Project crashing and jobProject crashing and job
sequencingsequencing
Presented by :Presented by :
Payal Buha (014)Payal Buha (014)
Ibtisam Sorthia (048)Ibtisam Sorthia (048)
Khushbu Dhorajiya (018)Khushbu Dhorajiya (018)
Krupali Suhagiya (050)Krupali Suhagiya (050)
Chandrika Makwana (032)Chandrika Makwana (032)
Submitted to :Submitted to : Mr. Vishal SondagraMr. Vishal Sondagra
INTRODUCTIONINTRODUCTION
• Project crashingProject crashing is a method for shorteningis a method for shortening
project duration by reducing one or moreproject duration by reducing one or more
critical activitiescritical activities to a time less than normalto a time less than normal
activity time.activity time.
• The process of determining the job order onThe process of determining the job order on
some machine or in some work center issome machine or in some work center is
known as sequencing or priority sequencing.known as sequencing or priority sequencing.
Project crashingProject crashing
• Project crashing is a method for shorteningProject crashing is a method for shortening
the project duration by reducing the time ofthe project duration by reducing the time of
one (or more)of the critical project activitiesone (or more)of the critical project activities
to less than its normal activity time.to less than its normal activity time.
• This reduction in the normal activity time isThis reduction in the normal activity time is
referred to as crashing.referred to as crashing.
Conti….Conti….
• Crashing is achieved by devoting moreCrashing is achieved by devoting more
resources, usually measures in terms ofresources, usually measures in terms of
dollars, to the activities to be crashed.dollars, to the activities to be crashed.
• The objective of project crashing project is toThe objective of project crashing project is to
reduce project duration while minimizing thereduce project duration while minimizing the
cost of crashing.cost of crashing.
THE GENERAL RELATIONSHIP OF TIMETHE GENERAL RELATIONSHIP OF TIME
AND COSTAND COST
• Crashing costs increase as project durationCrashing costs increase as project duration
decreases.decreases.
• Indirect costs increase as productionIndirect costs increase as production
duration increases.duration increases.
• Reduce project length as long as crashingReduce project length as long as crashing
costs are less than indirect costs.costs are less than indirect costs.
Conti….Conti….
Conti….Conti….
• The objective of crashing was to reduce theThe objective of crashing was to reduce the
scheduled completion time to reap thescheduled completion time to reap the
results of the projects sooner.results of the projects sooner.
• However, there may be other reasons forHowever, there may be other reasons for
reducing project time.reducing project time.
• There also may be direct financial penaltiesThere also may be direct financial penalties
for not completing a project on time.for not completing a project on time.
Trade-off conceptTrade-off concept
Here, we adopt the “Trade-off” concept.Here, we adopt the “Trade-off” concept.
• WWe attempt to “crash” some “e attempt to “crash” some “criticalcritical” events” events
by allocating moreby allocating more reresources to them,sources to them, so thatso that
the time of one or more critical activities isthe time of one or more critical activities is
reduced to a time thatreduced to a time that is lessis less than the normalthan the normal
activityactivity time.time.
What criteria should it be based onWhat criteria should it be based on
when deciding to crashing criticalwhen deciding to crashing critical
times?times?
The critical path is 1-2-3, the completion time =11The critical path is 1-2-3, the completion time =11
How? Path: 1-2-3 = 5+6=11 weeksHow? Path: 1-2-3 = 5+6=11 weeks
Path: 1-3 = 5 weeksPath: 1-3 = 5 weeks
Now, how many days can we “crash” it?Now, how many days can we “crash” it?
1
3
25 (1) 6(3)
Conti…Conti…
• The maximum time that can be crashed for:The maximum time that can be crashed for:
Path 1-2-3 = 1 + 3 = 4Path 1-2-3 = 1 + 3 = 4
Path 1-3 = 0Path 1-3 = 0
• ShouldShould we use up all these 4 weeks?we use up all these 4 weeks?
1
3
25 (1) 6(3)
5(0)
• If we used all 4 days, then path 1-2-3 has
(5-1) + (6-3) = 7 completion weeks
Now, we need to check if the completion time for path 1-3
has lesser than 7 weeks (why?)
Now, path 1-3 has (5-0) = 5 weeks
Since path 1-3 still shorter than 7 weeks, we used up all 4
crashed weeks
• Question: What if path 1-3 has, say 8 weeks completion
time?
1
3
2
5 (1)
6(3)
5(0)
4(0) 3(0)
• Now, we cannot use all 4 days (Why?)
Because path 1-2-3 will not be critical path anymore
path 1-3 would now has longest hour to finish
• Rule: When a path is a critical path, it will not stay as
a critical path
• So, we can only reduce the path 1-2-3 completion
time to the same time
• as path 1-3. (HOW?)
1 3
25 (1) 6(3)
8(0)
• We can only reduce total time for path 1-2-3 =We can only reduce total time for path 1-2-3 =
path 1-path 1-33,,
that is 8 weeksthat is 8 weeks
If the cost for path 1-2 and path 2-3 is the sameIf the cost for path 1-2 and path 2-3 is the same
thenthen
We can random pick them to crash so that itsWe can random pick them to crash so that its
completioncompletion
Time is 8 weeksTime is 8 weeks
1
3
25 (1) 6(3)
8(0)
1
3
25 (1)5 (1) 6(3)6(3)
8(0)8(0)
1
2
3
5 (1)5 (1)
6(3)6(3)
8(0)8(0)
OR
4(0)4(0) 4(1)4(1)
3(0)3(0)
JOB SEQUENCINGJOB SEQUENCING
 Sequencing or priority sequencing: the process ofSequencing or priority sequencing: the process of
determining which job is started first on somedetermining which job is started first on some
machines or work center by priority rule.machines or work center by priority rule.
 Priority rule: the rule used for btaining a jobPriority rule: the rule used for btaining a job
sequencing.sequencing.
Priority rule evaluation criteriaPriority rule evaluation criteria
To meet corresponding objectives ofTo meet corresponding objectives of
scheduling.scheduling.
Common standard measures:Common standard measures:
 Meeting due date of customers orMeeting due date of customers or
downstream operations.downstream operations.
 Minimizing flow time (the time a jobMinimizing flow time (the time a job
spends in the shop flow).spends in the shop flow).
 Minimizing WIP.Minimizing WIP.
 Minimizing idle time of machines andMinimizing idle time of machines and
workers (Maximizing utilization).workers (Maximizing utilization).
Sequencing rulesSequencing rules
• FCFSFCFS (first come-first served)(first come-first served)
 Jobs are processed in the sequence in whichJobs are processed in the sequence in which
they entered the shop;they entered the shop;
 The simplest and nature way of sequencingThe simplest and nature way of sequencing
as in queuing of a bankas in queuing of a bank
Conti….Conti….
• SPT (shortest processing time)SPT (shortest processing time)
 Jobs are sequenced in increasing order ofJobs are sequenced in increasing order of
their processing time,their processing time,
 The job with shortest processing time is first,The job with shortest processing time is first,
the one with the next shortest processingthe one with the next shortest processing
time is second, and so on,time is second, and so on,
Conti…Conti…
• EDD (earliest due date)EDD (earliest due date)
 Jobs are sequenced in increasing order ofJobs are sequenced in increasing order of
their due dates,their due dates,
 The job with earliest due date is first, theThe job with earliest due date is first, the
one with the next earliest due date isone with the next earliest due date is
second, and so on,second, and so on,
Conti…Conti…
• CR (Critical ratio)
 Critical ratio is the remaining time until due date
divided by processing time;
 Scheduling the job with the smallest CR next,
• CRi = Remaining time of Job I /
Processing time
of Job i
• = (Due date of Job i-current time) /
Processing time
of Job i
Conti…Conti…
 CR provides the balance between SPT and EDD,CR provides the balance between SPT and EDD,
such that the task with shorter remaining timesuch that the task with shorter remaining time
and longer processing time takes higher priority,and longer processing time takes higher priority,
 CR will become smaller as the current timeCR will become smaller as the current time
approaches due date, and more priority will givenapproaches due date, and more priority will given
to one with longer processing time,to one with longer processing time,
 For a job, if the numerator of its CR is negativeFor a job, if the numerator of its CR is negative
( the job has been already later), it is naturally( the job has been already later), it is naturally
scheduled next,scheduled next,
 If more than one jobs are later, higher priority isIf more than one jobs are later, higher priority is
given to one that has shorter processing timegiven to one that has shorter processing time
(SPT).(SPT).
Example of n jobs one machineExample of n jobs one machine
 A machine center in a job shop for a localA machine center in a job shop for a local
fabrication company has five unprocessedfabrication company has five unprocessed
jobs remaining at a particular point in time.jobs remaining at a particular point in time.
The jobs are labeled 1, 2, 3, 4, and 5 in theThe jobs are labeled 1, 2, 3, 4, and 5 in the
order that they entered the shop. Theorder that they entered the shop. The
respective processing times and due datesrespective processing times and due dates
are given in the table below.are given in the table below.
 Sequence the 5 jobs by above 4 rules andSequence the 5 jobs by above 4 rules and
compare results based on mean flow time,compare results based on mean flow time,
average tardiness, and number of tardy jobsaverage tardiness, and number of tardy jobs
Conti…Conti…
Job numberJob number Processing timeProcessing time Due dateDue date
11 1111 6161
22 2929 4545
33 3131 3131
44 11 3333
55 22 3232
Sequencing RulesSequencing Rules————FCFSFCFS
Mean Flow time=268/5=53.6Mean Flow time=268/5=53.6
Average tardiness=121/5=24.2Average tardiness=121/5=24.2
No. of tardy jobs=3.No. of tardy jobs=3.
1 11 61 0
2 40 45 0
3 71 31 40
4 72 33 39
5 74 32 42
Total 268 121
Sequencing RulesSequencing Rules————SPTSPT
Mean Flow time=135/5=27.0Mean Flow time=135/5=27.0
Average tardiness=43/5=8.6Average tardiness=43/5=8.6
No. of tardy jobs=1.No. of tardy jobs=1.
4 1 1 33 0
5 2 3 32 0
1 11 14 61 0
2 29 43 45 0
3 31 74 31 43
Total 135 43
Sequencing RulesSequencing Rules————EDDEDD
3 31 31 31 0
5 2 33 32 1
4 1 34 33 1
2 29 63 45 18
1 11 74 61 13
Total 235 33
Mean Flow time=235/5=47.0Mean Flow time=235/5=47.0
Average tardiness=33/5=6.6Average tardiness=33/5=6.6
No. of tardy jobs=4.No. of tardy jobs=4.
Sequencing RulesSequencing Rules————CRCR
Current time should be reset after scheduling one jobCurrent time should be reset after scheduling one job
Sequencing RulesSequencing Rules————CRCR Mean Flow time=289/5=57.8Mean Flow time=289/5=57.8
Average tardiness=87/5=17.4Average tardiness=87/5=17.4
No. of tardy jobs=4.No. of tardy jobs=4.
Both Jobs 4 and 5 are later, however Job 4 has shorter processing timeBoth Jobs 4 and 5 are later, however Job 4 has shorter processing time
and thus is scheduled first; Finally, job 1 is scheduled last.and thus is scheduled first; Finally, job 1 is scheduled last.
Sequencing RulesSequencing Rules————SummarySummary
DiscussionsDiscussions
 SPT results in smallest mean flow time;SPT results in smallest mean flow time;
 EDD yields the minimum maximum tardiness (42, 43, 18, andEDD yields the minimum maximum tardiness (42, 43, 18, and
31 for the 4 different rules);31 for the 4 different rules);
 Always true? Yes!Always true? Yes!
Example by videoExample by video
Sequencing n jobs on 1 machine - Example 4.mp4
CONCLUSION
CONCLUSION
Project crashing and job sequencing

More Related Content

PDF
Fundamentals of project management
PPTX
Critical Path Method (CPM) & Network Analysis
PPTX
Earned value management (EVM)
PPTX
Project Management PERT and CPM
PPTX
Program evaluation review technique (pert)
PPTX
Project Management
PPTX
Project management chapter 2
PPT
crashing of project
Fundamentals of project management
Critical Path Method (CPM) & Network Analysis
Earned value management (EVM)
Project Management PERT and CPM
Program evaluation review technique (pert)
Project Management
Project management chapter 2
crashing of project

What's hot (20)

PPT
Introduction to project management
PPT
Project Planning
PPT
Project Management: NETWORK ANALYSIS - CPM and PERT
PPT
Pert
PDF
Introduction to Project Management
PPT
Project planning-and-control
PPTX
Crashing and cost plan-cpm
PPT
Project management tools and techniques
PPT
Chap 3 Organization Structure
PPTX
Project Schedule Management - PMBOK6
PDF
Project Management C8 -cost_estimation_and_budgeting
PPTX
Project planning and scheduling techniques
PPT
Chapter 12(cpm pert)
PPT
Defining The Project
PDF
EVM of Project Management...
PPT
Financial Management Ch 09
PDF
PERT AND CPM PROJECT MANAGEMENT
PPT
Project organisation structure
Introduction to project management
Project Planning
Project Management: NETWORK ANALYSIS - CPM and PERT
Pert
Introduction to Project Management
Project planning-and-control
Crashing and cost plan-cpm
Project management tools and techniques
Chap 3 Organization Structure
Project Schedule Management - PMBOK6
Project Management C8 -cost_estimation_and_budgeting
Project planning and scheduling techniques
Chapter 12(cpm pert)
Defining The Project
EVM of Project Management...
Financial Management Ch 09
PERT AND CPM PROJECT MANAGEMENT
Project organisation structure
Ad

Viewers also liked (20)

PPTX
Crashing in Project Management
PPTX
Per tand project crashing
PPTX
Network Problem CPM & PERT
PPT
Scheduling and sequencing
PPTX
Pert & cpm project management
PPT
Sequencing
PPTX
Pert cpm
DOC
PPTX
Mpc sequencing
PPT
Human resource planning
PPT
PPTX
Time-Cost Trade off (Project Management)
PPT
Time cost optimisation
DOCX
OR Unit 5 queuing theory
PPTX
Spanning trees & applications
PPSX
Time cost-trade-off
PPT
Project time management
PDF
บทที่ 4 การวางแผนกำลังการผลิต
PPT
Program Evaluation and Review Technique
PPTX
Knapsack Problem
Crashing in Project Management
Per tand project crashing
Network Problem CPM & PERT
Scheduling and sequencing
Pert & cpm project management
Sequencing
Pert cpm
Mpc sequencing
Human resource planning
Time-Cost Trade off (Project Management)
Time cost optimisation
OR Unit 5 queuing theory
Spanning trees & applications
Time cost-trade-off
Project time management
บทที่ 4 การวางแผนกำลังการผลิต
Program Evaluation and Review Technique
Knapsack Problem
Ad

Similar to Project crashing and job sequencing (20)

PPT
Topic 5 Production Sequencing and Scheduling.ppt
PPT
Scheduling
PPT
Scheduling
PPT
Scheduling
PPTX
Pert,cpm, resource allocation and gert
PPTX
scheduling-sequencing-rules.pptx
PPTX
Operations scheduling
PDF
chapter 17.pdf
PPT
PPT
Crashing and Updating.ppt
PPTX
Production planning and control 2019
PPTX
C17
PPT
ch05_crashing.ppt
PPT
-PM-09-7.ppt
PDF
C03.05-Scheduling.key.pdf
PPTX
Project Management Diagnostics for Time Management
PPTX
OPERATIONS-SCHEDULING-AND-SEQUENCING.pptx
PDF
Production activity control - schedulling
PPTX
SCHEDULING IN PROJECT MANAGEMENT PROJECT SCHEDULE MANAGEMENT
PPSX
Critical path method & pert
Topic 5 Production Sequencing and Scheduling.ppt
Scheduling
Scheduling
Scheduling
Pert,cpm, resource allocation and gert
scheduling-sequencing-rules.pptx
Operations scheduling
chapter 17.pdf
Crashing and Updating.ppt
Production planning and control 2019
C17
ch05_crashing.ppt
-PM-09-7.ppt
C03.05-Scheduling.key.pdf
Project Management Diagnostics for Time Management
OPERATIONS-SCHEDULING-AND-SEQUENCING.pptx
Production activity control - schedulling
SCHEDULING IN PROJECT MANAGEMENT PROJECT SCHEDULE MANAGEMENT
Critical path method & pert

Recently uploaded (20)

PPTX
Pharmacology of Heart Failure /Pharmacotherapy of CHF
PPTX
Microbial diseases, their pathogenesis and prophylaxis
PPTX
Lesson notes of climatology university.
PDF
Supply Chain Operations Speaking Notes -ICLT Program
PDF
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
PDF
ANTIBIOTICS.pptx.pdf………………… xxxxxxxxxxxxx
PDF
Abdominal Access Techniques with Prof. Dr. R K Mishra
PDF
Computing-Curriculum for Schools in Ghana
PDF
BÀI TẬP BỔ TRỢ 4 KỸ NĂNG TIẾNG ANH 9 GLOBAL SUCCESS - CẢ NĂM - BÁM SÁT FORM Đ...
PPTX
school management -TNTEU- B.Ed., Semester II Unit 1.pptx
PDF
grade 11-chemistry_fetena_net_5883.pdf teacher guide for all student
PPTX
Renaissance Architecture: A Journey from Faith to Humanism
PDF
Saundersa Comprehensive Review for the NCLEX-RN Examination.pdf
PDF
Anesthesia in Laparoscopic Surgery in India
PDF
The Lost Whites of Pakistan by Jahanzaib Mughal.pdf
PDF
Black Hat USA 2025 - Micro ICS Summit - ICS/OT Threat Landscape
PPTX
IMMUNITY IMMUNITY refers to protection against infection, and the immune syst...
PPTX
Pharma ospi slides which help in ospi learning
PPTX
PPH.pptx obstetrics and gynecology in nursing
PPTX
Cell Structure & Organelles in detailed.
Pharmacology of Heart Failure /Pharmacotherapy of CHF
Microbial diseases, their pathogenesis and prophylaxis
Lesson notes of climatology university.
Supply Chain Operations Speaking Notes -ICLT Program
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
ANTIBIOTICS.pptx.pdf………………… xxxxxxxxxxxxx
Abdominal Access Techniques with Prof. Dr. R K Mishra
Computing-Curriculum for Schools in Ghana
BÀI TẬP BỔ TRỢ 4 KỸ NĂNG TIẾNG ANH 9 GLOBAL SUCCESS - CẢ NĂM - BÁM SÁT FORM Đ...
school management -TNTEU- B.Ed., Semester II Unit 1.pptx
grade 11-chemistry_fetena_net_5883.pdf teacher guide for all student
Renaissance Architecture: A Journey from Faith to Humanism
Saundersa Comprehensive Review for the NCLEX-RN Examination.pdf
Anesthesia in Laparoscopic Surgery in India
The Lost Whites of Pakistan by Jahanzaib Mughal.pdf
Black Hat USA 2025 - Micro ICS Summit - ICS/OT Threat Landscape
IMMUNITY IMMUNITY refers to protection against infection, and the immune syst...
Pharma ospi slides which help in ospi learning
PPH.pptx obstetrics and gynecology in nursing
Cell Structure & Organelles in detailed.

Project crashing and job sequencing

  • 1. Project crashing and jobProject crashing and job sequencingsequencing Presented by :Presented by : Payal Buha (014)Payal Buha (014) Ibtisam Sorthia (048)Ibtisam Sorthia (048) Khushbu Dhorajiya (018)Khushbu Dhorajiya (018) Krupali Suhagiya (050)Krupali Suhagiya (050) Chandrika Makwana (032)Chandrika Makwana (032) Submitted to :Submitted to : Mr. Vishal SondagraMr. Vishal Sondagra
  • 2. INTRODUCTIONINTRODUCTION • Project crashingProject crashing is a method for shorteningis a method for shortening project duration by reducing one or moreproject duration by reducing one or more critical activitiescritical activities to a time less than normalto a time less than normal activity time.activity time. • The process of determining the job order onThe process of determining the job order on some machine or in some work center issome machine or in some work center is known as sequencing or priority sequencing.known as sequencing or priority sequencing.
  • 3. Project crashingProject crashing • Project crashing is a method for shorteningProject crashing is a method for shortening the project duration by reducing the time ofthe project duration by reducing the time of one (or more)of the critical project activitiesone (or more)of the critical project activities to less than its normal activity time.to less than its normal activity time. • This reduction in the normal activity time isThis reduction in the normal activity time is referred to as crashing.referred to as crashing.
  • 4. Conti….Conti…. • Crashing is achieved by devoting moreCrashing is achieved by devoting more resources, usually measures in terms ofresources, usually measures in terms of dollars, to the activities to be crashed.dollars, to the activities to be crashed. • The objective of project crashing project is toThe objective of project crashing project is to reduce project duration while minimizing thereduce project duration while minimizing the cost of crashing.cost of crashing.
  • 5. THE GENERAL RELATIONSHIP OF TIMETHE GENERAL RELATIONSHIP OF TIME AND COSTAND COST • Crashing costs increase as project durationCrashing costs increase as project duration decreases.decreases. • Indirect costs increase as productionIndirect costs increase as production duration increases.duration increases. • Reduce project length as long as crashingReduce project length as long as crashing costs are less than indirect costs.costs are less than indirect costs.
  • 7. Conti….Conti…. • The objective of crashing was to reduce theThe objective of crashing was to reduce the scheduled completion time to reap thescheduled completion time to reap the results of the projects sooner.results of the projects sooner. • However, there may be other reasons forHowever, there may be other reasons for reducing project time.reducing project time. • There also may be direct financial penaltiesThere also may be direct financial penalties for not completing a project on time.for not completing a project on time.
  • 8. Trade-off conceptTrade-off concept Here, we adopt the “Trade-off” concept.Here, we adopt the “Trade-off” concept. • WWe attempt to “crash” some “e attempt to “crash” some “criticalcritical” events” events by allocating moreby allocating more reresources to them,sources to them, so thatso that the time of one or more critical activities isthe time of one or more critical activities is reduced to a time thatreduced to a time that is lessis less than the normalthan the normal activityactivity time.time.
  • 9. What criteria should it be based onWhat criteria should it be based on when deciding to crashing criticalwhen deciding to crashing critical times?times? The critical path is 1-2-3, the completion time =11The critical path is 1-2-3, the completion time =11 How? Path: 1-2-3 = 5+6=11 weeksHow? Path: 1-2-3 = 5+6=11 weeks Path: 1-3 = 5 weeksPath: 1-3 = 5 weeks Now, how many days can we “crash” it?Now, how many days can we “crash” it? 1 3 25 (1) 6(3)
  • 10. Conti…Conti… • The maximum time that can be crashed for:The maximum time that can be crashed for: Path 1-2-3 = 1 + 3 = 4Path 1-2-3 = 1 + 3 = 4 Path 1-3 = 0Path 1-3 = 0 • ShouldShould we use up all these 4 weeks?we use up all these 4 weeks? 1 3 25 (1) 6(3) 5(0)
  • 11. • If we used all 4 days, then path 1-2-3 has (5-1) + (6-3) = 7 completion weeks Now, we need to check if the completion time for path 1-3 has lesser than 7 weeks (why?) Now, path 1-3 has (5-0) = 5 weeks Since path 1-3 still shorter than 7 weeks, we used up all 4 crashed weeks • Question: What if path 1-3 has, say 8 weeks completion time? 1 3 2 5 (1) 6(3) 5(0) 4(0) 3(0)
  • 12. • Now, we cannot use all 4 days (Why?) Because path 1-2-3 will not be critical path anymore path 1-3 would now has longest hour to finish • Rule: When a path is a critical path, it will not stay as a critical path • So, we can only reduce the path 1-2-3 completion time to the same time • as path 1-3. (HOW?) 1 3 25 (1) 6(3) 8(0)
  • 13. • We can only reduce total time for path 1-2-3 =We can only reduce total time for path 1-2-3 = path 1-path 1-33,, that is 8 weeksthat is 8 weeks If the cost for path 1-2 and path 2-3 is the sameIf the cost for path 1-2 and path 2-3 is the same thenthen We can random pick them to crash so that itsWe can random pick them to crash so that its completioncompletion Time is 8 weeksTime is 8 weeks 1 3 25 (1) 6(3) 8(0)
  • 14. 1 3 25 (1)5 (1) 6(3)6(3) 8(0)8(0) 1 2 3 5 (1)5 (1) 6(3)6(3) 8(0)8(0) OR 4(0)4(0) 4(1)4(1) 3(0)3(0)
  • 15. JOB SEQUENCINGJOB SEQUENCING  Sequencing or priority sequencing: the process ofSequencing or priority sequencing: the process of determining which job is started first on somedetermining which job is started first on some machines or work center by priority rule.machines or work center by priority rule.  Priority rule: the rule used for btaining a jobPriority rule: the rule used for btaining a job sequencing.sequencing.
  • 16. Priority rule evaluation criteriaPriority rule evaluation criteria To meet corresponding objectives ofTo meet corresponding objectives of scheduling.scheduling. Common standard measures:Common standard measures:  Meeting due date of customers orMeeting due date of customers or downstream operations.downstream operations.  Minimizing flow time (the time a jobMinimizing flow time (the time a job spends in the shop flow).spends in the shop flow).  Minimizing WIP.Minimizing WIP.  Minimizing idle time of machines andMinimizing idle time of machines and workers (Maximizing utilization).workers (Maximizing utilization).
  • 17. Sequencing rulesSequencing rules • FCFSFCFS (first come-first served)(first come-first served)  Jobs are processed in the sequence in whichJobs are processed in the sequence in which they entered the shop;they entered the shop;  The simplest and nature way of sequencingThe simplest and nature way of sequencing as in queuing of a bankas in queuing of a bank
  • 18. Conti….Conti…. • SPT (shortest processing time)SPT (shortest processing time)  Jobs are sequenced in increasing order ofJobs are sequenced in increasing order of their processing time,their processing time,  The job with shortest processing time is first,The job with shortest processing time is first, the one with the next shortest processingthe one with the next shortest processing time is second, and so on,time is second, and so on,
  • 19. Conti…Conti… • EDD (earliest due date)EDD (earliest due date)  Jobs are sequenced in increasing order ofJobs are sequenced in increasing order of their due dates,their due dates,  The job with earliest due date is first, theThe job with earliest due date is first, the one with the next earliest due date isone with the next earliest due date is second, and so on,second, and so on,
  • 20. Conti…Conti… • CR (Critical ratio)  Critical ratio is the remaining time until due date divided by processing time;  Scheduling the job with the smallest CR next, • CRi = Remaining time of Job I / Processing time of Job i • = (Due date of Job i-current time) / Processing time of Job i
  • 21. Conti…Conti…  CR provides the balance between SPT and EDD,CR provides the balance between SPT and EDD, such that the task with shorter remaining timesuch that the task with shorter remaining time and longer processing time takes higher priority,and longer processing time takes higher priority,  CR will become smaller as the current timeCR will become smaller as the current time approaches due date, and more priority will givenapproaches due date, and more priority will given to one with longer processing time,to one with longer processing time,  For a job, if the numerator of its CR is negativeFor a job, if the numerator of its CR is negative ( the job has been already later), it is naturally( the job has been already later), it is naturally scheduled next,scheduled next,  If more than one jobs are later, higher priority isIf more than one jobs are later, higher priority is given to one that has shorter processing timegiven to one that has shorter processing time (SPT).(SPT).
  • 22. Example of n jobs one machineExample of n jobs one machine  A machine center in a job shop for a localA machine center in a job shop for a local fabrication company has five unprocessedfabrication company has five unprocessed jobs remaining at a particular point in time.jobs remaining at a particular point in time. The jobs are labeled 1, 2, 3, 4, and 5 in theThe jobs are labeled 1, 2, 3, 4, and 5 in the order that they entered the shop. Theorder that they entered the shop. The respective processing times and due datesrespective processing times and due dates are given in the table below.are given in the table below.  Sequence the 5 jobs by above 4 rules andSequence the 5 jobs by above 4 rules and compare results based on mean flow time,compare results based on mean flow time, average tardiness, and number of tardy jobsaverage tardiness, and number of tardy jobs
  • 23. Conti…Conti… Job numberJob number Processing timeProcessing time Due dateDue date 11 1111 6161 22 2929 4545 33 3131 3131 44 11 3333 55 22 3232
  • 24. Sequencing RulesSequencing Rules————FCFSFCFS Mean Flow time=268/5=53.6Mean Flow time=268/5=53.6 Average tardiness=121/5=24.2Average tardiness=121/5=24.2 No. of tardy jobs=3.No. of tardy jobs=3. 1 11 61 0 2 40 45 0 3 71 31 40 4 72 33 39 5 74 32 42 Total 268 121
  • 25. Sequencing RulesSequencing Rules————SPTSPT Mean Flow time=135/5=27.0Mean Flow time=135/5=27.0 Average tardiness=43/5=8.6Average tardiness=43/5=8.6 No. of tardy jobs=1.No. of tardy jobs=1. 4 1 1 33 0 5 2 3 32 0 1 11 14 61 0 2 29 43 45 0 3 31 74 31 43 Total 135 43
  • 26. Sequencing RulesSequencing Rules————EDDEDD 3 31 31 31 0 5 2 33 32 1 4 1 34 33 1 2 29 63 45 18 1 11 74 61 13 Total 235 33 Mean Flow time=235/5=47.0Mean Flow time=235/5=47.0 Average tardiness=33/5=6.6Average tardiness=33/5=6.6 No. of tardy jobs=4.No. of tardy jobs=4.
  • 27. Sequencing RulesSequencing Rules————CRCR Current time should be reset after scheduling one jobCurrent time should be reset after scheduling one job
  • 28. Sequencing RulesSequencing Rules————CRCR Mean Flow time=289/5=57.8Mean Flow time=289/5=57.8 Average tardiness=87/5=17.4Average tardiness=87/5=17.4 No. of tardy jobs=4.No. of tardy jobs=4. Both Jobs 4 and 5 are later, however Job 4 has shorter processing timeBoth Jobs 4 and 5 are later, however Job 4 has shorter processing time and thus is scheduled first; Finally, job 1 is scheduled last.and thus is scheduled first; Finally, job 1 is scheduled last.
  • 29. Sequencing RulesSequencing Rules————SummarySummary DiscussionsDiscussions  SPT results in smallest mean flow time;SPT results in smallest mean flow time;  EDD yields the minimum maximum tardiness (42, 43, 18, andEDD yields the minimum maximum tardiness (42, 43, 18, and 31 for the 4 different rules);31 for the 4 different rules);  Always true? Yes!Always true? Yes!
  • 30. Example by videoExample by video Sequencing n jobs on 1 machine - Example 4.mp4