TCPI FORMULAS IN PROJECT MANAGEMENT
Agenda
 Explanation & Definitions
 Understanding TCPI Through Example
 TCPI Formulas
DESIGNED AND DEVELOPED BY WWW.PMBYPM.COM | COPYRIGHT 2018 2
Agenda
 Explanation & Definitions
 Understanding TCPI Through Example
 TCPI Formulas
DESIGNED AND DEVELOPED BY WWW.PMBYPM.COM | COPYRIGHT 2018 3
Project Cost Efficiency
 Project Cost Efficiency can be defined as the ratio of work to cost.
 Work could be Completed Work or Remaining Work. (in appropriate units)
 Cost could be used up money or remaining money. (in dollars or any other monetary unit)
DESIGNED AND DEVELOPED BY WWW.PMBYPM.COM | COPYRIGHT 2018 4
Project Cost Efficiency = Work / Cost
Two Cost Efficiencies - CPI v/s TCPI
CPI – COST PERFORMANCE INDEX
 Project’s current cost efficiency.
 Actual cost efficiency of completed
work.
 CPI = EV/AC
TCPI – TO COMPLETE PERFORMANCE
INDEX
 Project’s future cost efficiency.
 Projected cost efficiency of remaining
work.
 To be determined….
DESIGNED AND DEVELOPED BY WWW.PMBYPM.COM | COPYRIGHT 2018 5
COMPLETED REMAINING
TOTAL PROJECT SCOPE/WORK
CPI TCPI ?
Reference
https://www.pmbypm.com/basics-earned-value-analysis/
https://www.slideshare.net/pmalik2/101-a-beginners-guide-to-earned-value-management
TCPI Definition
It is a measure of the cost performance that is required to be
achieved with the remaining resources in order to meet a specified
management goal, expressed as the ratio of the cost to finish the
outstanding work to the remaining budget.
Future projected cost efficiency to complete the project within
original or revised project budget.
DESIGNED AND DEVELOPED BY WWW.PMBYPM.COM | COPYRIGHT 2018 6
PMBOK Guide
Graphical Representation Of A Project
DESIGNED AND DEVELOPED BY WWW.PMBYPM.COM | COPYRIGHT 2018 7
Control Date
Time
CumulativeCost
EAC
BAC
AC
PV
EV
Agenda
 Explanation & Definitions
 Understanding TCPI Through Example
 TCPI Formulas
DESIGNED AND DEVELOPED BY WWW.PMBYPM.COM | COPYRIGHT 2018 8
Project Plan – Example Project
DESIGNED AND DEVELOPED BY WWW.PMBYPM.COM | COPYRIGHT 2018 9
Project Scope Build 80 Tables
Project Time Estimate (Duration) 5 Days
Cost Estimate Per Table $1000
Project Cost (Budget) $1000*80 = $80000
Reference
https://www.pmbypm.com/basics-earned-value-analysis/
https://www.slideshare.net/pmalik2/101-a-beginners-guide-to-earned-value-management
Project Status – Example Project
CPI = EV/AC
= 35000/36000
= 0.97
DESIGNED AND DEVELOPED BY WWW.PMBYPM.COM | COPYRIGHT 2018 10
Work No. of Tables Cost Monetary Value
Total 80 BAC or EAC 80*$1000 = $80000
Completed 35 $36000 (AC)
35*$1000 = $35000
(EV)
Remaining 45 (80-35) ETC 45*$1000 = $45000
TCPI = Remaining Work/Remaining Funds
= 45000/(80000-36000)
= 1.02
If CPI < 1 then, TCPI needs to be greater than 1 in order to complete the remaining work within the original project budget
Calculating TCPI
DESIGNED AND DEVELOPED BY WWW.PMBYPM.COM | COPYRIGHT 2018 11
TCPI = (monetary value of remaining work)/(remaining funds)
COMPLETED REMAINING
TOTAL PROJECT SCOPE/WORK
CPI TCPI ?
Calculating TCPI
 Monetary value of remaining work = monetary value of total work – monetary value
of completed work
 Monetary value of remaining work = BAC – EV
DESIGNED AND DEVELOPED BY WWW.PMBYPM.COM | COPYRIGHT 2018 12
TCPI = (monetary value of remaining work)/(remaining funds)
EV REMAINING
BAC
Calculating TCPI
 Monetary value of remaining work = monetary value of total work – monetary value
of completed work
 Monetary value of remaining work = BAC – EV
 Remaining funds = total budget – actual expenditure
 Remaining funds = BAC – AC
DESIGNED AND DEVELOPED BY WWW.PMBYPM.COM | COPYRIGHT 2018 13
TCPI = (monetary value of remaining work)/(remaining funds)
Agenda
 Explanation & Definitions
 Understanding TCPI Through Example
 TCPI Formulas
DESIGNED AND DEVELOPED BY WWW.PMBYPM.COM | COPYRIGHT 2018 14
TCPI Formulas
If Sponsor decides to revise the Project Budget to EAC, the formula becomes
DESIGNED AND DEVELOPED BY WWW.PMBYPM.COM | COPYRIGHT 2018 15
TCPIB = (BAC – EV) / (BAC – AC)
TCPIE = (BAC – EV) / (EAC – AC)
Calculations
 TCPIB = (80000 – 35000) / (80000 – 36000)
TCPIB = 1.02
If Budget imposed by Sponsor is $78000
 EAC = $78000
 TCPIE = ($80000 – $35000) / ($78000 – $36000)
TCPIE = 1.07
DESIGNED AND DEVELOPED BY WWW.PMBYPM.COM | COPYRIGHT 2018 16
YOUR OPINION IS IMPORTANT
TO US
FOR ANY QUESTIONS OR SUGGESTIONS CONTACT US @
HTTPS://WWW.PMBYPM.COM/CONTACT-PRAVEEN-MALIK/
DESIGNED AND DEVELOPED BY WWW.PMBYPM.COM | COPYRIGHT 2018 17

More Related Content

DOC
ZERO EMISSION CITY
PDF
Comportamiento de los huecos de la envolvente. Aspectos a tener en cuenta en ...
PPTX
Earned Value Management - Leading & Misleading in Project Control
PDF
Leed v4-view-from-mep-seats-140429
PDF
Green Building Construction in India
PPTX
Calculating ETC In 4 Different Scenarios
PPTX
101 - A Beginner's Guide To Earned Value Management
PPTX
Calculating Estimate At Completion (EAC) Using 5 Different Formulas
ZERO EMISSION CITY
Comportamiento de los huecos de la envolvente. Aspectos a tener en cuenta en ...
Earned Value Management - Leading & Misleading in Project Control
Leed v4-view-from-mep-seats-140429
Green Building Construction in India
Calculating ETC In 4 Different Scenarios
101 - A Beginner's Guide To Earned Value Management
Calculating Estimate At Completion (EAC) Using 5 Different Formulas

Similar to Learn The Right Way To Apply TCPI Formulas In Project Management (20)

PDF
An introduction to project accounting
PPTX
Earned Value Analysis in construction projects
PPT
D08 Quantify Project Value
PPT
D08 Quantify Project Value
PPT
L06 cost management
PDF
CCP_SEC4_Progress and Cost Control
PPT
Earned value
PPTX
Lecture 06 project_cost_management
PDF
ICEC 2014 Linking 6 Phase Project Life Cycle with TCM Framework-Slides
PPTX
PMBoK, discussion #5: Project Cost Management
PPTX
Nasa+evm+reference+card nov+2015
PPTX
Corporate Finance Slides on Capital Budgeting
PPTX
Project accounting an introduction
PDF
a clients most influential dimension to make bim fly
PDF
Performing against the wall - SPI after completion
PDF
Chap 7.3 Determine budget
PPTX
Capital Programs - O'Hare 21
PDF
CA Project and Portfolio Management v14.x: MS Project Integration: Tips, Tric...
PDF
Program Management 2.0: Work Breakdown Structure
PDF
AVEVA World Conference NA - Justin Weaver, Southern Company
An introduction to project accounting
Earned Value Analysis in construction projects
D08 Quantify Project Value
D08 Quantify Project Value
L06 cost management
CCP_SEC4_Progress and Cost Control
Earned value
Lecture 06 project_cost_management
ICEC 2014 Linking 6 Phase Project Life Cycle with TCM Framework-Slides
PMBoK, discussion #5: Project Cost Management
Nasa+evm+reference+card nov+2015
Corporate Finance Slides on Capital Budgeting
Project accounting an introduction
a clients most influential dimension to make bim fly
Performing against the wall - SPI after completion
Chap 7.3 Determine budget
Capital Programs - O'Hare 21
CA Project and Portfolio Management v14.x: MS Project Integration: Tips, Tric...
Program Management 2.0: Work Breakdown Structure
AVEVA World Conference NA - Justin Weaver, Southern Company
Ad

More from Praveen Malik, PMP (8)

PPTX
A Comprehensive Beginners Guide To Cost Planning
PPTX
How To Use Scheduling Lead And Lag With 4 Types Of Relationships
PPTX
How To Do Planning Using 4 Types of Project Dependencies?
PPTX
5 Steps Of Project Scheduling Process For Absolute Beginners
PPTX
Successful Project Managers Use These 5 Ways to Represent Project Schedule
PPTX
4 Project Estimation Techniques That Can Make You Super Successful
PDF
Ignore Project Scope & WBS At Your Own Peril
PPTX
How Project Network Diagram's Can Help You Become A Better Project Manager
A Comprehensive Beginners Guide To Cost Planning
How To Use Scheduling Lead And Lag With 4 Types Of Relationships
How To Do Planning Using 4 Types of Project Dependencies?
5 Steps Of Project Scheduling Process For Absolute Beginners
Successful Project Managers Use These 5 Ways to Represent Project Schedule
4 Project Estimation Techniques That Can Make You Super Successful
Ignore Project Scope & WBS At Your Own Peril
How Project Network Diagram's Can Help You Become A Better Project Manager
Ad

Recently uploaded (20)

PDF
Module 4: Burden of Disease Tutorial Slides S2 2025
PPTX
Institutional Correction lecture only . . .
PPTX
Lesson notes of climatology university.
PDF
Classroom Observation Tools for Teachers
PPTX
IMMUNITY IMMUNITY refers to protection against infection, and the immune syst...
PDF
TR - Agricultural Crops Production NC III.pdf
PDF
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
PDF
Insiders guide to clinical Medicine.pdf
PPTX
Microbial diseases, their pathogenesis and prophylaxis
PDF
Microbial disease of the cardiovascular and lymphatic systems
PDF
Pre independence Education in Inndia.pdf
PDF
Supply Chain Operations Speaking Notes -ICLT Program
PDF
Saundersa Comprehensive Review for the NCLEX-RN Examination.pdf
PPTX
human mycosis Human fungal infections are called human mycosis..pptx
PDF
O5-L3 Freight Transport Ops (International) V1.pdf
PDF
102 student loan defaulters named and shamed – Is someone you know on the list?
PDF
The Lost Whites of Pakistan by Jahanzaib Mughal.pdf
PDF
ANTIBIOTICS.pptx.pdf………………… xxxxxxxxxxxxx
PPTX
PPH.pptx obstetrics and gynecology in nursing
PDF
Sports Quiz easy sports quiz sports quiz
Module 4: Burden of Disease Tutorial Slides S2 2025
Institutional Correction lecture only . . .
Lesson notes of climatology university.
Classroom Observation Tools for Teachers
IMMUNITY IMMUNITY refers to protection against infection, and the immune syst...
TR - Agricultural Crops Production NC III.pdf
3rd Neelam Sanjeevareddy Memorial Lecture.pdf
Insiders guide to clinical Medicine.pdf
Microbial diseases, their pathogenesis and prophylaxis
Microbial disease of the cardiovascular and lymphatic systems
Pre independence Education in Inndia.pdf
Supply Chain Operations Speaking Notes -ICLT Program
Saundersa Comprehensive Review for the NCLEX-RN Examination.pdf
human mycosis Human fungal infections are called human mycosis..pptx
O5-L3 Freight Transport Ops (International) V1.pdf
102 student loan defaulters named and shamed – Is someone you know on the list?
The Lost Whites of Pakistan by Jahanzaib Mughal.pdf
ANTIBIOTICS.pptx.pdf………………… xxxxxxxxxxxxx
PPH.pptx obstetrics and gynecology in nursing
Sports Quiz easy sports quiz sports quiz

Learn The Right Way To Apply TCPI Formulas In Project Management

  • 1. To Complete Performance Index TCPI FORMULAS IN PROJECT MANAGEMENT
  • 2. Agenda  Explanation & Definitions  Understanding TCPI Through Example  TCPI Formulas DESIGNED AND DEVELOPED BY WWW.PMBYPM.COM | COPYRIGHT 2018 2
  • 3. Agenda  Explanation & Definitions  Understanding TCPI Through Example  TCPI Formulas DESIGNED AND DEVELOPED BY WWW.PMBYPM.COM | COPYRIGHT 2018 3
  • 4. Project Cost Efficiency  Project Cost Efficiency can be defined as the ratio of work to cost.  Work could be Completed Work or Remaining Work. (in appropriate units)  Cost could be used up money or remaining money. (in dollars or any other monetary unit) DESIGNED AND DEVELOPED BY WWW.PMBYPM.COM | COPYRIGHT 2018 4 Project Cost Efficiency = Work / Cost
  • 5. Two Cost Efficiencies - CPI v/s TCPI CPI – COST PERFORMANCE INDEX  Project’s current cost efficiency.  Actual cost efficiency of completed work.  CPI = EV/AC TCPI – TO COMPLETE PERFORMANCE INDEX  Project’s future cost efficiency.  Projected cost efficiency of remaining work.  To be determined…. DESIGNED AND DEVELOPED BY WWW.PMBYPM.COM | COPYRIGHT 2018 5 COMPLETED REMAINING TOTAL PROJECT SCOPE/WORK CPI TCPI ? Reference https://www.pmbypm.com/basics-earned-value-analysis/ https://www.slideshare.net/pmalik2/101-a-beginners-guide-to-earned-value-management
  • 6. TCPI Definition It is a measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal, expressed as the ratio of the cost to finish the outstanding work to the remaining budget. Future projected cost efficiency to complete the project within original or revised project budget. DESIGNED AND DEVELOPED BY WWW.PMBYPM.COM | COPYRIGHT 2018 6 PMBOK Guide
  • 7. Graphical Representation Of A Project DESIGNED AND DEVELOPED BY WWW.PMBYPM.COM | COPYRIGHT 2018 7 Control Date Time CumulativeCost EAC BAC AC PV EV
  • 8. Agenda  Explanation & Definitions  Understanding TCPI Through Example  TCPI Formulas DESIGNED AND DEVELOPED BY WWW.PMBYPM.COM | COPYRIGHT 2018 8
  • 9. Project Plan – Example Project DESIGNED AND DEVELOPED BY WWW.PMBYPM.COM | COPYRIGHT 2018 9 Project Scope Build 80 Tables Project Time Estimate (Duration) 5 Days Cost Estimate Per Table $1000 Project Cost (Budget) $1000*80 = $80000 Reference https://www.pmbypm.com/basics-earned-value-analysis/ https://www.slideshare.net/pmalik2/101-a-beginners-guide-to-earned-value-management
  • 10. Project Status – Example Project CPI = EV/AC = 35000/36000 = 0.97 DESIGNED AND DEVELOPED BY WWW.PMBYPM.COM | COPYRIGHT 2018 10 Work No. of Tables Cost Monetary Value Total 80 BAC or EAC 80*$1000 = $80000 Completed 35 $36000 (AC) 35*$1000 = $35000 (EV) Remaining 45 (80-35) ETC 45*$1000 = $45000 TCPI = Remaining Work/Remaining Funds = 45000/(80000-36000) = 1.02 If CPI < 1 then, TCPI needs to be greater than 1 in order to complete the remaining work within the original project budget
  • 11. Calculating TCPI DESIGNED AND DEVELOPED BY WWW.PMBYPM.COM | COPYRIGHT 2018 11 TCPI = (monetary value of remaining work)/(remaining funds) COMPLETED REMAINING TOTAL PROJECT SCOPE/WORK CPI TCPI ?
  • 12. Calculating TCPI  Monetary value of remaining work = monetary value of total work – monetary value of completed work  Monetary value of remaining work = BAC – EV DESIGNED AND DEVELOPED BY WWW.PMBYPM.COM | COPYRIGHT 2018 12 TCPI = (monetary value of remaining work)/(remaining funds) EV REMAINING BAC
  • 13. Calculating TCPI  Monetary value of remaining work = monetary value of total work – monetary value of completed work  Monetary value of remaining work = BAC – EV  Remaining funds = total budget – actual expenditure  Remaining funds = BAC – AC DESIGNED AND DEVELOPED BY WWW.PMBYPM.COM | COPYRIGHT 2018 13 TCPI = (monetary value of remaining work)/(remaining funds)
  • 14. Agenda  Explanation & Definitions  Understanding TCPI Through Example  TCPI Formulas DESIGNED AND DEVELOPED BY WWW.PMBYPM.COM | COPYRIGHT 2018 14
  • 15. TCPI Formulas If Sponsor decides to revise the Project Budget to EAC, the formula becomes DESIGNED AND DEVELOPED BY WWW.PMBYPM.COM | COPYRIGHT 2018 15 TCPIB = (BAC – EV) / (BAC – AC) TCPIE = (BAC – EV) / (EAC – AC)
  • 16. Calculations  TCPIB = (80000 – 35000) / (80000 – 36000) TCPIB = 1.02 If Budget imposed by Sponsor is $78000  EAC = $78000  TCPIE = ($80000 – $35000) / ($78000 – $36000) TCPIE = 1.07 DESIGNED AND DEVELOPED BY WWW.PMBYPM.COM | COPYRIGHT 2018 16
  • 17. YOUR OPINION IS IMPORTANT TO US FOR ANY QUESTIONS OR SUGGESTIONS CONTACT US @ HTTPS://WWW.PMBYPM.COM/CONTACT-PRAVEEN-MALIK/ DESIGNED AND DEVELOPED BY WWW.PMBYPM.COM | COPYRIGHT 2018 17