SlideShare a Scribd company logo
Crash
Activity Successor Normal
duration
Crash
duration
Normal
cost (LE)
Crash
Cost (LE)
Constraint
Z A 4 2 2660 2800 -
A B,D 10 7 5000 5750 -
B - 5 3 3500 4900 F4,D2A
D - 8 6 7150 8150 D3C,L4E
E D 10 6 2800 3200 D5X
X E 4 2 4000 4300 F5
Y C 5 5 5000 5000 F5
C D 7 4 5000 5600 -
A project has the following activities and relationships
Contract time 20 days, Penalty Value300 LE/Day, What is your
recommendation?
Finish
X
C
E
Y
AZ B
D
Start
4
0 5
5
0 5
10
10 20
7
5 12
0
0 0
4
0 4
10
4 14
5
16 21
8
16 24
0
24 24
F5
L4
D3
D5
D2
F5
Activity Successor
Z A
A B,D
B -
D -
E D
X E
Y C
C D
15
16
14
24
21
F4
If we don’t crash the project the total cost will be as following :
Total cost = Total normal cost + Penalty cost
Total normal cost = Ʃ Normal cost for each activity
=2660+5000+3500+7150+2800+4000+5000+5000= 35110 L.E.
Penalty cost = Penalty cost per month * No. of delayed month
= 300 * 4 = 1200 L.E.
Total cost = Total normal cost + Penalty cost
= 35110 + 1200 = 36310 L.E.
In This case total time of the project will be 24 w and Contractor will
deliver the project 4 month later than the time in the contract.
To avoid this delay the crash will be applied to this network to deliver
the project as possible as contract time.
The Crash rules :
1) Apply Crash only on activities which affect the total time.
2) Crash the least cost activity according to the least cost slope
Cost Slope =
𝑪𝒓𝒂𝒔𝒉𝒆𝒅 𝒄𝒐𝒔𝒕 𝑪.𝑪. −𝑵𝒐𝒓𝒎𝒂𝒍 𝑪𝒐𝒔𝒕(𝑵.𝑪.)
𝑵𝒐𝒓𝒎𝒂𝒍 𝑫𝒖𝒓𝒂𝒕𝒊𝒐𝒏 (𝑵.𝑫.) −𝑪𝒓𝒂𝒔𝒉𝒆𝒅 𝑫𝒖𝒓𝒂𝒕𝒊𝒐𝒏 (𝑪.𝑫.)
L.E  unite time
3) Activity will be crashed according to it’s crashability
Crashability = Normal Duration(N.D.) – Crash Duration (C.D.)
The Path which need to be crashed are the paths gives total time more
than contract time (20 w)
X E D (24w 20w)
2
500
4
100
Y C D
2
500
3
200
Z A D
2
500
3
250
2
70
(23 20)
(22 20)
Z A B
1
700
3
250
2
70
(21 20)
4E = 4*100 = 400 L.E.
3C = 3 * 200 = 600 L.E.
2Z = 2 * 70 = 140 L.E.
This path is already crashed 2Z from
the previous path (Z is Shared
activity in the two paths)
Total Crashed Cost = 600 + 400 + 140 = 1140 L.E.
Another Scenario to reach contract time 20 w
X E D (24 20)
2
500
4
100
Y C D
2
500
3
200
Z A D
2
500
3
250
2
70
(23 20)
(22 20)
Z A B
2
700
3
250
2
70
(21 20)
1C = 1 * 200 = 200 L.E.
NO need for crashing this path
1Z = 70 L.E.
2E = 2 * 100 = 200 L.E.
Act. D is
shared
Act.
2D =
2*500=
1000 L.E.
Total Crashed Cost for this scenario = 1000 + 400 + 200+70 = 1470 L.E.
X E D (24w 23w)
2
500
4
100
Y C D
2
500
3
200
Z A D
2
500
3
250
2
70
(23 23)
(22 23)
Z A B
1
700
3
250
2
70
(21 23)
Total Crashed Cost = 100 L.E.
1E = 1 * 100 = 100 L.E.
NO need for crashing this path
NO need for crashing this path
NO need for crashing this path
Scenario of ending the project with in 23 w
X E D (24w 22w)
2
500
4
100
Y C D
2
500
3
200
Z A D
2
500
3
250
2
70
(23 22)
(22 22)
Z A B
1
700
3
250
2
70
(21 22)
Total Crashed Cost = 200 + 200 = 400 L.E.
2E = 2 * 100 = 200 L.E.
1C = 200 L.E.
NO need for crashing this path
NO need for crashing this path
Scenario of ending the project with in 22 w
X E D (24w 21w)
2
500
4
100
Y C D
2
500
3
200
Z A D
2
500
3
250
2
70
(23 21)
(22 21)
Z A B
1
700
3
250
2
70
(21 21)
Total Crashed Cost = 300 + 400 + 70 = 770 L.E.
3E = 3* 100 = 300 L.E.
2C = 2 * 200 = 400 L.E.
1Z = 70 L.E.
NO need for crashing this path
Scenario of ending the project with in 21 w
Total time
Total
Normal
Cost
Total
crashed
cost
Total Penalty
Value
Total cost
24 35110 0 1200 36310
23 35110 100 900 36110
22 35110 400 600 36110
21 35110 770 300 36180
20 35110 1140 0 36250
Scenarios of the different completion time of the project can be
estimated according to this table:
Respect reputation and apply scenario 20 w
Finish
X
C
E
Y
AZ B
D
Start
4
0 5
5
0 5
10 16
4
5 9
0
0 0
2
0 2
10
2 12
5
14 19
8
12 20
0
20 20
F5
L4
D3
D5
D2
F5
12
12
12
20
19
F4
6
The final executed Network
UPDATE
Feedback form site at day 5 as following:
1) Activity C will start late by 2days
2) Activity A will finish late by 2 days
Finish
X
C
E
Y
AZ B
D
Start
4
0 5
5
0 5
10 16
4
7 11
0
0 0
2
0 2
10
2 14
5
16 21
8
14 22
0
22 22
F5
L4
D3
D5
D2
F5
14
12
14
22
21
F4
6
According to feedback at day 5 during construction
the project will finish in 22 day (2 days late from
contract time) , so we need to apply crash again but
take in your consideration :
1) The activities which have been finished.
Ex: Activity X,Y and Z finished before the feedback
date and Activity C not started yet according to
feedback (not allowed to be crashed) and Activity A
has been started but will finish late according to
feedback (allowed to be crashed if possible).
1) The activities which have been crashed before.
Ex: Activity E,C and Z
Y C D
2
500
0
200
Z A D
2
500
3
250
0
70
(22 20)
(22 20)
Z A B
1
700
3
250
0
70
(21 20)
2D = 2 * 500 = 1000 L.E.
This path is already crashed 2D from
the previous path (D is Shared
activity in the two paths)
1B = 1 * 700 = 700 L.E.
Total Crashed Cost = 1000 + 700 = 1700 L.E.
The network after update
Finish
X
C
E
Y
AZ B
D
Start
4
0 5
5
0 5
10 16
4
7 11
0
0 0
2
0 2
10
2 14
4
16 20
6
14 20
0
20 20
F5
L4
D3
D5
D2
F5
14
12
14
20
20
F4
6

More Related Content

PDF
Cash flow
PDF
PDF
Ch25 18
DOCX
Matlab tutorial2
PPT
Student Response - Function machines
PPTX
Numerical methods and programming
DOCX
Ejerciciooo3
Cash flow
Ch25 18
Matlab tutorial2
Student Response - Function machines
Numerical methods and programming
Ejerciciooo3

What's hot (20)

PPTX
Fundamentos de programación
PDF
K3+2.86
PDF
26. composite l2qtouchpad
PPTX
Decimal arithematic operation
PDF
PPTX
Applications of calculus in commerce and economics ii
PPT
Equations bingo (easy)
PPTX
Lp simplex method example in construction managment
KEY
App inventor独自カラー
PPTX
Engineering Graphics
PDF
คู่มือการใช้ Casiofx5800 p surveyingprograms
DOCX
Metodo estatico equivalente jessica garcia
PDF
Figures
PPTX
Applications of calculus in commerce and economics
PDF
Matlab Assignment JK Institute
PDF
PDF
Calculus 45S Slides May 14, 2008
PDF
Vector processing example
Fundamentos de programación
K3+2.86
26. composite l2qtouchpad
Decimal arithematic operation
Applications of calculus in commerce and economics ii
Equations bingo (easy)
Lp simplex method example in construction managment
App inventor独自カラー
Engineering Graphics
คู่มือการใช้ Casiofx5800 p surveyingprograms
Metodo estatico equivalente jessica garcia
Figures
Applications of calculus in commerce and economics
Matlab Assignment JK Institute
Calculus 45S Slides May 14, 2008
Vector processing example
Ad

Similar to Crash management (20)

PPT
Critical Path Method
PDF
MODULE 8 NOTES CEM (1).pdf
PPT
Time cost optimisation
PPTX
construction resource optimization 1.pptx
PPTX
Project crashing and project management - 01
PDF
Lecture7_2021_v2.pdf
DOC
Operation Research
DOCX
Assignment 101
PPT
crashing of project
PPTX
UNIT-2.pptx
PPT
PPTX
Project Management Diagnostics for Time Management
PDF
ملاحظات مهمة عن تعجيل المشاريع
DOCX
PMGT 510Principles of Project ManagementGroup Assign.docx
PPTX
crashing.pptxbbbbbbbbbbbbbbbbbbbbbbbbbbbbbb
DOCX
6Allocating Resources to the ProjectSolution to Project C.docx
PPT
CPM solution.ppt, Finance Department, Rajshahi University
PPTX
crashing-1 Cons Increases Direct Costs Increased Management Time May Increa...
DOCX
Deadline 6 PM Friday September 27, 201310 Project Management Que.docx
PPTX
Network crashing for project management.pptx
Critical Path Method
MODULE 8 NOTES CEM (1).pdf
Time cost optimisation
construction resource optimization 1.pptx
Project crashing and project management - 01
Lecture7_2021_v2.pdf
Operation Research
Assignment 101
crashing of project
UNIT-2.pptx
Project Management Diagnostics for Time Management
ملاحظات مهمة عن تعجيل المشاريع
PMGT 510Principles of Project ManagementGroup Assign.docx
crashing.pptxbbbbbbbbbbbbbbbbbbbbbbbbbbbbbb
6Allocating Resources to the ProjectSolution to Project C.docx
CPM solution.ppt, Finance Department, Rajshahi University
crashing-1 Cons Increases Direct Costs Increased Management Time May Increa...
Deadline 6 PM Friday September 27, 201310 Project Management Que.docx
Network crashing for project management.pptx
Ad

More from Ahmed Gamal (20)

PDF
Graduation book - BFRP
DOCX
hti traininig 2018
PDF
Resource management
PDF
Pert2 management
PDF
Pert management
PDF
Lob management
PDF
Lec 2 construction management
PDF
Earned value management
PDF
Cm ch4 scheduling
PDF
1- construction management
PDF
تدريب 2 التجمع الخامس و نادي مدينتي
PDF
01 introduction and layout of steel (1)
PDF
الامن الصناعي
PDF
programming fortran 77 Slide02
PDF
programming fortran 77 Slide01
DOC
7 fatigue
DOC
5 hardness
DOC
4 static shear
DOC
3 bending test
DOC
2 compression
Graduation book - BFRP
hti traininig 2018
Resource management
Pert2 management
Pert management
Lob management
Lec 2 construction management
Earned value management
Cm ch4 scheduling
1- construction management
تدريب 2 التجمع الخامس و نادي مدينتي
01 introduction and layout of steel (1)
الامن الصناعي
programming fortran 77 Slide02
programming fortran 77 Slide01
7 fatigue
5 hardness
4 static shear
3 bending test
2 compression

Recently uploaded (20)

PPTX
Course Overview of the Course Titled.pptx
PPTX
Chapter One an overview of political economy
PDF
The Untold Story of Swami Vijay Kumar Durai: Building PRS International
PDF
Case study -Uber strategic plan and management
PDF
Certified Information Systems Security Professional (CISSP) Specialization Ce...
PPTX
FSC Building Trust in LGs august 8 2025.pptx
PPTX
Organisational behaviour_ managerial applications of perception
PPTX
Strategic Plan 2023-2024 Presentation.pptx
PPTX
INTELLECTUAL PROPERTY LAW IN UGANDA.pptx
PPTX
Human resources management -job perception concept
PPTX
Chapter Three for international political
PDF
JOB APPLICATION AND RESUME WRITING IN MANAGEMENT
PPTX
2. CYCLE OF FUNCTIONING RIFLE -PP Presentation..pptx
PPT
Project Management - Scope Management.ppt
PDF
CISSP Domain 6: Security Assessment and Testing
PDF
ORGANIZATIONAL communication -concepts and importance._20250806_112132_0000.pdf
PDF
CHAPTER 14 Manageement of Nursing Educational Institutions- planing and orga...
PPTX
Basics of Project Management for development of leadership skills in practice
PDF
The Cyber SwarmShield by Stéphane Nappo
PPTX
4 5 6 7 Intro to Ramayan MANAGEMENT LESSONS and Qualities.pptx
Course Overview of the Course Titled.pptx
Chapter One an overview of political economy
The Untold Story of Swami Vijay Kumar Durai: Building PRS International
Case study -Uber strategic plan and management
Certified Information Systems Security Professional (CISSP) Specialization Ce...
FSC Building Trust in LGs august 8 2025.pptx
Organisational behaviour_ managerial applications of perception
Strategic Plan 2023-2024 Presentation.pptx
INTELLECTUAL PROPERTY LAW IN UGANDA.pptx
Human resources management -job perception concept
Chapter Three for international political
JOB APPLICATION AND RESUME WRITING IN MANAGEMENT
2. CYCLE OF FUNCTIONING RIFLE -PP Presentation..pptx
Project Management - Scope Management.ppt
CISSP Domain 6: Security Assessment and Testing
ORGANIZATIONAL communication -concepts and importance._20250806_112132_0000.pdf
CHAPTER 14 Manageement of Nursing Educational Institutions- planing and orga...
Basics of Project Management for development of leadership skills in practice
The Cyber SwarmShield by Stéphane Nappo
4 5 6 7 Intro to Ramayan MANAGEMENT LESSONS and Qualities.pptx

Crash management

  • 1. Crash Activity Successor Normal duration Crash duration Normal cost (LE) Crash Cost (LE) Constraint Z A 4 2 2660 2800 - A B,D 10 7 5000 5750 - B - 5 3 3500 4900 F4,D2A D - 8 6 7150 8150 D3C,L4E E D 10 6 2800 3200 D5X X E 4 2 4000 4300 F5 Y C 5 5 5000 5000 F5 C D 7 4 5000 5600 - A project has the following activities and relationships Contract time 20 days, Penalty Value300 LE/Day, What is your recommendation?
  • 2. Finish X C E Y AZ B D Start 4 0 5 5 0 5 10 10 20 7 5 12 0 0 0 4 0 4 10 4 14 5 16 21 8 16 24 0 24 24 F5 L4 D3 D5 D2 F5 Activity Successor Z A A B,D B - D - E D X E Y C C D 15 16 14 24 21 F4
  • 3. If we don’t crash the project the total cost will be as following : Total cost = Total normal cost + Penalty cost Total normal cost = Ʃ Normal cost for each activity =2660+5000+3500+7150+2800+4000+5000+5000= 35110 L.E. Penalty cost = Penalty cost per month * No. of delayed month = 300 * 4 = 1200 L.E. Total cost = Total normal cost + Penalty cost = 35110 + 1200 = 36310 L.E. In This case total time of the project will be 24 w and Contractor will deliver the project 4 month later than the time in the contract. To avoid this delay the crash will be applied to this network to deliver the project as possible as contract time.
  • 4. The Crash rules : 1) Apply Crash only on activities which affect the total time. 2) Crash the least cost activity according to the least cost slope Cost Slope = 𝑪𝒓𝒂𝒔𝒉𝒆𝒅 𝒄𝒐𝒔𝒕 𝑪.𝑪. −𝑵𝒐𝒓𝒎𝒂𝒍 𝑪𝒐𝒔𝒕(𝑵.𝑪.) 𝑵𝒐𝒓𝒎𝒂𝒍 𝑫𝒖𝒓𝒂𝒕𝒊𝒐𝒏 (𝑵.𝑫.) −𝑪𝒓𝒂𝒔𝒉𝒆𝒅 𝑫𝒖𝒓𝒂𝒕𝒊𝒐𝒏 (𝑪.𝑫.) L.E unite time 3) Activity will be crashed according to it’s crashability Crashability = Normal Duration(N.D.) – Crash Duration (C.D.)
  • 5. The Path which need to be crashed are the paths gives total time more than contract time (20 w) X E D (24w 20w) 2 500 4 100 Y C D 2 500 3 200 Z A D 2 500 3 250 2 70 (23 20) (22 20) Z A B 1 700 3 250 2 70 (21 20) 4E = 4*100 = 400 L.E. 3C = 3 * 200 = 600 L.E. 2Z = 2 * 70 = 140 L.E. This path is already crashed 2Z from the previous path (Z is Shared activity in the two paths) Total Crashed Cost = 600 + 400 + 140 = 1140 L.E.
  • 6. Another Scenario to reach contract time 20 w X E D (24 20) 2 500 4 100 Y C D 2 500 3 200 Z A D 2 500 3 250 2 70 (23 20) (22 20) Z A B 2 700 3 250 2 70 (21 20) 1C = 1 * 200 = 200 L.E. NO need for crashing this path 1Z = 70 L.E. 2E = 2 * 100 = 200 L.E. Act. D is shared Act. 2D = 2*500= 1000 L.E. Total Crashed Cost for this scenario = 1000 + 400 + 200+70 = 1470 L.E.
  • 7. X E D (24w 23w) 2 500 4 100 Y C D 2 500 3 200 Z A D 2 500 3 250 2 70 (23 23) (22 23) Z A B 1 700 3 250 2 70 (21 23) Total Crashed Cost = 100 L.E. 1E = 1 * 100 = 100 L.E. NO need for crashing this path NO need for crashing this path NO need for crashing this path Scenario of ending the project with in 23 w
  • 8. X E D (24w 22w) 2 500 4 100 Y C D 2 500 3 200 Z A D 2 500 3 250 2 70 (23 22) (22 22) Z A B 1 700 3 250 2 70 (21 22) Total Crashed Cost = 200 + 200 = 400 L.E. 2E = 2 * 100 = 200 L.E. 1C = 200 L.E. NO need for crashing this path NO need for crashing this path Scenario of ending the project with in 22 w
  • 9. X E D (24w 21w) 2 500 4 100 Y C D 2 500 3 200 Z A D 2 500 3 250 2 70 (23 21) (22 21) Z A B 1 700 3 250 2 70 (21 21) Total Crashed Cost = 300 + 400 + 70 = 770 L.E. 3E = 3* 100 = 300 L.E. 2C = 2 * 200 = 400 L.E. 1Z = 70 L.E. NO need for crashing this path Scenario of ending the project with in 21 w
  • 10. Total time Total Normal Cost Total crashed cost Total Penalty Value Total cost 24 35110 0 1200 36310 23 35110 100 900 36110 22 35110 400 600 36110 21 35110 770 300 36180 20 35110 1140 0 36250 Scenarios of the different completion time of the project can be estimated according to this table: Respect reputation and apply scenario 20 w
  • 11. Finish X C E Y AZ B D Start 4 0 5 5 0 5 10 16 4 5 9 0 0 0 2 0 2 10 2 12 5 14 19 8 12 20 0 20 20 F5 L4 D3 D5 D2 F5 12 12 12 20 19 F4 6 The final executed Network
  • 12. UPDATE Feedback form site at day 5 as following: 1) Activity C will start late by 2days 2) Activity A will finish late by 2 days Finish X C E Y AZ B D Start 4 0 5 5 0 5 10 16 4 7 11 0 0 0 2 0 2 10 2 14 5 16 21 8 14 22 0 22 22 F5 L4 D3 D5 D2 F5 14 12 14 22 21 F4 6
  • 13. According to feedback at day 5 during construction the project will finish in 22 day (2 days late from contract time) , so we need to apply crash again but take in your consideration : 1) The activities which have been finished. Ex: Activity X,Y and Z finished before the feedback date and Activity C not started yet according to feedback (not allowed to be crashed) and Activity A has been started but will finish late according to feedback (allowed to be crashed if possible). 1) The activities which have been crashed before. Ex: Activity E,C and Z
  • 14. Y C D 2 500 0 200 Z A D 2 500 3 250 0 70 (22 20) (22 20) Z A B 1 700 3 250 0 70 (21 20) 2D = 2 * 500 = 1000 L.E. This path is already crashed 2D from the previous path (D is Shared activity in the two paths) 1B = 1 * 700 = 700 L.E. Total Crashed Cost = 1000 + 700 = 1700 L.E.
  • 15. The network after update Finish X C E Y AZ B D Start 4 0 5 5 0 5 10 16 4 7 11 0 0 0 2 0 2 10 2 14 4 16 20 6 14 20 0 20 20 F5 L4 D3 D5 D2 F5 14 12 14 20 20 F4 6