Cost Planning
A Comprehensive Beginners Guide
1
Designed and Developed by https://www.pmbypm.com | Copyright 2018
• Create Scope Statement
• Create WBS
• Identify Work Package
Scope Planning
•Decompose Work Packages
•Identify activities
•Estimate Activity Resources
•Estimate Activity Duration
•Develop Schedule
Time Planning
• Activity Cost Estimation
• Determine Budget
Cost Planning
2
Designed and Developed by https://www.pmbypm.com | Copyright 2018
• Create Scope Statement
• Create WBS
• Identify Work Package
Scope Planning
•Decompose Work Packages
•Identify activities
•Estimate Activity Resources
•Estimate Activity Duration
•Develop Schedule
Time Planning
• Activity Cost Estimation
• Determine Budget
Cost Planning
3
Designed and Developed by https://www.pmbypm.com | Copyright 2018
Scope Planning
 For more details about Scope Planning, refer to –
https://www.slideshare.net/pmalik2/ignore-project-scope-wbs-at-your-own-peril-
84976876
4
Designed and Developed by https://www.pmbypm.com | Copyright 2018
5
Designed and Developed by https://www.pmbypm.com | Copyright 2018
Cost Baseline
Project ComponentProject Component
Contingency
Reserves
Project
Work Package A Work Package B Work Package C
Create WBS
• Create Scope Statement
• Create WBS
• Identify Work Package
Scope Planning
•Decompose Work Packages
•Identify activities
•Estimate Activity Resources
•Estimate Activity Duration
•Develop Schedule
Time Planning
• Activity Cost Estimation
• Determine Budget
Cost Planning
6
Designed and Developed by https://www.pmbypm.com | Copyright 2018
Time Planning
 https://www.slideshare.net/pmalik2/5-steps-of-project-scheduling-process-for-
absolute-beginners-86265406
 https://www.slideshare.net/pmalik2/how-project-network-diagrams-can-help-you-
become-a-better-project-manager
 https://www.slideshare.net/pmalik2/4-project-estimation-techniques-that-can-
make-you-super-successful
 https://www.slideshare.net/pmalik2/successful-project-managers-use-these-5-
ways-to-represent-project-schedule
7
Designed and Developed by https://www.pmbypm.com | Copyright 2018
For more details about Time Planning, refer to –
Time Planning
 STEP 1 – Identify Activities by Decomposing Work Packages
 STEP 2 – Develop Schedule After Sequencing and Estimation
8
Designed and Developed by https://www.pmbypm.com | Copyright 2018
9
Designed and Developed by https://www.pmbypm.com | Copyright 2018
Cost Baseline
Project ComponentProject Component
Contingency
Reserves
Project
Work Package A Work Package B Work Package C
Activity 2Activity 1 Activity 3 Activity 4
STEP 1 – Identify
Activities
10
Designed and Developed by https://www.pmbypm.com | Copyright 2018
STEP 2 – Develop
Schedule
• Create Scope Statement
• Create WBS
• Identify Work Package
Scope Planning
•Decompose Work Packages
•Identify activities
•Estimate Activity Resources
•Estimate Activity Duration
•Develop Schedule
Time Planning
• Activity Cost Estimation
• Determine Budget
Cost Planning
11
Designed and Developed by https://www.pmbypm.com | Copyright 2018
Activity Cost Estimation
 Estimate Activity Costs
 Include Resource Cost and Vendor Costs
 Include Direct Costs and Indirect Costs
 Add Activity Reserves
12
Designed and Developed by https://www.pmbypm.com | Copyright 2018
Designed and Developed by https://www.pmbypm.com | Copyright 2018
13 Cost Baseline
Project ComponentProject Component
Contingency
Reserves
Project
Work Package A Work Package B Work Package C
Activity B
$750
Activity A
$1800
Activity C
$900
Activity D
$1550
Estimate Activity
Costs
Determine Budget
 STEP 1 – Determine WP Cost by Aggregating Costs of Activities
 STEP 2 – Determine Total Project Cost by Aggregating WP Costs
 STEP 3 – Estimate Project Contingency Reserves
 STEP 4 – Add Contingency Reserves to Project Cost to determine Cost Baseline
 STEP 5 – Optimize Project Schedule & Develop Time Phased Project Budget
14
Designed and Developed by https://www.pmbypm.com | Copyright 2018
Designed and Developed by https://www.pmbypm.com | Copyright 2018
15 Cost Baseline
Project ComponentProject Component
Contingency
Reserves
Project
Work Package A
$3200
Work Package B
$5000
Work Package C
$1800
Activity
B $750
Activity A
$1800
Activity C
$900
Activity D
$1550
STEP 1 –
Aggregate
Activities Cost
Designed and Developed by https://www.pmbypm.com | Copyright 2018
16 Cost Baseline
Project ComponentProject Component
Contingency
Reserves
Project $9000
Work Package A
$3200
Work Package B
$5000
Work Package C
$1800
Activity
B $750
Activity A
$1800
Activity C
$900
Activity D
$1550
STEP 2 –
Aggregate WP
Cost
Designed and Developed by https://www.pmbypm.com | Copyright 2018
17
Cost Baseline
Project ComponentProject Component
Contingency
Reserves $1000
Project $9000
Work Package A
$3200
Work Package B
$5000
Work Package C
$1800
Activity
B $750
Activity A
$1800
Activity C
$900
Activity D
$1550
STEP 3 - Estimate
Contingency
Reserves
STEP 4 - Cost
Baseline = Project
Cost + Contingency
Reserves
Designed and Developed by https://www.pmbypm.com | Copyright 2018
18
Cost Baseline
$10000
Project ComponentProject Component
Contingency
Reserves $1000
Project $9000
Work Package A
$3200
Work Package B
$5000
Work Package C
$1800
Activity
B $750
Activity A
$1800
Activity C
$900
Activity D
$1550
STEP 5 - Time Phased Cost Baseline
Designed and Developed by https://www.pmbypm.com | Copyright 2018
19
Cost Baseline
CumulativeCost
Time
YOUR OPINION IS IMPORTANT TO US
For Any Questions Or Suggestions Contact Us @
https://www.pmbypm.com/contact-praveen-malik/
Designed and Developed by https://www.pmbypm.com | Copyright 2018
20

More Related Content

PPTX
101 - A Beginner's Guide To Earned Value Management
PPTX
Calculating Estimate At Completion (EAC) Using 5 Different Formulas
PPTX
Learn The Right Way To Apply TCPI Formulas In Project Management
PPTX
Calculating ETC In 4 Different Scenarios
PPTX
Successful Project Managers Use These 5 Ways to Represent Project Schedule
PPTX
5 Steps Of Project Scheduling Process For Absolute Beginners
PPTX
4 Project Estimation Techniques That Can Make You Super Successful
PDF
Methodologies of Project Progress Measurement
101 - A Beginner's Guide To Earned Value Management
Calculating Estimate At Completion (EAC) Using 5 Different Formulas
Learn The Right Way To Apply TCPI Formulas In Project Management
Calculating ETC In 4 Different Scenarios
Successful Project Managers Use These 5 Ways to Represent Project Schedule
5 Steps Of Project Scheduling Process For Absolute Beginners
4 Project Estimation Techniques That Can Make You Super Successful
Methodologies of Project Progress Measurement

What's hot (18)

PDF
PPTX
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...
PPTX
BIM SHOW LIVE 14 - 4D BIM: successful implementation at Gravesened Railway St...
PDF
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
PPTX
4D bim construction scheduling on the 1885 St. James pl. project
PPTX
Ms project presentation
PPTX
Lesson in fs cpm,cpa
PPTX
Jason douglas earned value 1 0
PPT
EVM in MS Project
PPSX
PMP Exam Preparation Course: 06 Project Cost Management
PPT
Earned value
PPTX
Police Headquarters Guaranteed Maximum Price
PPT
13 lecture project management
PPTX
Dashboard
PPT
Earned value analysis training
PDF
160155061 project-monitoring-control
PPTX
project control using earned value analysis - Part 01
PDF
E2E - ERP integrated planning for Pay costs
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...
BIM SHOW LIVE 14 - 4D BIM: successful implementation at Gravesened Railway St...
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
4D bim construction scheduling on the 1885 St. James pl. project
Ms project presentation
Lesson in fs cpm,cpa
Jason douglas earned value 1 0
EVM in MS Project
PMP Exam Preparation Course: 06 Project Cost Management
Earned value
Police Headquarters Guaranteed Maximum Price
13 lecture project management
Dashboard
Earned value analysis training
160155061 project-monitoring-control
project control using earned value analysis - Part 01
E2E - ERP integrated planning for Pay costs
Ad

Similar to A Comprehensive Beginners Guide To Cost Planning (20)

PPTX
Investment Planning: Meeting today's challenges and planning for the future
PDF
2_Project Scope Management
PDF
C03.08-09-ExecutionMonitoringControl.key.pdf
PPT
File 3 extra four slides 1
PPT
File 3 removed 1 word 2
PDF
GAFM Academy - THE ESSENTIALS OF PLANNING AND SCOPING A PROJECT
PDF
masVenta hybrid-project-management-june-2017 - Agile Austria Graz 2017
PPT
File 3 removed 1 word from 5 slides 2
PPT
PMP Module 4 - Cost
PPT
File 3 original copy 2
PPT
File 3 original copy 1
PPT
File 3 original
PPT
File 3 removed 1 word 1
PPT
File 3 removed 1 word from 5 slides 1
PPTX
Session 21 4th edition PMP
PPTX
PgMP_Brain Dump
PPTX
Robust Hybrid rather than Agile or Waterfall
PPT
File 3 removed 5 words 2
PPT
File 3 extra four slides 2
PPT
File 3 removed 5 words 1
Investment Planning: Meeting today's challenges and planning for the future
2_Project Scope Management
C03.08-09-ExecutionMonitoringControl.key.pdf
File 3 extra four slides 1
File 3 removed 1 word 2
GAFM Academy - THE ESSENTIALS OF PLANNING AND SCOPING A PROJECT
masVenta hybrid-project-management-june-2017 - Agile Austria Graz 2017
File 3 removed 1 word from 5 slides 2
PMP Module 4 - Cost
File 3 original copy 2
File 3 original copy 1
File 3 original
File 3 removed 1 word 1
File 3 removed 1 word from 5 slides 1
Session 21 4th edition PMP
PgMP_Brain Dump
Robust Hybrid rather than Agile or Waterfall
File 3 removed 5 words 2
File 3 extra four slides 2
File 3 removed 5 words 1
Ad

Recently uploaded (20)

PPTX
Computer Architecture Input Output Memory.pptx
PDF
ChatGPT for Dummies - Pam Baker Ccesa007.pdf
PDF
LDMMIA Reiki Yoga Finals Review Spring Summer
PDF
FORM 1 BIOLOGY MIND MAPS and their schemes
PDF
Empowerment Technology for Senior High School Guide
PDF
Practical Manual AGRO-233 Principles and Practices of Natural Farming
PPTX
Introduction to pro and eukaryotes and differences.pptx
PDF
IGGE1 Understanding the Self1234567891011
PDF
Computing-Curriculum for Schools in Ghana
PPTX
Virtual and Augmented Reality in Current Scenario
PDF
A GUIDE TO GENETICS FOR UNDERGRADUATE MEDICAL STUDENTS
PPTX
B.Sc. DS Unit 2 Software Engineering.pptx
PPTX
202450812 BayCHI UCSC-SV 20250812 v17.pptx
PDF
Paper A Mock Exam 9_ Attempt review.pdf.
PDF
Vision Prelims GS PYQ Analysis 2011-2022 www.upscpdf.com.pdf
PDF
Black Hat USA 2025 - Micro ICS Summit - ICS/OT Threat Landscape
PDF
Indian roads congress 037 - 2012 Flexible pavement
PDF
احياء السادس العلمي - الفصل الثالث (التكاثر) منهج متميزين/كلية بغداد/موهوبين
PPTX
20th Century Theater, Methods, History.pptx
PDF
Τίμαιος είναι φιλοσοφικός διάλογος του Πλάτωνα
Computer Architecture Input Output Memory.pptx
ChatGPT for Dummies - Pam Baker Ccesa007.pdf
LDMMIA Reiki Yoga Finals Review Spring Summer
FORM 1 BIOLOGY MIND MAPS and their schemes
Empowerment Technology for Senior High School Guide
Practical Manual AGRO-233 Principles and Practices of Natural Farming
Introduction to pro and eukaryotes and differences.pptx
IGGE1 Understanding the Self1234567891011
Computing-Curriculum for Schools in Ghana
Virtual and Augmented Reality in Current Scenario
A GUIDE TO GENETICS FOR UNDERGRADUATE MEDICAL STUDENTS
B.Sc. DS Unit 2 Software Engineering.pptx
202450812 BayCHI UCSC-SV 20250812 v17.pptx
Paper A Mock Exam 9_ Attempt review.pdf.
Vision Prelims GS PYQ Analysis 2011-2022 www.upscpdf.com.pdf
Black Hat USA 2025 - Micro ICS Summit - ICS/OT Threat Landscape
Indian roads congress 037 - 2012 Flexible pavement
احياء السادس العلمي - الفصل الثالث (التكاثر) منهج متميزين/كلية بغداد/موهوبين
20th Century Theater, Methods, History.pptx
Τίμαιος είναι φιλοσοφικός διάλογος του Πλάτωνα

A Comprehensive Beginners Guide To Cost Planning

  • 1. Cost Planning A Comprehensive Beginners Guide 1 Designed and Developed by https://www.pmbypm.com | Copyright 2018
  • 2. • Create Scope Statement • Create WBS • Identify Work Package Scope Planning •Decompose Work Packages •Identify activities •Estimate Activity Resources •Estimate Activity Duration •Develop Schedule Time Planning • Activity Cost Estimation • Determine Budget Cost Planning 2 Designed and Developed by https://www.pmbypm.com | Copyright 2018
  • 3. • Create Scope Statement • Create WBS • Identify Work Package Scope Planning •Decompose Work Packages •Identify activities •Estimate Activity Resources •Estimate Activity Duration •Develop Schedule Time Planning • Activity Cost Estimation • Determine Budget Cost Planning 3 Designed and Developed by https://www.pmbypm.com | Copyright 2018
  • 4. Scope Planning  For more details about Scope Planning, refer to – https://www.slideshare.net/pmalik2/ignore-project-scope-wbs-at-your-own-peril- 84976876 4 Designed and Developed by https://www.pmbypm.com | Copyright 2018
  • 5. 5 Designed and Developed by https://www.pmbypm.com | Copyright 2018 Cost Baseline Project ComponentProject Component Contingency Reserves Project Work Package A Work Package B Work Package C Create WBS
  • 6. • Create Scope Statement • Create WBS • Identify Work Package Scope Planning •Decompose Work Packages •Identify activities •Estimate Activity Resources •Estimate Activity Duration •Develop Schedule Time Planning • Activity Cost Estimation • Determine Budget Cost Planning 6 Designed and Developed by https://www.pmbypm.com | Copyright 2018
  • 7. Time Planning  https://www.slideshare.net/pmalik2/5-steps-of-project-scheduling-process-for- absolute-beginners-86265406  https://www.slideshare.net/pmalik2/how-project-network-diagrams-can-help-you- become-a-better-project-manager  https://www.slideshare.net/pmalik2/4-project-estimation-techniques-that-can- make-you-super-successful  https://www.slideshare.net/pmalik2/successful-project-managers-use-these-5- ways-to-represent-project-schedule 7 Designed and Developed by https://www.pmbypm.com | Copyright 2018 For more details about Time Planning, refer to –
  • 8. Time Planning  STEP 1 – Identify Activities by Decomposing Work Packages  STEP 2 – Develop Schedule After Sequencing and Estimation 8 Designed and Developed by https://www.pmbypm.com | Copyright 2018
  • 9. 9 Designed and Developed by https://www.pmbypm.com | Copyright 2018 Cost Baseline Project ComponentProject Component Contingency Reserves Project Work Package A Work Package B Work Package C Activity 2Activity 1 Activity 3 Activity 4 STEP 1 – Identify Activities
  • 10. 10 Designed and Developed by https://www.pmbypm.com | Copyright 2018 STEP 2 – Develop Schedule
  • 11. • Create Scope Statement • Create WBS • Identify Work Package Scope Planning •Decompose Work Packages •Identify activities •Estimate Activity Resources •Estimate Activity Duration •Develop Schedule Time Planning • Activity Cost Estimation • Determine Budget Cost Planning 11 Designed and Developed by https://www.pmbypm.com | Copyright 2018
  • 12. Activity Cost Estimation  Estimate Activity Costs  Include Resource Cost and Vendor Costs  Include Direct Costs and Indirect Costs  Add Activity Reserves 12 Designed and Developed by https://www.pmbypm.com | Copyright 2018
  • 13. Designed and Developed by https://www.pmbypm.com | Copyright 2018 13 Cost Baseline Project ComponentProject Component Contingency Reserves Project Work Package A Work Package B Work Package C Activity B $750 Activity A $1800 Activity C $900 Activity D $1550 Estimate Activity Costs
  • 14. Determine Budget  STEP 1 – Determine WP Cost by Aggregating Costs of Activities  STEP 2 – Determine Total Project Cost by Aggregating WP Costs  STEP 3 – Estimate Project Contingency Reserves  STEP 4 – Add Contingency Reserves to Project Cost to determine Cost Baseline  STEP 5 – Optimize Project Schedule & Develop Time Phased Project Budget 14 Designed and Developed by https://www.pmbypm.com | Copyright 2018
  • 15. Designed and Developed by https://www.pmbypm.com | Copyright 2018 15 Cost Baseline Project ComponentProject Component Contingency Reserves Project Work Package A $3200 Work Package B $5000 Work Package C $1800 Activity B $750 Activity A $1800 Activity C $900 Activity D $1550 STEP 1 – Aggregate Activities Cost
  • 16. Designed and Developed by https://www.pmbypm.com | Copyright 2018 16 Cost Baseline Project ComponentProject Component Contingency Reserves Project $9000 Work Package A $3200 Work Package B $5000 Work Package C $1800 Activity B $750 Activity A $1800 Activity C $900 Activity D $1550 STEP 2 – Aggregate WP Cost
  • 17. Designed and Developed by https://www.pmbypm.com | Copyright 2018 17 Cost Baseline Project ComponentProject Component Contingency Reserves $1000 Project $9000 Work Package A $3200 Work Package B $5000 Work Package C $1800 Activity B $750 Activity A $1800 Activity C $900 Activity D $1550 STEP 3 - Estimate Contingency Reserves
  • 18. STEP 4 - Cost Baseline = Project Cost + Contingency Reserves Designed and Developed by https://www.pmbypm.com | Copyright 2018 18 Cost Baseline $10000 Project ComponentProject Component Contingency Reserves $1000 Project $9000 Work Package A $3200 Work Package B $5000 Work Package C $1800 Activity B $750 Activity A $1800 Activity C $900 Activity D $1550
  • 19. STEP 5 - Time Phased Cost Baseline Designed and Developed by https://www.pmbypm.com | Copyright 2018 19 Cost Baseline CumulativeCost Time
  • 20. YOUR OPINION IS IMPORTANT TO US For Any Questions Or Suggestions Contact Us @ https://www.pmbypm.com/contact-praveen-malik/ Designed and Developed by https://www.pmbypm.com | Copyright 2018 20