EXAMPLE OF SCHEDULING
A REPETITIVE PROJECT WITH
PROBABILISTIC ACTIVITY DURATIONS
AND WORK BREAKS
(IV) Work Breaks 2
Example of a Repetitive Project with
Work Breaks
A B
C
E
D
F
G
H
J
SQS1 SQS2 SQS3 SQS4 SQS5
(IV) Work Breaks 3
0
1
2
3
4
5
6
7
8
9
10
0 30 60 90 120 150 180 210 240 270 300 330 360 390 420 450
Time
Unit
A B C D E F G H J
Average Total Idle Time = 1 day
Average Project Duration = 449 days
Controlling Sequence
0
1
2
3
4
5
6
7
8
9
10
0 30 60 90 120 150 180 210 240 270 300 330 360 390 420 450
Time
Unit
A B C D E F G H J
Average Total Idle Time = 438 days
Average Project Duration = 277 days
Early-start schedule has project duration of 277 days but also has 438 days of idle time.
SQS-AL with no work breaks has average project duration of 449 days. SQS-AL schedule with no work breaks.
--288J
--102H
--282G
--78F
--120E
--120D
--68C
--114B
--0A
Crew
Return Date
(CLT2)
Work
Break
Location
Crew
Arrival Date
(CLT1)
Activity
(IV) Work Breaks 4
0
1
2
3
4
5
6
7
8
9
10
0 30 60 90 120 150 180 210 240 270 300 330 360 390 420 450
Time
Unit
A B C D E F G H J
Average Total Idle Time = 3 days
Average Project Duration = 376 days
Controlling Sequence
0
1
2
3
4
5
6
7
8
9
10
0 30 60 90 120 150 180 210 240 270 300 330 360 390 420 450
Time
Unit
A B C D E F G H J
Average Total Idle Time = 3 days
Average Project Duration = 342 days
Controlling Sequence
SQS-AL schedule with two work breaks has average project duration of 376 days.
SQS-AL schedule with three work breaks has average project duration of 342 days.
SQS-AL schedule with two work breaks.
SQS-AL schedule with three work breaks.
--180J
--84H
254G7-G8174G
--60F
--102E
--44D
98C4-C522C
134B5-B638B
--0A
Crew
Return Date
(CLT2)
Work
Break
Location
Crew
Arrival Date
(CLT1)
Activity
--214J
--102H
288G7-G8208G
--78F
--102E
--78D
--68C
134B5-B638B
--0A
Crew
Return Date
(CLT2)
Work
Break
Location
Crew
Arrival Date
(CLT1)
Activity
B5-B6
G7-G8
C4-C5
Improve
duration
by 73 days
Improve
duration
by 107 days
(IV) Work Breaks 5
Method Work Break
Positions
Average
Project
Duration
Average
Total Idle
Time
Project Duration
plus
idle time
CPM - 277 438 715
SQS-AL - 449 1 450
SQS-AL* G7-G8 410 3 413
SQS-AL** G7-G8, B5-B6 376 3 379
SQS-AL*** G7-G8, B5-B6,C4-C5 342 3 345
Results from Introducing Work Breaks
• SQS-AL reduces idle time by 22 months, compared to
CPM.
• SQS-AL*** with 3 work breaks reduces project duration
by 5 months, compared to SQS-AL w/o work breaks.

More Related Content

PPTX
Brunswick motors, inc
PPTX
Rough run Oblivious Bloom Intersection
PDF
JTF2018_B30_k8s_operator_nobusue
PDF
Corporate Design The Missing Organizational Issue
PDF
GC minyak jelantah
PPT
Quick Sort
PDF
Model and schedule resource-sharing activities in repetitive projects using c...
Brunswick motors, inc
Rough run Oblivious Bloom Intersection
JTF2018_B30_k8s_operator_nobusue
Corporate Design The Missing Organizational Issue
GC minyak jelantah
Quick Sort
Model and schedule resource-sharing activities in repetitive projects using c...

More from Chachrist Srisuwanrat (11)

PDF
Repetitive Scheduling Method RSM
PDF
Time-Cost Tradeoff by Examples
PDF
Project analysis and advanced data calculation and conditional formatting
PDF
Optimization in ChaStrobe Software with Genetic Algorithm
PDF
ChaStrobe Application, a simulation-based scheduling software for repetitive ...
PDF
Example of repetitive project with probabilistic activity durations
PDF
Literature review of existing repetitive project scheduling techniques 2008
PDF
Five characteristics of repetitive activities in construction projects
PDF
Sequence step algorithm repetitive project scheduling for project with probab...
PPTX
Microsoft Project Workshop
DOCX
Ms project 2010 workshop on july 2014
Repetitive Scheduling Method RSM
Time-Cost Tradeoff by Examples
Project analysis and advanced data calculation and conditional formatting
Optimization in ChaStrobe Software with Genetic Algorithm
ChaStrobe Application, a simulation-based scheduling software for repetitive ...
Example of repetitive project with probabilistic activity durations
Literature review of existing repetitive project scheduling techniques 2008
Five characteristics of repetitive activities in construction projects
Sequence step algorithm repetitive project scheduling for project with probab...
Microsoft Project Workshop
Ms project 2010 workshop on july 2014
Ad

Recently uploaded (20)

PPTX
Orientation - ARALprogram of Deped to the Parents.pptx
PDF
احياء السادس العلمي - الفصل الثالث (التكاثر) منهج متميزين/كلية بغداد/موهوبين
PPTX
Cell Types and Its function , kingdom of life
PDF
What if we spent less time fighting change, and more time building what’s rig...
PDF
1_English_Language_Set_2.pdf probationary
PDF
Weekly quiz Compilation Jan -July 25.pdf
PPTX
Introduction to Building Materials
PDF
Practical Manual AGRO-233 Principles and Practices of Natural Farming
PPTX
CHAPTER IV. MAN AND BIOSPHERE AND ITS TOTALITY.pptx
PDF
A systematic review of self-coping strategies used by university students to ...
PDF
Chinmaya Tiranga quiz Grand Finale.pdf
PPTX
Final Presentation General Medicine 03-08-2024.pptx
PDF
RMMM.pdf make it easy to upload and study
PPTX
Digestion and Absorption of Carbohydrates, Proteina and Fats
PDF
Complications of Minimal Access Surgery at WLH
PPTX
202450812 BayCHI UCSC-SV 20250812 v17.pptx
PDF
Trump Administration's workforce development strategy
PPTX
Introduction-to-Literarature-and-Literary-Studies-week-Prelim-coverage.pptx
PDF
Black Hat USA 2025 - Micro ICS Summit - ICS/OT Threat Landscape
PPTX
A powerpoint presentation on the Revised K-10 Science Shaping Paper
Orientation - ARALprogram of Deped to the Parents.pptx
احياء السادس العلمي - الفصل الثالث (التكاثر) منهج متميزين/كلية بغداد/موهوبين
Cell Types and Its function , kingdom of life
What if we spent less time fighting change, and more time building what’s rig...
1_English_Language_Set_2.pdf probationary
Weekly quiz Compilation Jan -July 25.pdf
Introduction to Building Materials
Practical Manual AGRO-233 Principles and Practices of Natural Farming
CHAPTER IV. MAN AND BIOSPHERE AND ITS TOTALITY.pptx
A systematic review of self-coping strategies used by university students to ...
Chinmaya Tiranga quiz Grand Finale.pdf
Final Presentation General Medicine 03-08-2024.pptx
RMMM.pdf make it easy to upload and study
Digestion and Absorption of Carbohydrates, Proteina and Fats
Complications of Minimal Access Surgery at WLH
202450812 BayCHI UCSC-SV 20250812 v17.pptx
Trump Administration's workforce development strategy
Introduction-to-Literarature-and-Literary-Studies-week-Prelim-coverage.pptx
Black Hat USA 2025 - Micro ICS Summit - ICS/OT Threat Landscape
A powerpoint presentation on the Revised K-10 Science Shaping Paper
Ad

Example of repetitive project with probabilistic activity durations and work breaks

  • 1. (IV) Work Breaks 1 Schedule work breaks in repetitive projects in order to reduce project duration Presented by Chachrist Srisuwanrat 2008 EXAMPLE OF SCHEDULING A REPETITIVE PROJECT WITH PROBABILISTIC ACTIVITY DURATIONS AND WORK BREAKS
  • 2. (IV) Work Breaks 2 Example of a Repetitive Project with Work Breaks A B C E D F G H J SQS1 SQS2 SQS3 SQS4 SQS5
  • 3. (IV) Work Breaks 3 0 1 2 3 4 5 6 7 8 9 10 0 30 60 90 120 150 180 210 240 270 300 330 360 390 420 450 Time Unit A B C D E F G H J Average Total Idle Time = 1 day Average Project Duration = 449 days Controlling Sequence 0 1 2 3 4 5 6 7 8 9 10 0 30 60 90 120 150 180 210 240 270 300 330 360 390 420 450 Time Unit A B C D E F G H J Average Total Idle Time = 438 days Average Project Duration = 277 days Early-start schedule has project duration of 277 days but also has 438 days of idle time. SQS-AL with no work breaks has average project duration of 449 days. SQS-AL schedule with no work breaks. --288J --102H --282G --78F --120E --120D --68C --114B --0A Crew Return Date (CLT2) Work Break Location Crew Arrival Date (CLT1) Activity
  • 4. (IV) Work Breaks 4 0 1 2 3 4 5 6 7 8 9 10 0 30 60 90 120 150 180 210 240 270 300 330 360 390 420 450 Time Unit A B C D E F G H J Average Total Idle Time = 3 days Average Project Duration = 376 days Controlling Sequence 0 1 2 3 4 5 6 7 8 9 10 0 30 60 90 120 150 180 210 240 270 300 330 360 390 420 450 Time Unit A B C D E F G H J Average Total Idle Time = 3 days Average Project Duration = 342 days Controlling Sequence SQS-AL schedule with two work breaks has average project duration of 376 days. SQS-AL schedule with three work breaks has average project duration of 342 days. SQS-AL schedule with two work breaks. SQS-AL schedule with three work breaks. --180J --84H 254G7-G8174G --60F --102E --44D 98C4-C522C 134B5-B638B --0A Crew Return Date (CLT2) Work Break Location Crew Arrival Date (CLT1) Activity --214J --102H 288G7-G8208G --78F --102E --78D --68C 134B5-B638B --0A Crew Return Date (CLT2) Work Break Location Crew Arrival Date (CLT1) Activity B5-B6 G7-G8 C4-C5 Improve duration by 73 days Improve duration by 107 days
  • 5. (IV) Work Breaks 5 Method Work Break Positions Average Project Duration Average Total Idle Time Project Duration plus idle time CPM - 277 438 715 SQS-AL - 449 1 450 SQS-AL* G7-G8 410 3 413 SQS-AL** G7-G8, B5-B6 376 3 379 SQS-AL*** G7-G8, B5-B6,C4-C5 342 3 345 Results from Introducing Work Breaks • SQS-AL reduces idle time by 22 months, compared to CPM. • SQS-AL*** with 3 work breaks reduces project duration by 5 months, compared to SQS-AL w/o work breaks.