Presentation of SPM
To: Sir Baist Hassan Qureshi …
Kuldeep Kumar
Introduction:
Microsoft Project is a project management software program
developed and sold by Microsoft
Designed to assist project managers in developing plans,
assigning resources to tasks, tracking progress, managing
budgets and analyzing workloads.
The application creates critical path schedules, and critical
chain which can be visualized in a Gantt chart.
MS Project's proprietary file format is *.mpp.
History:
Initially proposed by Microsoft's Manager of Product Development,
Alan M. Boyd as an internal tool to help manage the huge number of
software projects that were in development at any time inside the
company.
The first commercial version of Project was released for DOS in 1984.
Subsequent DOS versions: V2 (1985), V3 (1986) and V4 (1986)
First Windows version-1990
Macintosh version -1991
Subsequent versions-V3 (1992), V4 (1993), 1995, 1998 to 2016
Competitors:
Open Workbench
Primavera (software)
Project.net
Basecamp (software)
Gantt Project
Genius Inside
LiquidPlanner
MicroPlanner X-Pert
NavalPlan
Purpose:
• List each task necessary to complete a project in the order they should be
performed.
• Assign start and finish dates to tasks or let the program set them for you by you
specifying the duration of the task.
• Display the tasks graphically over a time line to get an overall view of the project.
• Assign workers, contractors, and other resources to tasks and print their
schedules.
• Compute the hours and cost necessary to complete a task or the entire project.
• Monitor a project’s progress and compare it to your original estimate.
• Analyze such items as cost, hours, slack time, resource allocation, etc. using
tables and graphs
Planning a Project:
•Define Goal
•Develop Task
•Establish Timeframes
•Resource Availability
•Organize.
Using MS Project
• Define te Project
• Build the plan
• Set a start Date
• Enter Tasks/durations.
• Assign resources
• Link Tasks
• Fine Tune the Plan
• Trach and Mange.,,,
• Set a baseline
• Enter actuals
• Adjust plan
• Close Project
Defining the Project:
• The objective of the project should be defined by the
person/group that is going to manage the project.
• Tasks, start times, and deadlines should be clearly established.
Purpose:
Set up Project Default:
• Set up Project Defaults:
• Set working order. (Schedule from Start Date forward or Finish Date
backwards)
• Set a start or finish date.
• Select/create the project calendar to use. (Controls working days and
hours)
Purpose Continue
Enter tasks:
• In chronological order, enter the tasks necessary to complete the
project.
• Set the task’s duration.
• When appropriate, set a task’s Start / Finish date.
Set Task Sequencing:
• Link tasks that must be completed sequentially.
• Set up Project Defaults:
• Do not link tasks that can be completed simultaneously.
Purpose Continue.
Create a Resource List:
• Create a list of contractors, laborers, equipment rental, fees,
etc. and their corresponding rates.
• Set working hours for each resource.
Assign Resources to Tasks
Analyze/Reevaluate/Adjust Project
Set up Project Defaults
Scheduling a Task:
When tasks must either end on a specific date or begin on a specific
date, you can create constraints.
MS Project Management (Overviews) | Software Mange Tool | Software Project Mangement
Track and Mange the Project:
As the project proceeds, you may wish to record its progress,
nothing any deviations from your planned schedule…
Creating a Baseline:
• A baseline us a snapshot of you project before actual work
begins and change are made to the schedule…
• The baseline includes task start and finish dates, resources
and costs…
• Compare the actual project to the baseline…
Critical Path:
• The sequence of activities which have no float or slack is called
the critical path.
• Slack = Late Start – Early Start OR Late Finish - Early Finish
• Any delay of an activity on the critical path directly impacts the
planned project completion date.
• A project can have several, parallel, near critical paths. An additional
parallel path through the network with the total durations shorter
than the critical path is called a sub-critical or non-critical path.
Time-Cost Trade-OFFS: Crashing:
• When we say that an activity will take a certain number of days or
weeks, what we really mean is this activity normally takes this many
days or weeks. We could make it take less time, but to do so would
cost more money.
• Crashing is a process of expediting project schedule by compressing
the total project duration.
• The key is to attain maximum decrease in schedule time with
minimum cost.
• More resources are needed to speed-up a part of a project
• Depends on what slack is available in a non-critical activity
When not to Crash:
• The key to project crashing is attaining maximum reduction in
schedule time with minimum cost. Quite simply, the time to stop
crashing is when it no longer becomes cost effective. A simple
guideline is:
• Crash only activities that are critical.
• Crash from the least expensive to most expensive.
• Crash an activity only until:
• It reaches its maximum time reduction.
• It causes another path to also become critical.
• It becomes more expensive to crash than not to crash
Creating a Crash Table:
• Identify the critical path and the corresponding tasks.
• Export the work package tasks (ID and Task Name fields), the original
duration (Duration field), and the original cost (Cost field) from your MS
Project schedule, and open that file in Excel.
• You must calculate the potential crash duration for each critical path task
and the cost to crash each task.
• On the Excel worksheet, add a column to calculate crash reduction, which
is how many weeks you can crash each task. Crash reduction is simply the
original duration minus the crash duration.
• Add another column to calculate the crash cost per week, which is the
crash cost divided by the crash reduction value.
Thank You

More Related Content

PPTX
Ms project presentation
PPTX
44259126 ms-project-presentation
PPTX
Successful Project Managers Use These 5 Ways to Represent Project Schedule
PDF
Scheduling by using microsoft project 2013
PDF
Ms project lectures
PPTX
Ms project training ppt
PPT
Ms Project 2007(advanced)
PPT
Ms Project 2007(Basic)
Ms project presentation
44259126 ms-project-presentation
Successful Project Managers Use These 5 Ways to Represent Project Schedule
Scheduling by using microsoft project 2013
Ms project lectures
Ms project training ppt
Ms Project 2007(advanced)
Ms Project 2007(Basic)

What's hot (20)

PPTX
How Project Network Diagram's Can Help You Become A Better Project Manager
PPTX
How To Use Scheduling Lead And Lag With 4 Types Of Relationships
PDF
Microsoft Project and Portfolio Management
PDF
Microsoft Project - MSP | 2013-2016
PPTX
A Comprehensive Beginners Guide To Cost Planning
PPTX
Ms project 2016 overview
PPTX
Project management with ms project 2007
PPT
MS Project 2007 Tips and Tricks
PDF
sMs project tutorial_iit
PDF
MS Project
PPTX
Microsoft Project for Professionals - 5 Simple & Practical Steps to Mastering...
PPTX
Microsoft Project 2013
PPTX
4 Project Estimation Techniques That Can Make You Super Successful
PPTX
Scheduling MS project 09.13.rev 1
PPTX
PPTX
MICROSOFT PROJECT TUTORIAL
PPTX
MS Project
PPTX
Project 2013 - 4 Simple & Practical Steps to Mastering Reporting Basics in un...
PPTX
Duration - The Holy Grail of MS Project?
PDF
Ms Project Workshop
How Project Network Diagram's Can Help You Become A Better Project Manager
How To Use Scheduling Lead And Lag With 4 Types Of Relationships
Microsoft Project and Portfolio Management
Microsoft Project - MSP | 2013-2016
A Comprehensive Beginners Guide To Cost Planning
Ms project 2016 overview
Project management with ms project 2007
MS Project 2007 Tips and Tricks
sMs project tutorial_iit
MS Project
Microsoft Project for Professionals - 5 Simple & Practical Steps to Mastering...
Microsoft Project 2013
4 Project Estimation Techniques That Can Make You Super Successful
Scheduling MS project 09.13.rev 1
MICROSOFT PROJECT TUTORIAL
MS Project
Project 2013 - 4 Simple & Practical Steps to Mastering Reporting Basics in un...
Duration - The Holy Grail of MS Project?
Ms Project Workshop
Ad

Similar to MS Project Management (Overviews) | Software Mange Tool | Software Project Mangement (20)

PPTX
MS Project Presentation
PPTX
dokumen.tips_ms-project-presentation.pptx
PPTX
ms-project-presentation.pptx
PPT
Project management teaching
PDF
Ms Project 2010
PPT
Chapter-5-Scheduling-and-Resource-Allocation.ppt
PDF
Information Technology Project Management 5th Edition Marchewka Solutions Manual
PDF
Practical Use of Microsoft Project for Project Managers
PDF
Information Technology Project Management 5th Edition Marchewka Solutions Manual
PPT
Using Microsoft Project 2003
PPT
Project management concepts_basic
DOCX
Ms project literature to read
PDF
Information Technology Project Management 5th Edition Marchewka Solutions Manual
PPTX
Online3-SlideDeck.pptx
PDF
Microsoft project 2003
PDF
PM Training Slides
PPTX
Project management
PPTX
Workshop microsoft office MS Project.pptx
PDF
Microsoft Project Course with PMP Concepts
PDF
Master MSProject 2010
MS Project Presentation
dokumen.tips_ms-project-presentation.pptx
ms-project-presentation.pptx
Project management teaching
Ms Project 2010
Chapter-5-Scheduling-and-Resource-Allocation.ppt
Information Technology Project Management 5th Edition Marchewka Solutions Manual
Practical Use of Microsoft Project for Project Managers
Information Technology Project Management 5th Edition Marchewka Solutions Manual
Using Microsoft Project 2003
Project management concepts_basic
Ms project literature to read
Information Technology Project Management 5th Edition Marchewka Solutions Manual
Online3-SlideDeck.pptx
Microsoft project 2003
PM Training Slides
Project management
Workshop microsoft office MS Project.pptx
Microsoft Project Course with PMP Concepts
Master MSProject 2010
Ad

Recently uploaded (20)

PPTX
WiFi Honeypot Detecscfddssdffsedfseztor.pptx
PPTX
Patient Appointment Booking in Odoo with online payment
PPTX
Monitoring Stack: Grafana, Loki & Promtail
PDF
Nekopoi APK 2025 free lastest update
PDF
Design an Analysis of Algorithms I-SECS-1021-03
PDF
Complete Guide to Website Development in Malaysia for SMEs
PPTX
assetexplorer- product-overview - presentation
PDF
iTop VPN Free 5.6.0.5262 Crack latest version 2025
PDF
How to Make Money in the Metaverse_ Top Strategies for Beginners.pdf
DOCX
Greta — No-Code AI for Building Full-Stack Web & Mobile Apps
PDF
Wondershare Filmora 15 Crack With Activation Key [2025
PDF
CCleaner Pro 6.38.11537 Crack Final Latest Version 2025
PDF
EN-Survey-Report-SAP-LeanIX-EA-Insights-2025.pdf
PDF
CapCut Video Editor 6.8.1 Crack for PC Latest Download (Fully Activated) 2025
PDF
Design an Analysis of Algorithms II-SECS-1021-03
PDF
AI-Powered Threat Modeling: The Future of Cybersecurity by Arun Kumar Elengov...
PDF
Navsoft: AI-Powered Business Solutions & Custom Software Development
PPTX
Operating system designcfffgfgggggggvggggggggg
PPTX
Computer Software and OS of computer science of grade 11.pptx
PDF
Designing Intelligence for the Shop Floor.pdf
WiFi Honeypot Detecscfddssdffsedfseztor.pptx
Patient Appointment Booking in Odoo with online payment
Monitoring Stack: Grafana, Loki & Promtail
Nekopoi APK 2025 free lastest update
Design an Analysis of Algorithms I-SECS-1021-03
Complete Guide to Website Development in Malaysia for SMEs
assetexplorer- product-overview - presentation
iTop VPN Free 5.6.0.5262 Crack latest version 2025
How to Make Money in the Metaverse_ Top Strategies for Beginners.pdf
Greta — No-Code AI for Building Full-Stack Web & Mobile Apps
Wondershare Filmora 15 Crack With Activation Key [2025
CCleaner Pro 6.38.11537 Crack Final Latest Version 2025
EN-Survey-Report-SAP-LeanIX-EA-Insights-2025.pdf
CapCut Video Editor 6.8.1 Crack for PC Latest Download (Fully Activated) 2025
Design an Analysis of Algorithms II-SECS-1021-03
AI-Powered Threat Modeling: The Future of Cybersecurity by Arun Kumar Elengov...
Navsoft: AI-Powered Business Solutions & Custom Software Development
Operating system designcfffgfgggggggvggggggggg
Computer Software and OS of computer science of grade 11.pptx
Designing Intelligence for the Shop Floor.pdf

MS Project Management (Overviews) | Software Mange Tool | Software Project Mangement

  • 1. Presentation of SPM To: Sir Baist Hassan Qureshi … Kuldeep Kumar
  • 2. Introduction: Microsoft Project is a project management software program developed and sold by Microsoft Designed to assist project managers in developing plans, assigning resources to tasks, tracking progress, managing budgets and analyzing workloads. The application creates critical path schedules, and critical chain which can be visualized in a Gantt chart. MS Project's proprietary file format is *.mpp.
  • 3. History: Initially proposed by Microsoft's Manager of Product Development, Alan M. Boyd as an internal tool to help manage the huge number of software projects that were in development at any time inside the company. The first commercial version of Project was released for DOS in 1984. Subsequent DOS versions: V2 (1985), V3 (1986) and V4 (1986) First Windows version-1990 Macintosh version -1991 Subsequent versions-V3 (1992), V4 (1993), 1995, 1998 to 2016
  • 4. Competitors: Open Workbench Primavera (software) Project.net Basecamp (software) Gantt Project Genius Inside LiquidPlanner MicroPlanner X-Pert NavalPlan
  • 5. Purpose: • List each task necessary to complete a project in the order they should be performed. • Assign start and finish dates to tasks or let the program set them for you by you specifying the duration of the task. • Display the tasks graphically over a time line to get an overall view of the project. • Assign workers, contractors, and other resources to tasks and print their schedules. • Compute the hours and cost necessary to complete a task or the entire project. • Monitor a project’s progress and compare it to your original estimate. • Analyze such items as cost, hours, slack time, resource allocation, etc. using tables and graphs
  • 6. Planning a Project: •Define Goal •Develop Task •Establish Timeframes •Resource Availability •Organize.
  • 7. Using MS Project • Define te Project • Build the plan • Set a start Date • Enter Tasks/durations. • Assign resources • Link Tasks • Fine Tune the Plan • Trach and Mange.,,, • Set a baseline • Enter actuals • Adjust plan • Close Project
  • 8. Defining the Project: • The objective of the project should be defined by the person/group that is going to manage the project. • Tasks, start times, and deadlines should be clearly established.
  • 9. Purpose: Set up Project Default: • Set up Project Defaults: • Set working order. (Schedule from Start Date forward or Finish Date backwards) • Set a start or finish date. • Select/create the project calendar to use. (Controls working days and hours)
  • 10. Purpose Continue Enter tasks: • In chronological order, enter the tasks necessary to complete the project. • Set the task’s duration. • When appropriate, set a task’s Start / Finish date. Set Task Sequencing: • Link tasks that must be completed sequentially. • Set up Project Defaults: • Do not link tasks that can be completed simultaneously.
  • 11. Purpose Continue. Create a Resource List: • Create a list of contractors, laborers, equipment rental, fees, etc. and their corresponding rates. • Set working hours for each resource. Assign Resources to Tasks Analyze/Reevaluate/Adjust Project Set up Project Defaults
  • 12. Scheduling a Task: When tasks must either end on a specific date or begin on a specific date, you can create constraints.
  • 14. Track and Mange the Project: As the project proceeds, you may wish to record its progress, nothing any deviations from your planned schedule…
  • 15. Creating a Baseline: • A baseline us a snapshot of you project before actual work begins and change are made to the schedule… • The baseline includes task start and finish dates, resources and costs… • Compare the actual project to the baseline…
  • 16. Critical Path: • The sequence of activities which have no float or slack is called the critical path. • Slack = Late Start – Early Start OR Late Finish - Early Finish • Any delay of an activity on the critical path directly impacts the planned project completion date. • A project can have several, parallel, near critical paths. An additional parallel path through the network with the total durations shorter than the critical path is called a sub-critical or non-critical path.
  • 17. Time-Cost Trade-OFFS: Crashing: • When we say that an activity will take a certain number of days or weeks, what we really mean is this activity normally takes this many days or weeks. We could make it take less time, but to do so would cost more money. • Crashing is a process of expediting project schedule by compressing the total project duration. • The key is to attain maximum decrease in schedule time with minimum cost. • More resources are needed to speed-up a part of a project • Depends on what slack is available in a non-critical activity
  • 18. When not to Crash: • The key to project crashing is attaining maximum reduction in schedule time with minimum cost. Quite simply, the time to stop crashing is when it no longer becomes cost effective. A simple guideline is: • Crash only activities that are critical. • Crash from the least expensive to most expensive. • Crash an activity only until: • It reaches its maximum time reduction. • It causes another path to also become critical. • It becomes more expensive to crash than not to crash
  • 19. Creating a Crash Table: • Identify the critical path and the corresponding tasks. • Export the work package tasks (ID and Task Name fields), the original duration (Duration field), and the original cost (Cost field) from your MS Project schedule, and open that file in Excel. • You must calculate the potential crash duration for each critical path task and the cost to crash each task. • On the Excel worksheet, add a column to calculate crash reduction, which is how many weeks you can crash each task. Crash reduction is simply the original duration minus the crash duration. • Add another column to calculate the crash cost per week, which is the crash cost divided by the crash reduction value.