงานก่อสร้าง คณะวิศวกรรมศาสตร์และสถาปัตยกรรมศาสตร์
มหาวิทยาลัยเทคโนโลยีราชมงคลตะวันออก วิทยาเขตอุเทนถวาย
Topics
• Project Risk Analysis using Simulation
• Determine project duration under uncertainty
• Plot density and cumulative distribution of
project duration
• Advanced Data Calculation and Formatting
• Construct “Two-way Table”
• Apply “Conditional Formatting”
2
Project Risk Analysis using Simulation
3
Probabilistic Activity Duration
4
CPM Calculation Table
5
Use constant duration to verify formula
6
Forward Calculation (ESD, EFD)
• ESDj = MAX( EFDi )
• ESDj = ESDj + DURj
7
Backward Calculation (LSD, LFD)
• LFDj = MIN(LSDk)
• LSDj = LFDj - DURj
8
Float Calculation (TF)
• TF = LFD – EFD
• Is Critical = if(TF = 0, 1, 0)
9
Apply probabilistic duration
• Copy code in “Duration Description” to Duration column
• Note: your numbers will be different because of
randomization. Press F9 to view change.
10
So what is the project duration???
Best case? Most likely? Worst case?
11
Use “Home->Fill->Series” to create
project-duration collection table
12
Use “What-If Analysis->Data Table” to
collect data (project duration)
13
Use “countif” function to count project
durations that are less than or equal to
14
Plot Graph
15
Construct Is-Critical Table for Activities
to collect probability of being critical
Collection 2,000 data points
Using
Fill->Series
What-If Analysis->Data Table
16
Use “Data->What-If Analysis->Data Table”
to collect 2,000 Is-Critical data points
17
CountIf to determine %Critical
18
Project Duration Analysis
19
Do you?
• Believe A-B-E-G almost being critical half of the time?
• Know that A-D-G could be critical?
• Think all 3 paths could be critical at the same time?
• Worst duration could be TWICE of best duration?
20
BREAK
21
Advanced Data Calculation and Formatting
22
Advanced Data Calculation and Formatting
• Main calculation table
• Two-way Table
• Text function
• Conditional Formatting
23
Simple Example:
Land Cost Valuation and %Profit
• Land Size 3 rais with Cost 200,000 Baht/sq.w.
• FAR = 3
• NFA/GFA = 65%
• Construction Cost 17,000 Baht/sq.m.
• Mgmt & Mkt Cost 10% of (Land and Construction Cost)
• Sale Price 75,000 Baht/sq.m.
• What is the %Profit?
24
Calculation Table
25
Two-way Table Example:
Land Cost Valuation and %Profit
• Land Size 3 rais with Cost 180,000 to 220,000 Baht/sq.w.
• FAR = 3
• NFA/GFA = 65%
• Construction Cost 17,000 Baht/sq.m.
• Mgmt & Mkt Cost 10% of (Land and Construction Cost)
• Sale Price 60,000 to 90,000 Baht/sq.m.
• What is the %Profit for each combination
of Land Cost and Sale Price?
26
Construct Two-way Table
• Land Cost 180,000 to 220,000 Baht/sq.w.
• Sale Price 60,000 to 90,000 Baht/sq.m.
27
Data->What-if Analysis->Data Table
28
After click OK and Formatting cells
29
Add Desired %Profit and
Minimum Required %Profit
for Conditional Formatting Only
30
Home->Conditional Formatting->New
Rule (selecting J5)
31
Select J5->Format Painter
• Select J5
• Click Format Painter
• Crop cells in the table for formatting
32
Conditional Formatting
for Minimum Required %Profit
33
Select J5->Format Painter
34
Now you can also change and study
• NFA/GFA from 65% to 60%
• Construction Cost from 17,000 to 18,000 Baht/sq.m.
• Mgmt & Mkt Cost from 10% to 15%
35
Comparison
36
BREAK
Two-way Table
Conditional Formatting
37
Simulated Table Example:
Expected, Max, Min %Profit
• Land Cost 190,000 to 210,000 Baht/sq.w.
• NFA/GFA = 60-70%
• Construction Cost 17,000-21,000 Baht/sq.m.
• Mgmt & Mkt Cost 10-15% of (Land and Construction Cost)
• Sale Price 60,000 to 90,000 Baht/sq.m.
• What is the %Profit:
• Expected
• Max
• Min
38
39
Data->What-If Analysis->Data Table
40
Data Table runs and collects 10,000 data
of %Profit
41
Let’s get Land Cost, NFA/GFA,
Construction Cost, Mgmt&Mkt Cost, and
Sale Price
42
Data->What-If Analysis->Data Table
43
ORIGINAL
Land Cost 190,000 to 210,000 Baht/sq.w.
NFA/GFA = 60-70%
Construction Cost 17,000 to 21,000 Baht/sq.m.
Mgmt & Mkt Cost 10 to 15% of (Land and Construction Cost)
Sale Price 60,000 to 90,000 Baht/sq.m.
DESIRED
Land Cost 190,000 to 200,000 Baht/sq.w.
NFA/GFA = 60-70%
Construction Cost 17,000 to 18,000 Baht/sq.m.
Mgmt & Mkt Cost 10-15% of (Land and Construction Cost)
Sale Price 70,000 to 85,000 Baht/sq.m.
44
Example: Very Difficult Problem
• A group of consultant agrees to manage and sell a land.
• This land has 18 rais.
• They will be spited to 4 to 6 plots.
• These 4-6 plots will be sold at
• Plot 1: 190,000 Baht/rais for 2 to 4 rais or not at all
• Plot 2: 200,000 Baht/rais for 2 to 3 rais or not at all
• Plot 3: 200,000 Baht/rais for 2 to 3
• Plot 4: 210,000 Baht/rais for 2 to 3
• Plot 5: 210,000 Baht/rais for 2 to 3
• Plot 6: 200,000 or 210,000 Baht/rais depending on remaining land
• In the end, all 18 rais must be sold.
(continue next page)
45
Continue
• Consulting Fee 2% of all sale
• Performance Fee 15% of land sold above 195,000 Baht/rais
• If using sale agents, consultant must pay them 1% of the
land price sold by agents
• Probabilities:
• Plot 1 has 50% chance to be sold at this price or not at all
• Plot 2 has 50% chance to be sold at this price or not at all
• If sold, size of land (2, 3, or 4 rais depending), which is sold, has equal
chance (uniform distribution)
• There is 50% chance using sale agents in each plot
46
Questions
• What is the expected, max, min of:
• Land price per sq.w.?
• Net owner revenue after all fees in Baht?
• Net consulting + performance fees Baht?
• Absolute commission calculated from consulting +
performance fees in percent?
• Sale agent commission in Baht?
47
Calculation Table with Random Formula
48
Simulated Table with 30,000 Replications
49
Summary
50
Density and Cumulative Function of
Consultant Revenue
51
Consultant Revenue upon
Number of rais (0-18 rais) sold by Sale Agents
52
WHAT IF???
The consultant have already sold
3 rais at 200,000 Baht/sq.w. via sale agents
Can he increase number of rais to be sold at
190,000 Baht/rai?
If Yes, how many?
53
THANK YOU
Dr. Chachrist Srisuwanrat
สาขาวิชาการบริหารงานก่อสร้าง คณะวิศวกรรมศาสตร์และสถาปัตยกรรมศาสตร์
มหาวิทยาลัยเทคโนโลยีราชมงคลตะวันออก วิทยาเขตอุเทนถวาย

More Related Content

PPTX
PPTX
Analysis of rates
PPTX
rate analysis
PPT
Analysis of rates
PPTX
Introduction to estimation
PPTX
Tugasan Visual Umpukan Perjalanan (A169338)
PDF
Financial statement of Manufacturing Company
PPTX
Godrej summit 3rd Psahe !! Godrej Summit
Analysis of rates
rate analysis
Analysis of rates
Introduction to estimation
Tugasan Visual Umpukan Perjalanan (A169338)
Financial statement of Manufacturing Company
Godrej summit 3rd Psahe !! Godrej Summit

What's hot (18)

PDF
Ce1402 estimationandquantitysurveying (1)
PPT
Chapter 05
PPTX
Estimation
PPT
Adaptive Implementation of Spatial Policies: A Game
DOC
MANAGEMENT ACCOUNTING
PDF
E Brochure ATS Destinaire Sector 1 Noida Extension - Greenery Around You
PPTX
Rate analysis
PPTX
Earthworks of Parking Area Development Project
PPTX
Presentation1
PPTX
Time series statastics
PPTX
TUGASAN VISUALISASI PENJANAAN PERJALANAN (modul 6)
PPTX
Costsheet final
DOC
Managerial economic
PDF
Copy of Financial report
PDF
1 schmanuf
PPTX
Section 1.2
PPTX
Job order costing
PPTX
Presentation aggregate planning
Ce1402 estimationandquantitysurveying (1)
Chapter 05
Estimation
Adaptive Implementation of Spatial Policies: A Game
MANAGEMENT ACCOUNTING
E Brochure ATS Destinaire Sector 1 Noida Extension - Greenery Around You
Rate analysis
Earthworks of Parking Area Development Project
Presentation1
Time series statastics
TUGASAN VISUALISASI PENJANAAN PERJALANAN (modul 6)
Costsheet final
Managerial economic
Copy of Financial report
1 schmanuf
Section 1.2
Job order costing
Presentation aggregate planning
Ad

Viewers also liked (14)

PPTX
Paola Gargiulo "Open Access and Open Data in practice: l'esperienza e le iniz...
PPTX
PPM Challenge #2: Project Communications and Reporting – 2012 PPM Challenge a...
PPTX
Reporting Horizon 2020 project outputs with OpenAIRE (Project Publications Re...
PDF
Project Performance Reporting
PDF
Effectively managing project performance reporting
PDF
Reporting Basics of Project Management
PPT
Project Status Report
PPTX
Sensitivity analysis
PPTX
Project Performance Dashboard
PPTX
Executive Status Report Template
PPT
Project performance tracking analysis and reporting
PPTX
One page effective project status report
PPT
Risk Management Process in OH&S
PPT
Supply Chain Management in the Motor Vehicle Industry, the Example of Mini.
Paola Gargiulo "Open Access and Open Data in practice: l'esperienza e le iniz...
PPM Challenge #2: Project Communications and Reporting – 2012 PPM Challenge a...
Reporting Horizon 2020 project outputs with OpenAIRE (Project Publications Re...
Project Performance Reporting
Effectively managing project performance reporting
Reporting Basics of Project Management
Project Status Report
Sensitivity analysis
Project Performance Dashboard
Executive Status Report Template
Project performance tracking analysis and reporting
One page effective project status report
Risk Management Process in OH&S
Supply Chain Management in the Motor Vehicle Industry, the Example of Mini.
Ad

Similar to Project analysis and advanced data calculation and conditional formatting (20)

PPTX
CFC Planning presentation
PDF
DOC-20250224aaaaaaaaaaawwwwwkkkllllllllj
PPTX
cost_production micro economics chapter theory of production
PDF
FINAL REVIEW PPT.pdf
PDF
CB312+-+Part1.pdf
PDF
PF2108 Project Cost Management Lecture 3 Cost Planning.pdf
PPTX
BIM Based Project Controls
PDF
Planning & Scheduling - Training
PDF
U1 p2 breakeven analysis
PPTX
Costs_Behaviour_Curves economicas and finance slides
PPT
Chapter 2 Construction Contract Pricing.ppt
PPTX
ECV All Chapters
PPTX
Cost revenue analysis 1
PPTX
building group 5
PPT
Engine90 crawford-decision-making (1)
PDF
Monte Carlo Simulation for project estimates v1.0
PPTX
Estimating and costing I Chapter 2.pptx
PDF
6 data envelopment_analysis
 
PDF
Machining time and costs
PPTX
Quantity surveyor
CFC Planning presentation
DOC-20250224aaaaaaaaaaawwwwwkkkllllllllj
cost_production micro economics chapter theory of production
FINAL REVIEW PPT.pdf
CB312+-+Part1.pdf
PF2108 Project Cost Management Lecture 3 Cost Planning.pdf
BIM Based Project Controls
Planning & Scheduling - Training
U1 p2 breakeven analysis
Costs_Behaviour_Curves economicas and finance slides
Chapter 2 Construction Contract Pricing.ppt
ECV All Chapters
Cost revenue analysis 1
building group 5
Engine90 crawford-decision-making (1)
Monte Carlo Simulation for project estimates v1.0
Estimating and costing I Chapter 2.pptx
6 data envelopment_analysis
 
Machining time and costs
Quantity surveyor

More from Chachrist Srisuwanrat (12)

PDF
Repetitive Scheduling Method RSM
PDF
Time-Cost Tradeoff by Examples
PDF
Optimization in ChaStrobe Software with Genetic Algorithm
PDF
ChaStrobe Application, a simulation-based scheduling software for repetitive ...
PDF
Model and schedule resource-sharing activities in repetitive projects using c...
PDF
Example of repetitive project with probabilistic activity durations and work ...
PDF
Example of repetitive project with probabilistic activity durations
PDF
Literature review of existing repetitive project scheduling techniques 2008
PDF
Five characteristics of repetitive activities in construction projects
PDF
Sequence step algorithm repetitive project scheduling for project with probab...
PPTX
Microsoft Project Workshop
DOCX
Ms project 2010 workshop on july 2014
Repetitive Scheduling Method RSM
Time-Cost Tradeoff by Examples
Optimization in ChaStrobe Software with Genetic Algorithm
ChaStrobe Application, a simulation-based scheduling software for repetitive ...
Model and schedule resource-sharing activities in repetitive projects using c...
Example of repetitive project with probabilistic activity durations and work ...
Example of repetitive project with probabilistic activity durations
Literature review of existing repetitive project scheduling techniques 2008
Five characteristics of repetitive activities in construction projects
Sequence step algorithm repetitive project scheduling for project with probab...
Microsoft Project Workshop
Ms project 2010 workshop on july 2014

Recently uploaded (20)

PDF
GENETICS IN BIOLOGY IN SECONDARY LEVEL FORM 3
PDF
Computing-Curriculum for Schools in Ghana
PPTX
Orientation - ARALprogram of Deped to the Parents.pptx
PDF
advance database management system book.pdf
PDF
ChatGPT for Dummies - Pam Baker Ccesa007.pdf
PDF
احياء السادس العلمي - الفصل الثالث (التكاثر) منهج متميزين/كلية بغداد/موهوبين
PDF
Hazard Identification & Risk Assessment .pdf
PPTX
Lesson notes of climatology university.
PPTX
Final Presentation General Medicine 03-08-2024.pptx
PDF
Weekly quiz Compilation Jan -July 25.pdf
PDF
LNK 2025 (2).pdf MWEHEHEHEHEHEHEHEHEHEHE
PDF
Supply Chain Operations Speaking Notes -ICLT Program
PDF
OBE - B.A.(HON'S) IN INTERIOR ARCHITECTURE -Ar.MOHIUDDIN.pdf
PDF
1_English_Language_Set_2.pdf probationary
PPTX
Final Presentation General Medicine 03-08-2024.pptx
PPTX
Cell Types and Its function , kingdom of life
PDF
A systematic review of self-coping strategies used by university students to ...
PDF
A GUIDE TO GENETICS FOR UNDERGRADUATE MEDICAL STUDENTS
PPTX
CHAPTER IV. MAN AND BIOSPHERE AND ITS TOTALITY.pptx
PPTX
Introduction to Building Materials
GENETICS IN BIOLOGY IN SECONDARY LEVEL FORM 3
Computing-Curriculum for Schools in Ghana
Orientation - ARALprogram of Deped to the Parents.pptx
advance database management system book.pdf
ChatGPT for Dummies - Pam Baker Ccesa007.pdf
احياء السادس العلمي - الفصل الثالث (التكاثر) منهج متميزين/كلية بغداد/موهوبين
Hazard Identification & Risk Assessment .pdf
Lesson notes of climatology university.
Final Presentation General Medicine 03-08-2024.pptx
Weekly quiz Compilation Jan -July 25.pdf
LNK 2025 (2).pdf MWEHEHEHEHEHEHEHEHEHEHE
Supply Chain Operations Speaking Notes -ICLT Program
OBE - B.A.(HON'S) IN INTERIOR ARCHITECTURE -Ar.MOHIUDDIN.pdf
1_English_Language_Set_2.pdf probationary
Final Presentation General Medicine 03-08-2024.pptx
Cell Types and Its function , kingdom of life
A systematic review of self-coping strategies used by university students to ...
A GUIDE TO GENETICS FOR UNDERGRADUATE MEDICAL STUDENTS
CHAPTER IV. MAN AND BIOSPHERE AND ITS TOTALITY.pptx
Introduction to Building Materials

Project analysis and advanced data calculation and conditional formatting

  • 1. PROJECT SIMULATION AND ADVANCED DATA CALCULATION IN EXCEL Dr. Chachrist Srisuwanrat สาขาวิชาการบริหารงานก่อสร้าง คณะวิศวกรรมศาสตร์และสถาปัตยกรรมศาสตร์ มหาวิทยาลัยเทคโนโลยีราชมงคลตะวันออก วิทยาเขตอุเทนถวาย
  • 2. Topics • Project Risk Analysis using Simulation • Determine project duration under uncertainty • Plot density and cumulative distribution of project duration • Advanced Data Calculation and Formatting • Construct “Two-way Table” • Apply “Conditional Formatting” 2
  • 3. Project Risk Analysis using Simulation 3
  • 6. Use constant duration to verify formula 6
  • 7. Forward Calculation (ESD, EFD) • ESDj = MAX( EFDi ) • ESDj = ESDj + DURj 7
  • 8. Backward Calculation (LSD, LFD) • LFDj = MIN(LSDk) • LSDj = LFDj - DURj 8
  • 9. Float Calculation (TF) • TF = LFD – EFD • Is Critical = if(TF = 0, 1, 0) 9
  • 10. Apply probabilistic duration • Copy code in “Duration Description” to Duration column • Note: your numbers will be different because of randomization. Press F9 to view change. 10
  • 11. So what is the project duration??? Best case? Most likely? Worst case? 11
  • 12. Use “Home->Fill->Series” to create project-duration collection table 12
  • 13. Use “What-If Analysis->Data Table” to collect data (project duration) 13
  • 14. Use “countif” function to count project durations that are less than or equal to 14
  • 16. Construct Is-Critical Table for Activities to collect probability of being critical Collection 2,000 data points Using Fill->Series What-If Analysis->Data Table 16
  • 17. Use “Data->What-If Analysis->Data Table” to collect 2,000 Is-Critical data points 17
  • 18. CountIf to determine %Critical 18
  • 20. Do you? • Believe A-B-E-G almost being critical half of the time? • Know that A-D-G could be critical? • Think all 3 paths could be critical at the same time? • Worst duration could be TWICE of best duration? 20
  • 22. Advanced Data Calculation and Formatting 22
  • 23. Advanced Data Calculation and Formatting • Main calculation table • Two-way Table • Text function • Conditional Formatting 23
  • 24. Simple Example: Land Cost Valuation and %Profit • Land Size 3 rais with Cost 200,000 Baht/sq.w. • FAR = 3 • NFA/GFA = 65% • Construction Cost 17,000 Baht/sq.m. • Mgmt & Mkt Cost 10% of (Land and Construction Cost) • Sale Price 75,000 Baht/sq.m. • What is the %Profit? 24
  • 26. Two-way Table Example: Land Cost Valuation and %Profit • Land Size 3 rais with Cost 180,000 to 220,000 Baht/sq.w. • FAR = 3 • NFA/GFA = 65% • Construction Cost 17,000 Baht/sq.m. • Mgmt & Mkt Cost 10% of (Land and Construction Cost) • Sale Price 60,000 to 90,000 Baht/sq.m. • What is the %Profit for each combination of Land Cost and Sale Price? 26
  • 27. Construct Two-way Table • Land Cost 180,000 to 220,000 Baht/sq.w. • Sale Price 60,000 to 90,000 Baht/sq.m. 27
  • 29. After click OK and Formatting cells 29
  • 30. Add Desired %Profit and Minimum Required %Profit for Conditional Formatting Only 30
  • 32. Select J5->Format Painter • Select J5 • Click Format Painter • Crop cells in the table for formatting 32
  • 33. Conditional Formatting for Minimum Required %Profit 33
  • 35. Now you can also change and study • NFA/GFA from 65% to 60% • Construction Cost from 17,000 to 18,000 Baht/sq.m. • Mgmt & Mkt Cost from 10% to 15% 35
  • 38. Simulated Table Example: Expected, Max, Min %Profit • Land Cost 190,000 to 210,000 Baht/sq.w. • NFA/GFA = 60-70% • Construction Cost 17,000-21,000 Baht/sq.m. • Mgmt & Mkt Cost 10-15% of (Land and Construction Cost) • Sale Price 60,000 to 90,000 Baht/sq.m. • What is the %Profit: • Expected • Max • Min 38
  • 39. 39
  • 41. Data Table runs and collects 10,000 data of %Profit 41
  • 42. Let’s get Land Cost, NFA/GFA, Construction Cost, Mgmt&Mkt Cost, and Sale Price 42
  • 44. ORIGINAL Land Cost 190,000 to 210,000 Baht/sq.w. NFA/GFA = 60-70% Construction Cost 17,000 to 21,000 Baht/sq.m. Mgmt & Mkt Cost 10 to 15% of (Land and Construction Cost) Sale Price 60,000 to 90,000 Baht/sq.m. DESIRED Land Cost 190,000 to 200,000 Baht/sq.w. NFA/GFA = 60-70% Construction Cost 17,000 to 18,000 Baht/sq.m. Mgmt & Mkt Cost 10-15% of (Land and Construction Cost) Sale Price 70,000 to 85,000 Baht/sq.m. 44
  • 45. Example: Very Difficult Problem • A group of consultant agrees to manage and sell a land. • This land has 18 rais. • They will be spited to 4 to 6 plots. • These 4-6 plots will be sold at • Plot 1: 190,000 Baht/rais for 2 to 4 rais or not at all • Plot 2: 200,000 Baht/rais for 2 to 3 rais or not at all • Plot 3: 200,000 Baht/rais for 2 to 3 • Plot 4: 210,000 Baht/rais for 2 to 3 • Plot 5: 210,000 Baht/rais for 2 to 3 • Plot 6: 200,000 or 210,000 Baht/rais depending on remaining land • In the end, all 18 rais must be sold. (continue next page) 45
  • 46. Continue • Consulting Fee 2% of all sale • Performance Fee 15% of land sold above 195,000 Baht/rais • If using sale agents, consultant must pay them 1% of the land price sold by agents • Probabilities: • Plot 1 has 50% chance to be sold at this price or not at all • Plot 2 has 50% chance to be sold at this price or not at all • If sold, size of land (2, 3, or 4 rais depending), which is sold, has equal chance (uniform distribution) • There is 50% chance using sale agents in each plot 46
  • 47. Questions • What is the expected, max, min of: • Land price per sq.w.? • Net owner revenue after all fees in Baht? • Net consulting + performance fees Baht? • Absolute commission calculated from consulting + performance fees in percent? • Sale agent commission in Baht? 47
  • 48. Calculation Table with Random Formula 48
  • 49. Simulated Table with 30,000 Replications 49
  • 51. Density and Cumulative Function of Consultant Revenue 51
  • 52. Consultant Revenue upon Number of rais (0-18 rais) sold by Sale Agents 52
  • 53. WHAT IF??? The consultant have already sold 3 rais at 200,000 Baht/sq.w. via sale agents Can he increase number of rais to be sold at 190,000 Baht/rai? If Yes, how many? 53
  • 54. THANK YOU Dr. Chachrist Srisuwanrat สาขาวิชาการบริหารงานก่อสร้าง คณะวิศวกรรมศาสตร์และสถาปัตยกรรมศาสตร์ มหาวิทยาลัยเทคโนโลยีราชมงคลตะวันออก วิทยาเขตอุเทนถวาย